YELLOWTAIL SPILLWAY CONCRETE REPAIR
Solicitation number
140R6021R0023
Issued by

About this file

This solicitation is for concrete repair work on the Yellowtail Spillway. The Department of the Interior Bureau of Reclamation is seeking bids to repair concrete damage at the Yellowtail Spillway. Bids are due by February 21, 2023 under solicitation number 140R6021R0023. The selected contractor will be responsible for performing all necessary concrete repair work to restore the structural integrity of the spillway. Relevant experience with similar concrete repair projects, especially those involving dams and spillways, will be considered in the award decision.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior Bureau of Reclamation Missouri Basin and Arkansas-Rio Grande-Texas Gulf Regions Billings, Montana September 2021

Request for Proposal Solicitation No. 140R6021R0023

Yellowtail Dam Spillway

Tunnel Concrete Repair, Apron Protection, and Rockfall Protection System, Yellowtail Unit, Lower Bighorn Division, Pick-Sloan Missouri Basin Program, Montana

FOR OFFICIAL USE ONLY

i

YELLOWTAIL DAM SPILLWAY TUNNEL CONCRETE REPAIR, APRON

PROTECTION, AND ROCKFALL PROTECTION

YELLOWTAIL UNIT, LOWER BIGHORN DIVISION

PICK-SLOAN MISSOURI BASIN PROGRAM

MONTANA

FOREWORD

Work under these specifications is located in the vicinity of the Yellowtail Dam spillway stilling basin. Yellowtail Dam is located in south central Montana on the Big Horn River, approximately one mile west of Fort Smith, Big Horn County, Montana.

The work to be performed includes the following:

1. Remove and replace damaged portions of concrete along the crown of the spillway tunnel.

2. Construct a reinforced concrete slab on the spillway apron along the east side of the stilling basin, graded to drain into the river channel downstream.

3. Furnish and install fiberglass-reinforced plastic (FRP) grating system between the west stilling basin parapet wall and the adjacent cliff face.

4. Design, furnish, and install a rockfall protection system along the cliff face to the west and south of the spillway stilling basin.

POINT OF CONTACT – The Contract Specialist for this action is Ms. Charlee Maurer. All questions and correspondence concerning this solicitation shall be directed to her via e-mail at camaurer@usbr.gov.

METHOD OF PROCUREMENT – This requirement is solicited as a Request For Proposal using the Federal Acquisition Regulation Part 15, Contracting by Negotiation.

ORGANIZED SITE VISIT – An organized site visit has not yet been scheduled by the Government. An amendment will be issued within three weeks of issuing the solicitation to provide prospective offers with the organized site visit information.

Prospective offerors interested in attending should contact Ms. Maurer via email. All offerors are strongly encouraged to attend this meeting.

CONTRACTOR QUESTIONS – The Government will not address questions received from prospective after 4:00 PM MDT on October 11, 2021.

RECLAMATION SAFETY AND HEALTH STANDARDS (2014 EDITION) – For information regarding Bureau of Reclamation's publication "RECLAMATION SAFETY AND HEALTH STANDARDS" (2014 Edition at http://www.usbr.gov/ssle/safety/RSHS/rshs.html) which is applicable to work under this contract, see clause at "WBR 1452.223-81 SAFETY AND

HEALTH."

mailto:camaurer@usbr.gov http://www.usbr.gov/ssle/safety/RSHS/rshs.html ii

SYSTEM FOR AWARD MANAGEMENT (SAM) – Effective October 2018, all contractors interested in doing business with the Federal Government must be registered in the System for Award Management (SAM) database at the time they submit their offer.

Additionally, the contractors “DUNS and BRADSTREET” and banking information are required for the SAM registration and annual confirmation requirements must be accomplished through the SAM website at https://www.sam.gov. For assistance with registering in SAM, contact the Federal Services Desk at 1-866-606-8220.

INVOICE PROCESSING PLATFORM (IPP) – Payment requests for the anticipated contract or agreement must be submitted electronically through the U.S. Department of Treasury’s “Invoice Processing Platform” (IPP) System via the IPP website at https://www.ipp.gov. Contractors are required to use the IPP website to access and use IPP for submitting request for payment.

Registration assistance can be obtained by contacting the “IPP Production Helpdesk” via email ippgroup@bos.fbr.org or phone 1-866-973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor can submit a waiver request in writing to the Contractor Officer with its proposal. Note: Waivers will be on a case by case basis and not automatically granted as determined by the Contract Officer. Please see Paragraph G.3, DOI-AAAP-0028 for more specific information on the process for submitting invoices in IPP.

https://www.sam.gov/ https://www.ipp.gov/ mailto:ippgroup@bos.fbr.org

Table of Contents - 1

TABLE OF CONTENTS

PART I – THE SCHEDULE

SECTION A -- SOLICITATION, OFFER, AND AWARD, STANDARD FORM 1442

SECTION B -- PRICE SCHEDULE

SECTION C -- DESCRIPTION / SPECIFICATIONS

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Workflow Restrictions 01 32 20 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s On-site Safety Personnel 01 42 10 Reference Standards 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 – EXISTING CONDITIONS

02 70 10 Removal and Control of Water

DIVISION 03 – CONCRETE

03 11 10 Concrete Forming 03 20 00 Concrete Reinforcing 03 20 30 Grouted Anchor Bars 03 30 00 Cast-In-Place Concrete 03 37 10 Shotcrete 03 62 20 Nonshrink Grout for Equipment and Metalwork 03 81 10 Concrete Removal

Table of Contents - 2

DIVISION 05 – METALS

05 12 10 Structural Steel

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 51 30 FRP Grating System

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

DIVISION 31 – EARTHWORK

31 02 10 Water for Dust Abatement 31 23 11 Earthwork for Structures 31 32 32 Geotextile

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 33 23 Rockfall Protection System

DIVISION 33 – EXTERIOR IMPROVEMENTS

33 46 40 Underslab Drainage

DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors 51 20 00 Record of Operations 51 32 00 Rockfall Analysis 51 32 33 Photographs

DIVISION 52 – DRAWINGS

52 00 00 Drawings

DIVISION 53 – GEOLOGIC INVESTIGATIONS AND RECORDS

53 20 00 Records of Geologic and Subsurface Investigations

SECTION D -- NOT USED

SECTION E -- INSPECTION AND ACCEPTANCE

E.1 52.236-5 Material and Workmanship........................................................ E-1 E.2 52.246-12 Inspection of Construction ......................................................... E-1 E.3 52.246-21 Warranty of Construction .......................................................... E-3

SECTION F – DELIVERIES OR PERFORMANCE

F.1 52.211-10 Commencement, Prosecution, and Completion of Work .......... F-1 F.2 52.211-12 Liquidated Damages .................................................................. F-1 F.3 52.211-13 Time Extensions ......................................................................... F-1 F.4 52.211-18 Variation in Estimated Quantity ................................................ F-1 F.5 52.242-14 Suspension of Work ................................................................... F-2

Table of Contents - 3

SECTION G -- CONTRACT ADMINISTRATION DATA

G.1 1452.201-70 Authorities and Delegations ....................................................... G-1 G.2 WBR 1452.201-80 Contracting Officer’s Representative’s Authorities and Limitations .......................................................................... G-2

G.3 DOI-AAAP-0028 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) .......................................................... G-3 G.4 DOI-AAAP-0050 Notice to Contractors – Contractor Performance Assessment Reporting System ....................................................................... G-4

SECTION H -- SPECIAL CONTRACT REQUIREMENTS–

H.1 MB-2 Payment for Technical Data ....................................................... H-1 H.2 MB-10 Implementation of Homeland Security Presidential Directive 12 ............................................................ H-1 H.3 MB-12 Unilateral Modifications – Forward Pricing Rate Agreement ... H-1

PART II – CONTRACT CLAUSES

SECTION I – CONTRACT CLAUSES

I.1 52.252-2 Clauses Incorporated by Reference ........................................... I-1 I.2 52.204-21 Basic Safeguarding of Covered Contractor Information Systems .................................................................. I-3 I.3 52.215-8 Order of Precedence -- Uniform Contract Format ..................... I-5 I.4 52.219-6 Notice of Total Small Business Set-Aside ................................. I-5 I.5 52.219-14 Limitations on Subcontracting ................................................... I-6 I.6 52.219-28 Post-Award Small Business Program Rerepresentation ............ I-7 I.7 52.222-23 Notice or Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction ..................... I-10 I.8 52.223-3 ALT I Hazardous Material Identification and Material Safety Data – Alternate I ............................................................ I-11 I.9 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items ............................................................... I-13 I.10 52.225-9 Buy American–Construction Materials ..................................... I-14 I.11 52.228-2 Additional Bond Security .......................................................... I-18 I.12 52.228-15 Performance and Payment Bonds – Construction ..................... I-18 I.13 52.232-5 Payments Under Fixed-Price Construction Contracts ............... I-19 I.14 52.232-27 Prompt Payment for Construction Contracts ............................. I-22 I.15 52.232-40 Providing Accelerated Payments to Small Business Subcontractors ............................................................................ I-31 I.16 52.236-2 Differing Site Conditions ........................................................... I-31 I.17 52.236-4 Physical Data ............................................................................. I-32 I.18 52.236-13 Accident Prevention ................................................................... I-32 I.19 52.236-14 Availability and Use of Utility Services .................................... I-33 I.20 52.236-21 ALT II Specifications and Drawings for Construction – Alternate II .... I-33 I.21 52.243-4 Changes ...................................................................................... I-34

Table of Contents - 4

I.22 52.252-6 Authorized Deviations in Clauses .............................................. I-35 I.23 1452.203-70 Restriction on Endorsements--Department of the Interior ......... I-36 I.24 1452.204-70 Release of Claims--Department of the Interior .......................... I-36 I.25 WBR 1452.209-82 Prohibition on Release of Information – Bureau of Reclamation ............................................................................... I-36 I.26 1452.215-70 Examination of Records by the Department of the Interior ....... I-36 I.27 WBR 1452.215-87 Incorporation of Technical Proposal .......................................... I-37 I.28 WBR 1452.223-80 Asbestos-Free Warranty............................................................. I-37 I.29 WBR 1452.223-81 Safety and Health -- Bureau of Reclamation ............................. I-37 I.30 WBR 1452.223-82 Protecting Federal Employees and the Public from Exposure to Tobacco Smoke in the Federal Workplace -- Bureau of Reclamation ........................................................... I-38 I.31 1452.228-70 Liability Insurance – Department of the Interior ....................... I-38 I.32 WBR 1452.228-84 Certification or Representatives for Corporate Sureties -- Bureau of Reclamation .............................................................. I-39 I.33 WBR 1452.231-81 Equipment Ownership and Operating Expense -- Bureau Of Reclamation .......................................................................... I-39 I.34 WBR 1452.232-80 Limitation of Funds.................................................................... I-41 I.35 WBR 1452.232-81 Payment for Mobilization and Preparatory Work ALT III Alternative III ............................................................................. I-43 I.36 WBR 1452.232-82 Other Invoice Requirements ...................................................... I-45 I.37 WBR 1452.233-81 Claims Accounting -- Bureau of Reclamation ........................... I-45 I.38 WBR 1452.236-8 Other Contracts (APR 1984) (Deviation) .................................. I-45 I.39 WBR 1452.236-84 Preservation of Cultural Resources -- Bureau of Reclamation .. I-46 I.40 WBR 1452.237-80 Security Requirements -- Bureau of Reclamation ..................... I-48 I.41 WBR 1452.243-80 Modification Proposals – Alternative IV -- Bureau of ALT IV Reclamation ............................................................................... I-61

PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

Attachment No. 1 .........General Decision Number MT20210076, Modification 2, August 6, 2021 Attachment No. 2 ………………..................................................... Standard Form 24 - Bid Bond Attachment No. 3 ……………………………………………………………… Form MB-PIV-1 Attachment No. 4 ………………………………….OF-306 Declaration for Federal Employment Attachment No. 5 ………………………….Limitations of Subcontracting Percentage Worksheet

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K -- REPRESENTATIONS, CERTIFICATIONS AND OTHER

STATEMENTS OF OFFERORS

K.1 52.204-8 Annual Representations and Certifications ...............................K-1 K.2 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment ..............................K-5 K.3 52.209-7 Information Regarding Responsibility Matters ........................K-8 K.4 52.209-13 Violation of Arms Control Treaties or Agreements- Certification ..............................................................................K-9

Table of Contents - 5

SECTION L -- INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS

L.1 52.204-7 System for Award Management ...............................................L-1 L.2 52.204-16 Commercial and Government Entity Code Reporting ..............L-2 L.3 52.204-22 Alternative Line Item Proposal .................................................L-4 L.4 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 ..............................................L-4 L.5 52.211-2 Availability of Specifications, Standards and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) ........................L-5 L.6 52.211-6 Brand Name or Equal ................................................................L-5 L.7 52.214-34 Submission of Offers in the English Language ........................L-6 L.8 52.214-35 Submission of Offers in U.S. Currency ....................................L-6 L.9 52.215-1 Instructions to Offerors – Competitive Acquisition ..................L-6 L.10 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data ...............................L-11 L.11 52.216-1 Type of Contract .......................................................................L-12 L.12 52.222-5 Construction Wage Rate Requirements – Secondary Site of the Work ........................................................................L-12 L.13 52.225-10 Notice of Buy American - Construction Materials ...................L-12 L.14 52.228-1 Bid Guarantee ...........................................................................L-13 L.15 1452.233-2 Service of Protest – Department of the Interior (Deviation) .....L-14 L.16 52.236-27 ALT I Site Visit (Construction) – Alternate I ......................................L-14 L.17 52.236-28 Preparation of Proposals – Construction...................................L-15 L.18 52.252-1 Solicitation Provisions Incorporated by Reference ...................L-15 L.19 52.252-5 Authorized Deviations in Provisions ........................................L-15 L.20 1452.215-71 Use and Disclosure of Proposal Information Department of the Interior ........................................................L-16 L.21 WBR 1452.215-81 Proposal Instructions – Bureau of Reclamation ........................L-17 L.22 WBR 1452.215-86 Intent to Incorporate Technical Proposal ..................................L-22 L.23 WBR 1452.233-82 Notice of Proposed Partnering – Bureau of Reclamation .........L-23 L.24 WBR 1452.236-86 Instruction for Mobilization and Preparatory Work Schedule Line Item – Multiple Schedules ................................L-23

SECTION M -- EVALUATION FACTORS FOR AWARD

M.1 WBR 1452.215-80 Source Selection Evaluation Procedures – Bureau Of Reclamation ..............................................................................M-1 M.2 WBR 1452.215-82 Evaluation Factors for Award – Quality Predominance ...........M-1 M.3 WBR 1452.225-82 Notice of World Trade Organization Government Procurement Agreement Evaluations – Bureau of Reclamation ....................M-5

END OF CONTENTS

PART I – THE SCHEDULE

Bureau of Reclamation Missouri Basin Region Regional Office PO Box 36900 Billings MT 59107

Bureau of Reclamation Missouri Basin Region Attn: Darlene Dillon 2021 4th Ave. North Billings MT 59101

Charlee Maurer 406-247-7819

09/01/2021

, Yellowtail Unit, Lower Bighorn Division, Pick-Sloan Missouri Basin Program, Montana

The Magnitude of this project is between $1 Million and $5 Million.

The North American Industry Classification System (NAICS) code is: 237990, Other Heavy and Civil Engineering Construction.

The Small Business Size Standard is: $39.5 Million.

The Product or Service Description: PSC - Z2KA, Repair or Alteration of Dams

The project is issued as a Total Small Business Set-Aside.

Proposals are to be submitted via email to camaurer@usbr.gov. Our email server limits attachments to 25 MB per message, therefore offerors may need to submit multiple emails in order to ensure we receive their complete proposal (Volumes 1-3).

Taxpayer Identification Number (TIN):______________________________________ Data Universal Number System (DUNS):_______________________________________ Commercial and Government Entity Code (CAGE):______________________________ within

Paragraph F.1

11/01/2021

X

X

Missouri Basin

Gerri Voto-Braun

The Invoicing Processing Platform (IPP) US Department of Treasury https://www.ipp.gov

Yellowtail Dam Spillway Repairs, Apron Protection, and Rockfall System

See attached Continuation of Section B (CLINS 1-14)

00010 1 AU $________________

Yellowtail Dam Spillway – Tunnel Concrete Repair, Apron Protection, and Rockfall Protection System

Price Schedule

B - 1

CONTINUATION OF SECTION B – SUPPLIES OR SERVICES AND PRICES

YELLOWTAIL DAM SPILLWAY

TUNNEL CONCRETE REPAIR, APRON PROTECTION,

AND ROCKFALL PROTECTION SYSTEM

Yellowtail Unit, Lower Bighorn Division

Pick-Sloan Missouri Basin Program Montana

B.1 PRICE SCHEDULES

(a) Offers will be considered for award on the following Price Schedules, but no offer will be considered for award on only a part of the Price Schedules.

(1) Offerors shall complete Price Schedules A and B. Offers for less than the total of Schedules A and B will be considered nonresponsive and will not be evaluated for award.

(2) Offers will be evaluated based on the total of Price Schedules A and B.

(3) The Government will award Price Schedule A or Price Schedules A and B;

depending on available funds.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedules are estimated quantities for comparison of offers only.

Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number

Solicitation 140R6021R0023

Apron Protection, and Rockfall Protection System

Price Schedule

B - 2

PRICE SCHEDULE A

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232

-81

Mobilization and Preparatory Work

For the lump sum of $

2 02 70 10 Removal and Control of Water

For the lump sum of $

3 03 20 30 Drilling Holes for Anchor Bars and Epoxy Grouting Bars in Place

71 LF $

4 03 30 00 Drainage Channel Concrete 171 CY $

5 03 37 10 Shotcrete for Tunnel Repairs 6 CY $

6 03 81 10 Core Drilling 4-inch Holes in Existing Concrete

5 LF $

7 03 81 10 Saw Cutting Existing Concrete

110 LF $

8 03 81 10 Concrete Removal 6 CY $

9 06 51 30 Grating Support System For the lump sum of $

10 06 51 30 FRP Grating 1,760 SF $

11 31 23 11 Excavation for Structures For the lump sum of $

12 31 23 11 Backfill and Compaction about Structures

For the lump sum of $

TOTAL FOR PRICE SCHEDULE A: $_________________

Solicitation 140R6021R0023

Apron Protection, and Rockfall Protection System Solicitation 140R6021R0023

Price Schedule

B - 3

PRICE SCHEDULE B

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

13 WBR

1452.232

-81

Mobilization and Preparatory Work

For the lump sum of $

14 32 33 23 Rockfall Protection System For the lump sum of $

TOTAL FOR PRICE SCHEDULE B: $_________________

TOTAL EVALUATED PRICE* = PRICE SCHEDULES A + B = $_________________

*Note: The Total Evaluated Price is used for evaluation purposes only. The resultant contract will either be the sum of (Price Schedule A) or (Price Schedules A and B) once the availability of funds is known.

END OF SUPPLIES OR SERVICES AND PRICES

Summary of Work

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work under these specifications is located in the vicinity of the Yellowtail Dam spillway stilling basin. Yellowtail Dam is located in south central Montana on the Big Horn River in Big Horn County, approximately 1 mile west of Fort Smith, Montana.

1.02 PRINCIPAL COMPONENTS OF WORK

A. The work to be performed under these specifications includes the following:

1. Remove and replace damaged portions of concrete along the crown of the spillway tunnel.

2. Construct a reinforced concrete slab on the spillway apron along the east side of the stilling basin, graded to drain into the river channel downstream.

3. Furnish and install a fiberglass-reinforced plastic (FRP) grating system between the west stilling basin parapet wall and the adjacent cliff face.

4. Design, furnish, and install a rockfall protection system along the cliff face to the west and south of the spillway stilling basin.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

1.04 DEFINITIONS

A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. CO: Contracting Officer

2. COR: Contracting Officer’s Representative

Summary of Work

01 11 00 - 2

3. FAR: Federal Acquisition Regulations

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Use of Site

01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species

(Technical memorandum No. 86-68220-07-05) 2012 Edition, available online at:

http://www.usbr.gov/mussels/prevention.

1.03 PROJECT CONDITIONS

A. Government land as shown on drawings may be used for required construction facilities.

B. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.

1. Government land on the apron adjacent to the stilling basin may be used for required staging, storage area, and construction facilities.

2. Limited additional staging and storage area for equipment will be provided near the powerplant and at the Government warehouse complex, located approximately one mile from the jobsite.

a. The available staging and storage at the warehouse will be identified at the pre-bid meeting with the Contractor.

b. The Government will not be liable for theft or damage to Contractor’s equipment and supplies while occupying the staging or storage area.

c. These additional staging and storage areas will be provided at no cost to the Contractor.

C. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

D. Areas on Government land below normal water surface (NWS) elevation 3192.0 may be used where use of such land will be discontinued, and construction facilities, materials, equipment, rubbish, and waste materials will be removed prior to refilling of afterbay.

http://www.usbr.gov/mussels/prevention

Use of Site

01 14 10 - 2

E. Housing for construction personnel will not be permitted on Government land.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.

3. Equipment will be inspected in accordance with the procedures described in USBR Cleaning Manual before allowing the equipment onsite.

3.02 RESTORATION

A. Restore Contractor use areas to pre-construction condition.

B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

Workflow Restrictions

01 14 12 - 1

SECTION 01 14 12

WORKFLOW RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, available at https://www.usbr.gov/safety/rshs/index.html

2. FHECP Yellowtail Dam Facility Hazardous Energy Control Program, built from FIST 1-1 which is available at:

www.usbr.gov/power/data/fist_pub.html

1.03 SUBMITTALS

A. Submit in accordance with Section 01 33 00 – Submittals.

B. RSN 01 14 12-1, Afterbay Restriction Request:

1. Outline requirements for accomplishing work including:

a. Afterbay restriction elevation required.

b. Commencement date and duration of work requiring restrictions.

2. Provide information indicating that required materials will be on site, or data indicating shipping dates of materials during restriction period.

3. Refer to Subparagraph 1.06B of this section for more details.

1.04 WORKING HOURS

A. Working hours are 7:00 a.m. to 5:30 p.m., Monday through Saturday, excluding holidays.

B. Contractor shall request the following from the COR in writing:

1. Additional working hours within a single shift (at least 7 days prior to need).

2. Additional full shifts (at least 21 days prior to need).

C. Contracting Officer will notify the Contractor in writing if there are changes to the working hours listed above.

https://www.usbr.gov/safety/rshs/index.html http://www.usbr.gov/power/data/fist_pub.html

Workflow Restrictions

01 14 12 - 2

1.05 SAFETY RESTRICTIONS

A. Work within the spillway tunnel and stilling basin or in the vicinity of the stilling basin will not be allowed without first performing lockout and tagout procedures on the spillway gates per RSHS and FHECP.

B. To minimize the risk of rockfall injuries, work in and around the spillway stilling basin will not be allowed to coincide with work on the abutment slope above.

1. If awarded as part of this contract, work on the rockfall attenuator shall be completed prior to commencement of all other work.

2. If work on the rockfall attenuator is not awarded as part of this contract, the Contractor shall provide temporary rockfall protection for all employees working in and around the spillway stilling basin (refer to Section 01 35 20 – Safety and Health).

1.06 OPERATIONAL RESTRICTIONS

A. At a minimum, work inside the tunnel and stilling basin or below maximum operating water surface elevation 3192.0 will not be allowed between March 1 and August 31 (inclusive) due to annual operational requirements of the spillway (refer to Section 51 20 00 – Record of Operations).

1. Work adjacent to the spillway stilling basin during this timeframe may also be subject to restrictions due to hazards associated with surging from the tunnel outlet during high releases.

2. The Government reserves the right to modify this schedule as needed.

B. From September to February, work inside the tunnel and stilling basin or below maximum operating water surface elevation 3192.0 will require a temporary restriction on the Yellowtail Afterbay elevation, requested at least 60 days in advance by the Contractor.

1. Work inside the tunnel and stilling basin will require the prior installation of stoplogs at the downstream end of the basin by Government personnel to prevent backflow from the afterbay and downstream channel (refer to Section 02 70 10 –

Removal and Control of Water). The maximum water surface elevation allowed in the afterbay during the installation and use of the stoplogs is 3190.0.

2. Work on the downstream end of the concrete drainage structure will require a lower afterbay restriction than the work within the tunnel (refer to Drawing 459-600-60015 and Drawing 459-600-60019 in Section 52 00 00 – Drawings).

The drawdown limit for the Yellowtail Afterbay is 3177.0.

3. Because afterbay restrictions significantly limit production rates at the powerplant as well as river flowrates below the afterbay dam, no restriction request will be considered unless it:

a. Falls within the allowable restriction period (September to February).

Workflow Restrictions

01 14 12 - 3

b. Provides reasonable assurance that materials and equipment required for pertinent work will be onsite or otherwise readily available, and that the

Contractor will be prepared to perform work during the period of time requested.

c. Can be reasonably accommodated based on normal Yellowtail Dam and Afterbay operation schedules.

C. Coordinate and schedule approved afterbay restrictions with COR. When work cannot be performed during an approved restriction period, notify COR that restriction is not required.

D. Reclamation will make every attempt to avoid imposing or altering afterbay restrictions once approved. However, in the unlikely event that emergency operations are required prior to or during approved restrictions, due to unforeseen conditions which could cause an adverse effect on the transmission system operation or reliability (e.g. abnormal electrical loads or extreme weather conditions), Reclamation reserves the right to revoke the applicable restriction, and to return facilities to operating conditions. In such an event:

1. The CO will provide written notification to the Contractor.

2. The Contractor shall remove personnel and equipment from the spillway tunnel, stilling basin, and afterbay within 24 hours of notification.

3. The CO will issue a Stop Work Order as well as supporting modifications to the contract.

1.07 ACCESS RESTRICTIONS

A. Due to scheduling constraints, on-site work will not be permitted prior to September 1, 2022.

B. Access to the spillway tunnel, stilling basin, and apron will require security barricade access along the powerplant service road; access along the spillway inlet service road is controlled by two locked gates and a security barricade. Upon request, Contractor will be issued padlock keys for access past the gates, and a proximity card for access past the barricades. Refer to Drawing No. 459-600-60015 in Section 52 00 00 – Drawings for details.

C. All vehicles and equipment traveling to the stilling basin must pass over the Powerplant Bulkhead Gate Deck, which was designed for AASHTO H-20 loading (see Information Drawing No. 459-600-205). At the west end of this deck, sharp turns and slope changes further restrict equipment access (see Photos 2 through 5 in Section 51 32 33 –

Photographs).

D. Other contractors may be working in the area of the Powerplant during execution of this contract. Access may be restricted near the Powerplant and across the bulkhead due to other contractors’ operations.

Workflow Restrictions

01 14 12 - 4

E. The Government will provide an aluminum staircase for access into the stilling basin and tunnel (refer to Photo 19 in Section 51 50 00 – Photographs). The Contractor shall be responsible for installing, maintaining, and removing the staircase, with facility assistance upon request.

F. Contractor requests for facility assistance must be conducted during facility working hours (Monday through Thursday, 7 a.m. to 5:30 p.m.).

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Yellowtail Dam Spillway – Tunnel Concrete Repair

Construction Program

01 32 20 - 1

SECTION 01 32 20

CONSTRUCTION PROGRAM

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. Schedule: The Critical Path Method (CPM) of planning and scheduling a construction project where activities are arranged based on activity relationships and network calculations determine when activities can be performed and the critical path of the project.

B. Project Calendar(s): Cross reference of numerical work days with calendar days. The project calendar serves as the basis for the day/date conversion and assigns work days and non-workdays.

C. Cost loading: Contractor earnings based on payments from Government to Contractor.

1.03 REFERENCE STANDARDS

A. Associated General Contractors of America (AGC)

1. AGC Manual-04 Construction Planning and Scheduling Manual

B. Bureau of Reclamation (USBR)

1. Project Management Framework Available on the Internet at:

https://www.usbr.gov/pm/docs/Project- Management-Framework-Report.pdf

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 – Submittals.

1. Furnish schedule and analysis data in PDF format.

2. Upon request, provide information and data used to develop and maintain the Construction Program to the COR.

B. RSN 01 32 20-1, Baseline Schedule:

1. Include:

a. Construction Program/Schedule database.

https://www.usbr.gov/pm/docs/Project-Management-Framework-Report.pdf https://www.usbr.gov/pm/docs/Project-Management-Framework-Report.pdf

Construction Program

01 32 20 - 2

b. Definition of project calendars.

c. Gantt chart (bar chart) for project.

C. RSN 01 32 20-2, Updated Schedule:

1. Include:

a. Construction Program database with updated activity and milestone data.

b. Definition of project calendars if revised from baseline calendars.

c. Gantt chart (bar chart) for project.

d. Narrative report.

1) Provide a written narrative stating status of project including the data date represented by the project.

2) List of Contractor-initiated changes to the current schedule stating the reason for the action taken and any unresolved issues relating to the Construction Program. Government reserves the right to reject Contractor-initiated changes to the current schedule that negatively impact any Government action that was initiated based on the current schedule.

3) If negative float exists, cite specific actions and conditions which caused the "behind schedule" condition and provide proposed course of action to complete the project within the specified delivery time.

1.05 SCHEDULE

A. Develop, maintain, and use approved Construction Program to plan, monitor, report, and evaluate accomplishment of work.

B. Prepare construction schedules using Critical Path Method outlined in AGC Manual.

C. Failure to include any element of the work will not release Contractor from completing all required work under the contract.

D. Construction Program:

1. Prepare detailed activity network for accomplishing required work organized by work breakdown structure.

2. Prepare schedule based on required sequence and interdependence of activities.

3. Include work of subcontractors, Government interfaces, and contract milestones.

4. Include contract title, contract number, data date, and Contractor's name on each sheet.

5. Include Yellowtail Afterbay drawdown period(s), as well as tasks to be performed during drawdown (refer to Section 01 14 12 – Workflow Restrictions).

Construction Program

01 32 20 - 3

6. Adjust Construction Program/schedule for seasonal weather conditions.

7. Define activities to a level of detail resulting in their durations being no greater than 20 workdays.

a. Durations for administrative activities (e.g., submittals and reviews, fabrication, manufacturing), or other specific activities identified in the contract will not be subject to the workday limitation.

8. Use durations in units of whole workdays.

9. Include activities for Government reviews and approvals of submittals that are critical to the project completion data.

10. Update schedule with changes directed by contract modifications or approved changes to sequencing.

E. Baseline Schedule:

1. Represents Contractor’s as-planned approach to accomplishing the work.

2. Include planned start and completion dates for features of work.

F. Updated Schedules:

1. Enter actual progress.

2. Assign a unique project file name for each schedule update.

G. Contract Change or Delay:

1. Submit a time impact evaluation within 14 days of contract change or delay, showing effects of change order or delay on the progress schedule.

2. Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed the contract milestone dates.

H. Float is not for the exclusive use by or benefit of either the Government or the

Contractor.

I. If in the opinion of the CO, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the CO.

1. The CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

2. Costs for actions required to improve progress will be the responsibility of the Contractor.

Construction Program

01 32 20 - 4

1.06 FAILURE TO COMPLY

A. Failure to comply with the requirements of this section shall be grounds for a determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the specified time.

B. The CO may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Apron Protection, and Rockfall Protection System Specification No. 60-C0647

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included in this section take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

C. Drawings:

1. Minimum identification in title block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

01 33 00 - 2

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Size: ANSI D size (22 inches by 34 inches) as defined by ASME Y14.1.

4. Draw to scale using computer drafting.

a. In accordance with NIBS NCS.

b. Electronic file format: Compatible with AutoCAD, Version 2018 or later.

c. Compile using “eTransmit” utility in AutoCAD.

d. Government will provide an electronic AutoCAD template.

e. Title block and sheet format:

1) Government will supply template.

2) Government will supply specific title block information to be used.

f. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

D. Manuals:

1. Copies:

a. Printed copies: Bound and indexed.

b. Electronic copies: Adobe pdf on thumb drive.

1) Bookmark longer files to assist in navigating file.

2. Contents:

a. Parts identification lists, lists of special tools, and accessories.

b. Detailed instructions for installing and maintaining equipment.

c. As-built drawings, photographs, and test records or reports if required by the specifications.

E. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

F. Samples Submittals:

1. Label with complete manufacturer’s product and color identification.

01 33 00 - 3

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

G. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

H. Photographs:

1. Professional quality, 8 inches by 10 inches, color, for each listed view.

a. Include contract number, name of equipment, and view title.

b. Include digital files in .jpeg or similar format.

I. Videos:

1. Include digital file in MP4 format.

2. Submit on thumb drive.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A – List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “No. of sets to be sent:” columns in Table 01 33 00A

– List of Submittals.

1. Electronic submittals:

a. In Portable Document Format (PDF).

1) Optical Character Recognition (OCR).

2) 508 compliant.

3) RSNs having more than one requirement shall be bookmarked.

4) RSNs with requirements for files other than PDF (e.g. .XER, .PLF, .DWGs, etc.) shall be combined using WINZip.

b. Include RSN transmittal letter.

c. Personally Identifiable Information (PII) shall be encrypted using WINZip or Adobe Acrobat before transmitting electronically.

2. Submit electronic submittals via e-mail or thumb drive based on size:

01 33 00 - 4

a. The Government can receive e-mails up to 25 MB. However, e-mails over 10 MB should be considered extra-large. E-mailing of electronic submittals exceeding 10 MB should only occur after transmittal of extra-large e-mail has been verified.

b. Address e-mail of electronic submittals less than extra-large size to:

1) mkimmet@usbr.gov and jnoland@usbr.gov

c. Electronic submittals that are too large to e-mail shall be submitted on thumb drive.

d. Submittals received after 5:00 p.m. Mountain Time, shall be documented as received the next business day.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

a. Resubmitted drawings shall include a revision block with date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 7 days after receiving comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

5. Resubmittals shall be complete submittals without reference to the original submittal.

F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return e-mail date.

mailto:mkimmet@usbr.gov mailto:jnoland@usbr.gov

01 33 00 - 5

B. Time in Excess of Specified:

1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.

a. Time extension will be to extent that excess review time caused delay to contract completion date.

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two (2) or more separate submittals or resubmittals will be counted only once in extending contract completion date.

2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to extent that:

a. Approval was required under contract, and

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR

52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Submittal Response:

1. Response letter will indicate whether the submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt.

a. Revise and resubmit submittals not approved or not acceptable.

b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.

1.07 TRANSMITTAL

A. Addresses for codes receiving paper copy submittals listed in Table 01 33 00A – List of Submittals:

1. CO: Bureau of Reclamation, Attention: GP-5000, P.O. Box 36900, Billings, MT

59107-6900. Physical address: 2021 4th Avenue North, Billings, MT 59101.

2. COR: Bureau of Reclamation, Attention: MT-430 (Noland), P.O. Box 30137.

Physical address: 2900 4th Ave North Suite 501, Billings, MT 59101.

B. E-mail address for electronic submittals listed in Table 01 33 00A – List of Submittals:

mkimmet@usbr.gov and jnoland@usbr.gov.

1. Submit electronic submittals that are too large for e-mail to the physical address above.

mailto:mkimmet@usbr.gov mailto:jnoland@usbr.gov

01 33 00 - 6

C. Submittals required by specifications, but not listed in Table 01 33 00A – List of Submittals:

1. Submit in accordance with this section.

2. Submit to COR unless otherwise specified.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used Table 01 33 00A. – List of Submittals

*CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent:*

CO COR

1 Performance and Payment Bonds - Construction 52.228-15

Performance and Payment Bonds

Within 10 calendar days after award

CO 1 electronic 0

2 Additional Bond Security 52.228-2

Additional Bond Security Within 10 calendar days after award

CO 1 electronic 0

3 Insurance-Work on a Government Installation 1452.228-70

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

Before commencing on-site work

CO 1 electronic

1 electronic

4 Liability Insurance 1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1 electronic 0

5 Equal Opportunity 52.222-26

Information required by Executive Order 112246

(SF-100)

Within 30 days following award

CO 1 electronic 0

6 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10

Certification that executive compensation and subcontract awards were reported

Within 10 days of each report being submitted

CO 1 electronic 0

7 Release of Claims 1452.204-70

Release of Claims (DI-137) against the Government

After completion of the work and prior to final payment

CO 1 electronic 0

8 Personal Identity Verification 52.204-09

SF-85 and OF-306 for each employee and subcontractor employee working on site

Within 10 days after receipt of Notice to Proceed or 45 days before commencing on-site work (for new hire)

CO 1 electronic 0

01 33 00 - 7

Table 01 33 00A. – List of Submittals *CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Respon-sible code

Sets to be sent:*

CO COR

9 Labor Standards Data 52.222-11

1)…