Solicitation - W50S6T26QA034.pdf
PDF 1 MB Posted
- Attached to
- HVAC Replacement BLDG 122
- Solicitation number
- W50S6T26QA034
- Issued by
-
Department of the Army National Guard
About this file
This is a Request for Quote (RFQ) for HVAC replacement services at Building 122, Fresno Air National Guard Base, California.
The California Air National Guard seeks a firm fixed price contract for complete HVAC unit replacement at Building 122 (SFS) located at Fresno Air National Guard Base. The requirement magnitude falls between $200,000 and $350,000. The solicitation is set-aside for Total Small Business under NAICS code 238220 (Plumbing, Heating, and Air-Conditioning Contractors) with a $19.0 million size standard. The contractor must provide all plant, labor, new materials, transportation, tools, equipment, appliances, insurance, and supervision necessary to complete the work. Performance must commence within 10 calendar days of receiving the Notice to Proceed and be completed within 90 calendar days. Quotes are due by 3:00 PM PDT on September 24, 2026, and must be submitted electronically to jarrod.sanchez@us.af.mil and justin.scales.1@us.af.mil. An organized site visit is scheduled for September 17, 2026, at 9:00 AM PDT at Fresno Air National Guard Base, West Gate (5323 E. McKinley Avenue, Fresno, CA 93727). The Government intends to award to the lowest priced responsive and responsible quoter. Performance and payment bonds are required within 10 calendar days of award. An offer guarantee is required. Construction wage rates per Davis-Bacon Act apply (CA20260018, dated September 3, 2026, for Fresno County). Payment will be made through WAWF in accordance with FAR clauses 52.232-5 and 52.232-27, with invoices submitted in duplicate to the Contracting Office for pre-approval before electronic submission.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
W50S6T26QA034 09 SEP 2026 1 61
HAYW262020
W7MX USPFO ACTIVITY CAANG 144
KO FOR CAANG DO NOT DELETE, 5323 E MCKINLEY FRESNO ANGB
FRESNO, CA 93727-2199
UNITED STATES
JARROD SANCHEZ, EMAIL: JARROD.SANCHEZ@US.AF.MIL TELEPHONE: 559-454-
W50S6T
W7MX USPFO ACTIVITY CAANG 144
KO FOR CAANG DO NOT DELETE, 5323 E MCKINLEY FRESNO ANGB
FRESNO, CA 93727-2199
UNITED STATES
JARROD SANCHEZ 559-454-5129
PROJECT TITLE: HVAC BLDG.122 REPLACEMENT SFS
PROJECT LOCATION: F6W3CE
PROJECT: HAYW262020 - HVAC BLDG.122 REPLACEMENT SFS
THE MAGNITUDE OF THIS REQUIREMENT IS BETWEEN $200,000 AND $350,000.
NOTICE TO QUOTERS: THIS EFFORT IS A HIGH-PRIORITY REQUIREMENT IN SUPPORT OF THE NATIONAL GUARD. FUNDS ARE NOT PRESENTLY AVAILABLE TO MAKE AWARD. IF FUNDS BECOME AVAILABLE FOR AWARD AND PRICES ARE DEEMED FAIR AND REASONABLE, IT IS THE GOVERNMENT’S INTENT TO MAKE AWARD.
THIS IS NOT A COMMITMENT OF FUNDS OR CONTRACT AWARD.
10 90
FAR 52.211-10
03:00 PM
24 SEP 2026
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section A - Solicitation/Contract Form
HVAC BLDG 122 Replacement SFSInstrument Name:
Product Service Code : K041
W50S6T26QA034
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quanti ty
Unit Unit Price Amount
0001 HVAC replacement at building 122 (SFS) in accordance with the Statement of Work (SOW). The contractor shall provide all plant, labor, new material, transportation, tools, equipment, appliances, insurance, and supervision necessary to performance construction per the incorporated
SOW.
Product Service Code: K041
North American Industry Classification System (NAICS):
238220
Pricing Arrangement: Firm Fixed Price
1 Job
Section C - Description/Specifications/Statement of Work
Requirements Replacement of HVAC Units at BLDG 122
Section E - Inspection and Acceptance
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.246-12 Inspection of Construction. 1996-08
Overall Contract Inspection/Acceptance Locations
0001 Inspection and Acceptance Location
Both Destination Instructions: Inspect and accept in accordance with the statement of work (SOW).
DoDAAC: F6W3CE CountryCode: USA
CIVIL ENG
AF BPN NO MILSBILLS PROCESSES, 5323 E. MCKINLEY AVE BLDG 125
FRESNO, CA 93727-2199
UNITED STATES
Benjamin Camarena
Section F - Deliveries or Performance
0001 Delivery Schedule From date of lead time event to completion of performance 90 Calendar Days
Date of Notice to Proceed Receipt 1 JobQuantity
Address and POC Place of Performance DoDAAC: F6W3CE CountryCode: USA
CIVIL ENG
AF BPN NO MILSBILLS PROCESSES, 5323 E. MCKINLEY AVE BLDG 125 FRESNO,
CA 93727-2199 UNITED STATES
Section G - Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.201-7000 Contracting Officer's Representative.
1991-12
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.
2018-12
252.236-7000 Modification Proposals--Price Breakdown.
1991-12
DFARS Clauses Incorporated by Full Text
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.232-7006 Wide Area WorkFlow Payment Instructions.
2023-01
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) As used in this clause- Definitions.
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) The WAWF system provides the method to electronically process Electronic invoicing.
vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) To access WAWF, the Contractor shall- WAWF access.
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) The Contractor should follow the training instructions of the WAWF WAWF training.
Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/
(e) Document submissions may be via web WAWF methods of document submission.
entry, Electronic Data Interchange, or File Transfer Protocol.
(f) The Contractor shall use the following information when WAWF payment instructions.
submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) The Contractor shall submit payment requests using the following Document type.
document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items-
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
Not Applicable
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
INVOICE 2-IN-1 (SERVICES ONLY)
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) The Contractor shall use the information in the Routing Data Document routing.
Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC F87700
Issue By DoDAAC W50S6T
Admin DoDAAC W50S6T
Inspect By DoDAAC
NA
Ship To Code
NA
NA
Ship From Code
Mark For Code
NA
Service Approver (DoDAAC)
F6W3CE
Service Acceptor (DoDAAC)
F6W3CE
Accept at Other DoDAAC
NA
LPO DoDAAC
NA
DCAA Auditor DoDAAC
NA
Other DoDAAC(s)
NA
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) The Contractor shall ensure a receiving report meets the Receiving report.
requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
arthur.galindo.1@us.af.mil;
juan.oyervidez@us.af.mil;
nathaniel.cardenas_lozano.2@us.af.mil;
jarrod.sanchez@us.af.mil
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section H - Special Contract Requirements
1.0 INSURANCE - MINIMUM AMOUNTS
1.1 Reference Contract Clause titled, "Insurance -Work on a Government Installation (FAR 52.228- 5). Types and minimum amounts are as follows:
TYPE AMOUNTS
Workmen's Compensation $100,000* (see paragraph 1.2, below)
Comprehensive General Liability $500,000 per occurrence for bodily injury
Comprehensive Automobile Liability $200,000 per person and $500,000 per accident for bodily injury and $20,000 for property damage
1.2 *Except in states with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.
1.3 NOTE: Before commencing work under this contract, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained. The policies referenced in the certification (s) shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer. The Contractor shall maintain a copy of proofs of required insurance, and shall make copies available to the Contracting Officer upon request. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance, and shall make copies available to the Contracting Officer upon request.
2.0 INVOICING AND PAYMENT
2.1 Properly prepared invoices, bearing the contract number, shall be submitted in duplicate to the Contracting Office, on any designated invoice forms provided at the pre-construction meeting PRIOR to uploading in Wide Area Workflow (WAWF). This submission will be for review prior to submitting an electronic invoice through Wide Area Workflow (WAWF). Payment will be made by in accordance with FAR clause 52.232-5 Fixed-Price Construction Contracts and FAR clause
52.232-27, Prompt Payment for Construction Contracts, all payments will be made by electronic transfer of funds (EFT).
2.1 To meet compliance with DFARS 252.232-7003, Electronic Submission of Payment Requests, you shall submit your request for payment (invoice) through WAWF. For more information on the WAWF system, including how to register, visit https://piee.eb.mil. Payment will be made by paying office specified in the contract award in accordance with the clauses Payments under Fixed-Price Construction Contracts, FAR 52.232-5, and Prompt Payment for Construction Contracts, FAR 52.232-27.
2.2 The Government will make payment through WAWF upon satisfactory completion of work AND receipt of a proper certification for payment. Do not input invoice into WAWF until the pre-approval of invoice is received from the Contracting Officer. This will lessen the need for rejections in WAWF. Payment may be withheld unless all contractual requirements have been timely received (including but not limited to): RECEIPT OF PROPER WEEKLY PAYROLLS IAW CONSTRUCTION WAGE REQUIREMENTS, DD 1354, Waste Tickets, etc. Payrolls shall indicate CLIN to which they are applicable.
2.3 All requests for payments through WAWF must include a Subcontractor Payment Register pursuant to FAR Clause 52.232-5 and a contractor's certification that reads as follows:
I hereby certify, to the best of my knowledge and belief that - The amounts requested are only for performance in accordance with the specifications, terms and conditions of the contract;
All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and requirements of Chapter 39 of Title 31, United States Code; This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from subcontractor or supplier in accordance with the terms and conditions of the subcontract; and This certification is not to be construed as final acceptance of a subcontractor's performance.
2.4 A release of claims is required for all final payment requests and shall be submitted by the contractor with the final invoice.
*** END OF NARRATIVE 1 ***
Section I - Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.203-12 Limitation on Payments to Influence Certain Federal Transactions.
2020-06
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
2017-01
52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)
2026-02
52.204-19 Incorporation by Reference of Representations and Certifications.
2014-12
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Deviation 2026- O0038)
2026-02
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.
(Deviation 2026-O0038)
2026-02
52.212-4 Terms and Conditions- Commercial Products and Commercial Services. (Deviation 2026-O0038)
2026-02
52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)
2026-02
52.222-3 Convict Labor. (Deviation 2026- O0038)
2026-02
52.222-6 Construction Wage Rate Requirements. (Deviation 2026- O0038)
2026-02
52.222-7 Withholding of Funds. (Deviation 2026-O0038)
2026-02
52.222-8 Payrolls and Basic Records.
(Deviation 2026-O0038)
2026-02
52.222-9 Apprentices and Trainees.
(Deviation 2026-O0038)
2026-02
52.222-10 Compliance with Copeland Act Requirements. (Deviation 2026- O0038)
2026-02
52.222-11 Subcontracts (Labor Standards).
(Deviation 2026-O0038)
2026-02
52.222-12 Contract Termination-Debarment. 2014-05
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.
2014-05
52.222-14 Disputes Concerning Labor Standards. (Deviation 2026- O0038)
2026-02
52.222-15 Certification of Eligibility. 2014-05
52.222-35 Equal Opportunity for Veterans.
(Deviation 2026-O0038)
2026-02
52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)
2026-02
52.222-37 Employment Reports on Veterans. (Deviation 2026- O0038)
2026-02
52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)
2026-02
52.222-54 Employment Eligibility Verification. (Deviation 2026- O0038)
2026-02
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)
2026-02
52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)
2026-02
52.222-90 Addressing DEI Discrimination by Federal Contractors.
(Deviation 2026-O0040, Revision 1)
2026-04
52.223-5 Pollution Prevention and Right-to- Know Information.
2024-05
52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners.
(Deviation 2026-O0038)
2026-02
52.226-8 Encouraging Contractor Policies 2024-05 to Ban Text Messaging While Driving.
52.228-2 Additional Bond Security. 1997-10
52.228-5 Insurance-Work on a Government Installation.
1997-01
52.228-11 Individual Surety-Pledge of Assets.
2021-02
52.228-14 Irrevocable Letter of Credit. 2014-11
52.228-15 Performance and Payment Bonds-Construction.
2020-06
52.232-23 Assignment of Claims. 2014-05
52.232-27 Prompt Payment for Construction Contracts.
2017-01
52.232-33 Payment by Electronic Funds Transfer-System for Award Management.
2018-10
52.232-39 Unenforceability of Unauthorized Obligations.
2013-06
52.232-40 Providing Accelerated Payments to Small Business Subcontractors.
2023-03
52.233-1 Disputes. (Deviation 2026- O0038)
2026-02
52.233-3 Protest after Award. (Deviation 2026-O0038)
2026-02
52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026-
2026-02
O0038)
52.236-2 Differing Site Conditions.
(Deviation 2026-O0038)
2026-02
52.236-3 Site Investigation and Conditions Affecting the Work. (Deviation 2026-O0038)
2026-02
52.236-5 Material and Workmanship.
(Deviation 2026-O0038)
2026-02
52.236-6 Superintendence by the Contractor. (Deviation 2026- O0038)
2026-02
52.236-7 Permits and Responsibilities.
(Deviation 2026-O0038)
2026-02
52.236-8 Other Contracts. (Deviation 2026- O0038)
2026-02
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (Deviation 2026-O0038)
2026-02
52.236-10 Operations and Storage Areas.
(Deviation 2026-O0038)
2026-02
52.236-11 Use and Possession Prior to Completion. (Deviation 2026- O0038)
2026-02
52.236-12 Cleaning Up. (Deviation 2026- O0038)
2026-02
52.236-13 Accident Prevention. (Deviation 2026-O0038)
2026-02
52.236-14 Availability and Use of Utility Services. (Deviation 2026-O0038)
2026-02
52.236-17 Layout of Work. (Deviation 2026- O0038)
2026-02
52.236-21 Specifications and Drawings for Construction. (Deviation 2026- O0038)
2026-02
52.240-91 Security Prohibitions and Exclusions. (Deviation 2026- O0038)
2026-02
52.240-93 Basic Safeguarding of Covered Contractor Information Systems.
(Deviation 2026-O0038)
2026-02
52.242-14 Suspension of Work. 1984-04
52.243-5 Changes and Changed Conditions. (Deviation 2026- O0038)
2026-02
52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)
2026-04
52.246-21 Warranty of Construction. 1994-03
52.249-10 Default (Fixed-Price Construction).
1984-04
52.253-1 Computer Generated Forms.
2026-02
DFARS Clauses Incorporated by Reference
Alternate Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials.
2011-09
252.203-7002 Requirement to Inform Employees of Whistleblower Rights.
2022-12
252.204-7000 Disclosure of Information. 2016-10
252.204-7003 Control of Government Personnel Work Product.
1992-04
252.204-7004 Antiterrorism Awareness Training for Contractors.
2023-01
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting.
2024-05
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
2023-01
252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.
2019-05
252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials.
2014-09
252.223-7008 Prohibition of Hexavalent Chromium.
2023-01
252.225-7012 Preference for Certain Domestic Commodities.
2022-04
252.225-7048 Export-Controlled Items. 2013-06
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.
2023-01
252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.
2023-06
252.232-7010 Levies on Contract Payments. 2006-12
252.233-7001 Choice of Law (Overseas). 1997-06
252.243-7001 Pricing of Contract Modifications. 1991-12
252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations.
2010-10
252.246-7007 Contractor Counterfeit Electronic Part Detection and Avoidance System.
2023-01
252.246-7008 Sources of Electronic Parts. 2023-01
252.247-7023 Transportation of Supplies by Sea.
2024-10
FAR Clauses Incorporated by Full Text
Date
Alternate Deviation
Variation Effective Date
52.219-28 Postaward Small Business Program Rerepresentation.
Postaward Small Business Program Rerepresentation (Feb 2026) (Deviation 2026-O0038)
(a) Definitions. As used in this clause-
Long-term contract means a contract of more than five years in duration, including options.
However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern-
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts-
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document /support--table-size-standards.
(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-
(1) Was set aside for small business and has a value above the simplified acquisition threshold;
(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or
(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it [ ] is, [ ] is not a small business concern under ____NAICS Code assigned to ____contract number.
(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (g)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not, a small disadvantaged business concern as defined in 13 CFR 124.1001.
(3) Women-owned small business (WOSB) joint venture eligible under the WOSB Program. The Contractor represents that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]
(4) Economically disadvantaged women-owned small business (EDWOSB) joint venture. The Contractor represents that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __ .]
(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the SDVOSB Program. The Contractor represents that it [ ] is, [ ] is not an SDVOSB joint venture eligible under the SDVOSB Program that complies with the requirements of 13 CFR 128.402.
[____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]
(6) HUBZone joint venture eligible under the HUBZone Program.[ Complete only if the offeror is a HUBZone small business concern. ] The offeror represents, as part of its offer, that It [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [____The Contractor shall enter the name and unique entity identifier of each party to the joint venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [____Contractor to sign and date and insert authorized signer's name and title.]
52.223-11 Ozone-Depleting Substances.
Ozone-Depleting Substances (Feb 2026) (Deviation 2026-O0038)
(a) Definition. As used in this clause-
Ozone-depleting substance means any substance the Environmental Protection Agency designates in 40 CFR part 82 as-
(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform; or
(2) Class II, including, but not limited to, hydrochlorofluorocarbons.
(b) Requirement. In accordance with 40 CFR 82.84(a)(5), the Contractor shall label products that contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j(b), (c), (d), and (e) and 40 CFR part 82, subpart E, as follows:
Warning: Contains (or manufactured with, if applicable) *____, a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.
* The Contractor shall insert the name of the substance(s).
52.225-9 Buy American-Construction Materials. (Deviation 2026- O0038)
2026-02
Buy American-Construction Materials (Feb 2026) (Deviation 2026-O0038)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.
However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States.
Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
____________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United
States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3) (i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)
(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute or Balance of Payments Program.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars)* Item 1:
Foreign construction material. ____ ____ ____ Domestic construction material. ____ ____ ____
Item 2:
Foreign construction material. ____ ____ Domestic construction material. ____ ____ ____ [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.][Include other applicable supporting information.]
52.232-5 Payments under Fixed-Price Construction Contracts.
2014-05
Payments under Fixed-Price Construction Contracts (May 2014)
(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.
(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.
(1) The Contractor's request for progress payments shall include the following substantiation:
(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.
(ii) A listing of the amount included for work performed by each subcontractor under the contract.
(iii) A listing of the total amount of each subcontract under the contract.
(iv) A listing of the amounts previously paid to each such subcontractor under the contract.
(v) Additional supporting data in a form and detail required by the Contracting Officer.
(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-
(i) Consideration is specifically authorized by this contract; and
(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.
(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)
I hereby certify, to the best of my knowledge and belief, that-
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
____ (Name)
____ (Title)
____ (Date)
(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-
(1) Notify the Contracting Officer of such performance deficiency; and
(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-
(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or
(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.
(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.
(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-
(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or
(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.
(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.
(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).
(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .