This is a Solicitation, Offer, and Award form (Standard Form 1442) for a construction contract issued by Army Contracting Command – Rock Island (ACC-RI) for Sky Foundry B299 Electrical Relocation at Rock Island Arsenal, Joint Manufacturing and Technology Center (RIA-JMTC).
The Government intends to award one Firm Fixed Price (FFP) contract to the lowest price, responsive, and responsible contractor. The solicitation number is W519TC26RA021, with a project number of 1241659. Offers are due by 10:00 AM Central Time on 10 APR 2026 at the address specified (ACC-RI, Rock Island Island Building 60, 3055 Rodman Avenue, Rock Island, IL 61299-0000). A mandatory pre-construction site visit is scheduled for 11:00 AM Central Time on 2 April 2026 at Building 299, Rock Island Arsenal, with reservations required at least three business days prior. The contractor must begin performance within 14 calendar days of receiving notice to proceed and complete the work within 150 calendar days after award. Performance and payment bonds are required and must be furnished within 10 calendar days after award. The estimated magnitude of construction is between $250,000 and $500,000. Davis-Bacon Act WD # IL20260001 Modification 3 applies. The project scope involves relocating electrical service to where it can be used to install equipment per SOW RIPD-E4000-26-4-13. The contract includes a Product Service Code Y1BG and NAICS code 238210. Inspection and acceptance are delegated to W52H1B (Rock Island Arsenal – JMTC), with invoices submitted via Wide Area Workflow (WAWF) using specified DoDAAC codes. The solicitation incorporates comprehensive FAR and DFARS clauses covering wage determinations, Buy American requirements for construction materials, value engineering change proposals, contract administration, representations and certifications, and standard federal contracting requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 299_Diagram.png | PNG image | |
| Solicitation Amendment W519TC26RA0210001 SF 30.pdf | ||
| RIPD E4000-26-4-13 Building 299 Zone 8 Bus Relocations.docx | DOCX document | |
| 26-4-13 Quality Assurance Surveillance Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price
Amount
0001 Product Service Description: Sky Foundry B299 Electrical Relocation in accordance with Attachment 0001 RIPD: E4000-26-4-1 and Attachment 0002 26-4-13 QASP CLIN only - Requisition Document Number
(MILSTRIP, DLMS, FEDSTRIP):
W56DRX0012411659
Pricing Arrangement: Firm Fixed Price
1 Lot
W519TC26RA021
Section C - Description/Specifications/Statement of Work
SOLICITATION NARRATIVE
1. The Army Contracting Command - Rock Island (ACC-RI) hereby issues the solicitation, W519TC26RA021 for Sky Foundry B299 Electrical Relocation at the Rock Island Arsenal, Joint Manufacturing and Technology Center (RIA-JMTC). This solicitation is issued in accordance with Federal Acquisition Regulation (FAR) Part 36 (Construction and Architect - Engineer Contracts).
The Government intends to award one (1) Firm Fixed Price (FFP) Contract to the lowest price, responsive, and responsible contractor whose proposal conforms to the terms and conditions of the solicitation and represents the lowest total evaluated price. Contractors are responsible for providing their best price at the time of the proposal submission. Contractor's responsibility will be determined as outlined in FAR 9.104-1.
WAGE DETERMINATIONS
Davis-Bacon Act WD # IL20260001 Modification 3 applies to this action
2. The Government anticipates price competition, therefore, cost data is not required to be submitted with the offeror's proposal. However, the Government reserves the right to request cost data in the event price competition does not exist.
3. SITE VISIT INFORMATION
A pre-construction site visit is scheduled for 11:00AM Central Time on 2 April 2026, at Rock Island Arsenal -Joint Manufacturing and Technology Center (RIA-JMTC) with meeting Government representatives at the Northeast corner of Building 299, Rock Island Arsenal.
All attendees will be required to wear steel toed safety shoes, safety glasses. Reservations for this site visit are mandatory for all attendees at least three business days prior to the site visit. If you currently have badge access you still must make a reservation for the site visit in order for the government to control the number of attendees at any given time. You will not be allowed to attend without a reservation regardless of installation access.
POC for this action is Contract Specialist, John Jacobsen, at john.e.jacobsen16.civ@army.mil.
4. The following attachments are a part of this solicitation:
0001 RIPD E4000-26-4-13
0002 Quality Assurance Surveillance Plan (QASP)
0003 Site Visit Information
5. A Contracting Officer's Representative or a Performance Certified will be assigned to this action upon award.
6. PHOTOGRAPHIC EQUIPMENT RESTRICTIONS
There are restrictions on the use of photographic devices in all non-public areas of Arsenal Island.
This includes digital cameras, cell phones and PDAs with cameras. You must get permission to use any type of photographic device in any non-public area on Arsenal Island. All requests must be coordinated with the Contracting Officer's Representative (COR) or designated Contracting Officer for this effort prior to using any photographic device.
7. Army Contracting Command - Rock Island Government Point of Contact
Contract Specialist, John Jacobsen, john.e.jacobsen16.civ@army.mil
Contracting Officer, Sophia Muckenfuss, sophia.l.muckenfuss.civ@army.mil
END Solicitation Narrative
*** END OF NARRATIVE ***
Requirements B299 Electrical Relocation Electrical service will be relocated to where it can be used to install equipment per SOW RIPD-E4000-26-4-13
Product Service Code : Y1BG North American Industry Classification System (NAICS) : 238210
Section E - Inspection and Acceptance
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.246-12 Inspection of Construction. 1996-08
52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements.
1996-08
Overall Contract Inspection/Acceptance Locations
0001 Inspection and Acceptance Location
Both Destination Instructions: IAW RIPD and QASP
DoDAAC: W52H1B CountryCode: USA
W0K8 RIA INSTL STK REC ACCT
BLDG 299 GILLESPIE AV AND BECK LANE, ROCK ISLAND IL 61299-5000
ROCK ISLAND, IL 61299-5000
UNITED STATES
Section F - Deliveries or Performance
0001 Delivery Schedule From date of lead time event to completion of performance 150 Calendar Days
Date of Award 1 LotQuantity
Address and POC Place of Performance DoDAAC: W52H1B CountryCode: USA
W0K8 RIA INSTL STK REC ACCT
BLDG 299 GILLESPIE AV AND BECK LANE, ROCK ISLAND IL 61299-5000 ROCK
ISLAND, IL 61299-5000 UNITED STATES
Period of Performance From 01 May 2026 To 30 Sep 2026
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.247-34 F.o.b. Destination. 1991-01
Section G - Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.201-7000 Contracting Officer's Representative.
1991-12
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.
2018-12
252.236-7000 Modification Proposals--Price Breakdown.
1991-12
DFARS Clauses Incorporated by Full Text
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.232-7006 Wide Area WorkFlow Payment Instructions.
2023-01
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) Definitions. As used in this clause--
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.
sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items--
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
Invoice and Receiving Report (combo)
DO NOT SELECT FAST PAY AS THIS OPTION DELAYS ACCEPTANCE AND PAYMENT
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC HQ0303
Issue By DoDAAC W519TC
Admin DoDAAC** W519TC
Inspect By DoDAAC W52H1B
Ship To Code W52H1B
Ship From Code N/A
Mark For Code N/A
Service Approver (DoDAAC) N/A
Service Acceptor (DoDAAC) N/A
Accept at Other DoDAAC N/A
LPO DoDAAC N/A
DCAA Auditor DoDAAC N/A
Other DoDAAC(s) N/A
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) . The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.Receiving report
John.e.jacobsen16.civ@army.mil
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(h) Inspection and Acceptance is delegated to W52H1B - Rock Island Arsenal - Joint Manufacturing & Technology Center (RIA-JMTC).
Authorized Representatives
Mark Ashford Virginia Gooding Rene Robinson
Samuel Brewer Jeffrey Haynes Jami Roessler
Bryan Brittenham Scott Hoffmann
Lawrence Cruse David Holgorsen Nicholas Sallach
Lisa Digney Kyle Joffrion Rajesh Tummala
Sandra Duncan Raymond Jones Matthew Von Holdt
Nancy Ehrhardt Christian Maier Kynndel Wallarab
Thomas Eng Lorri McArthur Russel West
Nickolas Frere Chad McDaniel Richard White
Jennifer Mueller Lori Witte
Brandy Goettsch John Pingilley Scott Young
Cynthia Remaly Melissa Ramsden Paricha Young
Tim Roach Michael Rel
(End of clause)
Section I - Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.202-1 Definitions. 2020-06
52.203-3 Gratuities. 1984-04
52.203-6 Restrictions on Subcontractor Sales to the Government.
(Alternate I)
2020-06 Alternate I 2021-11
52.203-12 Limitation on Payments to Influence Certain Federal Transactions.
2020-06
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
2017-01
52.204-13 System for Award Management- Maintenance. (Deviation)
2026-02
52.204-19 Incorporation by Reference of Representations and Certifications.
2014-12
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Deviation)
2026-02
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.
2026-02
(Deviation)
52.212-4 Terms and Conditions- Commercial Products and Commercial Services. (Deviation)
2026-02
52.214-29 Order of Precedence-Sealed Bidding.
1986-01
52.219-8 Utilization of Small Business Concerns. (Deviation)
2026-02
52.222-3 Convict Labor. (Deviation) 2026-02
52.222-6 Construction Wage Rate Requirements. (Deviation)
2026-02
52.222-7 Withholding of Funds. (Deviation) 2026-02
52.222-8 Payrolls and Basic Records.
(Deviation)
2026-02
52.222-9 Apprentices and Trainees.
(Deviation)
2026-02
52.222-10 Compliance with Copeland Act Requirements. (Deviation)
2026-02
52.222-11 Subcontracts (Labor Standards).
(Deviation)
2026-02
52.222-12 Contract Termination-Debarment. 2014-05
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.
2014-05
52.222-14 Disputes Concerning Labor Standards. (Deviation)
2026-02
52.222-15 Certification of Eligibility. 2014-05
52.222-19 Child Labor-Cooperation with Authorities and Remedies.
(Deviation)
2026-02
52.222-35 Equal Opportunity for Veterans.
(Deviation)
2026-02
52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation)
2026-02
52.222-37 Employment Reports on Veterans. (Deviation)
2026-02
52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (Deviation)
2026-02
52.222-50 Combating Trafficking in Persons. (Deviation)
2026-02
52.222-54 Employment Eligibility Verification. (Deviation)
2026-02
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation)
2026-02
52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation)
2026-02
52.223-5 Pollution Prevention and Right-to- Know Information.
2024-05
52.223-23 Sustainable Products. (Deviation) 2026-02
52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.
2024-05
52.228-2 Additional Bond Security. 1997-10
52.228-5 Insurance-Work on a Government Installation.
1997-01
52.228-11 Individual Surety-Pledge of Assets.
2021-02
52.228-12 Prospective Subcontractor Requests for Bonds.
2022-12
52.228-14 Irrevocable Letter of Credit. 2014-11
52.228-15 Performance and Payment Bonds-Construction.
2020-06
52.229-3 Federal, State, and Local Taxes. 2013-02
52.229-12 Tax on Certain Foreign Procurements.
2021-02
52.232-17 Interest. 2014-05
52.232-23 Assignment of Claims. (Alternate I)
2014-05 Alternate I 1984-04
52.232-27 Prompt Payment for Construction Contracts.
2017-01
52.232-33 Payment by Electronic Funds Transfer-System for Award Management.
2018-10
52.232-39 Unenforceability of Unauthorized Obligations.
2013-06
52.232-40 Providing Accelerated Payments to Small Business Subcontractors.
2023-03
52.233-1 Disputes. (Deviation) 2026-02
52.233-3 Protest after Award. (Deviation) 2026-02
52.233-4 Applicable Law for Breach of Contract Claim. (Deviation)
2026-02
52.236-2 Differing Site Conditions.
(Deviation)
2026-02
52.236-3 Site Investigation and Conditions Affecting the Work. (Deviation)
2026-02
52.236-5 Material and Workmanship.
(Deviation)
2026-02
52.236-6 Superintendence by the Contractor. (Deviation)
2026-02
52.236-7 Permits and Responsibilities.
(Deviation)
2026-02
52.236-8 Other Contracts. (Deviation) 2026-02
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (Deviation)
2026-02
52.236-10 Operations and Storage Areas.
(Deviation)
2026-02
52.236-11 Use and Possession Prior to Completion. (Deviation)
2026-02
52.236-12 Cleaning Up. (Deviation) 2026-02
52.236-13 Accident Prevention. (Deviation) 2026-02
52.236-14 Availability and Use of Utility Services. (Deviation)
2026-02
52.236-15 Schedules for Construction Contracts. (Deviation)
2026-02
52.236-17 Layout of Work. (Deviation) 2026-02
52.236-21 Specifications and Drawings for Construction. (Deviation)
2026-02
52.240-91 Security Prohibitions and Exclusions. (Deviation)
2026-02
52.242-13 Bankruptcy. 1995-07
52.242-14 Suspension of Work. 1984-04
52.243-4 Changes. (Deviation) 2026-02
52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation)
2026-02
52.246-26 Reporting Nonconforming Items. 2024-08
52.249-10 Default (Fixed-Price Construction).
1984-04
DFARS Clauses Incorporated by Reference
Date
Alternate Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials.
2011-09
252.203-7002 Requirement to Inform Employees of Whistleblower
2022-12
Rights.
252.204-7003 Control of Government Personnel Work Product.
1992-04
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-
O0013 REVISION 1)
2024-05 Deviation 2024- O0013
2024-05
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
2023-01
252.204-7022 Expediting Contract Closeout. 2021-05
252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.
2019-05
252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials.
2014-09
252.223-7008 Prohibition of Hexavalent Chromium.
2023-01
252.225-7012 Preference for Certain Domestic Commodities.
2022-04
252.225-7048 Export-Controlled Items. 2013-06
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.
2023-01
252.225-7060 Prohibition on Certain Procurements from the Xinjiang
2023-06
Uyghur Autonomous Region.
252.226-7001 Utilization of Indian Organizations, Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns.
2023-01
252.232-7010 Levies on Contract Payments. 2006-12
252.243-7001 Pricing of Contract Modifications. 1991-12
252.243-7002 Requests for Equitable Adjustment.
2022-12
252.244-7001 Contractor Purchasing System Administration. (Alternate I)
2025-01 Alternate I 2025-01
252.246-7007 Contractor Counterfeit Electronic Part Detection and Avoidance System.
2023-01
252.246-7008 Sources of Electronic Parts. 2023-01
252.247-7023 Transportation of Supplies by Sea.
2024-10
FAR Clauses Incorporated by Full Text
Date
Alternate Deviation
Variation Effective Date
52.219-28 Postaward Small Business Program Rerepresentation.
(Deviation) (Alternate I)
2026-02 Alternate I 2026-02
Alternate I (Feb 2026) (Deviation). As prescribed in 19.101(a)(2)(iii)(B), substitute the following paragraph (g)(1) for paragraph (g)(1) of the basic clause:
(g)(1) The Contractor represents its small business size status for each one of the NAICS codes assigned to this contract.
NAICS Code Small business concern (yes/no) [Contracting Officer to insert NAICS codes.]
52.219-28 Postaward Small Business Program Rerepresentation.
(Deviation)
2026-02
Postaward Small Business Program Rerepresentation (Feb 2026) (Deviation)
(a) Definitions. As used in this clause-
Long-term contract means a contract of more than five years in duration, including options.
However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern-
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts-
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document /support--table-size-standards.
(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-
(1) Was set aside for small business and has a value above the simplified acquisition threshold;
(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the
Contractor waived the price evaluation preference; or
(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it [ ] is, [ ] is not a small business concern under ____NAICS Code assigned to ____contract number.
(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (g)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not, a small disadvantaged business concern as defined in 13 CFR 124.1001.
(3) Women-owned small business (WOSB) joint venture eligible under the WOSB Program. The Contractor represents that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]
(4) Economically disadvantaged women-owned small business (EDWOSB) joint venture. The Contractor represents that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __ .]
(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the SDVOSB Program. The Contractor represents that it [ ] is, [ ] is not an SDVOSB joint venture eligible under the SDVOSB Program that complies with the requirements of 13 CFR 128.402.
[____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]
(6) HUBZone joint venture eligible under the HUBZone Program.[ Complete only if the offeror is a HUBZone small business concern. ] The offeror represents, as part of its offer, that It [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [____Contractor to sign and date and insert authorized signer's name and title.]
52.225-9 Buy American-Construction Materials. (Deviation)
Buy American-Construction Materials (Feb 2026) (Deviation)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.
However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
none________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3) (i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)
(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars)* Item 1:
Foreign construction material. ____ ____ ____ Domestic construction material. ____ ____ ____
Item 2:
Foreign construction material. ____ ____ Domestic construction material. ____ ____ ____ [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.][Include other applicable supporting information.]
52.248-3 Value Engineering-Construction. 2025-10
Value Engineering-Construction (Oct 2025)
(a) General. The Contractor is encouraged to develop, prepare, and submit value engineering change proposals (VECP's) voluntarily. The Contractor shall share in any instant contract savings realized from accepted VECP's, in accordance with paragraph (f) of this clause.
(b) Definitions. "Collateral costs," as used in this clause, means agency costs of operation, maintenance, logistic support, or Government-furnished property.
Collateral savings, as used in this clause, means those measurable net reductions resulting from a VECP in the agency's overall projected collateral costs, exclusive of acquisition savings, whether or not the acquisition cost changes.
Contractor's development and implementation costs, as used in this clause, means those costs the Contractor incurs on a VECP specifically in developing, testing, preparing, and submitting the VECP, as well as those costs the Contractor incurs to make the contractual changes required by Government acceptance of a VECP.
Government costs, as used in this clause, means those agency costs that result directly from developing and implementing the VECP, such as any net increases in the cost of testing, operations, maintenance, and logistic support. The term does not include the normal administrative costs of processing the VECP.
Instant contract savings, as used in this clause, means the estimated reduction in Contractor cost of performance resulting from acceptance of the VECP, minus allowable Contractor's development and implementation costs, including subcontractors' development and implementation costs (see paragraph (h) of this clause).
Value engineering change proposal (VECP) means a proposal that-
(1) Requires a change to this, the instant contract, to implement; and
(2) Results in reducing the contract price or estimated cost without impairing essential functions or characteristics; provided, that it does not involve a change-
(i) In deliverable end item quantities only; or
(ii) To the contract type only.
(c) VECP preparation. As a minimum, the Contractor shall include in each VECP the information described in paragraphs (c)(1) through (7) of this clause. If the proposed change is affected by contractually required configuration management or similar procedures, the instructions in those procedures relating to format, identification, and priority assignment shall govern VECP preparation. The VECP shall include the following:
(1) A description of the difference between the existing contract requirement and that proposed, the comparative advantages and disadvantages of each, a justification when an item's function or characteristics are being altered, and the effect of the change on the end item's performance.
(2) A list and analysis of the contract requirements that must be changed if the VECP is accepted, including any suggested specification revisions.
(3) A separate, detailed cost estimate for (i) the affected portions of the existing contract requirement and (ii) the VECP. The cost reduction associated with the VECP shall take into account the Contractor's allowable development and implementation costs, including any amount attributable to subcontracts under paragraph (h) of this clause.
(4) A description and estimate of costs the Government may incur in implementing the VECP, such as test and evaluation and operating and support costs.
(5) A prediction of any effects the proposed change would have on collateral costs to the agency.
(6) A statement of the time by which a contract modification accepting the VECP must be issued in order to achieve the maximum cost reduction, noting any effect on the contract completion time or delivery schedule.
(7) Identification of any previous submissions of the VECP, including the dates submitted, the agencies and contract numbers involved, and previous Government actions, if known.
(d) Submission. The Contractor shall submit VECP's to the Resident Engineer at the worksite, with a copy to the Contracting Officer.
(e) Government action.
(1) The Contracting Officer will notify the Contractor of the status of the VECP within 45 calendar days after the contracting office receives it. If additional time is required, the Contracting Officer will notify the Contractor within the 45-day period and provide the reason for the delay and the expected date of the decision. The Government will process VECP's expeditiously; however, it will not be liable for any delay in acting upon a VECP.
(2) If the VECP is not accepted, the Contracting Officer will notify the Contractor in writing, explaining the reasons for rejection. The Contractor may withdraw any VECP, in whole or in part, at any time before it is accepted by the Government. The Contracting Officer may require that the Contractor provide written notification before undertaking significant expenditures for VECP effort.
(3) Any VECP may be accepted, in whole or in part, by the Contracting Officer's award of a modification to this contract citing this clause. The Contracting Officer may accept the VECP, even though an agreement on price reduction has not been reached, by issuing the Contractor a notice to proceed with the change. Until a notice to proceed is issued or a contract modification applies a VECP to this contract, the Contractor shall perform in accordance with the existing contract. The decision to accept or reject all or part of any VECP is a unilateral decision made solely at the discretion of the Contracting Officer.
(f) Sharing-
(1) Rates. The Government's share of savings is determined by subtracting Government costs from instant contract savings and multiplying the result by-
(i) 45 percent for fixed-price contracts; or
(ii) 75 percent for cost-reimbursement contracts.
(2) Payment. Payment of any share due the Contractor for use of a VECP on this contract shall be authorized by a modification to this contract to-
(i) Accept the VECP;
(ii) Reduce the contract price or estimated cost by the amount of instant contract savings; and
(iii) Provide the Contractor's share of savings by adding the amount calculated to the contract price or fee.
(g) Collateral savings. If a VECP is accepted, the Contracting Officer will increase the instant contract amount by 20 percent of any projected collateral savings determined to be realized in a typical year of use after subtracting any Government costs not previously offset. However, the Contractor's share of collateral savings will not exceed the contract's firm-fixed-price or estimated cost, at the time the VECP is accepted, or $100,000, whichever is greater. The Contracting Officer is the sole determiner of the amount of collateral savings.
(h) Subcontracts. The Contractor shall include an appropriate value engineering clause in any subcontract of $90,000 or more and may include one in subcontracts of lesser value. In computing any adjustment in this contract's price under paragraph (f) of this clause, the Contractor's allowable development and implementation costs shall include any subcontractor's allowable development and implementation costs clearly resulting from a VECP accepted by the Government under this contract, but shall exclude any value engineering incentive payments to a subcontractor. The Contractor may choose any arrangement for subcontractor value engineering incentive payments; provided, that these payments shall not reduce the Government's share of the savings resulting from the VECP.
(i) Data. The Contractor may restrict the Government's right to use any part of a VECP or the supporting data by marking the following legend on the affected parts:
These data, furnished under the Value Engineering-Construction clause of contract ____, shall not be disclosed outside the Government or duplicated, used, or disclosed, in whole or in part, for any purpose other than to evaluate a value engineering change proposal submitted under the clause. This restriction does not limit the Government's right to use information contained in these data if it has been obtained or is otherwise available from the Contractor or from another source without limitations.
If a VECP is accepted, the Contractor hereby grants the Government unlimited rights in the VECP and supporting data, except that, with respect to data qualifying and submitted as limited rights technical data, the Government shall have the rights specified in the contract modification implementing the VECP and shall appropriately mark…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .