B08_Attachment_No__01_-_Specifications.pdf
PDF 810 KB Posted
- Attached to
- REPLACE WATER METERS MARIN HEADLANDS Federal contract opportunity
- Solicitation number
- 140P8626R0007
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_Attachment_No__09_Questions___Answers_140P8626R0007_0002.pdf | ||
| Sol_140P8626R0007_Amd_0002.pdf | ||
| B08_Attachment_No__08_Questions___Answers_140P8626R0007_0001.pdf | ||
| Sol_140P8626R0007_Amd_0001.pdf | ||
| B08_Attachment_No__07_Site_Visit_Sign_In_Sheet_0001.pdf | ||
| B08_Attachment_No__04_-_Photos.pdf | ||
| B08_Attachment_No__06_-_Proposal_Submission_Package.pdf | ||
| Sol_140P8626R0007.pdf | ||
| B08_Attachment_No__03_-__Fort_Cronkhite_Map.pdf | ||
| B03_Attachment_No__05_-_Construction_Wage_Decision.pdf | ||
| B08_Attachment_No__02_-_Fort_Baker_and_Barry_Maps.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GOLDEN GATE NATIONAL RECREATION AREA
SAUSALITO, CALIFORNIA
Replace Fort Cronkhite, Fort Baker, and Fort Barry Water Meters GOGA
PMIS# 340407, 350434
PROJECT SPECIFICATIONS
National Park Service Pacific West Region
June 2026
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 ................................................................................................................... Summary of Work 01 26 01 ........................................................................................... Contract Modification Procedures 01 27 00…… ................................................................................... Definition of Contract Line Items 01 31 00…………..................................................................... Project Management & Coordination 01 32 16…. ........................................................................................................ Construction Schedule 01 33 23… ........................................................................................................... Submittal Procedures 01 35 23… ............................................................................................................ Safety Requirements 01 40 00… .......................................................................................................... Quality Requirements 01 45 00… .................................................................................................... Environmental Protection 01 57 19.12………………………………………………….Noise and Exterior Light Management 01 67 00…………………………………………………………………… .Product Requirements 01 73 40… ............................................................................................................................. Execution 01 74 19… ................................................................. Construction Waste Management and Disposal 01 77 00… ............................................................................................................ Closeout Procedures Submittal List
DIVISION 02 – 48 – TECHNICAL SPECIFICATIONS
33 10 00………………………………………………………………………….….Water Meters
01 11 00 - 3
SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work under other contracts.
3. Government Furnished Materials.
4. Contractor use of the site
5. Contractor access and use of site
6. Work Restrictions.
7. Special Construction Requirements.
8. Field Verification
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The project location is in the Golden Gate National Recreation Area (GOGA). Marin Headlands, Fort Baker, Fort Barry, and Fort Cronkhite.
B. The Work consists of the following:
1. Replacement of existing water meters throughout Fort Cronkhite, Fort Baker, and Fort
Barry with lead-free cold water ultra sonic water meters. Water meters will include two-way endpoint for mobile reading and data collection along with some replacement of Crissy boxes where needed. Base bid includes 84 water meters at Fort Baker and Fort Barry and 36 meters at Fort Cronkhite.
C. Legally dispose of/recycle all demolished materials.
D. Project will be constructed under a single Contract.
E. Contractor shall provide all labor, materials, tools and other equipment, services and supervision required to complete the work described below. The scope of this project includes only the items listed in the contract line items and will be bid according to the contact line items in section 01 27 00. No other restroom facilities nearby or within Golden Gate Recreation area are included in this project scope. No surrounding parking lots or auxiliary structures are included in this project scope.
F. A Construction Schedule laying out project start and completion dates along with scope tasks shall be submitted per the Spec Section 01 32 16 “Construction Schedule.”
G. The Contractor is responsible for verifying quantities, measurements, and existing site conditions. All interested parties are strongly encouraged to do a site visit to familiarize themselves with local conditions that may affect the cost of contract performance. Interested parties may coordinate the site visit through the CO.
1.3 WORK UNDER OTHER CONTRACTS
A. General: The National Park Service and/or facilities-based partners of the National Park
Service may, during the course of this Contract, have other construction work in progress within the park and near this project site. The Contractor shall work with the Contracting
01 11 00 - 4
Officer and others as necessary to minimize impacts and coordinate activities of the work.
1.4 PERIOD OF PERFORMANCE
A. The period of performance shall be 120 days after Notice to Proceed (NTP).
B. Contractor shall submit written certification that the project is substantially complete, and final inspection is requested. The Contracting Officer’s Representative will complete an inspection within seven (7) business days of receipt of request.
C. When the COR determines that the work is substantially complete, he will prepare a list of deficiencies to be corrected before final acceptance, and a Letter of Substantial Completion will be issued by the CO.
D. Contractor shall coordinate manufacturer warranty inspection. Warranty documents shall be provided to the COR within 30 days of project completion.
1.5 GOVERNMENT-FURNISHED MATERIALS:
A. There will be no government furnished materials, and all materials shall be contractor furnished from outside the park.
1.6 CONTRACTOR USE OF SITE
A. The Contractor's use of the premises is restricted to the designated work area. Materials and equipment must be stored inside a designated exterior storage area. Maintain all equipment and materials within lockable trailer.
B. Temporary facilities include portable toilets rented by the contractor and cleaned on a weekly or as-needed basis by the contractor.
C. Storage of Materials: Confine storage of materials to the pre-approved staging areas.
D. Protection of Historic Features: The Golden Gate National Recreation Area contains many project locations which are highly sensitive sites and contains historical resources. The Contractor shall closely follow the plans shown and alert the Contracting Officer immediately of any major deviations. A short start-up meeting with the Contracting Officer will be required prior to beginning work. Confine all operations to work limits of the project.
Prevent damage to historic features that lie within the work limits, including but not limited to historic buildings and features, archeological resources including features both above and below grade, cultural landscapes and features including plantings, manhole covers, gutters, paving, drainage features, utilities, walkways, etc. Protect historic features from damage due to the work of this contract. Application of spray paint or any permanent markings to site features is prohibited. (Only chalk-based paint or crayon should be used).
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas as directed and approved by the Contracting Officer, at no additional expense to the Government.
2. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
4. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
01 11 00 - 5
5. Take measures to prevent equipment from compacting soils adjacent to or within the construction zone that will not be displaced by a constructed facility such as the parking lot.
6. All geologic and fossil materials within the park are protected. Avoid disturbing soils or rock within or outside the project are, except as specified in the contract documents or as directed by the Contracting Officer.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within the park will not be permitted.
H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
I. Contractor shall provide OSHA and other required postings regard safety at the site.
J. All Contractor employees and subcontractor employees shall be advised of the rules and regulations of the National Park Service.
K. Contractor and subcontractor vehicles not required on the worksite itself shall be parked in a location to be reviewed and approved by NPS.
1.7 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Building or road closures may be permitted, when required, upon specific approval of Contracting Officer. Submit closure request to Contracting Officer at least 30 calendar days in advance of requested closure date. Closure may be permitted for a maximum of 3 calendar days at a time.
B. Emergency Vehicle Access: Contractor must maintain access for emergency vehicles at all times unless specifically exempted as a condition within the project contract. Any exemption should be limited to minimal temporary delays and include notification to park dispatch.
Contractor will stop all work as necessary to allow passage of emergency vehicles and direct traffic flow to accommodate immediate passage of these vehicles. For those projects in which trenching is required, the Contractor shall have a sufficient number of steel plates on hand to bridge any gap necessary for emergency vehicle access.
1.8 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Government and Park Partner Occupancy: Government and Park Partners will occupy the premises during entire construction period. Cooperate with Government and Park
01 11 00 - 6
Partners during construction operations to minimize conflicts and facilitate Government and Park Partner usage. Perform the Work so as not to interfere with Government and Park Partner's operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
c. The contractor will be required to shut water off from buildings while replacing meters. Water lines must be bled and service must be on at all buildings at the end of each work day.
1.9 CONDUCT OF OPERATIONS
A. Contractor personnel shall comply with all Federal and State law and regulations, including the Golden Gate National Recreation Area Superintendent's Compendium. Any exception must be specifically justified and approved in writing by the Contracting Officer.
1. The Superintendent's Compendium can be found at this internet address:
https://www.nps.gov/goga/learn/management/lawsandpolicies.htm
B. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.10 WORK RESTRICTIONS
A. On Site Work Hours: The 40-hour work week shall be generally performed during normal business working hours of 7 a.m. to 5:30p.m., Monday through Friday.
B. Work will be permitted in the evenings or on Saturdays by prior authorization of the NPS
Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No onsite work shall be performed during federal holiday periods unless otherwise directed by the Contracting Officer.
D. Early Morning Hours: See section 01 57 19.12 Noise and Exterior Lighting Management.
E. Hours for Core Drilling, other noisy activity. See section 01 57 19.12 Noise and Exterior Lighting Management.
F. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. Existing Utilities: USA Notification & Utility Field Meeting
a. The Contractor shall contact Underground Service Alert (USA) (1-800-642-
2444) seven (7) calendar days prior to start of each ground disturbing phase and shall be responsible for maintaining a valid USA location tag through https://www.nps.gov/goga/learn/management/lawsandpolicies.htm
01 11 00 - 7 renewal during the construction. The Contractor shall schedule a utility field meeting prior to any excavation. This shall be so stated in the USA notification.
The Contractor shall be responsible to coordinate the utility field meeting at which time he shall explain the limits and impacts to USA member utilities.
b. The majority of the utilities within the Marin Headlands are owned by NPS. As such, very few utilities will actually be marked out by USA. It is the Contractor's responsibility to field locate & mark all utilities within the project work area. Field location and marking shall be performed a minimum of three
(3) days prior to ground disturbance; notify CO upon completion of field location and marking for CO review and approval. No trenching shall be performed prior to CO approval.
4. Water and Wastewater Systems: The Contractor is not authorized to open/close valves, operate pumps and/or de-energize the utility water or wastewater system; An NPS USRO must do or be onsite to observe. This does not apply to individual housing units.
5. See Spec Section 01 73 40, Article 3.2 "Execution" for utility marking and coordination with other utility providers.
G. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated.
H. Notify Contracting Officer not less than seven working days in advance of proposed utility interruptions.
1. Do not proceed with utility interruptions without Contracting Officer's written permission.
2. Hours for Utility Shutdowns: Government's restrictions when outages are allowed and the maximum length of time for the outage is 12 hours.
I. All buildings are occupied. Overnight outages are not allowed. If water cannot be reconnected by the end of the workday, it is incumbent on the contractor to install temporary water.
J. Smoking: Smoking is not permitted, except in park designated smoking areas.
1.11 FIELD VERIFICATION
A. See Section 01 73 40 Execution.
1.12 SPECIAL CONSTRUCTION REQUIREMENTS
A. Hot Work Permit: A hot work permit is required for any cutting, welding or heat gun work.
No open flame torch work will be allowed. The NPS Fire Inspection office will issue the permit to the Contractor. Permit will be good through completion of work. The Contractor will be responsible for ensuring that all workers and subcontractors follow permit conditions.
END OF SECTION
01 26 01 - 8
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 CONTRACT MODIFICATION PROCEDURES
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor's projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
01 26 01 - 9
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Scheduling
5. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Material handling
2. Trash removal, dumpsters
3. Barricades
4. Small tools
5. Safety supplies
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation- Policy and company calculation to be made available.
4) FUTA- Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA- Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
01 26 01 - 10
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred.
Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder's Risk Insurance: This covers the contractor's loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov't provided form. The government form is available at: http://www.nps.gov/dscw/upload/ContractorEstimateForm_1-24- 13.xls
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor's failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All http://www.nps.gov/dscw/upload/ContractorEstimateForm_1-24-13.xls http://www.nps.gov/dscw/upload/ContractorEstimateForm_1-24-13.xls
01 26 01 - 11 delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources.
Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized, then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the
01 26 01 - 12 established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only.
Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project.
Overhead…………………10% Profit……………………...10%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, then the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3.E.1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION (Not used)
01 27 00 - 13
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 - DEFINITION OF CONTRACT LINE ITEMS
PART 1 – GENERAL
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No 1.
1. Remove and dispose of existing water meters and any associated apparatuses at Fort
Cronkhite. Replace water meters with new. Replace any associated fittings necessary for proper and leak-free meter system. Buildings in this CLIN: 1010, 1011, 1012, 1013, 1033, 1034, 1035, 1042, 1044, 1045, 1046, 1049, 1050, 1054, 1055, 1056, 1057, 1058, 1059, 1060, 1061, 1062, 1063, 1064, 1065, 1066, 1067, 1068, 1069, 1070, 1071, 1073, 1076, 1077, 1301, Marine Mammal Center (36 Total Meters)
2. Contractor is responsible for confirming sizes for each meter. There are approximately three 5/8”, thirteen 1”, seven 1.5”, twelve 2”, and one 6” meters. All 36 need transmitters with approximately 4 needing Crissy Box replacements. The meter for building 1046 will be new, as there is no existing meter.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No 2.
1. Remove and dispose of existing water meters and any associated apparatuses at Fort
Baker. Replace water meters with new. Replace any associated fittings necessary for proper and leak-free meter system. Buildings in this CLIN: 405, 407, 435, 507, 513, 519 NW, 519 Rear, 522, 523, 527, 529, 530, 531, 533, 546, 547, 549, 557, 561, 562, 567, 601 N, 601 S, 602 W, 602 E, 603, 604, 605, 606, 607, 623, 629, 631, 636, 637, 644, 645, 679, 686, 1003, 1550, 1552, 1553, 1556, 1557, 1559, 1560 IRR, 1560, 1561, 1562, 1563, Dock-USCG, Ramp - Travis AFB #1, Ramp - Travis AFB #2, Vista Point GGB, NPS IRR High Parade Ground, NPS IRR Low Parade Ground, IRR 4 N, IRR 5 S, Parking Lodge IRR #2, Parking Lodge IRR #3 (61 Total Meters)
2. Contractor is responsible for confirming sizes for each meter. There are approximately two 5/8”, two ¾”, twelve 1”, thirteen 1.5”, twenty-eight 2”, and four 3- 4” meters. All 61 need transmitters with approximately 10 needing Crissy Box replacements. The meter at building 435 needs a manhole replacement cover approximately 3’5” in diameter. Building 513 will need a new meter, as there is no existing meter.
C. Contract Line Item No 3.
1. Remove dispose of existing water meters and any associated apparatuses at Fort Barry.
Replace water meters with new. Replace any associated fittings necessary for proper
01 27 00 - 13
DEFINITION OF CONTRACT LINE ITEMS
and leak-free meter system. Buildings in this CLIN: 934A, 934B, 936, 937A, 937B, 939A, 939B, 940, 941, 942, 944, 945, 960, 981, 983, 984, 986, 901A, 901B, 955A, 955B, 956A, 956B (23 Total Meters)
2. Contractor is responsible for confirming sizes for each meter. There are approximately two 5/8”, one ¾”, twelve 1”, two 1.5”, and five 2”. All 23 need transmitters with approximately 1 needing a Crissy Box replacement.
END OF SECTION 01 27 00
01 31 00 - 15
PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Construction Coordination.
2. Submittals
3. Requests for Information (RFIs).
4. Project meetings.
5. Environmental Coordination.
6. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor's construction schedule.
2. Section 017340 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate water shutdowns with the Contracting Officer and COR. Notification must be given no less than one week in advance.
B. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Delivery and processing of submittals.
4. Pre-installation conferences.
5. Project closeout activities.
1.3 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components, or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base
Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate dimensions shown on the Contract Drawings and make specific note
01 31 00 - 16 of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
b. Indicate required installation sequences.
2. Number of Copies: Submit one electronic copy of each submittal. Contracting Officer will return one electronic copy.
B. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Site-Specific Safety Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF 1413).
7. Satisfactory evidence of liability insurance coverage and workman's compensation for the Contactor and all subcontractors.
8. Proof of Performance Bond.
C. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI electronically utilizing the NPS standard RFI format, with attachments in either Word or Adobe .pdf format as necessary.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include building numbers, dimensions, thicknesses, structural grid references, 01 31 00 - 17 and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer's Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor.
B. Attending shall be the following:
1. CO and COR
2. Contractor's Project Manager
3. Contractor's Superintendent
4. Major subcontractors
5. NPS Project Manager
6. Others as appropriate
C. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Workplan & Schedule
5. Resolution of comments on required Division 01 documents.
6. Coordination of Subcontractors.
7. Labor law application.
8. Modifications.
9. Payments to Contractor.
10. Payroll reports.
11. Contract time.
12. Liquidated damages.
13. Contractor Performance Evaluation.
14. Display of Hotline posters.
15. Notice to proceed.
16. Correspondence procedures.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
01 31 00 - 18
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials.
25. Value engineering.
D. Progress Meetings: The Contracting Officer will schedule progress meetings at agreed upon regular intervals.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Safety items/ 'toolbox' safety meeting topic.
c. Submittal status.
d. Review of off-site fabrication and delivery schedules.
e. Requests for information (RFI) and other issues.
f. Modifications.
g. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
h. Inspections of work in progress and projected (Special inspections,
i. Construction Schedule update (provide updated CPM).
j. Status of Project Record Drawings and O&M manuals.
k. Other business relating to work.
l. Permit requirements.
3. Contractor shall:
a. Prepare agenda for Progress meetings in format approved by the
Contracting Officer.
b. Distribute written notice of each Progress meeting 4 business days in advance of meeting date, except for meetings scheduled at established intervals.
E. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related Change Orders.
d. Purchases.
e. Deliveries.
f. Submittals,
g. Possible conflicts.
01 31 00 - 19
h. Time schedules.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
PART 2 - PRODUCTS (Not used)
PART 3 - EXECUTION (Not used)
01 32 16 - 20
CONSTRUCTION SCHEDULE
SECTION 01 32 16 - CONSTRUCTION SCHEDULE
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 SUBMITTALS
A. Electronic Copies: All schedules and reports submitted as noted in paragraphs B through H below, shall be submitted to NPS in the native electronic file format. A pdf version of the schedule shall also be provided on 11x17 sheets in a manner that is clearly readable one page at a time. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.
B. Schedule of Values:
1. After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule. Include bond costs, mobilization, general condition costs, overhead, and profit, and each major category of work.
2. The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments as provided for in the General Conditions.
C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit PDF of baseline schedule, large enough to show entire schedule for entire construction period.
D. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percentage completion of each schedule activity and necessary supporting data. Provide two paper copies.
E. Construction Schedule Revisions and Time Impact Analysis: For each Construction
Schedule revision submit copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.
F. Construction Schedule
1. Submit PDF of Construction Schedule in critical path (CPM) format showing starting and completion dates for each activity or item of work. Precedence Diagramming
01 32 16 - 21
Method (PDM) shall be used in preparing the CPM diagrams. CPM schedule shall show work items properly sequenced and intermeshed. Prepare a separate sub-network for each major area of work: drilling, concrete form, concrete pour, steel erection, rough carpentry. Schedule submittals shall include NPS-provided references to special events, activities, and park partners
2. The level of detail shall be such that construction field work is divided into activities for each individual water meter. This is required for adequate tenant notice of water shutdowns.
3. In developing the logic diagram, ensure that all work, reviews and approvals are included in the logic diagram, and that the work sequences are logical and that the diagram shows a coordinated plan of work.
4. Provide an updated three-week look ahead for each meeting.
G. Schedule of Values:
1. After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule. Include bond costs, mobilization, general condition costs, overhead, and profit, and each major category of work.
2. The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments as provided for in the General Conditions.
1.3 QUALITY ASSURANCE
A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:
Review software limitations, content and format for reports.
1. Verify availability of qualified personnel needed to develop and update schedule.
2. Discuss constraints, including phasing, work stages, area separations, interim milestones and partial Government occupancy.
3. Review schedule for work of separate Government contracts.
4. Review time required for review of submittals and re-submittals.
5. Review requirements for tests and inspections by independent testing and inspecting agencies.
6. Review time required for completion and startup procedures.
7. Review time required for obtaining and activating permits.
8. Review and finalize list of construction activities to be included in schedule.
9. Review baseline schedule comments, resolve issues and progress on incorporating them
10. Review procedures for updating schedule.
11. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.
1.4 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing the Construction Baseline Schedule, ensure that the Subcontractor's work at all tiers, as well as the prime Contractor's work, is included and coordinated.
01 32 16 - 22
2. Secure time commitments for performing critical elements of the Work from parties involved.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated duration for each meter.
2. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.
Activity Duration: Define activities so no activity is longer than 1 day, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
a. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
B. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receipt of the Contractor's proposed Construction
Baseline Schedule, the Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the initial Construction Baseline Schedule. Any areas which, in the opinion of the Contracting Officer, conflict with timely completion of the project shall be subject to revision by the Contractor.
2. Within seven calendar days…