Sol_140P8126B0007.pdf

PDF 650 KB Posted

Attached to
LAKE - EXTEND RAMP AT PEARCE FERRY
Solicitation number
140P8126B0007
Issued by

About this file

Solicitation Summary

This is an Invitation for Bid (IFB) for construction services issued by the National Park Service, Power Management Division at Lake Mead National Recreation Area. The solicitation number is 140P8126B0007, and the project involves extending the existing takeout ramp at Pearce Ferry on the Colorado River. The project magnitude is estimated between $1.5 million to $1.9 million, with a NAICS code of 237990 (Other Heavy and Civil Engineering Construction) and a small business size standard of $45 million. This is a competitive 100 percent Small Business Set-Aside with a firm fixed-price contract type.

The work encompasses resetting 1,800 square feet of precast concrete panels to extend the existing ramp 55 feet toward the river, pouring a new 8,400 square foot concrete pad for staging equipment and vehicles, and widening the overall launch ramp by 40 feet to provide additional launching and staging area for rafting and jetboat expeditions. Bids are due by 2:00 PM local time on July 8, 2026, with a mandatory site visit on June 3, 2026 at 11:00 AM at Pearce Ferry Boat Ramp (coordinates 36°07'31.3"N 113°58'57.3"W). The performance period runs from July 6, 2026 to November 28, 2026, with work to commence within 10 calendar days of the notice to proceed and be completed within 150 calendar days. Bids must be submitted electronically to PWR_MABO_Lake_Bid@nps.gov as a single PDF file with a 34MB size limitation. A bid bond equal to 20 percent of the bid price or $3 million, whichever is less, is required and must be received by bid opening. Performance and payment bonds at 100 percent of the original contract price are required within 10 days of award. Questions must be submitted by June 10, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140P8126B0007

NPS, PWR - LAKE MABO

601 Nevada Way Boulder City NV 89005-2426

0044038228

PPL

Caroline Bachelier 0000000000

05/21/2026

07/08/2026

10 90

Project Title: LAKE Extend Ramp at Pearce Ferry

This is a competitive 100% Small Business Set-Aside Invitation for Bid (IFB). The project magnitude is estimated between $1.5M to $1.9M. The North American Industry Classification System (NAICS) code is

237990 with a size standard of $45M.

All work shall be in strict compliance with the specifications and drawings.

Site Visit

Date: June 3, 2026

Time: 11am Local Time

Location: Pearce Ferry Boat Ramp, coordinates: 36°07'31.3"N 113°58'57.3"W

This is an electronic bid opening only. Submit bids to PWR_MABO_Lake_Bid@nps.gov with the subject line as IFB 140P8126B0007 - LAKE Extend Pearce Ferry Ramp. Submit entire bid package as one .pdf file. The size limitation of the email box is 34MB.

Continued...

1 68

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

Caroline Bachelier

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P8126B0007

The bid package should include completed and signed SF1442, acknowledgement of any amendments (if required), completed Price

Schedule, and a bid guarantee. The Bid Opening will be held 24 hours after the bid due date/time. Bid opening information will be in an amendment.

Any questions concerning this solicitation MUST be submitted in writing and received by the

Contracting Officer NO LATER THAN June 10, 2026. Questions received after this date may or may not be addressed, at the discretion of the

Contracting Officer. Questions may be sent via email to caroline_bachelier@ios.doi.gov. Each question should clearly specify the IFB area to which it refers to. Answers will be provided through an amendment to the solicitation.

Project will expand the existing takeout ramp on the Colorado River at Pearce Ferry by resetting 1800 SF of precast concrete panels to extend the existing ramp 55 feet towards the river, pour a new 8,400 SF concrete pad for staging equipment and vehicles at the top of the launch ramp, and widen the overall launch ramp by 40¿ in order to provide more launching and staging area for rafting and jetboat expeditions on the Colorado River through the

Grand Canyon.

Delivery: 11/28/2026

Delivery Location Code: 0011285198

NPS, Lake Mead NRA

101 Katzenbach Drive

Boulder City NV 89005 US

00010 Extend Takeout Ramp at Pearce Ferry

Product/Service Code: Y1PZ

Product/Service Description: CONSTRUCTION OF

OTHER NON-BUILDING FACILITIES

Period of Performance: 07/06/2026 to

11/28/2026

pg. 4

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.222-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals-Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications – Commercial Products and Commercial Services.

Agencies will not consider or use these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM

A Bid bond is required. If a bid bond is not received, bid will be considered non-responsive and will not be considered.

Requirement is subject to the availability of funds, 52.232-18.

pg. 5

Section A – Solicitation / Contract Form

Invitation for Bids (IFB), 140P8126B0007, is issued on a Standard Form (SF) 1442, Solicitation, Offer, and Award document.

Reference DIAR 1436.270-1 Uniform contract format.

Special Notice for Bidders

Signing of the bid shall be deemed to be a representation by the bidder that:

1.) Bidder is a construction contractor who owns, operates, or maintains a place of business, regularly engaged in the work described herein; or

2.) If newly entering into a construction activity, bidder has made all necessary arrangements for personnel, construction equipment, and required licenses to perform construction work as specified; and

3.) Upon request, prior to award, bidder will promptly furnish to the Government a statement of facts in detail as to bidder’s previous experience (including recent and current contracts), organization (including company officers), technical qualifications, financial resources and facilities available to perform the contemplated work.

This will be an electronic bid opening. A Microsoft Teams meeting information will be provided with an amendment. Submit entire bid package as one .PDF file.

Section B - Supplies or Services/Prices

Preparation of Bids: The Government will not be responsible for any costs incurred by offeror in the research, preparation, or submission of its bid.

• Complete Standard Form (SF) 1442: Offeror is to complete Blocks 14 through 20. Bidders shall include their SAM registered UIED number in Block 14 of the SF1442 when submitting their offer.

• Indicate the lump sum (total) proposal price in Block 17. A detailed breakdown of the offeror’s proposal price (e.g., labor, materials, profit, overhead, and other pricing elements) are not requested at this time; however, may be requested by the Contracting Officer during the pre-award process.

• Offeror must include original signatures of individual(s) authorized to sign for the company in accordance with FAR 4.102.

• Bidders must acknowledge all solicitation amendments when submitting final bids.

• Bid bonds must be provided.

A bid MUST be submitted to email PWR_MABO_LAKE_Bid@nps.gov or it will be considered non-responsive. The bid opening will occur 24 hours after the bid due date to avoid any potential delays in receiving the bids in the NPS email system.

Section C - Description/Specifications

STATEMENT OF WORK

The specifications and drawings are included as attachments in Section J.

Section D – Packaging and Marking

Not Applicable https://www.acquisition.gov/diar/part-1436-%E2%80%93-construction-and-architect%E2%80%93engineer-contracts#d1e4756 mailto:PWR_MABO_LAKE_Bid@nps.gov

pg. 6

Section E - Inspection and Acceptance

52.246-12 INSPECTION OF CONSTRUCTION. (AUG 1996)

Section F - Deliveries or Performance

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK.

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire project 150 calendar days after Notice to Procced is issued. The time stated for completion shall include final cleanup of the premises.

52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (DEV JAN 2026)

(a)

(1) Within five days after the work commences on the contract or another period of time determined by the Contracting Officer, the Contractor shall prepare and submit to the Contracting Officer for approval a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the work (including acquiring materials, plant, and equipment).

(2) The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period.

(3) If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall continually update the actual progress in the schedule and shall submit it to the Contracting Officer by the means prescribed in the contract for transmittals or as directed by the Contracting Officer.

(c)

(1) If the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to recover lost time and execute in accordance with the approved schedule, without additional cost to the Government.

(2) Such steps may include increasing the number of shifts, overtime operations, days of work, and/or the amount of construction plant.

(3) The Contractor shall submit, for approval, supplementary schedule(s) that demonstrate how the lost time will be recovered.

(d) If the Contractor does not recover the lost time, the Contracting Officer may determine that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

(End of clause)

52.242-14 SUSPENSION OF WORK (APR 1984)

Section G - Contract Administration Data

(a) Contact Information:

Contracting Officer Caroline Bachelier Email: Caroline_Bachelier@nps.gov mailto:Caroline_Bachelier@nps.gov

pg. 7

Contracting Officer Representative Mark Fiorina Email: mark_fiorina@nps.gov

(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.

(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.

(d) Any request for contract changes/modifications shall be submitted to the CO.

(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items. An example of a field change is: rerouting planned location of a sidewalk to avoid a tree (when quantities are not changed). All field changes must be approved by the CO prior to execution.

(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.

FINAL PAYMENT

Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, and release of claims. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.

AVAILABILITY OF UTILITIES SERVICES

Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.

UTILITIES CONSERVATION

The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.

OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS

The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.

NOTICE TO CONTRACTORS - CPARS (DEC 2015) Notice to Contractors

1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.

mailto:mark_fiorina@nps.gov

pg. 8

3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.

4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.

5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.

a) Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.

b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.

c) All information provided should be reviewed for accuracy prior to submission.

d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting "Accept the Ratings and Close the Evaluation".

e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as "Pending" with or without comments and whether or not it has been closed.

f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."

6) The following guidelines apply concerning your use of the past performance evaluation:

a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.

b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.

c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.

7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.

8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.

(End of notice)

DOI ELECTRONIC INVOICING AND PAYEMENT REQUIREMENTS - Invoice Processing Platform (IPP) (FEB 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System

(IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP

pg. 9 website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

Contractor shall not submit to IPP until they receive an approved invoice/payment request from COR and CO.

Completed copy of Invoice/Payment Request Form

Invoice on contractor letterhead

Completed copy of the Limitations on Subcontracting Report (Include if acquisition is being set-aside and clause 52.219-14 is included)

Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts

A copy of the current construction schedule (refer to project specification section.

A copy of the current Schedule of Values

Payrolls

Release of Claims for final invoice

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

1452.201-70 AUTHORITIES AND DELEGATIONS. (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov

pg. 10 with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

(End of clause)

1452.204-70 RELEASE OF CLAIMS (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of clause)

Section H - Special Contract Requirements

Not Applicable Section I - Contract Clauses

52.202-1 DEFINITIONS. (JUN 2020)

52.203-3 GRATUITIES. (APR 1984)

52.203-5 COVENANT AGAINST CONTINGENT FEES. (MAY 2014)

52.203-7 ANTI-KICKBACK PROCEDURES. (JUN 2020)

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER

ACTIVITY. (MAY 2014)

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY. (MAY 2014)

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS. (JUN 2020)

52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM

EMPLOYEES OF WHISTLEBLOWER RIGHTS. (NOV 2023)

52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR

STATEMENTS. (JAN 2017)

pg. 11

52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS. (DEV

MAR 2026)

(a) Definitions. As used in this clause:

Executive means officers, managing partners, or any other employees in management positions.

First-tier subcontract means a subcontract awarded directly by the Contractor to acquire supplies or services (including construction) for performing a prime contract. It does not include the Contractor’s supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a contractor’s general and administrative expenses or indirect costs.

Month of award means the month in which the Contracting Officer signs a contract or the month in which the Contractor signs a first-tier subcontract.

Total compensation means the cash and noncash dollar value earned by the executive during the Contractor's preceding fiscal year and includes the information described at 17 CFR 229.402(c)(2).

(b) Requirement. Section 2(d)(2) of the Federal Funding Accountability and Transparency Act of 2006 (Pub. L. 109-282), as amended by section 6202 of the Government Funding Transparency Act of 2008 (Pub. L. 110-252), requires the Contractor to report information on subcontract awards. The law requires all reported information be made public; therefore, the Contractor is responsible for notifying its subcontractors that the required information will be made public. Nothing in this clause requires disclosing classified information.

(c) Reporting. Unless otherwise directed by the Contracting Officer, or as provided in paragraph (f) of this clause, the Contractor shall report the following in the System for Award Management at https://www.sam.gov as follows:

(1) Executive compensation of the prime contractor. The Contractor shall report the names and total compensation of each of the five most highly compensated executives for its preceding completed fiscal year, if—

(i) In the Contractor's preceding fiscal year, the Contractor received—

(A)80 percent or more of its annual gross revenues from Federal contracts (and subcontracts); loans, grants (and subgrants);

cooperative agreements; and other forms of Federal financial assistance; and

(B)$25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts); loans, grants (and subgrants);

cooperative agreements; and other forms of Federal financial assistance; and

(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986. (To determine if the public has access to the compensation information, see the U.S.

Security and Exchange Commission total compensation filings at http://www.sec.gov/answers/execomp.htm.).

(2) First-tier subcontract information. The Contractor shall report the following information by the end of the month following the month of award of each first-tier subcontract award:

(i) Unique entity identifier for the subcontractor receiving the award and for the subcontractor’s ultimate parent company, if the subcontractor has a parent company.

(ii) Name of the subcontractor.

(iii) Amount of the subcontract award.

(iv) Date of the subcontract award.

(v) A description of the products or services (including construction) being provided under the subcontract, including the overall purpose and expected outcomes or results of the subcontract.

(vi) The subcontract number assigned by the Prime Contractor.

https://www.sam.gov/ http://www.sec.gov/answers/execomp.htm

pg. 12

(vii) Subcontractor’s physical address.

(viii) Subcontractor’s primary performance location.

(ix) The prime contract number, and order number if applicable.

(x) Awarding agency name and code.

(xi) Funding agency name and code.

(xii) Government contracting office code.

(xiii) The applicable North American Industry Classification System code.

(3) Executive compensation of the first-tier subcontractor. The Contractor shall report by the end of the month following the month of award of a first-tier subcontract award and annually thereafter (calculated from the prime contract award date) the names and total compensation of each of the five most highly compensated executives for that subcontractor in the subcontractor’s preceding completed fiscal year, if—

(i) In the subcontractor’s preceding fiscal year, the subcontractor received—

(A)80 percent or more of its annual gross revenues from Federal contracts (and subcontracts); loans, grants (and subgrants);

cooperative agreements; and other forms of Federal financial assistance; and

(B)$25,000,000 or more in annual gross revenues from Federal contracts (and subcontracts); loans, grants (and subgrants);

cooperative agreements; and other forms of Federal financial assistance; and

(ii) The public does not have access to information about the compensation of the executives through periodic reports filed under section 13(a) or 15(d) of the Securities Exchange Act of 1934 (15 U.S.C. 78m(a), 78o(d)) or section 6104 of the Internal Revenue Code of 1986 (see http://www.sec.gov/answers/execomp.htm).

(d) Restriction. The Contractor shall not split or break down subcontracts to a value below the threshold at the Federal Acquisition Regulation 4.208(e), on the date of subcontract award, to avoid the reporting requirements in paragraph (c) of this clause.

(e) Duration. Continued reporting on first-tier subcontracts is not required unless one of the reported data elements changes during the performance of the subcontract. The Contractor is not required to make further reports after a first-tier subcontract expires.

(f) Exceptions.

(1) If the Contractor in the previous tax year had gross income, from all sources, under $300,000, the Contractor is exempt from the requirement to report subcontractor awards.

(2) If a subcontractor in the previous tax year had gross income from all sources under $300,000, the Contractor does not need to report awards for that subcontractor.

(g) Prepopulated data. The Subcontract Reports in SAM will prepopulate with some information from SAM and the Federal Procurement Data System (FPDS). If the FPDS information is incorrect, the Contractor should notify the Contracting Officer. If the SAM information is incorrect, the Contractor is responsible for correcting this information.

(End of clause)

52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE. (DEV MAR 2026)

(a) Definitions. As used in this clause—

Commercial and Government Entity code means— http://www.sec.gov/answers/execomp.htm

pg. 13

(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location (referred to as “CAGE code”); or

(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency to entities located outside the United States and its outlying areas that the DLA CAGE Branch records and maintains in the CAGE master file (referred to as “NCAGE code”).

Unique Entity Identifier (UEI) means an identifier used to identify a specific commercial, nonprofit, or Government entity.

(b) Active registration.

(1) The Contractor shall maintain an active Federal Government contracts registration in the System for Award Management (SAM) at https://www.sam.gov during contract performance and through final payment under this contract. To maintain an active registration in SAM, the Contractor shall review at least annually its registration in SAM and validate that the information is current, accurate, and complete.

(2) The Contractor is responsible for the currency, accuracy, and completeness of the information provided within SAM, and for any liability resulting from the Government’s reliance on inaccurate or incomplete information. Updating SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(c) Novation and change-of-name agreements.

(1) If the Contractor has legally changed its business name or “doing business as” name (whichever is shown on the contract), or has transferred the assets used to perform the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in part 42 of the Federal Acquisition Regulation (FAR), the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to —

(i) Change the legal business name in SAM;

(ii) Comply with the requirements of FAR part 42; and

(iii) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor shall provide with its written notification sufficient documentation to support the legally changed name.

(2) If the Contractor fails to comply with the requirements of paragraph (c)(1) of this clause, or fails to perform the agreement at paragraph (c)(1)(iii) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.

(d) Assignees.

(1) The Contractor shall not change the legal business name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims (see FAR part 32). Assignees shall be separately registered in SAM.

(2) Information provided to the Contractor’s SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be incorrect information within the meaning of the “Suspension of Payment” paragraph of the EFT clause of this contract.

(e) Unique entity identifier (UEI). The Contractor shall ensure that its UEI is maintained throughout the life of the contract.

(f) Commercial and Government Entity (CAGE) code. The Contractor shall ensure that the CAGE code is maintained throughout the life of the contract. To update a CAGE code, the Contractor shall initiate the change by updating its SAM registration.

(g) Communicating changes. The Contractor shall communicate any change to its UEI or CAGE code to the Contracting Officer

pg. 14 within 30 days after the change, so a modification can be issued to update the UEI or CAGE code on this contract. A change in the UEI does not necessarily require a novation.

(End of clause)

52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS. (DEV MAR 2026)

(a) Definition. As used in this clause—

First-tier subcontract means a subcontract awarded directly by the Contractor to acquire supplies or services (including construction) for performing a prime contract. It does not include the Contractor's supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a contractor's general and administrative expenses or indirect costs.

(b) Requirement. The Contractor shall report, according to paragraphs (c) and (d) of this clause, annually by October 31, for services performed under this contract during the preceding Government fiscal year (October 1-September 30).

(c) Report elements. The Contractor shall report the following information:

(1) Contract number and, as applicable, order number.

(2) The total dollar amount invoiced for services performed during the previous Government fiscal year under the contract.

(3) The number of Contractor direct labor hours expended on the services performed during the previous Government fiscal year.

(4) Data reported by subcontractors under paragraph (f) of this clause.

(d) Remedies. The Contractor shall submit the information required in paragraph (c) of this clause in the System for Award Management (SAM) at https://www.sam.gov (see SAM User Guide). If the Contractor fails to submit the report in a timely manner, the Contracting Officer will exercise appropriate contractual remedies. In addition, the Contracting Officer will make the Contractor's failure to comply with the reporting requirements a part of the Contractor's performance information under the Federal Acquisition Regulation part 42.

(e) Review. Agencies will review Contractor-reported information for reasonableness and consistency with available contract information.

If the agency believes that revisions to the Contractor’s reported information are warranted, the agency will notify the Contractor no later than November 15. By November 30, the Contractor shall revise the report, or put its reason in writing for the agency.

(f) First-tier subcontracts.

(1) The Contractor shall require each first-tier subcontractor providing services under this contract, with subcontract(s) each valued at or above the thresholds set forth in 4.303(b), to provide the following detailed information to the Contractor in sufficient time to submit the report:

(i) Subcontract number (including subcontractor name and unique entity identifier); and

(ii) The number of first-tier subcontractor direct-labor hours expended on the services performed during the previous Government fiscal year.

(2) The Contractor shall tell the subcontractor that the information will be made available to the public as required by section 743 of Division C of the Consolidated Appropriations Act, 2010.

(End of clause)

52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS

DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT. (DEV MAY 2026)

(a) Definition. As used in this clause—

pg. 15

Commercially available off-the-shelf (COTS) item

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” in Federal Acquisition Regulation

(FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

(b) The Government suspends or debars Contractors to protect the Government's interests. Other than a subcontract for a commercially available off-the-shelf item, the Contractor shall not enter into any subcontract, in excess of the threshold specified in FAR 9.405-2(b) on the date of subcontract award, with a Contractor that is debarred, suspended, or proposed for debarment by any executive agency unless a compelling reason exists to do so.

(c) The Contractor shall require each proposed subcontractor whose subcontract will exceed the threshold specified in FAR 9.405-2(b) on the date of subcontract award, other than a subcontractor providing a commercially available off-the-shelf item, to disclose to the Contractor, in writing, whether as of the time of award of the subcontract, the subcontractor, or its principals, is or is not debarred, suspended, proposed for debarment, or voluntarily excluded by the Federal Government.

(d) A corporate officer or a designee of the Contractor shall notify the Contracting Officer, in writing, before entering into a subcontract with a party (other than a subcontractor providing a commercially available off-the-shelf item) that is debarred, suspended, proposed for debarment, or voluntarily excluded (see FAR 9.404 for information on the System for Award Management (SAM) Exclusions). The notice must include the following:

(1) The name of the subcontractor.

(2) The Contractor’s knowledge of the reasons for the subcontractor being listed with an exclusion in SAM.

(3) The compelling reason(s) for doing business with the subcontractor notwithstanding its being listed with an exclusion in SAM.

(4) The systems and procedures the Contractor has established to ensure that it is fully protecting the Government's interests when dealing with such subcontractor in view of the specific basis for the party's debarment, suspension, proposed debarment, or voluntary exclusion.

(e) Subcontracts. Unless this is a contract for the acquisition of commercial products or commercial services, the Contractor shall include the requirements of this clause, including this paragraph (e) (appropriately modified for the identification of the parties), in each subcontract that—

(1) Exceeds the threshold specified in FAR 9.405-2(b) on the date of subcontract award; and

(2) Is not a subcontract for commercially available off-the-shelf items.

(End of clause)

52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS. (DEV MAY 2026)

a) Definitions. As used in this clause-

Inverted domestic corporation means a foreign incorporated entity that meets the definition of an inverted domestic corporation under 6 U.S.C. 395(b), applied in accordance with the rules and definitions of 6 U.S.C. 395(c).

Subsidiary means an entity in which more than 50 percent of the entity is owned— http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section40102(4)&num=0&edition=prelim

pg. 16

(1) Directly by a parent corporation; or

(2) Through another subsidiary of a parent corporation.

(b) If the contractor reorganizes as an inverted domestic corporation or becomes a subsidiary of an inverted domestic corporation at any time during the period of performance of this contract, applicable law may prohibit the Government from paying for Contractor activities performed after the date when it becomes an inverted domestic corporation or subsidiary.

The Government may seek any available remedies in the event the Contractor fails to perform in accordance with the terms and conditions of the contract as a result of Government action under this clause.

(c) Exceptions to this prohibition are located at 9.108-3.

(d) In the event the Contractor becomes either an inverted domestic corporation, or a subsidiary of an inverted domestic corporation during contract performance, the Contractor shall give written notice to the Contracting Officer within five business days from the date of the inversion event.

(End of clause)

52.214-29 ORDER OF PRECEDENCE - SEALED BIDDING. (JAN 1986)

52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE. (DEV JAN 2026)

(a) Definition. Small business concern, as used in this clause—

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the size standards in this solicitation.

(2) Affiliates, as used in paragraph (a)(1) of this clause, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) Applicability. This clause applies only to-

(1) Contracts that have been set aside for small business concerns; and

(2) Orders set aside for small business concerns under multiple-award contracts as described in 8.4 and 16.5.

(c) General.

(1) Offers are solicited only from small business concerns. Offers received from concerns that are not small business concerns shall be considered nonresponsive and will be rejected.

(2) Any award resulting from this solicitation will be made to a small business concern.

(End of clause)

52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS. (DEV JAN 2026)

(a) Definitions. As used in this contract—

HUBZone small business concern means a small business concern that meets the requirements described in 13 CFR 126.200, certified by the Small Business Administration (SBA) and designated by SBA as a HUBZone small business concern in the Small Business Search (SBS) and the System for Award Management (SAM).

Service-disabled veteran-owned small business (SDVOSB) concern means an SDVOSB concern that meets the requirements described in 13 CFR 128.300, is certified by SBA, and is designated by SBA as an SDVOSB concern in SBS and SAM.

pg. 17

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation and qualified as a small business under the criteria and size standards in 13 CFR part 121, including the size standard that corresponds to the NAICS code assigned to the contract or subcontract.

Small disadvantaged business (SDB) concern means a small business concern under the size standard applicable to the acquisition, that-

(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR 124.105) by-

(i) One or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States; and

(ii) Each individual claiming economic disadvantage has a net worth not exceeding the threshold at 13 CFR 124.104(c)(2) after taking into account the applicable exclusions set forth at 13 CFR 124.104(c)(2); and

(2) The management and daily business operations of which are controlled (as defined at 13.CFR 124.106) by individuals, who meet the criteria in paragraphs (1)(i) and (ii) of this definition.

Veteran-owned small business (VOSB) concern means a small business concern-

(1) Not less than 51 percent of which is owned and controlled by one or more veterans (as defined at 38 U.S.C.101(2)) or, in the case of any publicly owned business, not less than 51 percent of the stock of which is owned by one or more veterans; and

(2) The management and daily business operations of which are controlled by one or more veterans.

Women-owned small business (WOSB) concern means a small business concern-

(1) That is at least 51 percent owned by one or more women, or, in the case of any publicly owned business, at least 51 percent of the stock of which is owned by one or more women;

(2) Whose management and daily business operations are controlled by one or more women; and

(3) That is certified by SBA or an approved third- party certifier in accordance with 13 CFR 127.300 and is designated by SBA as a WOSB concern in SBS and SAM.

(b) It is the policy of the United States that small business concerns, VOSB concerns, SDVOSB concerns, HUBZone small business concerns, SDB concerns, and WOSB concerns shall have the maximum practicable opportunity to participate in performing contracts let by any Federal agency, including contracts and subcontracts for subsystems, assemblies, components, and related services for major systems.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .