Brackish Groundwater National Desalination Research Facility (BGNDRF) Portable Media Filter for PFAS Removal
Solicitation 140R4021Q0004
BUREAU OF RECLAMATION
ALBUQUERQUE AREA OFFICE
SEE ADDENDUMIS CHECKED
CODE 18a. PAYMENT WILL BE MADE BY
CODE
FACILITYCODE
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
OFFEROR
R4Q
555 Broadway Blvd NE, Suite 100 Albuquerque Area Office Upper Colorado Region Bureau of Reclamation
0009910000 CODE 16. ADMINISTERED BYCODE
X
X
333999
SIZE STANDARD:
% FOR:SET ASIDE:UNRESTRICTED ORR40
RFPIFB
10. THIS ACQUISITION ISCODE
RFQ
14. METHOD OF SOLICITATION
13b. RATING
NAICS:
SMALL BUSINESS
02/05/2021 1700 MT
01/06/2021
505-462-3602Tina Villegas (No collect calls)
INFORMATION CALL:
FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME
4. ORDER NUMBER3. AWARD/ 6. SOLICITATION
140R4021Q0004
5. SOLICITATION NUMBER
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF
1 30 OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
Albuquerque NM 87102
TELEPHONE NO.
17a. CONTRACTOR/
Alamogordo NM 88310 500 La Velle Rd Alamogordo Field Division Bureau of Reclamation-UC-BGNDRF
15. DELIVER TO
Salt Lake City UT 84138 125 South State Street, Room 8100 Regional Office Upper Colorado Region
9. ISSUED BY
7.
2. CONTRACT NO.
EFFECTIVE DATE
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
ISSUE DATE
DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
11.
SEE SCHEDULEX
12. DISCOUNT TERMS
THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13a.
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
8(A)
Bureau of Reclamation
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
The Brackish Groundwater National Desalination Research Facility (BGNDRF) in Alamogordo, New Mexico has a need for a portable media filtration system to remove Per- and poly-fluorinated substances (PFAS) as per the attached Statement of Objectives (Attachment 1).
The Government intends to award a firm fixed-price contract in accordance with FAR Part
13. The Government will award to the Offeror whose proposal offers the best value in terms of
(Use Reverse and/or Attach Additional Sheets as Necessary)
HEREIN, IS ACCEPTED AS TO ITEMS:
X
DATED
Kristen Ruiz Jimenez
. YOUR OFFER ON SOLICITATION (BLOCK 5),
INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
ARE
ARE
31c. DATE SIGNED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL
SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
OFFER
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
ARE NOT ATTACHED.
ARE NOT ATTACHED.
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
30b. NAME AND TITLE OF SIGNER (Type or print)
30a. SIGNATURE OF OFFEROR/CONTRACTOR
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
25. ACCOUNTING AND APPROPRIATION DATA
29. AWARD OF CONTRACT:
REF.
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER
37. CHECK NUMBER
FINALPARTIAL
36. PAYMENT
FINALPARTIAL
35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER33. SHIP NUMBER
COMPLETE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)
42b. RECEIVED AT (Location)
42a. RECEIVED BY (Print)
41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
STANDARD FORM 1449 (REV. 2/2012) BACK
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
technical capability and cost. Within the best value continuum, the Government will employ a tradeoff analysis of cost or price and non-cost factors in evaluating the proposal submitted in accordance with FAR Part 13.
Please include a completed schedule of services with your proposal submission see Attachment 2.
Pricing must include all applicable taxes and fees.
Any solicitation questions or clarification requests must be submitted via email to Tina
Villegas at tvillegas@usbr.gov no later than
January 21, 2021 at 1700 MT.
Solicitation response is due February 5, 2021 by
1700 MT via email to Tina Villegas at tvillegas@usbr.gov.
Period of Performance: 02/26/2021 to 06/26/2021
00010 Portable Media Filter for PFAS Removal
Product/Service Code: 4610
Product/Service Description: WATER PURIFICATION
EQUIPMENT
32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
30 2 of
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 3 of 30
Contract Clauses:
52.204-13 System for Award Management Maintenance. (OCT 2018)
52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020)
52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. (NOV 2015)
52.211-5 Material Requirements. (AUG 2000)
52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Items). (OCT 2020)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) (Section 1634 of Pub. L. 115-91).
(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (AUG 2020) (Section 889(a)(1)(A) of Pub. L. 115-232).
(iv) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
(v) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(vi) 52.222-26, Equal Opportunity (SEP 2016) (E.O. 11246).
(vii) 52.225-13, Restrictions on Certain Foreign Purchases (JUN 2008) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(viii) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(ix) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub.
L. 108-77, 108-78 (19 U.S.C. 3805 note).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (APR 1984).
(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).
(iii) 52.232-11, Extras (APR 1984).
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 4 of 30
(iv) 52.232-25, Prompt Payment (JAN 2017).
(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).
(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (DEC 2013).
(vii) 52.233-1, Disputes (MAY 2014).
(viii) 52.244-6, Subcontracts for Commercial Items (AUG 2020)
(ix) 52.253-1, Computer Generated Forms (Jan 1991).
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at or above the threshold specified in FAR 4.1403(a) on the date of award of this contract).
(ii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2020) (E.O. 13126). (Applies to contracts for supplies exceeding the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract).
(iii) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment (JUN 2020) (41 U.S.C. chapter 65) (Applies to supply contracts over the threshold specified in FAR 22.602 on the date of award of this contract, in the United States, Puerto Rico, or the U.S. Virgin Islands).
(iv) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).
(v) 52.222-36, Equal Employment for Workers with Disabilities (JUN 2020) (29 U.S.C. 793) (Applies to contracts over the threshold specified in FAR 22.1408(a) on the date of award of this contract, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, "United States" includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)
(vi) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).
(vii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C.
chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).
(viii)(A) 52.222-50, Combating Trafficking in Persons (OCT 2020) (22 U.S.C.
chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 5 of 30
(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).
(ix) 52.222-55, Minimum Wages Under Executive Order 13658 (DEC 2015) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia)).
(x) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017) (E.O.
13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))
(xi) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2011) (E.O. 13423) (Applies to services performed on Federal facilities).
(xii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693)(applies to contracts for products as prescribed at FAR 23.804(a)(1)).
(xiii) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (JUN 2016) (E.O. 13693) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).
(xiv) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR® Program or Federal Energy Management Program (FEMP) will be-
(A) Delivered;
(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;
(C) Furnished by the Contractor for use by the Government; or
(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance).
(xv) 52.223-20, Aerosols (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).
(xvi) 52.223-21, Foams (JUN 2016) (E.O. 13693) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent; or contracts for construction of buildings or facilities.
(xvii) 52.225-1, Buy American-Supplies (MAY 2014) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 6 of 30 micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract, and the acquisition-
(A) Is set aside for small business concerns; or
(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000).
(xviii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN 2020) (42 U.S.C. 1792) (Applies to contracts greater than the threshold specified in FAR 26.404 on the date of award of this contract, that provide for the provision, the service, or the sale of food in the United States).
(xix) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information).
(xx) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)
(xxi) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. App. 1241) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)
(2) Listed below are additional clauses that may apply:
(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (JUN 2016) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.
(ii) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020) (Applies to contracts over the threshold specified in FAR 9.405-2(b) on the date of award of this contract).
(iii) 52.211-17, Delivery of Excess Quantities (SEP 1989) (Applies to fixed-price supplies).
(iv) 52.247-29, F.o.b. Origin (FEB 2006) (Applies to supplies if delivery is f.o.b.
origin).
(v) 52.247-34, F.o.b. Destination (NOV 1991) (Applies to supplies if delivery is f.o.b. destination).
(c) FAR 52.252-2, Clauses Incorporated by Reference (FEB 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text.
Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
FAR and DOI Clauses – https://www.acquisition.gov/far/
(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require https://www.acquisition.gov/far/
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 7 of 30 repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its post acceptance rights-
(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.
(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(End of clause)
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (JUN 2020)
52.225-3 Buy American - Free Trade Agreements - Israeli Trade Act. (MAY 2014) - Alternate II
(MAY 2014)
52.232-23 Assignment of Claims. (MAY 2014)
52.242-17 Government Delay of Work. (APR 1984)
52.243-1 Changes - Fixed-Price. (AUG 1987)
52.244-6 Subcontracts for Commercial Items. (OCT 2020)
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 8 of 30
1452.201-70 Authorities and delegations (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority.
The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 9 of 30
WBR 1452.201-80 Contracting Officer’s Representative’s Authorities and Limitations -- Bureau of Reclamation (MAY 2018)
(a) Performance of the work under this contract shall be subject to the technical direction of the Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:
(1) Inspecting and accepting or rejecting work performed under the contract.
(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.
(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.
(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer. (c) Technical direction must be within the scope of work stated in the contract. Only the Contracting Officer is authorized to determine if a change is within the scope of the contract; therefore, the COR does not have the authority to, and may not, issue any technical direction that -
(1) Constitutes a direction of additional work outside the Contract requirements;
(2) Constitutes a change as defined in the contract clause entitled “Changes;”
(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;
(4) Changes any of the expressed terms, conditions or specifications of the contract; or
(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.
(d) All technical direction shall be issued in writing by the COR.
(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -
(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or
(2) Advise the Contractor that the Government will issue a written change order.
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 10 of 30
(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”
(End of clause)
WBR 1452.237-80 Security Requirements – Bureau of Reclamation (February 2017)
(a) General Security Requirements:
(1) This clause addresses security requirements, including general procedural requirements, information security requirements, contractor employee suitability requirements, identification card requirements, site security requirements, vessel exclusion barriers, and information technology security requirements. Within this clause, COR means Contracting Officer's Representative. If there is no COR appointed and identified to the Contractor, the term instead will mean the Program Manager or any other authorized individual responsible for technical oversight under the contract. “Work site” means the Government facility, office, construction site, and any other area within the Government office or facility that the Contractor must access to accomplish work under this contract.
(2) The work performed under this contract shall only be accomplished by individuals (in the employment of the Contractor or any subcontractors) whose conduct and behavior is consistent with the efficiency of the Federal Service and the requirements of this contract, and who are acceptable to the CO. If Reclamation finds a Contractor employee to be unsuitable or unfit for his or her assigned duties, the CO will direct the Contractor to remove the individual from the contract and access to the Federal facility at which the contract activities are occurring.
(3) The Contractor’s employees governed by this contract may need access to sensitive information and/or sensitive areas. The Federal Government (Government) reserves the right, in its sole discretion, to determine suitability of Contractor personnel and deny access to any sensitive information or project specific area to any personnel for any cause.
(4) The Contractor is responsible for informing and ensuring compliance by its employees with any applicable security procedures of the Government facility where work may be performed under this contract.
(5) Any Contractor employee that will have access to a Federally-controlled facility or information system will be required to have a Government-issued identification card, consisting of a Personal Identity Verification (PIV) Card, a temporary identification card, or a visitor badge. (Note: within the Department of the Interior this card is known as a DOI Access Card.) During performance of the contract, the Contractor shall keep the COR apprised of any changes in personnel, or changes in personnel access or duration, to ensure that performance is not delayed by compliance with credentialing processes.
(6) A Contractor employee will not be provided access to a Government facility or information system until a Government PIV Card, temporary identification card, or visitor identification badge has been issued to the Contractor employee. For those individuals that will be receiving a PIV Card, the Government may, at its discretion, issue a temporary identification card or visitor identification badge after the electronic background investigation forms have been received and the investigation is initiated.
(7) All Contractor employees shall access the facility via the facility’s entry screening system and visibly display the Government-issued PIV Card, temporary identification card, or visitor identification badge at all times. Contractor employees must visibly wear the Government-issued identification card at all times they are on Government facilities. Contractor employees are responsible for the safekeeping of all Government-issued identification cards, whether on-site or off-site. Cards that have been lost, damaged, or stolen must be reported to the COR and DOI Access Sponsor within 24 hours. The Contractor shall return
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 11 of 30 all identification cards and card keys and any other Government property and information upon completion of performance or when personnel depart permanently or for a period of 7 days or more. The Contractor may be required to turn in access control cards or identification cards on a daily basis.
(8) Misuse or loss of access control or identification cards, or failure to comply with required surrender of such cards may, at Government discretion, result in Contractor personnel being denied access to the work site, at no cost to Government. The Contractor may be charged up to $500 for each occurrence for any required replacement of Government-issued access control or identification cards due to loss or misuse. At the end of contract performance, or when a Contractor employee is no longer working under this contract, the Contractor shall ensure that all access control and identification cards are returned to the COR.
(9) All Contractor personnel, including subcontractor personnel, with access to the work site shall be U.S.
citizens or foreign individuals legally residing in, or legally admitted to, the U.S. For all non-U.S. citizens working under this contract, irrespective of length of time working on the contract, the Contractor shall provide to the COR, legible and valid copies of the individual’s passport and visa (unless individual is on the Visa Waiver Program) a minimum of 14 calendar days prior to beginning work or arriving at the facility. A driver’s license is not acceptable identification. In addition, a completed form I-94 shall be submitted to the COR upon the individual’s arrival at the work facility and prior to beginning work.
(10) The Contractor shall report all contacts with entities, individuals, and counsel/representatives (including foreign entities and foreign nationals) who seek in any way to obtain unauthorized access to sensitive information or areas. The Contractor shall report any violations of contract provisions, laws, executive orders, regulations, and guidance to the Contracting Officer (CO). The Contractor shall report any information raising a doubt as to whether an individual’s eligibility for continued employment or access to sensitive information is consistent with the interests of National Security and the Public Trust.
(11) Unsanctioned, negligent, or willful inappropriate action on the part of the Contractor (or its employees) may result in termination of the contract or removal of some Contractor employees from Reclamation facilities at no cost to the Government. These actions include, but are not limited to, exploration of a sensitive system and/or information, introduction of unauthorized and/or malicious software, inappropriate release of sensitive information, or failure to follow prescribed access control policies and/or security procedures. Failure to comply with Reclamation policies, procedures, or other published security requirements may result in termination of the contract or removal of some contracted employees from Reclamation buildings and/or facilities at no cost to the Government.
(12) All provisions of this clause shall equally apply to all subcontractors. The Contractor shall incorporate the substance of this clause in all subcontracts.
(13) These security requirements apply to all sections of this Contract including Contract Drawings and other Contract Specifications as applicable. Related documents include other general provisions of Construction or Operations and Maintenance type Contracts, including FAR clauses by reference or as amended by related documents.
(b) Information Security Requirements.
(1) Sensitive Information. The term “sensitive information” means any information which warrants a degree of protection and administrative control as defined by Reclamation or that meets the criteria for exemption from public disclosure set forth under Sections 552 and 552a of Title 5, United States Code: the Freedom of Information Act and the Privacy Act. Sensitive information is generally categorized as FOR OFFICIAL USE ONLY (FOUO) information or CONTROLLED UNCLASSIFIED INFORMATION (CUI), but in some cases may include other unclassified information. (The protection of National Security information is beyond the scope of this clause. If any work on National Security information is required under this contract, it is addressed under other contract clauses.) The Contractor shall protect this type of information from unauthorized release into public domain, or to unauthorized persons, organizations, or
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 12 of 30 subcontractors. Information which, either alone or in aggregate, is deemed sensitive by Reclamation shall be handled and protected in accordance with Reclamation directives and standards for identifying and safeguarding sensitive information (SLE 02-01), which is available from the COR or at http://www.usbr.gov/recman/DandS.html#sle.
(i) Any Government-furnished information or material does not become the property of the Contractor and may be withdrawn at any time. Upon expiration or termination of the contract, all documents released to the Contractor and any material created using data from such documents shall be returned to the COR for final disposition. Government-furnished information residing on any electronic systems (laptops, servers, desktops, media) shall be deleted from those systems using a COR-approved data erasure solution. Only with prior authorization from the CO may the Contractor retain the material. The Contractor or subcontractor shall not disclose or release the materials provided to the Contractor to any individuals of the Contractor's organization not directly engaged in providing services under the contract or that do not have a valid need-to-know. All technical data provided to the Contractor by the Government shall be protected from public or private disclosure in accordance with the markings printed on them. All other information relating to the items to be delivered or the services to be performed under this contract shall not be disclosed by any means without prior approval of the CO. Prohibited dissemination or disclosure includes, but is not limited to: permitting access to such information by foreign nationals or by immigrant aliens who may be employed by the Contractor, publication of technical or scientific papers, advertising, disclosure to Contractor staff not investigated and deemed acceptable at the appropriate information sensitivity level, and any other public release. The Contractor shall maintain, and furnish upon request of the CO, records of the names of individuals who have access to sensitive material in its custody. All questions regarding information security, access, and control shall be referred to the COR.
(ii) The Contractor shall not release to anyone outside the Contractor’s organization any sensitive, or otherwise protected information, regardless of medium in which it is contained (for example, film, tape, document, electronic), pertaining to any part of this contract or any Reclamation program or activity, unless the CO has given prior written approval. This includes, but is not limited to, news releases, marketing promotions, articles, interviews, reports, social media posts, and any other media releases. Requests for approval shall identify the specific information to be released, the medium to be used, the purpose for the release, and a description of the need-to-know. The Contractor shall submit its request to the CO ten business days before the proposed date for release. Subcontractors shall submit requests for authorization to release through the prime Contractor to the CO.
(iii) The Contractor shall notify the COR immediately when known or suspected loss/compromise of sensitive information or other documents, notes, drawings, sketches, reports, photographs, exposed film or similar information which may affect the security interests of Government has occurred. This requirement extends to employees and other personnel working on behalf of the Contractor, and expands responsibility to include prompt reporting of security issues, including observed or subsequently discovered efforts by unauthorized persons to gain unauthorized access to sensitive information.
(2) Classified Information.
(i) The disclosure of U.S. Government documents by third parties can result in damage to our national security. While this contract may not deal directly with classified information, each contractor is obligated to protect classified information pursuant to all applicable laws and to use Government information technology systems in accordance with agency procedures so that the integrity of such systems is not compromised.
(ii) Unauthorized disclosures of classified documents (whether in print, on a blog, or on websites, or other electronic or non-electronic media) do not alter the documents' classified status or automatically result in declassification of the documents. To the contrary, classified information, whether or not already posted on public websites or disclosed to the media, remains classified, and must be treated as such by Federal employees and contractors, until it is declassified by an appropriate U.S. Government authority. Executive Order 13526, Classified National Security Information (December 29, 2009), Section 1.1.(c) states, 140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 13 of 30
"Classified Information shall not be declassified automatically as a result of any unauthorized disclosure of identical or similar information." Although the Department has taken steps to prevent access to publicly disclosed classified materials from Departmental computers, it is important to understand our continuing duties and responsibilities in this regard.
(iii) Contractors (which include all employees of the contractor, as well as subcontractors and its employees performing work for the contractor) are reminded of the following obligations with respect to the treatment of classified information and the use of unclassified government information technology systems:
(iv)The contractor shall not, while using unclassified Government computers or other devices (such as phones or tablets) access documents that are marked classified (including classified documents made publicly available by a third party), as doing so risks that material still classified will be placed onto unclassified systems. This requirement does not restrict contractor access to unclassified, publicly available news reports (and other unclassified material) that may in turn discuss classified material, as distinguished from access to underlying documents that themselves are marked classified (including if the underlying classified documents are available on public web sites or otherwise in the public domain).
(v) For contracts that require access to classified information, the contractor is responsible for obtaining the required national security clearance through the Department of the Defense National Industrial Security Program Operating Manual (NISPOM). Any classified contracts will be coordinated through the Reclamation Chief Security Officer, or for IT requirements, the Bureau Chief Information Security Officer. No contractor shall access classified information unless proper clearances have been obtained and transmitted to Reclamation. For further information, refer to 443 DM 1 or DOD NISPOM 5220.22-M dated February 28, 2006 (incorporating change 2 dated May 18, 2016). \
(vi) Classified information shall not be removed from official premises.
(vii) Classified information shall not be disclosed without proper authorization.
(End of clause)
WBR 1452.242-80 POSTAWARD CONFERENCE --BUREAU OF RECLAMATION (JUL 1993)
(a) Prior to the Contractor starting work, a postaward conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.
(b) The conference will be held at the Brackish Groundwater National Desalination Research Facility, 500 LaVelle Road, Alamogordo, NM 88310.
(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting Officer shall establish the date for the conference.
(d) The Contractor shall include any associated costs for attendance at the conference, in its offer.
(End of clause)
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 14 of 30
WBR 1452.243-80 MODIFICATION PROPOSALS -- BUREAU OF RECLAMATION (DEC 2001)
(a) In submitting any proposal for a modification under this contract (including any proposal for an equitable adjustment resulting from a change under the Changes clause of this contract), the Contractor shall:
(1) Comply with the contract time limits for submission of a proposal or as specified by the Contracting Officer;
(2) Apply the contract cost principles and procedures in Part 31 of the Federal Acquisition Regulation (FAR) in effect on the date of this contract;
(3) Furnish a breakdown of all costs estimated to complete the work required by the modification (i.e., cost of added work, incurred cost of deleted work already performed, estimated cost of deleted work not yet performed, and net cost of the modification) to include all costs associated with materials (identified by item and quantity), equipment (identified by item, quantity and whether contractor-owned or rented), categories of direct labor, bond and insurance premium adjustments, subcontracts, overhead and other indirect costs, profit/fee, and any other pricing information requested by the Contracting Officer, in sufficient detail to permit an analysis of fair and reasonable price;
(4) Furnish a written justification for any requested time extensions; and
(5) For any pricing adjustment expected to exceed $500,000 (considering both increases and decreases) --
(i) Submit cost and pricing data using the format specified in Table 15-2 of FAR 15.408 unless the Contracting Officer agrees that an exception applies under the circumstances set forth in FAR 15.403-1;
(ii) Certify in substantially the format prescribed in FAR 15.406-2 that to the best of its knowledge and belief, the data are accurate, complete and current as of the date of agreement on the negotiated price of the modification; and
(iii) Comply with the requirements of either the Subcontractor Cost or Pricing Data clause or the Subcontractor Cost or Pricing Data -- Modifications clause of this contract when the adjustment includes a subcontract modification involving a pricing adjustment expected to exceed 500,000.
(b) Under the Changes clause of this contract, failure of the Contractor to timely assert its right for an adjustment or to submit a proposal for an adjustment by the date specified in the clause (or another date specified by the Contracting Officer) may result in a unilateral adjustment of the contract by the Contracting Officer pursuant to the Disputes clause of this contract.
(End of clause)
DOI-AAAP-0028 Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)
Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP).
"Payment requests" means any request for contract financing payment or invoicing payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions-Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, submit an electronic copy of the invoice to the Contracting Officer Representative (COR) to sign and copy the Contracting Officer and Contract Specialist. Once the invoice is signed by the COR, then upload and submit signed invoice to IPP. Failure to email the invoice correctly may cause significant delay or possible rejection of your payment request.
Contracting Officer, Kristen Ruiz Jimenez at kruizjimenez@usbr.gov Contract Specialists, Tina Villegas at tvillegas@usbr.gov http://www.ipp.gov/ http://www.ipp.gov/ mailto:kruizjimenez@usbr.gov mailto:tvillegas@usbr.gov
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 15 of 30
Contracting Officer Representative, Randy Shaw at zstoll@usbr.gov
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in CCR) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3-5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause) mailto:zstoll@usbr.gov mailto:ippgroup@bos.frb.org%20
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 16 of 30
Contract Provisions:
52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
FAR and DOI Clauses - https://www.acquisition.gov/far/
The following provisions are included by reference:
52.204-7 System for Award Management. (OCT 2018)
52.204-16 Commercial and Government Entity Code Reporting. (AUG 2020)
52.204-22 Alternative Line Item Proposal. (JAN 2017)
(End of provision)
52.204-8 Annual Representations and Certifications. (MAR 2020)
(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 333999 - All Other Miscellaneous General Purpose Machinery Manufacturing.
(2) The small business size standard is 500 employees.
(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.
(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.
(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:
___ (i) Paragraph (d) applies.
___ (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:
(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless-https://www.acquisition.gov/far/
140R4021Q0004 – BGNDRF Portable Media Filter for PFAS Removal Page 17 of 30
(A) The acquisition is to be made under the simplified…