This is a Questions and Answers document (#2) for National Park Service contract 140P8626R0007 concerning MAHE Water Meters installation at Golden Gate National Recreation Area (GOGA).
The document addresses contractor responsibilities and project parameters for replacing water meters with ultrasonic meters equipped with Orion Cellular C endpoints for mobile reading and data collection. Key clarifications include: the contractor must furnish all ultrasonic water meters, Orion Cellular C endpoints, and related installation materials per construction specifications; field verification of existing meter sizes is the contractor's responsibility; connections are between existing meters and existing piping; change orders are available for degraded piping requiring replacement to achieve a leak-free system; fittings must be lead-free and sanitized with a 50/50 water bleach solution. The contractor must contact USA utility for trenching of new meters but not for existing meter replacement. No more than one day of water outage is permitted at each location. The Government will provide access to secured locations and has existing equipment to read the new meters, eliminating contractor obligations for handheld readers or software. The National Park Service will monitor all digging activities and clear vegetation if necessary. The contractor may coordinate with NPS regarding laydown yards or shipping container storage. Programming, activation, and commissioning of endpoints will be performed jointly by the contractor and the park. Specific quantities of meter sizes and Christy box replacements are referenced in the construction specifications, which contractors must consult for detailed bidding requirements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
CONTRACTING OPERATIONS - WEST
1849 C Street
NW Washington, DC 20240
140P8626R0007
MAHE Water Meters, GOGA
Question & Answers #2
1. May it be assumed that specific points of connection are between the existing meter and the existing piping? Answer: Yes
2. If piping is degraded and in poor condition, will a change order be considered for the new piping to create a leak free system? Answer: Yes
3. What materials are the existing water lines? Answer: Some are copper. The contractor is to verify metals in field.
4. Can a count of how many are above grade and below grade meters? Answer: Information in specs, contractor to verify quantities.
5. Will any of the above grade meters require new enclosures? If so, how many? Answer: No, they are either in utility closets or basements.
6. Will the new meters require sanitizing? Answer: Any fittings or apparatus needs to be sprayed with a
50/50 water bleach solution, all fittings need to be lead free.
7. How long may each individual location be without water? Answer: No more than one day.
8. Will USA utility location need to be contacted for each underground meter or box being replaced? Answer: USA utility would need to be contacted for any trenching of new meters, not for existing.
9. Will any of the areas be secured locations requiring an escort? Answer: Yes, access will be provided.
10. Will a laydown yard or an area for a shipping container be provided? Answer: Contractor can coordinate with NPS prior to construction
11. Will an archeological observer be required while digging? Answer: For any digging, NPS will need to be notified and it will be monitored by NPS.
12. If trees or scrubs impede the scope of work, will the prime be responsible for removal and what is the procedure? Answer: All water meters are accessible and if an issue arises NPS can clear vegetation.
13. Section 01 11 00 states that the new water meters need to include endpoints for mobile reading and data collection. However, the spec does not identify a requirement to furnish a handheld reader, tablet, or software. Please confirm whether the Government already has the equipment and software required to read the new meters, or whether the contractor is required to provide a compatible reading device and software. Answer: The Government already has the equipment to read the meters.
14. To confirm our understanding of the base bid requirements, could you please confirm the following:
1. The contractor is to furnish all ultrasonic water meters, Orion Cellular C endpoints, and all related installation materials. Answer: See construction specifications.
2. The contractor is responsible for field-verifying all existing meter sizes prior to ordering materials. Answer: See construction specifications.
3. If a meter schedule is available showing the quantity of each meter size (5/8", 3/4", 1", 1½", 2", 4", and 6"), could you please provide it? If not, should bidders determine the quantities independently? Answer: See construction specifications.
4. The specifications state that Christy boxes are to be replaced "where needed." Should the base bid include:
1. replacement of all existing Christy boxes,
2. an estimated quantity of replacements,
3. or only those determined to require replacement during construction?
Answer: for all of #4 See construction specifications.
5. Will programming, activation, and commissioning of the Orion Cellular C endpoints be the responsibility of the contractor, or will that be performed by the Government or its water utility representative? Answer: See construction specifications. Park will work with the contractor to commission.