Solicitation 23R0006 Placement and Cleaning Chemical Portable Toilets 22 Feb 2023.pdf
PDF 2 MB Posted
- Attached to
- Chemical Portable Toilets
- Solicitation number
- W9124C23R0006
About this file
This is a performance work statement for a firm fixed price contract to provide portable chemical toilet services at Fort Jackson in South Carolina. The contractor will place and service 844 regular portable chemical toilets, 1 handicap toilet, and make 120 additional regular toilets and 10 handicap toilets available for temporary use. The contractor will also provide 20 portable hand sanitizing stations as needed. The performance period is one base year and four 1-year option periods. The contractor must dispose of waste off-post in compliance with all regulations and furnish all vehicles, equipment, supplies and facilities required to perform the services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W9124C23R0006 22-Feb-2023
b. TELEPHONE NUMBER
803-751-4372
8. OFFER DUE DATE/LOCAL TIME
10:00 AM 03 Mar 2023
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA X ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W9124C9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
ROGER MILLER
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
1 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.X
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
MICC - FT JACKSON
4340 MAGRUDER AVE
FORT JACKSON SC 29207
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE 16. ADMINISTERED BY
SEE SCHEDULE
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
803-751-5234FAX:
TEL: 803-751-4343 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$8,000,000
NAICS:
562991
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF148
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W9124C23R0006
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 2 Months Phase-In Period
FFP
Contractor shall become familiar with performance requirements in order to commence full performance of services on the contract start date. The contractor will be responsible for ensuring they implement. See Attached Performance Work Statement.
FOB: Destination
PSC CD: W085
NET AMT
0002 10 Months Lease/Service Portable Toilets
FFP
(Quantity 675) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 675 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
0003 10 Months Lease/Service Portable Handicap Toilets
FFP
(Quantity 1; Chemical Portable Toilets), The contractor must furnish and maintain one (1) handicap portable chemical toilet to be placed at permanent locations throughout Fort Jackson. Each furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed; as well as signature of the servicing driver.
Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch, and coat hook. Permanent locations are listed in Technical Exhibit (TE)-3 and the sign in roster is listed in Technical Exhibit TE-4. See attached Performance Work Statement (PWS) for additional information.
0004 3,000 Each Lease 3 Day Ordering Period
FFP
Leasing/SVC three (3) Day Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a three (3) day period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See Attached Performance Work Statement.
0005 2,000 Each Lease 1 Week Ordering Period
FFP
Leasing/SVC One (1) Week Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a one (1) week period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
0006 300 Each Lease Consecutive Weeks
FFP
Lease/SVC Consecutive Weeks. Temporary leasing and servicing of single regular portable chemical toilets for consecutive weeks. Price shall include the discounted weekly price per toilet per consecutive week after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement for additional information.
0007 300 Each Lease Per Day after the 1st Week
FFP
Lease/SVC per day after the 1st week Temporary leasing and servicing of a single regular portable chemical toilet per day the first week of leasing/servicing.
Price shall include the discounted daily per toilet per day after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement for additional informaiton.
0008 150 Each Lease Handicap for 3 Day period
FFP
Lease/SVC Handicap Toilet for 3 Day Period.
Temporary leasing and servicing of a single handicap portable chemical toilet for a three (3) day period. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
0009 25 Each Lease Handicap for 1 Week
FFP
Handicap Lease/SVC for 1 Week.
Temporary leasing and servicing of a single handicap portable chemical toilet for a one week period. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
0010 500 Each Additional Cleaning of Portable Toilets
FFP
Additional Cleaning of Portable Toilets.
Additional cleaning of individual portable chemical toilets. This additional cleaning ordered shall be above what is specified in the performance work statement (PWS) and resulting contract. This additional cleaning is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
0011 500 Each Relocation or Moving of Portable Toilets
FFP
Relocation or Moving of Portable Toilets.
Relocation or repositioning of an individual portable chemical toilet. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
0012 2 Each Replace damaged Portable Toilet
FFP
Replace damaged Portable Toilets.
Replacement costs for damaged portable chemical toilets above and beyond the normal usage.
This CLIN shall only be utilized if replacement is required due to damage beyond normal usage or an accident for which the Government is at fault. This CLIN shall not be utilized for normal wear and tear of the portable chemical toilets. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
0013 110,000 Gallon Pit Latrine Cleaning
FFP
Pit Latrine Cleaning The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the cleaning of Pit latrines on the installation, as defined in this Performance Work Statement (PWS) except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
See attached Performance Work Statement (PWS) for additional information.
0014 336,000 Gallon Off Post Disposal
FFP
Off Post Disposal The contractor shall perform this service IAW PWS, Section 3.4, entitled Waste Management and Disposal. The contractor must dispose of chemical toilet waste at an off post location in accordance with all local, state and Federal regulations. The contractor may not bring waste from offsite (outside Fort Jackson) for disposal. All handling of waste shall be in accordance with all state and Federal requirements including the South Carolina Department of Health and Environmental Control (SC DHEC) and/or City of Columbia requirements.
See attached Performance Work Statement (PWS) for additional information.
0015 30 Each Lease Hand Sanitize Station
FFP
(QTY 1) Lease/SVC Portable Hand Sanitize Station.
The contractor must furnish and maintain one (1) portable hand sanitize station to be placed as required at a temporary location on Fort Jackson. The hand sanitize station shall be serviced and maintained in strict accordance with the terms and conditions outlined in the PWS.
See attached Performance Work Statement (PWS) for additional information.
0016 12 Months Chemical Toilets (FORGE)
FFP
(Quantity 219) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 219 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
1001 12 Months OPTION Lease/Service Portable Toilets
FFP
(Quantity 675) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 675 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
1002 10 Months OPTION Lease/Service Portable Handicap Toilets
FFP
(Quantity 1; Chemical Portable Toilets), The contractor must furnish and maintain one (1) handicap portable chemical toilet to be placed at permanent locations throughout Fort Jackson. Each furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed; as well as signature of the servicing driver.
Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch, and coat hook. Permanent locations are listed in Technical Exhibit (TE)-3 and the sign in roster is listed in Technical Exhibit TE-4. See attached Performance Work Statement (PWS) for additional information.
1003 3,000 Each OPTION Lease 3 Day Ordering Period
FFP
Leasing/SVC three (3) Day Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a three (3) day period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See Attached Performance Work Statement.
1004 2,000 Each OPTION Lease 1 Week Ordering Period
FFP
Leasing/SVC One (1) Week Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a one (1) week period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
1005 300 Each OPTION Lease Consecutive Weeks
FFP
Lease/SVC Consecutive Weeks. Temporary leasing and servicing of single regular portable chemical toilets for consecutive weeks. Price shall include the discounted weekly price per toilet per consecutive week after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement for additional information.
1006 300 Each OPTION Lease Per Day after the 1st Week
FFP
Lease/SVC per day after the 1st week Temporary leasing and servicing of a single regular portable chemical toilet per day the first week of leasing/servicing.
Price shall include the discounted daily per toilet per day after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement for additional informaiton.
1007 150 Each OPTION Lease Handicap for 3 Day period
FFP
Lease/SVC Handicap Toilet for 3 Day Period.
Temporary leasing and servicing of a single handicap portable chemical toilet for a three (3) day period. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
1008 25 Each OPTION Lease Handicap for 1 Week
FFP
Handicap Lease/SVC for 1 Week.
Temporary leasing and servicing of a single handicap portable chemical toilet for a one week period. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
1009 12 Months OPTION Replace Damaged Chemical Toilets
FFP
(Cost to replace damaged Chemical Toilets) The contractor must submit the cost to replace the chemical toilets throughout the Fort Jackson's Training Sites. In accordance with the attached Performance Work Statement.
1010 500 Each OPTION Relocation or Moving of Portable Toilets
FFP
Relocation or Moving of Portable Toilets.
Relocation or repositioning of an individual portable chemical toilet. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
1011 2 Each OPTION Replace damaged Portable Toilet
FFP
Replace damaged Portable Toilets.
Replacement costs for damaged portable chemical toilets above and beyond the normal usage.
This CLIN shall only be utilized if replacement is required due to damage beyond normal usage or an accident for which the Government is at fault. This CLIN shall not be utilized for normal wear and tear of the portable chemical toilets. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
1012 110,000 Gallon OPTION Pit Latrine Cleaning
FFP
Pit Latrine Cleaning The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the cleaning of Pit latrines on the installation, as defined in this Performance Work Statement (PWS) except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
See attached Performance Work Statement (PWS) for additional information.
1013 336,000 Gallon OPTION Off Post Disposal
FFP
Off Post Disposal The contractor shall perform this service IAW PWS, Section 3.4, entitled Waste Management and Disposal. The contractor must dispose of chemical toilet waste at an off post location in accordance with all local, state and Federal regulations. The contractor may not bring waste from offsite (outside Fort Jackson) for disposal. All handling of waste shall be in accordance with all state and Federal requirements including the South Carolina Department of Health and Environmental Control (SC DHEC) and/or City of Columbia requirements.
See attached Performance Work Statement (PWS) for additional information.
1014 30 Each OPTION Lease Hand Sanitize Station
FFP
(QTY 1) Lease/SVC Portable Hand Sanitize Station.
The contractor must furnish and maintain one (1) portable hand sanitize station to be placed as required at a temporary location on Fort Jackson. The hand sanitize station shall be serviced and maintained in strict accordance with the terms and conditions outlined in the PWS.
See attached Performance Work Statement (PWS) for additional information.
1015 12 Months OPTION Chemical Toilets (FORGE)
FFP
(Quantity 219) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 219 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
2001 12 Months OPTION Lease/Service Portable Toilets
FFP
(Quantity 675) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 675 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
2002 10 Months OPTION Lease/Service Portable Handicap Toilets
FFP
(Quantity 1; Chemical Portable Toilets), The contractor must furnish and maintain one (1) handicap portable chemical toilet to be placed at permanent locations throughout Fort Jackson. Each furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed; as well as signature of the servicing driver.
Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch, and coat hook. Permanent locations are listed in Technical Exhibit (TE)-3 and the sign in roster is listed in Technical Exhibit TE-4. See attached Performance Work Statement (PWS) for additional information.
2003 3,000 Each OPTION Lease 3 Day Ordering Period
FFP
Leasing/SVC three (3) Day Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a three (3) day period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See Attached Performance Work Statement.
2004 2,000 Each OPTION Lease 1 Week Ordering Period
FFP
Leasing/SVC One (1) Week Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a one (1) week period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
2005 300 Each OPTION Lease Consecutive Weeks
FFP
Lease/SVC Consecutive Weeks. Temporary leasing and servicing of single regular portable chemical toilets for consecutive weeks. Price shall include the discounted weekly price per toilet per consecutive week after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement for additional information.
2006 300 Each OPTION Lease Per Day after the 1st Week
FFP
Lease/SVC per day after the 1st week Temporary leasing and servicing of a single regular portable chemical toilet per day the first week of leasing/servicing.
Price shall include the discounted daily per toilet per day after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement for additional informaiton.
2007 150 Each OPTION Lease Handicap for 3 Day period
FFP
Lease/SVC Handicap Toilet for 3 Day Period.
Temporary leasing and servicing of a single handicap portable chemical toilet for a three (3) day period. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
2008 25 Each OPTION Lease Handicap for 1 Week
FFP
Handicap Lease/SVC for 1 Week.
Temporary leasing and servicing of a single handicap portable chemical toilet for a one week period. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
2009 500 Each OPTION Additional Cleaning of Portable Toilets
FFP
Additional Cleaning of Portable Toilets.
Additional cleaning of individual portable chemical toilets. This additional cleaning ordered shall be above what is specified in the performance work statement (PWS) and resulting contract. This additional cleaning is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
2010 500 Each OPTION Relocation or Moving of Portable Toilets
FFP
Relocation or Moving of Portable Toilets.
Relocation or repositioning of an individual portable chemical toilet. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
2011 2 Each OPTION Replace damaged Portable Toilet
FFP
Replace damaged Portable Toilets.
Replacement costs for damaged portable chemical toilets above and beyond the normal usage.
This CLIN shall only be utilized if replacement is required due to damage beyond normal usage or an accident for which the Government is at fault. This CLIN shall not be utilized for normal wear and tear of the portable chemical toilets. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
2012 110,000 Gallon OPTION Pit Latrine Cleaning
FFP
Pit Latrine Cleaning The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the cleaning of Pit latrines on the installation, as defined in this Performance Work Statement (PWS) except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
See attached Performance Work Statement (PWS) for additional information.
2013 336,000 Gallon OPTION Off Post Disposal
FFP
Off Post Disposal The contractor shall perform this service IAW PWS, Section 3.4, entitled Waste Management and Disposal. The contractor must dispose of chemical toilet waste at an off post location in accordance with all local, state and Federal regulations. The contractor may not bring waste from offsite (outside Fort Jackson) for disposal. All handling of waste shall be in accordance with all state and Federal requirements including the South Carolina Department of Health and Environmental Control (SC DHEC) and/or City of Columbia requirements.
See attached Performance Work Statement (PWS) for additional information.
2014 30 Each OPTION Lease Hand Sanitize Station
FFP
(QTY 1) Lease/SVC Portable Hand Sanitize Station.
The contractor must furnish and maintain one (1) portable hand sanitize station to be placed as required at a temporary location on Fort Jackson. The hand sanitize station shall be serviced and maintained in strict accordance with the terms and conditions outlined in the PWS.
See attached Performance Work Statement (PWS) for additional information.
2015 12 Months OPTION Chemical Toilets (FORGE)
FFP
(Quantity 219) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 219 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
3001 12 Months OPTION Lease/Service Portable Toilets
FFP
(Quantity 675) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 675 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
3002 10 Months OPTION Lease/Service Portable Handicap Toilets
FFP
(Quantity 1; Chemical Portable Toilets), The contractor must furnish and maintain one (1) handicap portable chemical toilet to be placed at permanent locations throughout Fort Jackson. Each furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed; as well as signature of the servicing driver.
Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch, and coat hook. Permanent locations are listed in Technical Exhibit (TE)-3 and the sign in roster is listed in Technical Exhibit TE-4. See attached Performance Work Statement (PWS) for additional information.
3003 3,000 Each OPTION Lease 3 Day Ordering Period
FFP
Leasing/SVC three (3) Day Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a three (3) day period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See Attached Performance Work Statement.
3004 2,000 Each OPTION Lease 1 Week Ordering Period
FFP
Leasing/SVC One (1) Week Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a one (1) week period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
3005 300 Each OPTION Lease Consecutive Weeks
FFP
Lease/SVC Consecutive Weeks. Temporary leasing and servicing of single regular portable chemical toilets for consecutive weeks. Price shall include the discounted weekly price per toilet per consecutive week after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement for additional information.
3006 300 Each OPTION Lease Per Day after the 1st Week
FFP
Lease/SVC per day after the 1st week Temporary leasing and servicing of a single regular portable chemical toilet per day the first week of leasing/servicing.
Price shall include the discounted daily per toilet per day after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement for additional informaiton.
3007 150 Each OPTION Lease Handicap for 3 Day period
FFP
Lease/SVC Handicap Toilet for 3 Day Period.
Temporary leasing and servicing of a single handicap portable chemical toilet for a three (3) day period. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
3008 25 Each OPTION Lease Handicap for 1 Week
FFP
Handicap Lease/SVC for 1 Week.
Temporary leasing and servicing of a single handicap portable chemical toilet for a one week period. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
3009 500 Each OPTION Additional Cleaning of Portable Toilets
FFP
Additional Cleaning of Portable Toilets.
Additional cleaning of individual portable chemical toilets. This additional cleaning ordered shall be above what is specified in the performance work statement (PWS) and resulting contract. This additional cleaning is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
3010 500 Each OPTION Relocation or Moving of Portable Toilets
FFP
Relocation or Moving of Portable Toilets.
Relocation or repositioning of an individual portable chemical toilet. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
3011 2 Each OPTION Replace damaged Portable Toilet
FFP
Replace damaged Portable Toilets.
Replacement costs for damaged portable chemical toilets above and beyond the normal usage.
This CLIN shall only be utilized if replacement is required due to damage beyond normal usage or an accident for which the Government is at fault. This CLIN shall not be utilized for normal wear and tear of the portable chemical toilets. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
3012 110,000 Gallon OPTION Pit Latrine Cleaning
FFP
Pit Latrine Cleaning The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the cleaning of Pit latrines on the installation, as defined in this Performance Work Statement (PWS) except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
See attached Performance Work Statement (PWS) for additional information.
3013 336,000 Gallon OPTION Off Post Disposal
FFP
Off Post Disposal The contractor shall perform this service IAW PWS, Section 3.4, entitled Waste Management and Disposal. The contractor must dispose of chemical toilet waste at an off post location in accordance with all local, state and Federal regulations. The contractor may not bring waste from offsite (outside Fort Jackson) for disposal. All handling of waste shall be in accordance with all state and Federal requirements including the South Carolina Department of Health and Environmental Control (SC DHEC) and/or City of Columbia requirements.
See attached Performance Work Statement (PWS) for additional information.
3014 30 Each OPTION Lease Hand Sanitize Station
FFP
(QTY 1) Lease/SVC Portable Hand Sanitize Station.
The contractor must furnish and maintain one (1) portable hand sanitize station to be placed as required at a temporary location on Fort Jackson. The hand sanitize station shall be serviced and maintained in strict accordance with the terms and conditions outlined in the PWS.
See attached Performance Work Statement (PWS) for additional information.
3015 12 Months OPTION Chemical Toilets (FORGE)
FFP
(Quantity 219) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 219 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
4001 12 Months OPTION Lease/Service Portable Toilets
FFP
(Quantity 675) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 675 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
4002 10 Months OPTION Lease/Service Portable Handicap Toilets
FFP
(Quantity 1; Chemical Portable Toilets), The contractor must furnish and maintain one (1) handicap portable chemical toilet to be placed at permanent locations throughout Fort Jackson. Each furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed; as well as signature of the servicing driver.
Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch, and coat hook. Permanent locations are listed in Technical Exhibit (TE)-3 and the sign in roster is listed in Technical Exhibit TE-4. See attached Performance Work Statement (PWS) for additional information.
4003 3,000 Each OPTION Lease 3 Day Ordering Period
FFP
Leasing/SVC three (3) Day Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a three (3) day period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See Attached Performance Work Statement.
4004 2,000 Each OPTION Lease 1 Week Ordering Period
FFP
Leasing/SVC One (1) Week Ordering Period. Temporary leasing and servicing of a single regular portable chemical toilet for a one (1) week period. This is to be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
4005 300 Each OPTION Lease Consecutive Weeks
FFP
Lease/SVC Consecutive Weeks. Temporary leasing and servicing of single regular portable chemical toilets for consecutive weeks. Price shall include the discounted weekly price per toilet per consecutive week after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement for additional information.
4006 300 Each OPTION Lease Per Day after the 1st Week
FFP
Lease/SVC per day after the 1st week Temporary leasing and servicing of a single regular portable chemical toilet per day the first week of leasing/servicing.
Price shall include the discounted daily per toilet per day after the first week of leasing/servicing. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement for additional informaiton.
4007 150 Each OPTION Lease Handicap for 3 Day period
FFP
Lease/SVC Handicap Toilet for 3 Day Period.
Temporary leasing and servicing of a single handicap portable chemical toilet for a three (3) day period. To be ordered as needed by the Contracting Officer or Ordering Officer. See attached Performance Work Statement (PWS) for additional information.
4008 25 Each OPTION Lease Handicap for 1 Week
FFP
Handicap Lease/SVC for 1 Week.
Temporary leasing and servicing of a single handicap portable chemical toilet for a one week period. To be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
4009 12 Months OPTION Replace Damaged Chemical Toilets
FFP
(Cost to replace damaged Chemical Toilets) The contractor must submit the cost to replace the chemical toilets throughout the Fort Jackson's Training Sites. In accordance with the attached Performance Work Statement.
4010 500 Each OPTION Relocation or Moving of Portable Toilets
FFP
Relocation or Moving of Portable Toilets.
Relocation or repositioning of an individual portable chemical toilet. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
4011 2 Each OPTION Replace damaged Portable Toilet
FFP
Replace damaged Portable Toilets.
Replacement costs for damaged portable chemical toilets above and beyond the normal usage.
This CLIN shall only be utilized if replacement is required due to damage beyond normal usage or an accident for which the Government is at fault. This CLIN shall not be utilized for normal wear and tear of the portable chemical toilets. This is to be ordered as needed by the Contracting Officer or Ordering Officer.
See attached Performance Work Statement (PWS) for additional information.
4012 110,000 Gallon OPTION Pit Latrine Cleaning
FFP
Pit Latrine Cleaning The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the cleaning of Pit latrines on the installation, as defined in this Performance Work Statement (PWS) except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
See attached Performance Work Statement (PWS) for additional information.
4013 336,000 Gallon OPTION Off Post Disposal
FFP
Off Post Disposal The contractor shall perform this service IAW PWS, Section 3.4, entitled Waste Management and Disposal. The contractor must dispose of chemical toilet waste at an off post location in accordance with all local, state and Federal regulations. The contractor may not bring waste from offsite (outside Fort Jackson) for disposal. All handling of waste shall be in accordance with all state and Federal requirements including the South Carolina Department of Health and Environmental Control (SC DHEC) and/or City of Columbia requirements.
See attached Performance Work Statement (PWS) for additional information.
4014 30 Each OPTION Lease Hand Sanitize Station
FFP
(QTY 1) Lease/SVC Portable Hand Sanitize Station.
The contractor must furnish and maintain one (1) portable hand sanitize station to be placed as required at a temporary location on Fort Jackson. The hand sanitize station shall be serviced and maintained in strict accordance with the terms and conditions outlined in the PWS.
See attached Performance Work Statement (PWS) for additional information.
4015 12 Months OPTION Chemical Toilets (FORGE)
FFP
(Quantity 219) Leave/Service Chemical Portable Toilets. The contractor must furnish and maintain 219 single seat, portable chemical toilets to be placed at permanent locations throughout Fort Jackson. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, latch and coat hook. Permanent locations are listed in Technical Exhibit (TE) 3 and the sign in roster is listed in Technical Exhibit TE-4. See Performance Work Statement for additional information.
4016 2 Months Phase Out Period
FFP
Contractor shall become familiar with performance requirements in order to commence full performance of services on the contract start date. The contractor will be responsible for ensuring they implement. See Attached Performance Work Statement.
Section C - Descriptions and Specifications
ATTACHMENT 2, PWS
W9124C-23-D-00XX
PERFORMANCE WORK STATEMENT
Portable Chemical Toilets Directorate of Public Works
Fort Jacksons, SC
W9124C-23-D-00XX
Table of Contents PART 1 – General Information PART 2 – Definitions and Acronyms PART 3 – Government Furnished Property, Equipment, and Services PART 4 – Contractor Furnished Items and Services PART 5 – Specific Tasks PART 6 – Applicable Publications PART 7 – Attachment/Technical Exhibit Listing
TECHNICAL EXHIBIT 1 Performance Requirements Summary TECHNICAL EXHIBIT 2 Deliverables Schedule TECHNICAL EXHIBIT 3 Permanent Location of Chemical Toilets TECHNICAL EXHIBIT 4 Servicing Sign in Roster TECHNICAL EXHIBIT 5 Fort Jackson Vetting Policy
Fort Jackson Contractor Vetting Policy Enclosure 1
Fort Jackson Contractor Vetting Policy Enclosure 2
Fort Jackson Contractor Vetting Policy Enclosure 3
Fort Jackson Contractor Vetting Policy Enclosure 4
PERFORMANCE WORK STATEMENT
Portable Chemical Toilets Fort
Jackson, Columbia SC
Part 1
GENERALINFORMATION
1. GENERAL: This is a non-personal services contract to provide for the placement and cleaning of Portable Chemical Toilets and portable hand sanitizing stations on Fort Jackson in South Carolina. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.1 Description of Services/Introduction: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the placement and cleaning of Portable Chemical Toilets on the installation, as defined in this Performance Work Statement (PWS) except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
1.2 Background: Fort Jackson is the largest and most active Initial Entry Training Center in the U.S. Army, training over 50 percent of all soldiers and nearly 60 percent of women entering the army each year. The Fort Jackson’s primary mission is providing the Army with highly trained, disciplined, motivated and physically fit warriors who espouse the Army’s core values and are focused on teamwork. During training, soldiers are conducting field exercises at various ranges and remote locations around the installation. Often permanent utility connections are not available and/or permanent latrine facilities are not nearby. Surges in numbers of soldiers being trained require more facilities as well.
Therefore, portable chemical toilets are used in the absence of available latrine facilities.
Additionally, special events often generate a need for portable chemical toilets. Training and special events are often intermittent and unpredictable in nature. However, most chemical toilet requirements are recurring and predictable.
1.3 Objectives:
• Place chemical toilets per the direction of the Contracting Officer (KO) or the Contracting Officer’s Representative (COR).
• Remove waste product from the chemical toilets as required.
• Clean toilets as required.
• Maintain all chemical toilets so that the result is a sanitary and functional portable latrine.
1.4 Scope: The Contractor shall furnish and maintain 845 single seat, portable chemical toilets (844 regular and 1 handicap toilets) to be placed at permanent locations throughout Fort Jackson. The Contractor shall also make an additional 120 portable chemical toilets, 10 handicap toilets, and 20 portable hand sanitizing stations available that may be placed as required at temporary locations for short terms throughout the installation. Additionally, the contractor may be asked to empty 3 pit latrines if they are in use. Each contractor furnished portable toilet, portable hand sanitizing station, and pit latrine shall be serviced (see definition) and maintained in strict accordance with the terms and conditions of this contract. Each contractor furnished chemical toilet placed at an established permanent site shall have an attached sign in roster enabling the means to record the date and time of service completed, as well as signature of the servicing driver. Each portable chemical toilet shall be completely closed, well ventilated, contain a single seat chemical toilet and storage tank, toilet tissue, toilet tissue holder, toilet seat, urinal, door, and latch. Each chemical toilet when placed will seat level and the door will latch and close tightly. Permanent locations are listed in Technical Exhibit (TE)-3 and the sign in roster is listed in Technical Exhibit TE-4. Contractor shall submit an updated Technical Exhibit as outlined in TE-3 or comparable to the COR on a quarterly basis or as requested by the Contracting Officer. This updated TE shall capture all changes of location and/or quantity as directed by the COR.
The Contractor shall place and service portable chemical toilets throughout the Installation at locations and quantities as indicated in the TE-3.
1.5 Period of Performance: The period of performance shall consist of a 30-day phase-in period, one (1) Base Year of 11 months and four (4) 12-month options years. Period of Performance reads as follows:
Phase-in- 30 Days Base Year- 11 Months Option Year I- 12 Months
Option Year II- 12 Months Option Year III- 12 Months Option Year IV- 12 Months Six month Option to extend services in accordance with 52.217-8
1.6 General Information:
1.6.1 Quality Control: The Contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS.
The Contractor shall develop and implement procedures to identify, prevent, and ensure non- recurrence of defective services. The Contractor’s Quality Control Program (QCP) is how it assures all performed work complies with the requirement of the contract. Within 30 days after contract award, three copies of a comprehensive written QCP shall be submitted to the KO and COR within 5 working days when changes are made thereafter.
After acceptance of the quality control plan the Contractor shall receive the Contracting Officer’s acceptance in writing of any proposed change to the QCP system.
1.6.2 Quality Assurance: The Government shall evaluate the Contractor’s performance under this contract in accordance…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .