This document is a Solicitation, Offer, and Award (Standard Form 1442) for a construction project to replace the fire and security alarm system at the Herbert Hoover National Historic Site in West Branch, Iowa.
The key details are:
- This is a sealed bid Invitation for Bids (IFB) for a firm-fixed-price contract with a 240-calendar day period of performance after the notice to proceed.
- The project involves replacing the existing fire alarm and intrusion alarm systems in 19 buildings, with a combination of wireless and wired systems, and networking the fire and intrusion alarm panels.
- The project is valued between $1-5 million and is 100% set aside for small businesses under NAICS code 238210.
- Bids are due by October 30, 2024 at 11:00 AM CT, with a virtual bid opening. A bid guarantee of 20% is required, and performance and payment bonds of 100% of the final contract award amount.
- The procuring agency is the Department of the Interior, National Park Service, Midwest Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6024B0005_Amd_0003.pdf | ||
| B11_QA_11-4-2024_0003.docx | DOCX document | |
| B12_MISC_Site_Visit_Questions_0002.docx | DOCX document | |
| B12_MISC_Site_Visit_Attendees_0002.pdf | ||
| Sol_140P6024B0005_Amd_0002.pdf | ||
| B11_QA_10-3-2024_0001.docx | DOCX document | |
| Sol_140P6024B0005_Amd_0001.pdf | ||
| B08_Sol_-_Att_5_-_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| B08_Sol_-_Att_2_-_Drawings.pdf | ||
| B08_Sol_-_Att_6_-_Submittal_List.pdf | ||
| B08_Sol_-_Att_4_-_Notice_to_Contractors.pdf | ||
| B08_Sol_-_Att_1_-_Specifications.pdf | ||
| B08_Sol_-_Att_3_-_Wage_Determination.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
NPS, MWR - MWRO MABO
601 Riverfront Drive
Omaha NE 68102
PMH
mwromabobids@nps.gov
Bridget Parizek 4028007927 x
09/26/2024
140P6024B0005
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
HEHO - Replace Fire and Security Alarm System
This solicitation is a Sealed Bid. This is an electronic Invitation for Bid (IFB) for construction work at Herbert Hoover National Historic Site in West Branch, Iowa.
The resulting contract will be firm-fixed price. The complete specifications, provisions, and clauses are available at http://www.sam.gov. Please replace any mention of "substantial completion" with "final completion" throughout the entire specification document.
Work will consist of: Removing existing fire alarm system and intrusion alarm system from 19 buildings; a wireless fire alarm system and a wireless intrusion alarm system will be provided for 13 buildings; a wired fire alarm system and a wired intrusion alarm system will be provided for 5 buildings; each of the 19 buildings will have a fire alarm control panel and intrusion alarm panel. In addition to this, the Visitor Center/Post Office will have a master fire alarm control panel and a master intrusion alarm panel; all the fire alarm panels and intrusion alarm panels will be networked together with new multimode fiber optic cable installed in new or existing underground conduits; selective work to provide a finished project such as cutting and patching, wood framing, gypsum board wall, door and frame, and painting.
Continued ...
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 240 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10
10/30/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
NPS, MWR - MWRO MABO
601 Riverfront Drive
Omaha NE 68102
PMH
Bridget Parizek
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 55
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P6024B0005
Bid Opening Information: The sealed bid opening process will be conducted virtually. There will be no in person bid opening available. Refer to the virtual bid opening information below for call-in information.
Bid Opening Date/Time: October 30, 2024 @ 11:00AM
CT
Dial in: 202-640-1187
Conference ID: 410 811 907#
Project location: Herbert Hoover National
Historic Site, 110 Parkside Dr, West Branch, IA
52358
PROJECT MAGNITUDE: Between $1,000,000 and
$5,000,000
Bonds: Required as stated in Block 12. A bid guarantee is required 20%, but not to exceed $3M.
Bid bond is required to be submitted on a
Standard Form 24. A copy of the bid guarantee shall be emailed with your bid package.
Performance and Payment bonds/protection in the amount of 100% of the final contract award amount.
NAICS: The associated NAICS code is 238210, Electrical Contractors and Other Wiring
Installation Contractors, with a small business size standard of $19M.
Notice of Set-Aside: 100% set-aside for Total
Small Businesses
Period of performance: 240 calendar days from the
Notice to Proceed
Site Visit: A site visit is highly encouraged.
Please see 52.236-27 for specific guidance.
Wage Rates: Wage Rate requirements are incorporated into the terms and conditions as an attachment.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 55
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P6024B0005
System for Award Management (SAM): The successful offeror must be registered in SAM.gov and have current online Representations and
Certifications. Please access http://www.sam.gov to update your records prior to submitting final offer.
Method and Instructions for Submitting Offer:
Refer to Section B, Bid Schedule, and Section L, Instructions, Conditions, and Notices to Offerors or Respondents. Complete bid package shall be emailed directly to mwromabobids@nps.gov
Questions: All questions shall be submitted in writing to bridget_parizek@nps.gov. All questions must be submitted in writing no later than 5 days following the scheduled site visit.
Delivery: 240 Days After Notice to Proceed
Delivery Location Code: 0009060382
NPS, MWR, Herbert Hoover NHS
110 Parkside Drive
P.O. Box 607
West Branch IA 52358 US
00010 Replace Fire and Security Alarm System
Product/Service Code: Z2JZ
Product/Service Description: REPAIR OR ALTERATION
OF MISCELLANEOUS BUILDINGS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 5 of 55
TABLE OF CONTENT
Part I – The Schedule SECTION A – Solicitation/Contract Form Special Notice for Bidders SECTION B – Bid Schedule SECTION C – Specifications/Drawings SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance 52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996) SECTION F - Deliveries or Performance 52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.242-14 -- Suspension of Work (Apr 1984) SECTION G - Contract Administration Data 1452.201-70 Authorities and Delegations (Sep 2011) Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021) Construction Contract Administration SECTION H - Special Contract Requirements Part II – Contract Clauses SECTION I - Contract Clauses 52.252-2 – Clauses Incorporated by Reference (Feb 1998) 52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) .15 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.214-26 Audit and Records – Sealed Bidding (Jun 2020) Alternate I (Mar 2009) 52.214-29 Order of Precedence – Sealed Bidding (Jan 1986) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.219-8 Utilization of Small Business Concerns (Feb 2024) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988)
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 6 of 55
52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers With Disabilities (Jun 2020) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employee Eligibility Verification (May 2022) 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (May 2024) 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) 52.223-10 Waste Reduction Program (May 2024) 52.225-13 Restriction on Certain Foreign Purchases (Feb 2021) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance- Work on a Government Installation (Jan 1997) 52.228-12 Prospective Subcontractor Request for Bonds (May 2014) 52.229-3 Federal, State, and Local Taxes (Feb 2013) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach Of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 17 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-16 Quantity Surveys (Apr 1984) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (July 1995)
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 7 of 55
52.243-4 Changes (Jun 2007) 52.244-5 Competition in Subcontracting (Dec 1996) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Feb 2024) 52.245-1 Government Property (Sep 2021) 52.245-9 Use and Charges (Apr 2012) 52.246-21 Warranty of Construction (Mar 1994) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - (ALT I) (Sept 1996) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)
CLAUSES INCORPORATED BY FULL TEXT
1452.203-70 -- Restrictions on Endorsements (Jul 1996) 1452.204-70 -- Release of Claims (Jul 1996) 1452.228-70 -- Liability Insurance—Department of the Interior (Jul 1996) 52.204-21 – Basic Safeguarding of Covered Contractor Information Systems (Nov 2021) 52.204-30 Federal Acquisition Supply Chain Security Act Orders – Prohibition (Dec 2023) 52.219-14 Limitations on Subcontracting (Oct 2022)(DEVIATION Oct 2022) 52.225-9 -- Buy American–Construction Materials (Oct 2022) 52.228-11 Individual Surety - Pledges of Assets (Feb 2021) (DEVIATION May 2023) 52.228-15 Performance and Payment Bonds- Construction (Jun 2020) (DEVIATION May 2023) 52.252-6 – Authorized Deviations in Clauses (Nov 2020) Part III – List of Documents, Exhibits, and Other Attachments SECTION J – List of Attachments Part IV – Representations and Instructions SECTION K - Representations, Certifications, and Other Statements of Offerors 52.252-1 – Solicitation Provisions Incorporated by Reference (Feb 1998) 52.203-18 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements - Representation (Jan 2017) 52.204-17 Ownership of Control of Offeror (Aug 2020) 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications (Jun 2020)
PROVISIONS INCORPORATED BY FULL TEXT
52.201-1 Acquisition 360: Voluntary Survey (Sep 2023) 52.204-8 -- Annual Representations and Certifications (Feb 2024) 52.204-24 Representation Regarding Certain Telecommunication and Video Surveillance Services or Equipment (Nov 2021) 52.204-26 Covered Telecommunications Equipment or Services-Representation (Oct 2020) 52.204-29 Federal Acquisition Supply Chain Security Act Orders – Representation and Disclosures (Dec 2023) 52.209-7 – Information Regarding Responsibility Matters (Oct 2018) 52.209-13 Violation of Arms Control Treaties or Agreements – Certification (Nov 2021) (End of provision) 52.222-23 -- Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.229-11 Tax on Certain Foreign Procurements—Notice and Representation 52.252-5 – Authorized Deviations in Provisions (Nov 2020) SECTION L - Instructions, Conditions, and Notices to Offerors 52.252-1 – Solicitation Provisions Incorporated by Reference (Feb 1998) 52.204-7 System for Award Management (Oct 2018) 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991)
PROVISIONS INCORPORATED BY FULL TEXT
52.211-3 -- Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (Jun 1988) 52.214-3 Amendments to Invitations for Bids (Dec 2016) 52.214-4 False Statements in Bids (Apr 1984)
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 8 of 55
52.214-5 Submission of Bids (Dec 2016) 52.214-6 Explanation to Prospective Bidders (Apr 1984) 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999) 52.214-12 Preparation of Bids (Apr 1984) 52.214-18 Preparation of Bids -- Construction (Apr 1984) 52.214-19 Contract Award -Sealed Bidding -- Construction (Aug 1996) 52.216-1 – Type of Contract (Apr 1984) 52.222-5 -- Construction Wage Rate Requirements—Secondary Site of the Work (May 2014) 52.225-10 -- Notice of Buy American Requirement--Construction Materials (May 2014) 52.228-1 Bid Guarantee (Sep 1996) 52.236-27 – Site Visit (Construction) (Feb 1995) 1452.233-2 Service of Protest Department of the Interior (SEPT 2006) (DEVIATION) (JUL 1996)
INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS OR RESPONDENTS
SECTION M - EVALUATION FACTORS FOR AWARD
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 9 of 55
Part I – The Schedule
SECTION A – Solicitation/Contract Form
Invitation for Bids (IFB) are issued on a Standard Form (SF) 1442, Solicitation, Offer, and Award document.
Reference DIAR 1436.270-1 Uniform contract format.
Special Notice for Bidders
Signing of the bid shall be deemed to be a representation by the bidder that:
1.) Bidder is a construction contractor who owns, operates, or maintains a place of business, regularly engaged in the work described herein; or
2.) If newly entering into a construction activity, bidder has made all necessary arrangements for personnel, construction equipment, and required licenses to perform construction work as specified;
and
3.) Upon request, prior to award, bidder will promptly furnish to the Government a statement of facts in detail as to bidder’s previous experience (including recent and current contracts), organization (including company officers), technical qualifications, financial resources and facilities available to perform the contemplated work.
4.) North American Industry Classification System (NAICS) code and small business size standard. The NAICS code for this acquisition is 238210 with a size standard of $19 Million. To be considered for award your company must obtain a Unique Entity Identifier (UEI). Your company needs to be registered in the System for Award Management (SAM) and be considered a small business for the size standard associated with the NAICS code stated above/utilized throughout this solicitation - this registration needs to be in an “active” status in SAM.gov at the time of IFB submission close date - as well as, at the time of award and throughout the entire award/contract performance.
5.) Bidder agrees to the requirements contained in FAR 52.219-14, Limitations on Subcontracting
The bid opening will be held virtually. Bids are to be emailed and delivery confirmed on or before the date and time of the virtual bid opening. Bids are required to be submitted electronically following instructions contained in this solicitation.
CALL-IN INFORMATION: Bid Openings will be performed via meeting ID/conference call.
Interested parties may attend the bid openings by using the call-in information below:
Bid Opening Date/Time: October 30, 2024 @ 11:00AM CT Dial in: 202-640-1187 Conference ID: 410 811 907#
SECTION B – Bid Schedule
Preparation of Bids: The Government will not be responsible for any costs incurred by offeror in the research, preparation, or submission of its bid.
Bid pricing shall be provided in accordance with Section L and is incorporated herein.
Contract Line Item Number (CLIN) Contract Line Item Title Price 10 Replace Fire and Security Alarm
System
TOTAL: $
https://www.acquisition.gov/diar/part-1436-construction-and-architect-engineer-contracts#Section_1436_270_1_T48_5075734113
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 10 of 55
SECTION C – Specifications/Drawings
Project work consists of: Removing existing fire alarm system and intrusion alarm system from 19 buildings; a wireless fire alarm system and a wireless intrusion alarm system will be provided for 13 buildings; a wired fire alarm system and a wired intrusion alarm system will be provided for 5 buildings; each of the 19 buildings will have a fire alarm control panel and intrusion alarm panel. In addition to this, the Visitor Center/Post Office will have a master fire alarm control panel and a master intrusion alarm panel; all the fire alarm panels and intrusion alarm panels will be networked together with new multimode fiber optic cable installed in new or existing underground conduits; selective work to provide a finished project such as cutting and patching, wood framing, gypsum board wall, door and frame, and painting. Additional requirements information is provided in the solicitation, specifications, supporting documents and other pertinent attachments.
“Specifications and other supporting documents are attached and incorporated herein. Refer to SECTION J.”
SECTION D - Packaging and Marking
No clauses included
SECTION E - Inspection and Acceptance
52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not --
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph
(i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 11 of 55
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may --
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of Clause)
SECTION F - Deliveries or Performance
Work shall be completed by skilled personnel per industry standards and manufacturer specifications.
52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 240 calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
52.236-15 Schedules for Construction Contracts (Apr 1984)
(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 12 of 55 increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
(End of clause)
52.242-14 -- Suspension of Work (Apr 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.
However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
SECTION G - Contract Administration Data
(a) Contact Information:
The Contract Specialist/Contracting Officer administrating the Contract:
Bridget Parizek Contract Specialist National Park Service Telephone No. (402) 800-7927 Email: bridget_parizek@nps.gov
(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.
mailto:bridget_parizek@nps.gov
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 13 of 55
(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.
(d) Any request for contract changes/modifications shall be submitted to the CO.
(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items.
All field changes must be approved by the CO prior to execution.
(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.
FINAL PAYMENT
Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, warranty of construction, release of claims and any other documents requested by the contracting office as applicable. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.
AVAILABILITY OF UTILITIES SERVICES
Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.
UTILITIES CONSERVATION
The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.
OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS
The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.
INTERIM AND FINAL INSPECTIONS
1. Prior to covering, enclosing, or hiding any of type work, the Contractor must contact the Government representative to perform an interim inspection. Failure to contact the Government representative perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.
2. When ready for final inspection, the Contractor shall notify the CO and COR, requesting a final inspection in writing to the CO. The final inspection shall normally be requested a minimum of three (3) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.
3. The final inspection will be onsite with the Contractor, the Contracting Officer’s Representative, and Contract Specialist/Contracting Officer (when possible).
1452.201-70 Authorities and Delegations (Sep 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 14 of 55 this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
The COR for this contract will be:
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.
(End of Local Clause)
Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Copy of vendor invoice document in PDF format, completed on the pay application document provided by contracting, which shows pricing breakdown for all line items. Once all signatures (Contractor’s / COR / CO) and approvals are completed on the pay application, the vendor can then upload this document into IPP as their invoice attachment.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email https://www.ipp.gov/
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 15 of 55 from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date.
Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
Construction Contract Administration
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
SECTION H - Special Contract Requirements
GREEN PROCUREMENT
To the extent that the construction services provided by the Contractor require provision of any of the types of products listed at https://sftool.gov/greenprocurement, the Contractor is expected to provide the green type of product unless that type of product is not available competitively within a reasonable time, at a reasonable price, is not life cycle cost efficient in the case of energy consuming products, or does not meet reasonable performance standards.
Part II – Contract Clauses
SECTION I - Contract Clauses
52.252-2 – Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov
52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-14 Service Contract Reporting Requirements (Oct 2016) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) mailto:IPPCustomerSupport@fiscal.treasury.gov https://www.doi.gov/pam/acquisition/policy/constructioncontract https://sftool.gov/greenprocurement http://www.acquisition.gov/
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 16 of 55
52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.214-26 Audit and Records – Sealed Bidding (Jun 2020) Alternate I (Mar 2009) 52.214-29 Order of Precedence – Sealed Bidding (Jan 1986) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.219-8 Utilization of Small Business Concerns (Feb 2024) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (Jun 2020) 52.222-36 Equal Opportunity for Workers With Disabilities (Jun 2020) 52.222-37 Employment Reports on Veterans (Jun 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-54 Employee Eligibility Verification (May 2022) 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (May 2024) 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) 52.223-10 Waste Reduction Program (May 2024) 52.225-13 Restriction on Certain Foreign Purchases (Feb 2021) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance- Work on a Government Installation (Jan 1997) 52.228-12 Prospective Subcontractor Request for Bonds (May 2014) 52.229-3 Federal, State, and Local Taxes (Feb 2013) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-17 Interest (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach Of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984)
140P6024B0005 HEHO – Replace Fire and Security Alarm System Page 17 of 55
52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-16 Quantity Surveys (Apr 1984) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (July 1995) 52.243-4 Changes (Jun 2007) 52.244-5 Competition in Subcontracting (Dec 1996) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Feb 2024) 52.245-1 Government Property (Sep 2021) 52.245-9 Use and Charges (Apr 2012) 52.246-21 Warranty of Construction (Mar 1994) 52.248-3 Value Engineering-Construction (Oct 2020) 52.249-2 Termination for…