Solicitation 47PG0121R0006.pdf
PDF 5 MB Posted
- Attached to
- Operations and Mechanical Maintenance Services - Hruska Courthouse and Zorinsky Federal Building - Omaha, NE
- Solicitation number
- 47PG0121R0006
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation 47PG0121R0006 Amendment 2.pdf | ||
| Pricing Spreadsheet Hruska Zorinsky - Amendment 1.xlsx | XLSX spreadsheet | |
| Solicitation 47PG0121R0006 Amendment 1.pdf | ||
| 47PG0121R0006 - M.9 Proposal Matrix.xlsx | XLSX spreadsheet | |
| Pricing Spreadsheet Hruska Zorinsky - New Combined BID Sheet Tab.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATION AND BID FORMS
OPERATIONS AND MECHANICAL MAINTENANCE SERVICES
Roman L. Hruska U.S. Courthouse
111 S.18TH Plz
Omaha, Nebraska 68102
And
Edward Zorinsky Federal Building
1616 Capitol Ave.
Omaha, Nebraska 68102
Solicitation Number: 47PG0121R0006
Solicitation Issue Date: April 2, 2021
Questions Submission Deadline: April 23, 2021 @ 3:00PM CDT
Quote Submission Deadline: May 14, 2021 @ 3:00PM CDT
Period of Performance: August 1, 2021 through March 31, 2022 (8 month base period, with 4, one year option periods available)
1. Base Period: 8/1/2021 – 3/31/2022
2. Option I: 4/1/2022 – 3/31/2023
3. Option II: 4/1/2023 – 3/31/2024
4. Option III: 4/1/2024 – 3/31/2025
5. Option IV: 4/1/2025 – 3/31/2026
TOTAL SET-ASIDE: 100% Set-Aside for Service Disabled Veteran Owned Small
Businesses
Brief Description and Location of Work: The Contractor must provide all administration, management, supervision, labor, materials, supplies, repair parts, tools and equipment; and must plan, schedule, coordinate, inspect and ensure effective and economical completion of all
Solicitation 47PG0121R00061 of 291 work and services specified for the operation, maintenance and repair of the building(s), equipment and related services specified in this contract for the Roman L. Hruska U.S.
Courthouse and Edward Zorinsky Federal Buildings and all equipment, electrical and mechanical systems, structures, architectural finishes, and utilities, located on, within, or beneath, this facility’s interior and exterior extending to the legal property line, except as otherwise noted for the Zorinsky Building in section C.2.21. Elevator Maintenance Services are excluded from the scope of work. Subcontracting for qualified Fire Alarm maintenance and
Remote Monitoring services and 3rd party Pressure Vessel and Roof Anchor. PM Inspections are required of the O&M contractor
Solicitation 47PG0121R00062 of 291
NOTICE CONCERNING SOLICITATION
NAICS CODE: 561210, Facilities Support Services
SBA SIZE STANDARD: $41.5 million
TOTAL SET-ASIDE FOR SERVICE DISABLED VETERAN OWNED SMALL BUSINESSES
GENERAL SERVICES ADMINISTRATION’S MISSION
“The mission of GSA is to deliver the best value in real estate, acquisition, and technology services to government and the American people.”
PERFORMANCE BASED SPECIFICATION
This is a performance-based solicitation. The Government’s requirements are expressed in the form of the minimum quality standard to be met. The Contractor is to determine the optimal work schedule, resource allocations and performance methods. Therefore, it is strongly advised that you review the complete solicitation so that you are aware of all the terms and conditions.
SHALL vs. MUST
Throughout this solicitation, the terms “shall” and “must” are used. “shall” and “must” denote the imperative. They indicate an obligation to act. In this solicitation, and any resulting contract, “shall” and “must” have the same meaning.
SITE VISIT
Offerors are encouraged to attend a site visit at each location. Due to COVID-19 constraints/precautions, tours will be given on first call, first served basis. Offerors must contact
Terry Morgan at terry.morgan@gsa.gov and Tim Ronan at tim.ronan@gsa.gov in advance to confirm your attendance at one of the scheduled tours. No tours will be held at individual requests and those not on the pre-approved participant list will not be able to attend. Tours are only available at the dates and times stated below. Offerors must retain form (M.10) after the site visit and return the original signed form with technical proposal.
Due to COVID-19 conditions, please note the following precautionary measures:
(a) Site Visit tours are limited to a total of 10 participants. Offerors must be on the pre-approved list in order to attend (first call, first-served basis).
(b) All participants MUST bring their own face mask in order to participate in the tour.
(c) Face masks must be worn at all times during the tour.
(d) Participants are encouraged to practice social distancing as practicable during the tour.
(e) Participants are subject to a COVID Health Questionnaire (may be written or verbal) immediately prior to the tour.
Solicitation 47PG0121R00063 of 291
Tours will be available on April 13, 2021 beginning at 8:00am CDT and on April 14, 2021 beginning at 8:00AM CDT. Tours will begin at the Roman L. Hruska U.S. Courthouse. The
Offerors must determine any conditions that affect the work and make a thorough site investigation before submitting an offer.
ACQUISITION BUDGET
The annual budgeted amount for this acquisition at the Roman L. Hruska U.S. Courthouse has been established at $352,000 - $430,000 per year. The annual budgeted amount for this acquisition at the Edward Zorinsky Federal Building has been established at $382,000 -
$467,000 per year.
Interested vendors: The budgeted amount provided is for your informational purposes only.
Offerors are not precluded from submitting a price that is outside the budgeted range provided by the government, nor is the government precluded from making an award which is outside the budgeted range. Offerors are to submit a competitive price that is commensurate with the requirements of the contract, which can be higher or lower than the budget range provided by the government. The budget range is being provided in an effort to assist you in formulating solutions that meet our requirements and our budget.
*The budgeted amount includes only what is described in the solicitation as “standard services,” which will be included in your proposed monthly price. All “above standard services” or
“additional service CLINs” are not included in the government-developed budget range.
Solicitation 47PG0121R00064 of 291
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ IFB RFP
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF. OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NAICS:
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8 (A)
EDWOSB
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
Solicitation 47PG0121R00065 of 291
Table of Contents
SECTION B SUPPLIES OR SERVICES PRICES/COSTS
SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Subsection 1: General Contract Requirements
C.1.0 General
C.1.1 Scope of Work
C.1.1.1 Discrepancy in the Specifications
C.1.2 Personnel (Staffing Plan)
C.1.2.1 Contractor Key Personnel
C.1.2.2 Authority
C.1.2.3 Communication Equipment
C.1.2.3.1 CIO 2100 IT Security Policy
C.1.2.4 Language
C.1.2.5 Employee Suitability
C.1.2.6 Employee Technical Qualifications
C.1.2.7 Certifications
C.1.2.7.1 Qualifications of Fire Alarm System Technicians
C.1.2.7.2 Qualifications of Water-Based Fire Suppression System Technicians
C.1.2.7.3 Qualifications of [Dry Chemical Extinguishing System], [Wet
Chemical Extinguishing System]; [Clean Agent Fire Extinguishing System];
[Halogenated Extinguishing System]; [Carbon Dioxide Extinguishing System];
[Ventilation System Fire Extinguishing System]; [Smoke Control]; [Fire
Damper]; [Smoke Damper]; [Combination Fire/Smoke Damper]; [Fire-rated
Door Assemblies]; [Smoke Door Assemblies]; [Portable Fire Extinguisher];
[Emergency and Standby Power]; [Emergency Lighting Equipment]; [Exit
Signage] Technicians
C.1.2.7.4 Qualifications for Electrical Technician
C.1.2.7.5 Qualifications for BAS Technician
C.1.2.7.6 Qualifications for BAS Operators and Programmers, EMCS, AMS, and
DALI Technicians
C.1.2.8 Employee Training
Solicitation 47PG0121R00066 of 291
C.1.2.8.1 Asbestos Awareness Training
C.1.2.8.2 Re-Tuning Training
C.1.2.8.3 Education Requirements and Certifications
C.1.2.8.4 NCMMS Training
C.1.2.8.5 Smart and Sustainable Buildings (SSB) Training)
C.1.2.8.6 Lead Awareness Training
C.1.2.9 Appearance
C.1.2.10 Standards of Conduct
C.1.2.11 Recording Presence
C.1.2.12 Personal Identity Verification Requirements
C.1.2.13 Credentials and Identification
C.1.2.14 Escorting
C.1.3 Quality Control Program
C.1.3.1 Quality Control Plan
C.1.3.2 Quality Control Plan Contents
C.1.3.2.1 Inspection Program
C.1.3.2.2 Methods
C.1.4 Quality Assurance
C.1.4.1 Contracting Officer's Representative (COR)
C.1.4.2 Government Monitoring
C.1.4.3 Performance Evaluations
C.1.5 Physical Security
C.1.5.1 Key Control
C.1.5.2 Lock Combinations
C.1.6 Safeguarding Sensitive Data and Information Technology Resources
C.1.6.1 General
C.1.6.2 Safeguarding and Dissemination of Controlled Unclassified Information39
C.1.6.2.1 General
C.1.6.2.2 Marking CUI
C.1.6.2.3 Authorized Recipients
Solicitation 47PG0121R00067 of 291
C.1.6.2.4.1 Electronic Transmission
C.1.6.2.4.2 Non-electronic Form or on Portable Electronic Data Storage
Devices
C.1.6.2.4.2.1 Mail
C.1.6.2.4.2.2 In-Person
C.1.6.2.5 Record Keeping
C.1.6.2.6 Safeguarding CUI Documents
C.1.6.2.7 Destroying CUI Building Information
C.1.6.2.8 Notice of Disposal
C.1.6.2.9 Incidents
C.1.6.2.10 Subcontracts
C.1.7 Hours of Operation
C.1.7.1 Normal Working Hours
C.1.7.2 Core Coverage Hours
C.1.7.3 Recognized Holidays
C.1.7.4 Extended Operating Hours: Reserved
C.1.7.5 Building Access
C.1.8 Conservation of Utilities
C.1.9 Use of NCMMS
C.1.9.1 General
C.1.9.2 Operations
C.1.9.3 Reporting
C.1.10 Documentation and Records
C.1.11 Ordinances, Taxes, Permits, and Licenses
C.1.12 Other Contractors
C.1.13 Government Forms
C.1.14 Contractor Maintenance Performance Plans
Subsection 2: Definitions
C.2.0 General
C.2.1 Above-Standard Services
C.2.2 Acceptance
Solicitation 47PG0121R00068 of 291
C.2.3 Accident
C.2.4 Action Plan
C.2.5 Acts of God
C.2.6 Additional Services
C.2.7 Advanced Meters
C.2.8 Advanced Metering Systems
C.2.9 Annual Child Care Facility Survey
C.2.10 Architectural and Structural
C.2.11 Basic Services
C.2.12 Building Automation System (BAS)
C.2.13 Building Operating Plan
C.2.14 Cooling Season
C.2.15 Consumable Parts
C.2.16 Contracting Officer (CO)
C.2.17 Contracting Officer's Representative (COR)
C.2.18 Contractor
C.2.19 Core Coverage Hours
C.2.20 Corrective Maintenance
C.2.21 Demand Response Program
C.2.22 Emergency Callback
C.2.23 Environmentally Sustainable Products and Services
C.2.24 Exterior
C.2.25 Facilities Engineering
C.2.26 Fire Protection and Life Safety Systems
C.2.27 GSAlink
C.2.28 Green Procurement Compilation (GPC)
C.2.30 Indefinite Quantity
C.2.31 Initial Deficiency Report
C.2.32 Modification of Contract
C.2.34 Negligence
Solicitation 47PG0121R00069 of 291
C.2.35 Non-Reimbursable Repairs
C.2.36 Normal Working Hours
C.2.37 Occupant Emergency Plan (OEP)
C.2.38 Ongoing Commissioning
C.2.39 Open Protocol Systems
C.2.40 Operations
C.2.41 Overtime Utilities
C.2.42 Partnering
C.2.43 Performance Based Work Statement (PBWS)
C.2.44 Predictive Maintenance
C.2.45 Preventive Maintenance
C.2.46 Quality Assurance Surveillance Plan (QASP)
C.2.47 Quality Control Plan
C.2.48 Rapid Building Assessment Program
C.2.49 Repair
C.2.50 Reimbursable Repair
C.2.51 Systems Thinking
C.2.52 Tour
C.2.53 Vertical Transportation Systems
C.2.54 Watch
C.2.55 Work Order
Subsection 3: Government-Furnished Property
C.3.0 General
C.3.1 Electric Power
C.3.2 Water Source
C.3.3 Contractor Office Space and Furnishings
C.3.4 Storage Space
C.3.5 Network Equipment and Computer Hardware
C.3.6 Government Furnished Equipment: RESERVED
Subsection 4: Contractor-Furnished Property Supplies/Materials/Equipment
Solicitation 47PG0121R000610 of 291
C.4.0 General
Subsection 5: Operations-specific Requirements
C.5.0 General
C.5.1 Tenant Environment
C.5.1.1 Tenant Furniture
C.5.2 Building Operating Plan
C.5.2.1 Components of the Building Operating Plan
C.5.3 Equipment Inventory
C.5.3.1 General:
C.5.3.2 Operations
C.5.3.3 Reporting
C.5.4 Safety Management
C.5.4.1 General
C.5.4.2 Workplace Safety and Health Program
C.5.4.2.1 Reporting
C.5.4.3 Scheduling and Record Keeping
C.5.4.3.1 Reporting
C.5.4.4 Fall Protection
C.5.4.5 Powered Platforms
C.5.4.6 Lock Out/Tag Out
C.5.4.7 Permit-Required Confined Spaces
C.5.4.8 Facility Hazards and Accidents
C.5.4.8.1 Hazards
C.5.4.8.1.1 Respiratory Protection
C.5.4.8.2 Accidents
C.5.4.9 Disruptive or Hazardous Equipment
C.5.4.9.1 Tools
C.5.4.9.2 Hooks, Cranes, Hoists Chains and Slings
C.5.4.10 Scheduled Disruption to Utilities, Lighting, Fire Protection & Life Safety
Systems, or Space Conditioning
C.5.4.11 Safety Data Sheets and Hazard Communication Plan
Solicitation 47PG0121R000611 of 291
C.5.4.11.1 Safety Data Sheets
C.5.4.11.2 Hazard Communication Plan
C.5.4.12 Labeling and signage
C.5.4.13. Emergency Shutdown Instructions
C.5.4.14 Electrical Safety
C.5.4.15 Labeling of Electrical Circuits and Panels
C.5.5 Environmental Management
C.5.5.1 General
C.5.5.2 Refrigerants
C.5.5.2.1 Operations
C.5.5.3 Local Air Quality Management Operating Permits
C.5.5.4 Stationary Engines
C.5.5.5 Fuel Storage Tank Management
C.5.5.6 Solid Waste: Reserved
C.5.5.7 Polychlorinated Biphenyl (PCB) Control
C.5.5.8 Asbestos Management
C.5.5.9 Lead Management
C.5.5.10 Respirable Crystalline Silica Management
C.5.5.11 Disposition of Hazardous Waste
C.5.5.12 Backflow Prevention Devices
C.5.5.13 Potable Water Systems
C.5.5.14 Parking Inlet Stormwater Management
C.5.5.15 Reporting
C.5.6 Energy and Water Efficiency
C.5.6.1 General
C.5.6.2 Operations
C.5.6.3 Reporting
C.5.7 Advanced Metering Systems
C.5.7.1 General
C.5.7.2 Operations
Solicitation 47PG0121R000612 of 291
C.5.7.3 Maintenance
C.5.7.4 Reporting
C.5.8 Building Automation Systems and IT Controls
C.5.8.1 General
C.5.8.2 Operations
C.5.8.2.1 GSA-hosted Systems Requirements
C.5.8.2.2 Excepted Systems Requirements (not hosted on GSA’s system infrastructure: RESERVED
C.5.8.3 Maintenance
C.5.8.3.1 BAS Control Systems and upgrades
C.5.8.3.1.1 Sensor Specifications
C.5.8.3.2 BAS Alarms
C.5.8.3.3 BAS Site Visits
C.5.8.4 Testing/Inspecting
C.5.8.5 Reporting
C.5.8.6 Smart Building Technology
C.5.8.7 Integrated Building Systems (IBS)
C.5.9 Fire Protection and Life Safety Equipment and Systems
C.5.9.1 General
C.5.9.2 Fire Alarm System Services and Emergency Communication Systems 80
C.5.9.3 Water-Based Fire Protection Systems
C.5.9.4 Fire-rated Door Assemblies
C.5.9.5 Fire Damper and Combination Fire/Smoke Dampers
C.5.9.6 Smoke Doors Assemblies
C.5.9.7 Smoke Dampers
C.5.9.8 Portable Fire Extinguishers
C.5.9.10 Smoke Control Systems
C.5.9.11 Emergency and Standby Power Systems
C.5.9.12 Emergency Lighting Systems and Exit Signage
C.5.9.13 Fire Resistance Rated Construction
C.5.9.14 Lightning Protection Systems
Solicitation 47PG0121R000613 of 291
C.5.9.15 Chemical Sensors
C.5.10 Tours
C.5.10.1 General
C.5.10.2 Proactive Facility Tours
C.5.10.3 Minimum Tour Frequencies
C.5.10.4. Monitoring of Central Plant Equipment: RESERVED
C.5.10.5 Operating Logs and Tour Check Sheets
C.5.10.6 Reporting
C.5.11 Repairs
C.5.11.1 General
C.5.11.2 Operations
C.5.11.2.1 Non-Reimbursable Repair
C.5.11.2.2 Partially Reimbursable Repairs
C.5.11.2.3 Fully Reimbursable Repairs
C.5.11.3 Warranties
C.5.11.4 Third-Party Contractors
C.5.12 Work Orders
C.5.12.1 General
C.5.12.2 Operations
C.5.12.2.1 Emergency Work Order
C.5.12.2.2 Emergency Call Back (Beyond Core Coverage Hours)
C.5.12.2.3 Urgent Work Order Response
C.5.12.2.4 Routine Work Order Response
C.5.12.3 Data Maintenance
C.5.12.4 Reporting
C.5.13 Additional Services Indefinite Quantity Provisions
C.5.13.1 General
C.5.13.2 Price Proposal for Additional Services Work Request
C.5.13.2.1 Parts and Materials
C.5.13.2.2 Labor
Solicitation 47PG0121R000614 of 291
C.5.13.3 Additional (Non-Pricing Schedule) Subcontracts
C.5.13.4 Order-Level Material (OLM) Markup
C.5.13.5 Proposal Review
C.5.13.6 Additional Services Work Request Ordering and Invoicing
C.5.13.7 Cost Documentation
C.5.13.8 Construction Services: RESERVED
C.5.14 Building Management and Support Services
C.5.14.1 General
C.5.14.2 Miscellaneous Work
C.5.14.3 Review of Design Documents
C.5.14.3.1 Reporting
C5.14.4 Inspections Assistance for Space Build Outs
C.5.14.5 Flag Procedures
C.5.14.6 Overtime Utilities
C.5.15 Monthly Progress Report
C.5.15.1 General
C.5.16 Reference Library
C.5.16.1 General
Subsection 6: Maintenance Specific Requirements
C.6.0 General
C.6.1 Maintenance Standard
C.6.2 Boiler and Pressure Vessel Systems
C.6.2.1 General
C.6.2.2 Operation
C.6.2.3 Boiler Maintenance
C.6.2.4 Testing and Inspecting
C.6.2.5 Reporting
C.6.3 Air Distribution Equipment
C.6.3.1 General
C.6.3.2 Operation
Solicitation 47PG0121R000615 of 291
C.6.3.3 Maintenance
C.6.3.4 Replacement of Air Filters
C.6.3.4.1 Replacement of Air Filters - MERV 13 or Higher
C.6.3.4.2 Replacement of Air Filters - MERV 12 or Lower
C.6.3.5 Testing and Inspecting
C.6.3.6 Reporting
C.6.4 Chiller Systems: RESERVED
C.6.5 Cooling Towers: RESERVED
C.6.6 HVAC Water Management
C.6.6.1 General
C.6.6.2 HVAC Water Management Plan
C.6.6.3 Operation
C.6.6.4 Maintenance
C.6.6.5 Testing and Inspecting
C.6.6.6 Reporting
C.6.6.7 Table of GSA established HVAC water management criteria
C.6.7. Domestic Plumbing Systems
C.6.7.1 General
C.6.8 Lighting Systems
C.6.8.1 General
C.6.8.2 Operation
C.6.8.3 Maintenance
C.6.8.4 Testing and Inspecting
C.6.9 Electrical Switchgear and Switchboards
C.6.10 Emergency Power Equipment
C.6.10.1 General
C.6.10.2 Operation (Fuel)
C.6.10.3 Maintenance
C.6.10.4 Testing and Inspecting
C.6.10.5 Reporting
Solicitation 47PG0121R000616 of 291
C.6.11 Oil Analysis and Oil Changes
C.6.11.1 General
C.6.11.2 Operations
C.6.11.3 Testing and Inspecting
C.6.11.4 Reporting
C.6.12 Vertical Transportation Systems
C.6.12.1 Elevator Associated Equipment Maintenance
C.6.13 Architectural and Structural Systems
C.6.13.1 General
C.6.13.2 Replacement Items and Painting
C.6.13.3 Machinery Rooms
C.6.13.4 Reserved
C.6.13.5 Architectural Woodwork
C.6.13.6 Directories
C.6.13.7 Roofs
C.6.13.8 Roof Anchorages
C.6.14 Perimeter Access Control Systems (Security fixtures)
C.6.14.1 General
C.6.15 Child Care Center (Zorinsky Federal Building)
Subsection 7: Administrative Instructions
C.7.0 Initial Inspection
C.7.1 Existing Deficiency Inspection/Initial Deficiency Report
C.7.2. Transition Phase
C.7.2.1 Transition Phase Schedule
C.7.3 Phase-out Transition Period
C.7.4 Contract Closeout Examination and Withholding of Final Payment
Subsection 8: Publications and Cited Standards
C.8.0 Publications
SECTION D – RESERVED
SECTION E – INSPECTION AND ACCEPTANCE
Solicitation 47PG0121R000617 of 291
E.1. - CONTRACTOR RESPONSIBILITY
E.2. - QUALITY REQUIREMENTS - QUALITY CONTROL PLAN (QCP)
E.3. - PROTECTION AND DAMAGE
E.4. - GSA QUALITY ASSURANCE
E.5. - GSA QUALITY ASSURANCE PLAN
E.5.C.2.A. General
E.5.C.2.B. GSA/Contractor Meetings
SECTION F – DELIVERIES OR PERFORMANCE
F.1. - PLACE OF PERFORMANCE
F.2. - TERM OF BLANKET PURCHASE AGREEMENT (BPA)
F.3. - REPORTING REQUIREMENTS
F.4. - FAILURE TO PROVIDE REQUIRED DOCUMENTATION
SECTION G - CONTRACT ADMINISTRATION DATA
G.1. – Role of Government Personnel in Contract Administration
G.1.1. Contracting Officer (CO)
G.1.2. Contracting Officer’s Representative (COR)
G.1.3. Building Management Specialist(BMS)/Quality Assurance Inspectors (QAI)
G.2. – System for Award Management (SAM)
G.3. - Payment
G.3.1. Submission of Invoices
G.3.2. Invoice Requirements
G.3.3. GSAM 552.232-72 Final Payments Under Building Services Contracts
G.3.4 Payment by Credit Card
G.3.5. Failure to Perform
G.3.6. Repairs due to Negligence or Error of Contractor
G.3.7. Federal Holidays, Unanticipated
G.3.8. Suspension of Work
G.3.9. Criminal Liability
G.3.10. Deductions
G.3.10.1 Calculation of Deductions
Solicitation 47PG0121R000618 of 291
G.3.10.2. Deduction Mechanical Labor Rates
G.3.10.3. Criteria for Mechanical Deductions - TABLE G-1 (TG1):
G.3.11 Payments for Reimbursable Building Operation Services:
G.4 Applicable Wage Determinations
G.4.1 Price Adjustment Process on Referenced Wage Determinations
SECTION H - RESERVED
SECTION I – CONTRACT CLAUSES
I.1.11. 52.219-27 Notice of Service-Disabled Veteran-Owned Small Business Set-
Aside (March 2020) [(DEVIATION JUN 2020)]
SECTION J LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENT
J.1 Building Information Sheet (BIS)
J.1.1 Hruska Federal Courthouse BIS
J.1.2 Zorinsky Federal Building BIS
J.2. Energy and Water Efficiency Monthly Report
J.3.0 Contractor Maintenance Performance Plans
J.3.1 General:
J.4.0 Contractor Chart of Deliverables
J.4.1 General
J.5 Smart Buildings
J.5.0 Smart and Sustainable Buildings
J.5.1 Specific BAS Requirements
J.5.1.1 Monthly Requirements
J.5.1.2 Semi-Annual / Seasonal
J.6.0 Preventive/Predictive Maintenance (PM) Equipment Inventory
J.6.1 Hruska U.S. Courthouse PM Equipment Inventory
J.6.1.1 Hruska U.S. Courthouse PM Equipment Inventory (GSA-Owned)
J.6.1.2 Hruska U.S. Courthouse (PM) Equipment Inventory (Agency-Owned)
J.6.1.2.1
J.6.1.2.2
J.6.1.2.3
J.6.2 Zorinsky Federal Building PM Equipment Inventory
Solicitation 47PG0121R000619 of 291
J.6.2.1 Zorinsky Federal Building (PM) Equipment Inventory (GSA-Owned)
J.6.2.2 Zorinsky Federal Building (PM) Equipment Inventory (Agency-Owned) ... 209
J.6.2.2.1
J.6.2.2.2
J.6.2.2.3
J.7 Asbestos Operations and Maintenance Guidance
J.8.0 GSA Approved Devices
J.9.0 Authorization for Waste Generator
J.10 Stormwater Management Plan and Maintenance Agreement
J.10.1 Exhibit “A” Insert Real Property Depiction
J.10.2 Exhibit Storm Inlet Filter BMP
J.10.3 Exhibit BMP Site Location Map
SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER
STATEMENTS OF BIDDERS/OFFERORS
K.1. - AUTHORIZED NEGOTIATORS
K.2. - MINIMUM ACCEPTANCE PERIOD
K.3 52.212-3 Offeror Representations and Certifications-Commercial Items (JAN
2021)
K.3. - CERTIFICATION OF REQUIRED INSURANCE
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS OR
RESPONDENTS
L.1 FAR 52.212-1, INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (JUN
2020)
L.2. - SUBMISSION OF PROPOSALS
L.2.1 - Submit Proposals To:
L.2.2 - Due Dates/Times:
L.2.3. Information to Be Included in Technical Proposal
L.2.4. Information to Be Included in Price Proposal
L.3. - FAR 52.237-1, SITE VISIT
L.4. - INSPECTION OF THE FACILITY (SITE VISIT)
L.4.1 - SPECIAL NOTICES
Solicitation 47PG0121R000620 of 291
L.4.2 - TOUR DATES/TIMES:
L.5. - FAR 52.216-1, TYPE OF CONTRACT (APR 1984)
L.6. - FAR 52.233-2, SERVICE OF PROTEST (SEPT 2006)
L.7. - NOTICE TO JOINT VENTURES/TEAMING
SECTION M – EVALUATION FACTORS FOR AWARD
M.1. - FAR 52.212-2, EVALUATION—COMMERCIAL ITEMS
M.2. - TECHNICAL PROPOSALS
M.2.1 - FACTOR 1 - WORK EXPERIENCE (Form is contained in M.5)
M.2.2 - FACTOR 2 - PAST PERFORMANCE
M.2.3 - FACTOR 3 - TECHNICAL/MANAGEMENT
Sub-Factor 3(a) - Preventive Maintenance Program
Sub-Factor 3(b) - NCMMS Usage and Data Management Plan
Sub-Factor 3(c) – Personnel (Staffing Plan)
M.2.4 - FACTOR 4 - SITE INSPECTION (Form is contained in M.8)
M.3. - PRICE EVALUATION
M.4. - WRITTEN NOTICE OF AWARD
M.5. - WORK EXPERIENCE
M.6. - FORM: PAST PERFORMANCE REFERENCE INFORMATION
M.7. – GOOGLE FORM EXAMPLE
M.8. - SITE INSPECTION VERIFICATION FORM
Solicitation 47PG0121R000621 of 291
SECTION B SUPPLIES OR SERVICES PRICES/COSTS
Section B is made up of two separate Microsoft Excel spreadsheets. One spreadsheet represents the line-item pricing for this award, the other spreadsheet provides a detailed breakdown of the quote. Both spreadsheets must be completed and returned with the Price
Proposal to be considered for award.
Solicitation 47PG0121R000622 of 291
SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Subsection 1: General Contract Requirements
C.1.0 General
This is a Performance Based Work Statement (PBWS) for Facilities Engineering: Operations, Maintenance, and Related Services defined under the scope of this contract. This PBWS describes the minimum requirements of the U.S. General Services Administration (GSA) and acceptable outcomes to be performed by the Operations and Maintenance Contractor (known from here on as Contractor). All, or part of, the successful offeror’s Management Plan must be incorporated into the contract.
GSA seeks to establish a partnering relationship with the Contractor to accomplish the program objectives in this contract. The objective of the partnering process is to provide an effective problem-finding/problem-solving management team composed of personnel from both parties, thus creating a single culture with one set of goals and objectives. Partnering requires that both parties recognize and address those opportunities and challenges that must be confronted to help maintain the health of the Contractor/GSA relationship. The relationship is based on trust, dedication to common goals, and an understanding of each other's individual expectations and values. The team must utilize a facilities engineering and systems thinking approach to provide solutions from a global perspective. The outcome of this initiative is for GSA to leverage
Contractor expertise to assist GSA in accomplishing these goals and objectives.
GSA intends to purchase Contractor provided technical and managerial expertise to assist in the holistic management of assets over the long term. This program strategy has taken the name
“facilities engineering” and has proven to be a successful model resulting in efficient and effective management of assets while maintaining a lower overall cost of operations. The facilities engineering model is dependent upon an effective partnership with a highly skilled Contractor whose objectives are based on mutual understanding of the stated requirements and objectives.
A higher level of effective communication between the Government and Contractor is essential for partnering and for this performance-based service contract to succeed, whereas the success of this contract is shared between the Government and the Contractor. More emphasis is placed on the Contractor’s self-management of quality, not the usual inspection by Government inspectors, although that is a part of this contract as well. All parties must act proactively to reduce service cost.
To establish a standard of facilities engineering practices, thought processes and problem solving throughout the model, GSA established a program philosophy rooted in “systems thinking” whereby the means and methods for providing building operations and maintenance are established through investigations, metrics, and feedback loops, and by establishing a partnership between the Government and Contractor to achieve joint performance objectives. The goal of applying systems thinking to facility management is to see that every action or decision in operating, maintaining, and retrofitting a building must result in an impact (financial, environmental, human resource, or any combination thereof), and to evaluate the “full circle”
Solicitation 47PG0121R000623 of 291 implications. Long term application of systems thinking throughout GSA has resulted in both
Contractor and Government joint command of short-term and long-term cohesive management of real property assets.
GSA is committed to Federal leadership in the design, construction, and operation of high-performance and sustainable buildings. A major element of this strategy is the implementation of common strategies for operating and maintaining buildings. As a result, this contract requires the
Contractor to participate and partner with the Government in the initiative of obtaining high performance and sustainable operations, inclusive of initiatives to conserve energy and water consumption, recycling programs, meeting or exceeding specific environmental, regulatory, or performance standards, and the utilization of green products and services. The following sections detail the GSA minimum requirements and acceptable outcomes. The Contractor must closely monitor all aspects of the work, identify deficiencies and implement corrective action, without reliance on Government oversight.
The Key Performance Indicators (KPIs) assess progress in key O&M program elements that significantly impact the tenant's working environment. Performance targets for the KPI are based on realistic and achievable outcomes, which are measured by the building's National Computer
Maintenance Management System (NCMMS), Work Order Throughput (WOT). Actual performance for each KPI is used by the parties to identify and implement improvements in O&M services and provide a forum for future discussions on CPARS between the Contractor and the
Government. All KPIs shall meet the established range as identified in NCMMS and are subject to change to maintain a quality of service. A report will be established monthly by the Government and can be accessed through the NCMMS Help-Center Data and is updated monthly.
To the extent possible and consistent with EO 13788, the Contractor must maximize the use of goods, products and materials that are produced in the United States.
C.1.1 Scope of Work
The Contractor must provide management, supervision, labor, materials, equipment, and supplies
(shipping & handling) and must be responsible for the efficient, effective, economical, and satisfactory operation, scheduled and unscheduled maintenance, repair of equipment and systems within the property line, except as otherwise noted for the Zorinsky Building in section
C.2.21, of the following locations:
NE0036ZZ Roman L. Hruska U.S. Courthouse 111 S. 18th PLZ, Omaha, Nebraska, 68102-1303
And NE0051ZZ Edward Zorinsky Federal Building
1616 Capitol Ave, Omaha, Nebraska, 68102-4908
Additional services may be ordered at the discretion of GSA for work relating to the operations, maintenance and repair or upgrade of the facilities listed above, but not covered in the basic services of the contract. Government furnished items are specifically excluded in this contract, except as specified in Section 3.
Solicitation 47PG0121R000624 of 291
C.1.1.1 Discrepancy in the Specifications
In any cases of discrepancy in the specifications, the matter must be immediately submitted to the Contracting Officer (CO). The decision of the CO as to the proper interpretation of the specifications must be final in accordance with the Disputes Clause of this Contract.
C.1.2 Personnel (Staffing Plan)
The Contractor must adhere to the submitted staffing plan and subcontracting plan that was submitted prior to award as part of the contractor’s proposal. Contractor must submit a staffing and subcontractor plan that provides sufficient numbers of staff at the various levels of expertise to ensure all scheduled and unscheduled services are performed and conditions are maintained to avoid any disruption to the tenant.
Any changes to the proposed staffing levels, qualifications of proposed staff or key personnel, or the areas of expertise or disciplines of the proposed staff must be submitted for review and approval from the CO or their designee. Vacancies due to extended absences, resignation, retirement, etc. greater than 60 days must be filled by the 61st calendar day of absence. Any approved reduction in personnel below the originally proposed staffing level and or failure to fulfill vacancies within the prescribed time frame may result in deductions in the contract price for that position and/or vacancy as identified in the table of deductions for this contract.
C.1.2.1 Contractor Key Personnel
The Contractor must designate a Contract Project Manager in writing and provide the name and contact information to the CO prior to the contract start date. The Contract Project Manager is considered essential to the work being performed under this Contract. Before removing, replacing, or diverting the Contract Project Manager, the Contractor must (1) notify the CO two weeks in advance and (2) submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the proposed change.
The Contract Project Manager must possess at least three years of recent (within the past five years) experience in the management and supervision of building mechanical operations and maintenance for buildings of the approximate size, complexity, and characteristics of the buildings to be covered by this Contract.
The Contractor must provide no fewer than two full-time On-Site Project Managers. Each
Project Manager will be responsible for a single location (Hruska and Zorinsky).
A detailed resume must be submitted to the CO or their designee for approval prior to the assignment of the project manager to the Contract. Both new and replacement project managers must meet these qualification standards.
Minimally, the resume must contain:
a. The full name of the proposed project manager.
Solicitation 47PG0121R000625 of 291
b. A detailed description of the proposed project manager’s employment history to reflect 5 years of experience within the past 7 years of employment. The names and addresses of the companies for whom the proposed project manager worked for DURING THESE PERIODS, along with the names and telephone numbers of the immediate supervisors.
c. Documentation of at least three years of verifiable IBM Tivoli Maximo Asset Management
CMMS.
d. Documentation of at least one year of verifiable Niagara EMCS experience or a certificate of basic Niagara EMCS training. This experience must include activities related to programming, troubleshooting, configuration, and systems startup; and,
e. Education, Diplomas, Licenses, Certificates, etc. currently held.
f. Demonstrates knowledge, skills, and ability with mechanical, electrical and plumbing systems in high-rise facilities that provide an establishment with such services as heat, air-conditioning (cool, humidify, dehumidify, filter, and circulate air), refrigeration, steam or high temperature water or electricity. Duties involve observing and interpreting readings on gauges, meters and charts which register various aspects of the system's operation, adjusting controls to insure safe and efficient operation of the system and to meet demands for the service provided, recording in logs various aspects of the system's operation, keeping the engines, machinery, and equipment of the system in good working order. This engineer may direct and coordinate activities of other staff members in performing tasks directly related to operating and maintaining the system or systems. The classification excludes head or chief engineers in establishments employing more than one engineer. Workers are required to be skilled in the repair of electronic control equipment; workers in establishments producing electricity, steam, or heated or cooled air primarily for sale, and Boiler Tenders.
C.1.2.2 Authority
The Contract Project Manager must have complete authority to act for the Contractor in every detail during the term of the contract and must have the authority to exercise financial expenditures and controls, accept notices of deductions, inspection reports, and all other correspondence on behalf of the Contractor.
C.1.2.3 Communication Equipment
The Contractor must provide key operational personnel (Managers, Supervisors, and Mechanical
Engineers, Mechanical Supervisors, Operating Engineers, Heating, Ventilation and Air
Conditioning (HVAC) Mechanics) with portable electronic means to communicate with GSA for all work covered under this Contract (Work Orders, emergencies, status of projects) at the commencement of the contract. Outside of normal working hours, the Contractor must maintain some designated form of communication with on-call staff to allow the CO or their designee to contact such on-call staff at any time for emergency response. Electronic communication methods are the following:
a Phone/Emails/Text messaging smartphone or tablet devices. The Contractor is responsible for all initial and monthly costs associated with the device(s). In areas where cellular service is unavailable, or unreliable, special exceptions must be made by the CO or designee on a case-by-case basis. Such devices must be on the list of GSA- approved devices and are to be processed through GSA’s procedures for remote mobile
Solicitation 47PG0121R000626 of 291 management. This must allow for mobile access to GSA email, the National Computerized
Maintenance Management System (NCMMS) mobile environment and Building
Automation Systems (BAS) alarms. The process for this and the list of currently approved devices is available upon request. Contractor personnel under this Contract must obtain and maintain an official GSA ENT account (this is your enterprise account for signing into systems administered by GSA) and monitor their GSA email account for all notifications.
b Fax. Receiving and sending faxes is acceptable as a secondary communication method for locations that have problems with wireless device signal strength. However, delaying faxes because of combined usage of voice and fax on the same line is not acceptable.
c Administrative Station – Government will provide at least one Desktop/Laptop device at each facility, contract group of buildings for NCMMS. Contractor must maintain the device per GSA IT requirements, including patching and security software. The Government must provide and maintain core Operating Systems, updates, revisions and Microsoft Office
(MS Office) tools.
C.1.2.3.1 CIO 2100 IT Security Policy
The Contractor must ensure compliance with GSA Order CIO 2100.1(L) or most current version.
Contractor core personnel (and subcontractors requiring IT access) under this Contract must obtain an official GSA email account. Employees must have clearance before they must access
GSA email, NCMMS, or other Government systems. The GSA Order CIO 2100 prohibits an employee or Contractor supporting GSA from creating or sending information using a non-official
GSA electronic messaging account (i.e., company or personal email account). The Contractor must ensure compliance with the Department of Homeland Security ICS-CERT cyber security guidance and recommendations. Guidance and most current version can be found at the web site in document titled “Web Links” at: Operations and Maintenance Specification
C.1.2.4 Language
On-site personnel and the Contractor’s Point of Contact (POC) for GSA need to be proficient in
English, and must be able to read, write, speak, and understand English.
C.1.2.5 Employee Suitability
The GSAR 552.237-71 Qualifications of Employees (1989) clause must be followed at all times during the performance of this Contract.
a. All Contract employees requiring routine unescorted access to federally controlled facilities or information systems, or both, for more than six months (Regular Employees) must be required to undergo a suitability determination before a personal identification verification (PIV) card is issued. Prior to the time that an identification card is issued, such
Regular Employees must be required to comply with normal facility access control procedures, including recording presence, temporary badging, and escorted entry, as applicable.
Solicitation 47PG0121R000627 of 291
b. Failure of a Regular Employee to receive a favorable suitability determination must be cause for removal of the employee from the work site and from other work in connection with the Contract.
c. Contract employees working less than six months (Temporary Employees) must, at the
Government's option, be required to undergo a lesser form of suitability determination.
Prior to the time that an identification card is issued, if at all, such Temporary Employees must be required to comply with normal facility access control procedures, including recording presence, temporary badge, and escorted entry, as applicable.
d. The Government, at its sole discretion, may grant temporary suitability determinations to
Regular or Temporary Employees. However, the granting of a temporary suitability determination to any such employee must not be considered as assurance that a favorable suitability determination must follow.
e. The CO or designee must provide the Contractor with the required clearance procedures for obtaining necessary clearances. The Contractor must comply with these clearance procedures.
f. The Contractor must be responsible for planning and scheduling its work in such a manner as to account for facility access issues. Difficulties encountered by the Contractor in gaining access to facilities by its employees and subcontractors must not be an excuse for any lack of Contractor performance under the Contract.
C.1.2.6 Employee Technical Qualifications
Employees or subcontractors performing Contract work involving the operation, maintenance or repair, inspection, or testing of any piece of equipment or system must be trained and possess the knowledge, experience and skills pertinent to the equipment or system as demonstrated by a current training certificate from an equipment manufacturer or a certificate by an organization acceptable to the CO. Contractor personnel must have NCMMS skills sufficient for “Use of
NCMMS” as described in this subsection. All personnel or sub-contractor personnel must possess all certifications and licenses required by Federal, state and local jurisdictions and National Fire
Protection Association (NFPA) 72, National Fire Alarm Code, section 10.5, for equipment that they must be operating, maintaining, repairing, inspecting or testing. At a minimum, a mechanic in each trade (e.g., electric, HVAC, plumbing) must be a licensed journeyman grade in the local municipality in which they are working. All personnel under the team leader or sub-contractor personnel must have the experience and skill set knowledge as described in the Service Contract
Act (SCA) Directory of Occupations, Fifth Edition or later. For example, HVAC mechanics need to be as proficient as dictated by the 23410 and 23411 series and general maintenance mechanic must be as proficient as dictated by the 23370 series.
C.1.2.7 Certifications
Copies of all certifications for Contractor employees must be kept on-site and provided to the
Government upon request. The Contractor must provide to the CO or their designee documentation of the certificates of training, licenses, and permits for all new employees not later than seven (7) business days prior to that person beginning work under the terms of this
Contract. The Contractor must ensure that all certificates of training, licenses, permits, and bonds
Solicitation 47PG0121R000628 of 291 are current and valid and are loaded in NCMMS.
C.1.2.7.1 Qualifications of Fire Alarm System Technicians
a. Technicians performing contract work involving the inspection, testing, and preventive maintenance or repair of fire alarm systems must be certified by the National Institute for
Certification in Engineering Technologies (NICET) and possess at least a NICET Level 2
(Associate Engineering Technician) in Fire Protection Engineering Technology, Fire Alarm
Systems. The Contractor must submit to the CO or designee the NICET level certification number and expiration date for each field technician and inspector responsible for performing fire alarm system preventive maintenance and repair services required under the terms of this Contract.
b. Technicians modifying the programming software of the fire alarm system must also be factory trained and certified by the system manufacturer for the specific type and brand of fire alarm system being serviced. The Contractor must submit to the CO or designee the factory trained certification number and expiration date for each specific manufacturer’s equipment for each technician responsible for performing programming of the fire alarm system.
C.1.2.7.2 Qualifications of Water-Based Fire Suppression System Technicians
Technicians performing contract work involving the inspection, testing, and preventive maintenance or repair of water-based fire suppression systems must be certified by the National
Institute for Certification in Engineering Technologies (NICET) and possess at least a NICET
Level 2 (Associate Engineering Technician) in Fire Protection Engineering Technology, Inspection, and Testing of Water-Based Systems. The Contractor must submit to the CO or designee the NICET level certification number and expiration date for each field technician and inspector responsible for performing water-based fire suppression system PM and repair services required under the terms of this Contract.
C.1.2.7.3 Qualifications of [Dry Chemical Extinguishing System], [Wet Chemical
Extinguishing System]; [Clean Agent Fire Extinguishing System]; [Halogenated
Extinguishing System]; [Carbon Dioxide Extinguishing System]; [Ventilation System Fire
Extinguishing System]; [Smoke Control]; [Fire Damper]; [Smoke Damper]; [Combination
Fire/Smoke Damper]; [Fire-rated Door Assemblies]; [Smoke Door Assemblies]; [Portable
Fire Extinguisher]; [Emergency and Standby Power]; [Emergency Lighting Equipment];
[Exit Signage] Technicians
Technicians must be trained and possess a current training certificate for inspecting, testing, and maintaining these components from an equipment manufacturer or a certificate by an organization acceptable to the CO. The Contractor must submit to the CO or designee the certification document and expiration date, issued by the equipment manufacturer or organization confirming the technician has been trained, for each field technician and inspector responsible for performing the inspection, testing, and maintenance of such systems/equipment under the terms of this
Solicitation 47PG0121R000629 of 291
Contract.
C.1.2.7.4 Qualifications for Electrical Technician
Technicians performing Subcontract work involving inspections, testing, and maintenance for the electrical switchgear must meet the qualifications by the American National Standards
Institute/International Electrical Testing Association ETT-2015, Standard for Certification of
Electrical Testing Technicians or qualifications by the National Institute for Certification in
Engineering Technologies (NICET) and hold at least a Level 3 certification. In addition, the individual must also meet requirements under 29 CFR 1910 Subpart S for a Qualified Person.
The Contractor must provide documentation to the CO or designee on qualifications identified in this standard. Certification can be obtained through; the ANSI/NETA Certification program or
Electrical Testing Technician Certification Institute. Guidance can be found at the web site in document titled “Web Links” at: Operations and Maintenance Specification
Alternate certifications presenting evidence of equal or greater skills and qualification may be substituted; however, the burden to evidence the quality of such certification falls fully upon the
Contractor.
C.1.2.7.5 Qualifications for BAS Technician
The Contractor shall be proficient in applicable controls systems (e.g., JCI, Honeywell, Siemens, Delta, Automated Logic, Alerton, and Tridium). All BAS Technicians shall be certified in the building-specific integrated system controls certification (i.e., Tridium Niagara, JCI/Metasys, Siemens Apogee, etc.). The Contractor shall be aware of building systems running on GSA IP
Enterprise Network and capable of initiating troubleshooting if network communications is suspected. This means being familiar with the procedure for logging GSA IT Help Desk tickets and following up to ensure tickets are being worked by the assigned party. Familiarization with the use of Integrated Control systems, GSA IP Addresses, function of network routers, function of network switches, networks communications, and BAS software will be necessary.
All BAS Technicians shall be certified in the building-specific integrated system controls certification (i.e., Tridium Niagara, JCI/Metasys, Siemens Apogee, etc.) within 60 calendar days of contract start date. GSA’s intent is to align the correct BAS technician certification for the BAS installed in the building.
C.1.2.7.6 Qualifications for BAS Operators and Programmers, EMCS, AMS, and DALI Technicians
All personnel involved in the operation, adjustment, and maintenance of all BAS, EMCS, AMS, and DALI systems, including energy management systems, must be trained and qualified. The
Contractor must provide to the COR or designee documentation of the level of experience, including any certificates of training, for all employees who will be involved in this function within
60 calendar days of contract start date.
Solicitation 47PG0121R000630 of 291
A qualified BAS Operator is an individual (or individuals) that is (are) capable of recognizing the
BAS in both normal and abnormal running conditions. A basic understanding of a functional system is important to recognize a BAS system in proper operation or not. Qualified individual(s) shall be capable of making basic system alterations. Adjusting temperatures is a regular request, and the operator shall have the skills necessary to make various changes in the system that include setpoint changes, manual overrides, and other related basic functions.