Sol_140P8626R0007.pdf
PDF 599 KB Posted
- Attached to
- REPLACE WATER METERS MARIN HEADLANDS Federal contract opportunity
- Solicitation number
- 140P8626R0007
About this file
This is a Solicitation, Offer, and Award (Standard Form 1442) for a construction contract to replace water meters at three locations within Golden Gate National Recreation Area in Marin County, California.
The National Park Service seeks a contractor to remove and dispose of existing water meters and install new lead-free, cold water ultrasonic water meters with two-way endpoints for mobile reading and data collection across Fort Cronkhite (36 meters), Fort Baker (61 meters), and Fort Barry (23 meters), for a total of 120 meters. The work includes replacement of associated fittings and Crissy boxes where needed. This is a Total Small Business Set-Aside acquisition with a NAICS code 238220 (plumbing contractors) and a $19 million size standard. The solicitation number is 140P8626R0007, issued June 24, 2026, with proposals due July 24, 2026 at 12:00 PM local time. Award is contemplated as a firm-fixed-price contract with a performance period from September 1, 2026 to January 1, 2027 (120 calendar days after notice to proceed). The contractor must commence work within 10 calendar days of the notice to proceed. An offer guarantee (20 percent of total proposal price or $3,000,000, whichever is less) and performance and payment bonds (100 percent of contract price) are required. The Government seeks offers below $450,000 but will consider offers at or above this figure if they provide best value. Davis-Bacon wage rates apply. A mandatory site visit is scheduled for July 8, 2026 at 10:00 AM at Fort Cronkhite. Proposals must be submitted electronically in two volumes (Technical/Past Performance and Business/Price) and must include project experience questionnaires, California contractor licenses, construction schedules, past performance information, Standard Form 1442, bid bond, and various certifications. Evaluation will be based on project experience, California contractor license validity, schedule quality, and past performance, with price evaluated for reasonableness and balance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Attachment_No__09_Questions___Answers_140P8626R0007_0002.pdf | ||
| Sol_140P8626R0007_Amd_0002.pdf | ||
| B08_Attachment_No__08_Questions___Answers_140P8626R0007_0001.pdf | ||
| Sol_140P8626R0007_Amd_0001.pdf | ||
| B08_Attachment_No__07_Site_Visit_Sign_In_Sheet_0001.pdf | ||
| B08_Attachment_No__03_-__Fort_Cronkhite_Map.pdf | ||
| B03_Attachment_No__05_-_Construction_Wage_Decision.pdf | ||
| B08_Attachment_No__01_-_Specifications.pdf | ||
| B08_Attachment_No__02_-_Fort_Baker_and_Barry_Maps.pdf | ||
| B08_Attachment_No__04_-_Photos.pdf | ||
| B08_Attachment_No__06_-_Proposal_Submission_Package.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P8626R0007
NPS, PWR - GOGA MABO
Building 201, Fort Mason San Francisco CA 94123
Patty_Payne@ios.doi.gov
0044038744 340407,35043
PPG
Patty Payne 5597306435
06/24/2026
07/24/2026
10 120
Replace Water Meters at Fort Cronkhite, Baker, and Barry, Golden Gate National Recreation Area, Marin
County, California he National Park Service (NPS) at Golden Gate National Recreation Area, located within Marin County, California, has a requirement for Replacement of existing water meters throughout Fort Cronkhite, Fort
Baker, and Fort Barry with lead-free cold water ultra sonic water meters. Water meters will include two-way endpoint for mobile reading and data collection along with some replacement of Crissy boxes where needed. Base bid includes 84 water meters at Fort Baker and Fort Barry and 36 meters at Fort
Cronkhite.
The Contractor shall provide all supervision, labor, equipment, testing, and supplies necessary to complete the work as identified in the project specifications and associated documents provided as attachments to the solicitation. All work shall be performed in accordance with local, state, and federal laws.
The Government contemplates award of a firm-fixed price contract resulting from this solicitation.
Continued...
1 53
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
NPS, PWR - GOGA MABO
Building 201, Fort Mason San Francisco CA 94123
PPG
Liset Gomez
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
The North American Industry Classification
System (NAICS) Code for this requirement is
238220, with a corresponding size standard of
$19 million in annual gross receipts for the past three years.
This acquisition is a Total Small Business
Set-Aside. Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.
See Section J Attachment 01: Specifications for a detailed description of the requirement.
Refer to provisions and clauses and other attachments for additional information about this requirement and instructions on how to submit a proposal.
A SITE VISIT has been scheduled. See Section L of the solicitation for more information.
Submit questions only through email to the person listed in Section L.
Proposals must be received in their entirety via email as instructed in Section L. They must be received no later than the date and time specified in Block 13 of the SF 1442 (unless a future Amendment to the Solicitation extends this deadline).
Delivery: 01/01/2027
Delivery Location Code: 0011283305
NPS, GOLDEN GATE NRA
Bldg. 201, Fort Mason
San Francisco CA 94123-1307 US
Period of Performance: 09/01/2026 to
01/01/2027
00010 Replace Water Meters at Fort Cronkhite
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
SUPPLY FACILITIES
00020 Replace Water Meters at Fort Baker
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
00030 Replace Water Meters at Fort Barry
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
Amy Wilson is designated at the Contracting
Officer's Representative (COR) for this contract and will be responsible for certifying receipt and acceptance of the services rendered.
Solicitation 06/24/2026
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 5 of
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
SECTION B – BID SCHEDULE
SECTION C – SPECIFICATIONS / DRAWINGS
SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
SECTION F – DELIVERIES OR PERFORMANCE
CLAUSES INCORPORATED BY REFERENCE
52.242-14 SUSPENSION OF WORK (APR 1984)
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
DELIVERABLE (POST-AWARD): CONTRACTOR’S DAILY LOGS
SECTION G – CONTRACT ADMINISTRATION DATA
CONTRACT ADMINISTRATION
CORRESPONDENCE
APPOINTMENT OF CONTRACTOR REPRESENTATIVE/SUPERINTENDENT
1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (Jul 1996)
CONSTRUCTION CONTRACT ADMINISTRATION
NOTICE TO CONTRACTORS – CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM
(FEB 2021)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
WAGE RATES
WORKERS COMPENSATION
SITE SPECIFIC SAFETY AND HEALTH PLAN
ARCHEOLOGICAL FINDINGS
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 6 of
CONDUCT OF OPERATIONS
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
PRE-CONSTRUCTION CONFERENCE
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR (APR 1984) .25
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-
DESIGNATED ITEMS (MAY 2008)
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020) (DEVIATION MAY
2023)
1452.228-70 LIABILITY INSURANCE (JUL 1996)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS
52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS-CERTIFICATION (NOV
2021)
SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
PROVISIONS INCORPORATED BY REFERENCE
OFFER AFFORDABILITY
SITE VISIT (CONSTRUCTION)
1452.215-71 USE AND DISCLOSURE OF PROPOSAL INFORMATION—DEPARTMENT OF THE
INTERIOR (APR 1984)
52.216-1 TYPE OF CONTRACT (APR 1984)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS (MAY 2014)
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 7 of
52.228-1 BID GUARANTEE (SEP 1996)
52.233-2 SERVICE OF PROTEST DEPARTMENT OF THE INTERIOR (JUL 1996) (DEVIATION)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
ACQUISITION 360: VOLUNTARY SURVEY
INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE
SOURCE SELECTION
RESPONSIBILITY DETERMINATION
SECTION M – EVALUATION FACTORS FOR AWARD
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 8 of
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
Solicitation, Offer, and Award (SF 1442) - pages 1- 4 of this package.
SECTION B – BID SCHEDULE
BID SCHEDULE
SOLICITATION NUMBER: 140P8626R0007
PARK - PMIS: GOGA - 340407, 35043
DEVELOPED AREA: Golden Gate National Recreation Area, Marin County, California PROJECT TITLE: Replace Water Meters at Fort Cronkhite, Baker, and Barry
Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. For any lump-sum line items, provide the total price only. For any unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals & extended prices to whole dollars.
CONTRACT LINE
ITEM NUMBER
(CLIN)
CONTRACT LINE ITEM
(CLI) TITLE QUANTITY UNIT OF
MEASURE
UNIT
PRICE
TOTAL
PRICE
Remove dispose of existing water meters and any associated apparatuses at Fort Cronkhite.
Replace water meters with new.
Replace any associated fittings necessary for proper and leak-free meter system. Buildings in this CLIN: 1010, 1011, 1012, 1013, 1033, 1034, 1035, 1042, 1044, 1045, 1046, 1049, 1050, 1054, 1055, 1056, 1057, 1058, 1059, 1060, 1061, 1062, 1063, 1064, 1065, 1066, 1067, 1068, 1069, 1070, 1071, 1073, 1076, Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 9 of
1077, 1301, Marine Mammal Center (36 Total Meters)
Remove dispose of existing water meters and any associated apparatuses at Fort Baker.
Replace water meters with new.
Replace any associated fittings necessary for proper and leak-free meter system. Buildings in this CLIN: 405, 407, 435, 507, 513, 519 NW, 519 Rear, 522, 523, 527, 529, 530, 531, 533, 546, 547, 549, 557, 561, 562, 567, 601 N, 601 S, 602 W, 602 E, 603, 604, 605, 606, 607, 623, 629, 631, 636, 637, 644, 645, 679, 686, 1003, 1550, 1552, 1553, 1556, 1557, 1559, 1560
IRR, 1560, 1561, 1562, 1563,
Dock-USCG, Ramp - Travis AFB #1, Ramp - Travis AFB #2, Vista Point GGB, NPS IRR High Parade Ground, NPS IRR Low Parade Ground, IRR 4 N, IRR 5 S, Parking Lodge IRR #2, Parking Lodge IRR #3 (61 Total Meters)
Remove dispose of existing water meters and any associated apparatuses at Fort Barry.
Replace water meters with new.
Replace any associated fittings necessary for proper and leak-free meter system. Buildings in this CLIN: 934A, 934B, 936, 937A, 937B, 939A, 939B, 940, 941, 942, 944, 945, 960, 981, 983, 984, 986, 901A, 901B, 955A, 955B, 956A, 956B (23 Total Meters)
TOTAL BASE PRICE (Contract Line Item Number 1 through 3) ---------------------------- All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 10 of
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 11 of
SECTION C – SPECIFICATIONS / DRAWINGS
Specifications are attached and incorporated herein by reference. Refer to section J.
SECTION D – PACKAGING AND MARKING
No clauses included.
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 12 of
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
SECTION F – DELIVERIES OR PERFORMANCE
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984) (DEVIATION JAN
2026)
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 13 of so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
DELIVERABLE (POST-AWARD): CONTRACTOR’S DAILY LOGS
Contractor shall prepare a daily log for each day work is performed under this contract. Copies of daily logs shall be submitted to the Contracting Officer, and may be compiled and submitted weekly, with payroll. Time necessary for completion of daily log is approximately 15 to 30 minutes. The contractor may choose to use its own format as long as the following elements are included on the log:
(a) Project Name
(b) Contract number
(c) Date
(d) Prime Contractor and/or Subcontractor
(e) Work performed, including number of employees by job categories (indicate if "prime" or
"sub")
(f) Heavy equipment on job, hours worked (indicate if "prime" or "sub")
(g) Materials delivered
(h) Official visitors to site
(i) Inspections performed
(j) Verbal instruction received from government on construction deficiencies
(k) Certification (prime contractor's signature/COR's signature)
(End of Clause)
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 14 of
SECTION G – CONTRACT ADMINISTRATION DATA
CONTRACT ADMINISTRATION
The Contracting Officer's Representative (COR) for this contract will be:
Amy Wilson Project Manager Golden Gate National Recreation Area
(415) 547-9718
Amy_Wilson@nps.gov
The Contract Specialist (CS) responsible for administering this contract will be:
Patty Payne Contract Specialist Patty_Payne@ios.doi.gov
The Contracting Officer (CO) with overall responsibility for this contract will be:
Liset Gomez Contracting Officer 415-265-5650 Liset_gomez@ios.doi.gov
(End of Clause)
CORRESPONDENCE
Copies of all correspondence and written notices between the Contracting Officer’s Representative and the Contractor shall be sent to the cognizant Contract Specialist at the email address below. All correspondence shall state the contract number in the subject line of the email.
Patty Payne Contract Specialist Patty_Payne@ios.doi.gov
(End of Clause)
APPOINTMENT OF CONTRACTOR REPRESENTATIVE/SUPERINTENDENT
Prior to the commencement of work under this contract, the Contractor shall provide the Contracting Officer with the name and telephone number of at least one responsible individual who will be available on a daily basis to respond to
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 15 of operational problems and/or emergencies. In the event the contract involves more than one subcontractor, the designated site superintendent shall be a W-2 employee of the prime contractor. The Contractor agrees that notice to the designated representative shall constitute notice to the Contractor and further agrees to be bound by any commitments or representations made by such representative.
(End of Clause)
1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer’s Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor’s performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor’s right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer’s response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the
Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.
(End of clause)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (Jul 1996)
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 16 of
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
CONSTRUCTION CONTRACT ADMINISTRATION
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
(End of clause)
NOTICE TO CONTRACTORS – CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We may request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
https://www.doi.gov/pam/acquisition/policy/constructioncontract https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.gov/
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 17 of
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING
PLATFORM (FEB 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov.
The Contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Contracting Officer’s Representative (COR), with a copy to the Contract Specialist, a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the NPS Contract Specialist/Contracting Officer (CS/CO) and the Contractor. If the COR recommends acceptance, the Contractor shall submit a copy of the final Invoice Package to the NPS through
IPP.
1. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments as required by contract clause 52.232-5) https://www.ipp.gov/
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 18 of
2. Certified copies of Payroll Reports per Contract clause 52.222-8 Payrolls and Basic Records
3. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
4. A copy of the current Schedule of Values
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone
(866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
WAGE RATES
Davis-Bacon Wage Rates apply for this project and are attached to this solicitation (See Section J).
The project is located in Marin County, California.
(End of Clause)
WORKERS COMPENSATION
The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance in accordance with the provisions of the Section 3700 of the Labor Code of the State of California. Evidence of coverage is required before commencement of project work.
(End of Clause)
SITE SPECIFIC SAFETY AND HEALTH PLAN
A site specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site specific plan. The site specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards mailto:IPPCustomerSupport@fiscal.treasury.gov
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 19 of anticipated. The site specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.
As work proceeds, the site specific safety and health plan shall be adapted to new situations and new conditions.
Changes and modifications to the accepted site specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office. Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.
Prior to submittal to the COR, the site specific safety and health plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The site specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site specific safety and health plan for review and approval by the safety office.
Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.
(End of Clause)
ARCHEOLOGICAL FINDINGS
(a) Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, he will be compensated by an equitable adjustment under the General Provisions of the Contract.
(End of Clause)
CONDUCT OF OPERATIONS
At all times the Contractor shall conduct his organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with approval of the Contracting Officer.
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 20 of
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 21 of
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
52.202-1 DEFINITIONS (JUN 2020)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020)
52.203-7 ANTI-KICKBACK PROCEDURES (JUN 2020)
52.203-8 CANCELLATION, RECESSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR
IMPROPER ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS
(JUN 2020)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO
INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (NOV 2023)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY
AGREEMENTS OR STATEMENTS (JAN 2017)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT
AWARDS (JUN 2020) (DEVIATION MAR 2026)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018) (DEVIATION
MAR 2026)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS (DEC 2014)
52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, PROPOSED FOR DEBARMENT, OR
VOLUNTARILY EXCLUDED (JAN 2025) (DEVIATION MAY 2026)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS
(NOV 2015) (DEVIATION MAY 2026)
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 22 of
52.215-2 AUDIT AND RECORDS-NEGOTIATIONS (JUN 2020)
52.215-8 ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997)
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020) (DEVIATION JAN
2026)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (JAN 2025) (DEVIATION JAN
2026)
52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022) (DEVIATION JAN 2026)
52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)
(DEVIATION JAN 2026)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS-OVERTIME
COMPENSATION (MAY 2018) (DEVIATION MAY 2026)
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018) (DEVIATION MAY
2026)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (JUL 2021)
52.222-9 APPRENTICES AND TRAINEES (JULY 2005) (DEVIATION FEB 2025)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) (DEVIATION MAY 2026)
52.222-12 CONTRACT TERMINATION - DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIRMENTS AND
RELATED REGULATIONS (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) (DEVIATION MAY 2026)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
(DEVIATION MAY 2026)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (JUN 2020) (DEVIATION MAY 2026)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR
RELATIONS ACT (DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (OCT 2025) (DEVIATION MAY 2026)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (JAN 2025) (DEVIATION MAY 2026)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2022)
52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS (DEVIATION
MAY 2026)
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 23 of
52.223-2 REPORTING OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION
(MAY 2024) (DEVIATION FEB 2025)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2024)
52.223-21 FOAMS (MAY 2024)
52.223-23 SUSTAINABLE PRODUCTS AND SERVICES (MAY 2024) (DEVIATION MAY 2026)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021)
52.226-7 DRUG-FREE WORKPLACE (MAY 2024)
52.226-8 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE
DRIVING (MAY 2024)
52.227-1 AUTHORIZATION AND CONSENT (JUN 2020)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT
INFRINGEMENT (JUN 2020)
52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA – SPECIAL WORKS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 INDIVIDUAL SURETY—PLEDGES OF ASSETS (FEB 2021) (DEVIATION MAY 2023)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (DEC 2022)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013) (DEVIATION OCT 2025)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD
MANAGEMENT (OCT 2018)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS (MAR 2023)
52.233-1 DISPUTES (MAY 2014)–ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984) (DEVIATION JAN 2026)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
(DEVIATION JAN 2026)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984) (DEVIATION JAN 2026)
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 24 of
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984) (DEVIATION JAN 2026)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991) (DEVIATION JAN 2026)
52.236-8 OTHER CONTRACTS (APR 1984) (DEVIATION JAN 2026)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (APR 1984) (DEVIATION JAN 2026)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984) (DEVIATION JAN 2026)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984) (DEVIATION JAN
2026)
52.236-12 CLEANING UP (APR 1984) (DEVIATION JAN 2026)
52.236-13 ACCIDENT PREVENTION (NOV 1991) (DEVIATION JAN 2026)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984) (DEVIATION JAN 2026)
52.236-17 LAYOUT OF WORK (APR 1984) (DEVIATION JAN 2026)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) (DEVIATION
JAN 2026)
52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (DEVIATION MAR 2026)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007) (DEVIATION OCT 2025)
52.244-6 SUBCONTRACTS FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
(JAN 2025) (DEVIATION FEB 2025)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.248-3 VALUE ENGINEERING – CONSTRUCTION (OCT 2025)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR
2012)-ALTERNATE I (SEP 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991) (DEVIATION MAY 2026)
(End of clause)
PRE-CONSTRUCTION CONFERENCE
If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
Document No.
140P8626R0007
Document Title PMIS# 340407, 35043 – Replace Water Meters at Fort
Cronkhite, Baker, and Barry, Golden Gate National Recreation Area
Page 25 of
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
(End of clause)
1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR (APR
1984)
For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215–2(d)), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.
(End of clause)
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-
DESIGNATED ITEMS (MAY 2008)
(a) Definitions. As used in this clause— “Postconsumer material” means a material or finished product that has served its intended use and has…