B08_Attachment_No__08_Questions___Answers_140P8626R0007_0001.pdf
PDF 105 KB Posted
- Attached to
- REPLACE WATER METERS MARIN HEADLANDS
- Solicitation number
- 140P8626R0007
About this file
This is a Questions and Answers document for National Park Service contract 140P8626R0007 concerning MAHE Water Meters at Golden Gate Area (GOGA). The document addresses four inquiries from potential contractors regarding meter installation and system requirements.
The Q&A clarifies operational logistics: NPS will coordinate with residents and businesses to provide access to meters located in houses or utility closets; water shutoffs during installation will be phased to prevent extended campus-wide outages; meter sizes and locations are documented in the specifications, though contractors must verify actual sizes before installation as some meters were inaccessible and estimated sizes were provided for bidding purposes; and specific endpoint system requirements are detailed in the accompanying specifications. This document does not establish pricing terms, response dates, or award information, but serves to answer clarifying questions about project execution and technical requirements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE
CONTRACTING OPERATIONS - WEST
1849 C Street
NW Washington, DC 20240
140P8626R0007
MAHE Water Meters, GOGA
Question & Answers
Question 1: Will access be given for meters within utility closets?
Answer 1: Yes, NPS will coordinate with residents and businesses to provide access to any meters that are in houses or in utility closets.
Question 2: Will the water be shut off during construction?
Answer 2: NPS will help coordinate with the contractor and businesses/residents for water shut offs during installation. This will need to be phased as to not have an entire campus without water for an extended period of time.
Question 3: Where can I find the sizes and location of the meters to be replaced?
Answer 3: All known sizes and locations are listed in the specifications. Contractor will need to verify all meter sizes before installation, as some were inaccessible. Estimated sizes were provided for those NPS could not access for purposes of bidding.
Question 4: Which endpoint system is required?
Answer 4: Details of required systems are in the specifications.