This document is a solicitation (Request for Proposals) for concrete repairs, installations, and pavement painting work at the National Centers for Animal Health in Ames, Iowa. The project includes work across four areas: Building 21 West Parking Lot, Building 12 concrete pad, Gate 16 Concrete Pad, and VV105 Roadway Repair. The solicitation is issued as a 100% Total Small Business Set-Aside, with a performance period of 180 days after notice to proceed. Pricing is requested on a fixed unit price basis for the base item and three option items. Proposals are due by August 6, 2024 at 11:00 AM CT. The contracting agency is the USDA Agricultural Research Service Midwest Area.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1126080
USDA ARS MWA AAO ACQ/PER PROP
1815 N UNIVERSITY STREET
PEORIA IL 61604
ARS-12505B
Tiffany Reval tiffany.reval@usda.gov
TIFFANY REVAL 5803180321
1x 06/21/2024
12505B24R0016
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
14 180 calendar days and complete it within ________________ ________________ calendar days after receiving
FAR 52.211-10
08/06/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
ZACHARY E. SCHULER
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 59
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12505B24R0016
FAR 52.228-1(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of bid.
FAR 52.232-18 -- Availability of Funds (Apr 1984)
Funds are not presently available for this contract. The Government¿s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the
Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the
Contracting Officer.
Delivery: 180 Days After Notice to Proceed
Delivery Location Code: ARS-126125
MWA NATIONAL ANIMAL DISEASE CENTER
1920 DAYTON AVENUE
P.O. BOX 70
AMES IA 50010 US
Period of Performance: 08/20/2024 to 02/04/2025
0001 Base Proposal- Area 1: Building 21 West Parking 1 LO
Lot
0002 Option #1-Area 2: Building 12 concrete pad 1 LO
(Option Line Item)
11/30/2024
Product/Service Code: Y1LZ
Product/Service Description: CONSTRUCTION OF
PARKING FACILITIES
0003 Option #2-Area 3: Gate 16 Concrete Pad 1 LO
(Option Line Item)
11/30/2024
Product/Service Code: Y1LZ
Product/Service Description: CONSTRUCTION OF
PARKING FACILITIES
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 59
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12505B24R0016
0004 Option #3-Area 4: VV105 Roadway Repair 1 LO
(Option Line Item)
11/30/2024
Product/Service Code: Y1LZ
Product/Service Description: CONSTRUCTION OF
PARKING FACILITIES
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SOLICITATION 12505B24R0016
Ames, Iowa
National Centers for Animal Health Concrete Repairs and Pavement Painting
National Centers for Animal Health Concrete Repairs and Pavement Painting
B - SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
C - SECTION C - DESCRIPTION/SPECS./WORK STATEMENT
D - SECTION D - PACKAGING AND MARKING
E - SECTION E - INSPECTION AND ACCEPTANCE
F - SECTION F - DELIVERIES OR PERFORMANCE
G - SECTION G - CONTRACT ADMINISTRATION DATA
H - SECTION H - SPECIAL CONTRACT REQUIREMENTS
I - SECTION I - CONTRACT CLAUSES
J - SECTION J - LIST OF ATTACHMENTS
L - SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS
M - SECTION M - EVALUATION FACTORS FOR AWARD
National Centers for Animal Health Concrete Repairs and Pavement Painting
B - SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 PRICE SCHEDULE:
(a) Definition of CLIN – Contract Line Item Number.
Line # Qty. Unit Description Price/Cost
0001 1 Lot Base Bid-Area 1: Building 21 West Parking Lot $ 0002 1 Lot Option 1- Area 2: Building 21 concrete pad $ 0003 1 Lot Option 2- Area 3: Gate 16 Concrete Pad $ 0004 1 Lot Option 3- Area 4: VV105 Roadway Repair $
Total $
(b) If an option is exercised, completion date shall be 180 days from the last exercised option.
End of this section
National Centers for Animal Health Concrete Repairs and Pavement Painting
C - SECTION C - DESCRIPTION/SPECS./WORK STATEMENT
C.1 DESCRIPTION OF WORK:
This project will include concrete repairs, installations, and pavement painting work in multiple areas on the Ames USDA campus.
C.2 GENERAL REQUIREMENTS:
C.2.1 Service Interruptions/Utility Outages If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the Contracting Officer Representative ten calendar days in advance to allow notification of affected tenants and customers. If the discontinued service is due to an emergency breakdown the Contractor shall notify the Contracting Officer Representative as soon as practicable.
At a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
C.2.2 Employee Conduct Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
C.2.3 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The Contracting Officer reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for required passes or badges.
National Centers for Animal Health Concrete Repairs and Pavement Painting
D - SECTION D - PACKAGING AND MARKING
(There are no Clauses in this Section)
National Centers for Animal Health Concrete Repairs and Pavement Painting
E - SECTION E - INSPECTION AND ACCEPTANCE
E.1 CONTRACT CLAUSES INCLUDED BY REFERENCE:
FAR 52.246-12 -- Inspection of Construction (Aug 1996) (End of clauses by reference)
E.2 AGAR CONTRACT CLAUSES INCLUDED BY FULL TEXT:
AGAR 452.246-70 -- INSPECTION AND ACCEPTANCE
INSPECTION AND ACCEPTANCE (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at: 1920 Dayton Avenue Ames, Iowa 50010
(End of clause)
E.3 FINAL INSPECTION:
(a) A final inspection shall be made only when all the materials have been furnished, all the work has been performed, and all the construction provided for by the contract in accordance with the terms has been completed. If, upon examination by the Contracting Officer and/or Government inspection personnel, the project is determined not sufficiently completed to have warranted a final inspection, the contractor may be charged with any additional cost of re-inspection when material and workmanship are not ready at the time specified by the Contractor for its inspection.
(b) The contractor shall give the Contracting Officer ten (10) calendar days advance notice, in writing, of the date the work will be fully completed and ready for final inspection.
(c) The Contractor's request for final inspection will not be approved unless all documentation required below, and all other contract requirements have been provided to the Contracting Officer:
-Guarantees and warranty schedule and contacts -Certified payroll records for all prime and subcontractor employees
(d) As soon as practicable, following final inspection, the Contracting Officer will inform the contractor, in writing, of any discrepancies and/or omissions noted at the final inspection. The Contracting Officer shall also state the time allowable for replacement of material and performance or re-performance o f any unsatisfactory work necessary for final acceptance.
E.4 FINAL ACCEPTANCE:
Upon written notification that all deficiencies identified during the final inspection have been corrected, the Contracting Officer will schedule a final acceptance inspection of the work. If all construction required by the contract is determined to be complete and all requisite contract deliverables (e.g., certified payroll records, as-built drawings, warranty documents, etc.) have been submitted and approved by the Government, the Contracting Officer shall notify the Contractor in writing of such acceptance. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
National Centers for Animal Health Concrete Repairs and Pavement Painting
F - SECTION F - DELIVERIES OR PERFORMANCE
F.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) The Contractor shall be required to
(a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 180 days from receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
F.2 CONTRACT CLAUSES INCLUDED BY REFERENCE:
FAR 52.236-15 -- Schedules for Construction Contracts (Apr 1984) FAR 52.242-14 -- Suspension of Work (Apr 1984)
(End of clauses by reference)
F.3 PERFORMANCE TIME
0001-Base Item: 180 calendar days after Notice to Proceed is issued.
0002-Option: 180 calendar days after Notice to Proceed is issued 0003-Option: 180 calendar days after Notice to Proceed is issued 0004-Option: 180 calendar days after Notice to Proceed is issued
National Centers for Animal Health Concrete Repairs and Pavement Painting
G - SECTION G - CONTRACT ADMINISTRATION DATA
G.1 CONTRACTING OFFICER'S REPRESENTATIVE
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
The COR will be named at time of award.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers having been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers exceeding the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.2 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS - INVOICE PROCESSING
PLATFORM (IPP):
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform System (IPP). The IPP website address is: https://www.ipp.gov.
“Payment requests” means any request for contract financing payment or invoicing payment by the Contractor. To constitute a proper invoice, the payment request shall comply with FAR 52.232-27, Prompt Payment for Construction Contracts, and include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of the clause.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3-5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
Attachments are required to be uploaded to IPP.gov.
https://www.ipp.gov/
National Centers for Animal Health Concrete Repairs and Pavement Painting
Prior to submitting an invoice to IPP.gov, the contractor is strongly encouraged to coordinate with the designated Contracting Officer’s Representative (COR), for review and verification of any measured quantities (if applicable) for payment and for compliance with the applicable progress payment requirements of this contract. Failure to do so, may cause a delay in approval and/or rejection of submitted invoices.
Pursuant to the payment terms contained in this contract, the contractor shall prepare and submit requests for payments (invoices) by following the instructions as described below:
1. To ensure timely processing of invoices under the contract/agreement, the contractor must submit all invoices to the following e-mail address:
thomas.walker@usda.gov
2. The contracting Representative and Contracting Officer shall approve the ARS 371 and ARS 372 prior to submitting the invoice to IPP. A proper invoice shall be submitted by email concurrent with submission to IPP and shall include the information as required by the payment terms and conditions contained in this contract.
3. The subject line of the email shall be formatted to read as follows:
Contract Number, Invoice Number Example: 12905B20C0022 Invoice No. 1
4. The Invoice shall be attached to the email and named using the following format:
Contract Number, Contractor Name, Invoice Number, Invoice Amount Example: 12905B20C0022 Contractor ABC Inv No 1-$5,678.00
5. Invoices shall not include information that would compromise Personally Identifiable Information, such as full social security numbers, dates of birth, etc.
6. The final invoice shall be submitted and will be approved in accordance with the payment terms and conditions contained in the contract, after all, if any, settlement actions are complete. The contractor must clearly identify the last payment as the “Final Invoice”.
Emailed Support documents must include, but are not limited to, the following documents:
Invoices must be submitted with ARS-371 and ARS-372, along with certified payroll records, Contractor Certification, and updated CPM Schedule.
mailto:thomas.walker@usda.gov
National Centers for Animal Health Concrete Repairs and Pavement Painting
H - SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:
AGAR 452.236-71 -- PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT
PROHIBITION AGAINST THE USE OF LEAD-BASED PAINT (NOV 1996)
Neither the Contractor nor any subcontractor performing under this contract shall use paints containing more than
0.06 of 1 percent lead by weight (calculated as lead metal) in the total nonvolatile content of the paint, or the equivalent measure of lead in the dried film of paint already applied, or both.
(End of Clause)
AGAR 452.236-72 -- USE OF PREMISES
USE OF PREMISES (NOV 1996)
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, written permission shall be obtained through the Contracting Officer. A camp is interpreted to include the camp site or trailer parking area of any employee working on the project for the Contractor.
(b) Unless excepted elsewhere in the contract, the Contractor shall(i)provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
(End of Clause)
AGAR 452.236-75 -- Maximum Workweek--Construction Schedule.
MAXIMUM WORKWEEK-- CONSTRUCTION SCHEDULE (NOV 1996)
Within 5 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.
The maximum workweek that will be approved is:
Regular work hours for the site are 7:00 AM to 4:30PM, Monday through Friday, excluding Government holidays.
Requests for exceptions to this schedule shall be made in writing forty-eight (48) hours in advance and approved by the Contracting Officer's Representative.
(End of clause)
AGAR 452.237-74 -- KEY PERSONNEL (FEB 1988)
(a) The contractor shall assign to this contract the following key personnel:
Title(s): Name(s):
Site Superintendent
(b) During the first ninety (90) days of performance, the contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-period, the contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the person(s) being replaced. The Contracting Officer will notify the contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
(End of Clause)
AGAR 452.237-75 -- Restrictions Against Disclosure.
National Centers for Animal Health Concrete Repairs and Pavement Painting
RESTRICTIONS AGAINST DISCLOSURE (FEB 1988)
(a) The Contractor agrees, in the performance of this contract, to keep all information contained in source documents or other media furnished by the Government in the strictest confidence. The Contractor also agrees not to publish or otherwise divulge such information in whole or in part in any manner or form, or to authorize or permit others to do so, taking such reasonable measures as are necessary to restrict access to such information while in the Contractor's possession, to those employees needing such information to perform the work provided herein, i.e., on a "need to know" basis. The Contractor agrees to immediately notify in writing, the Contracting Officer, named herein, in the event that the Contractor determines or has reason to suspect a breach of this requirement.
(b) The Contractor agrees not to disclose any information concerning the work under this contract to any persons or individual unless prior written approval is obtained from the Contracting Officer. The Contractor agrees to insert the substance of this clause in any consultant agreement or subcontract hereunder.
(End of Clause)
H.2 UTILITIES OUTAGE
Any interruption of utilities or services that would interfere with the operation of the facility will be permitted only with prior written approval from the Contracting Officer. Any utilities or service connections made at other than normal working hours will be at no additional cost to the Government. Permission to make such an interruption shall be requested in writing to the Contracting Officer, at least three (3) days prior to the day of interruption. Failure by the Contractor to comply with this requirement will cause the Contractor to be subject to liability for actual damages.
H.3 COOPERATION WITH OTHER CONTRACTORS
During the period of construction for the work covered by this contract, other contractors performing work for the Government may be operating concurrently at the site. To minimize interference and delay to the construction progress of all concerned, all contractors shall cooperate with each other and coordinate their construction operations to the fullest extent. As far as practicable, all contractors performing work for the Government at the site shall have equal rights to the use of all referenced facilities. In a dispute regarding the use of such facilities, the matter shall be referred to the Contracting Officer.
H.4 SUBMITTALS AND SHOP DRAWINGS
(a) The Contractor shall submit for approval, shop drawings of all manufactured products required in the construction for which such drawings are hereinafter required. When approved, one set will be retained; one set forwarded to the Government representative on the job and two sets forwarded to the Contractor. When changes or corrections are necessary, two sets will be returned to the Contractor with such corrections noted thereon, and he shall resubmit revised prints.
(b) Shop drawings shall be marked with the contract number and Work Order Number, project description, name of the Contractor, and accompanied by a letter of transmittal. If the shop drawings show variations from the contract requirements because of standard shop practice or other reason, the Contractor shall make specific mention of such variations in his letter of transmittal.
(c) Approval of shop drawings will be general and will not relieve the Contractor from the responsibility of furnishing material and work required by the contract.
(d) Shop drawings shall be submitted for approval in ample time to permit checking of the drawings, allow the Contractor to make any corrections and resubmit drawings prior to the time construction is started on work covered by any drawings.
(e) Non-approval of equipment due to failure to meet specifications, or non-approval of the Contractor’s drawings due to submission of incomplete or incorrect information cannot be considered as a basis for extension of time for completion of the contract.
(f) The quantity of shop drawings required are subject to change. This will occur only when the Government is under contract with an A-E firm to approve shop drawings. In this respect, A-E will coordinate final quantity required between all interested parties.
H.5 LIST OF MATERIALS
(a) The Contractor shall submit for approval a complete list, in duplicate, of brands, type, and make of various equipment and materials proposed to be used. If the Contractor fails to submit such a list, or names of equipment which does not comply with the specifications, or if the manufacturers named are unsatisfactory, the Government
National Centers for Animal Health Concrete Repairs and Pavement Painting reserves the right to reject same and to select satisfactory substitute materials. This selection shall be final and binding upon the Contractor, and the work shall be installed on this basis without change in contract price.
(b) In order to properly identify and to prove compliance with the requirements of the specifications, the Contractor shall give the following data for each product included in the list of materials.
Section heading of the specifications under which material is specified.
Manufacturer’s name and address.
Grade, type, trade or catalog number.
Size, capacity, and other pertinent data.
Compliance with Buy American Act and Bio-preferred
(c) All materials, fixtures, and equipment furnished and installed under this contract shall be new and of the best quality; shall be standard cataloged products or reputable manufacturers products or of special manufacture, satisfying completely the contract requirements.
(d) Similar items, unless otherwise specified herein or approved by the Contracting Officer, shall be the product of the same manufacturer, and those fulfilling the same requirements as to size and construction shall be identical.
(e) Substitutions and/or Approved Equal: Where particular make, brand or type of material or equipment is mentioned in these specifications, it is to denote quality standard of article desired, but does not restrict contractor to brand specified; however, any substitution must be met with approval of the Contracting Officer. Other products comparable in type, quality, utility, and price are acceptable if approved by the Contracting Officer. Burden of proof of equality shall rest with the Contractor. The Contracting Officer shall be sole judge of paralleled quality.
H.6 PROPERTY DAMAGE LIABILITY INSURANCE
The Contractor shall ensure that the property damage liability insurance policy (or rider) required by FAR 52.228-5, Insurance-Work on a Government Installation, is in full compliance with all the terms and conditions of this contract.
The policy shall not contain any exclusions or exceptions that would limit or adversely affect the Government’s rights and remedies under any other clause in this contract or other Federal regulation or law. Should there be any exclusions or exceptions contained in the policy that limits or adversely affects the Government’s rights, the Contractor shall be responsible for the full amount of any damages that occur to the immediate facilities, adjacent facilities/property, and other Government property under the control of the Contractor due to fraud, negligence, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes and laws. The Contractor shall have full responsibility and is liable for these facilities and properties until the Government has accepted the contract as being completed in full and a release from claims has been received from the Contractor.
For those areas where the Government has taken "beneficial occupancy" prior to completion and acceptance of the whole contract, the contractor shall not be responsible for those specific areas under Government control, except in such instances where damage occurs to those areas as a result of negligence, fraud, vandalism, willful misconduct, or violation of Federal, state, or local safety regulations, building codes, or laws in those areas under the control of the Contractor.
This liability and responsibility includes the activities of all the Contractor’s personnel, their subcontractors and suppliers.
H.7 SUBCONTRACTORS, OUTSIDE ASSOCIATES AND CONSULTANTS
Any subcontractors, outside associates or consultants required by the Contractor in connection with the services covered by the contract will be limited to individuals or firms that were specifically identified at time of award or agreed upon during negotiations. The Contractor shall obtain the Contracting Officer’s written consent before making any substitution for these individuals or firms.
National Centers for Animal Health Concrete Repairs and Pavement Painting
I - SECTION I - CONTRACT CLAUSES
PART II - CONTRACT CLAUSES
I.1 CONTRACT CLAUSES INCLUDED BY FULL TEXT:
52.203-6 Restrictions on Subcontractor Sales to the Government.
Restrictions on Subcontractor Sales to the Government (Jun 2020)
(a) Except as provided in (b) of this clause, the Contractor shall not enter into any agreement with an actual or prospective subcontractor, nor otherwise act in any manner, which has or may have the effect of restricting sales by such subcontractors directly to the Government of any item or process (including computer software) made or furnished by the subcontractor under this contract or under any follow-on production contract.
(b) The prohibition in (a) of this clause does not preclude the Contractor from asserting rights that are otherwise authorized by law or regulation.
(c) The Contractor agrees to incorporate the substance of this clause, including this paragraph (c), in all subcontracts under this contract which exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation
2.101 on the date of subcontract award.
(End of clause)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)
(a) Definitions. As used in this clause-
Internal confidentiality agreement or statement means a confidentiality agreement or any other written statement that the contractor requires any of its employees or subcontractors to sign regarding nondisclosure of contractor information, except that it does not include confidentiality agreements arising out of civil litigation or confidentiality agreements that contractor employees or subcontractors sign at the behest of a Federal agency.
Subcontract means any contract as defined in subpart 2.1 entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.
Subcontractor means any supplier, distributor, vendor, or firm (including a consultant) that furnishes supplies or services to or for a prime contractor or another subcontractor.
(b) The Contractor shall not require its employees or subcontractors to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting waste, fraud, or abuse related to the performance of a Government contract to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information (e.g., agency Office of the Inspector General).
(c) The Contractor shall notify current employees and subcontractors that prohibitions and restrictions of any preexisting internal confidentiality agreements or statements covered by this clause, to the extent that such prohibitions and restrictions are inconsistent with the prohibitions of this clause, are no longer in effect.
(d) The prohibition in paragraph (b) of this clause does not contravene requirements applicable to Standard Form 312 (Classified Information Nondisclosure Agreement), Form 4414 (Sensitive Compartmented Information Nondisclosure Agreement), or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
National Centers for Animal Health Concrete Repairs and Pavement Painting
(e) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015, (Pub. L. 113-235), and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions) use of funds appropriated (or otherwise made available) is prohibited, if the Government determines that the Contractor is not in compliance with the provisions of this clause.
(f) The Contractor shall include the substance of this clause, including this paragraph (f), in subcontracts under such contracts.
(End of clause) 52.204-2 Security Requirements.
Security Requirements Alternate II (Apr 1984).
(a) This clause applies to the extent that this contract involves access to information classified "Confidential," "Secret," or "Top Secret."
(b) The Contractor shall comply with-
(1) The Security Agreement DD Form441), including the National Industrial Security Program Operating Manual (32 CFR part 117); and
(2) Any revisions to that manual, notice of which has been furnished to the Contractor.
(c) If, subsequent to the date of this contract, the security classification or security requirements under this contract are changed by the Government and if the changes cause an increase or decrease in security costs or otherwise affect any other term or condition of this contract, the contract shall be subject to an equitable adjustment as if the changes were directed under the Changes clause of this contract.
(d) The Contractor agrees to insert terms that conform substantially to the language of this clause, including this paragraph (d) but excluding any reference to the Changes clause of this contract, in all subcontracts under this contract that involve access to classified information.
(e) The Contractor shall be responsible for furnishing to each employee and for requiring each employee engaged on the work to display such identification as may be approved and directed by the Contracting Officer. All prescribed identification shall immediately be delivered to the Contracting Officer, for cancellation upon the release of any employee. When required by the Contracting Officer, the Contractor shall obtain and submit fingerprints of all persons employed or to be employed on the project.
(End of clause)
FAR 52.204-21 -- Basic Safeguarding of Covered Contractor Information Systems.
BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)
(a) Definitions. As used in this clause– Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
National Centers for Animal Health Concrete Repairs and Pavement Painting
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements.This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
52.204-27 Prohibition on a ByteDance Covered Application.
Prohibition on a ByteDance Covered Application (Jun 2023)
(a) Definitions. As used in this clause—
Covered application means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.
Information technology, as defined in 40 U.S.C. 11101(6)—
(1) Means any equipment or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a contractor under a contract with the executive agency that requires the use—
(i) Of that equipment; or
National Centers for Animal Health Concrete Repairs and Pavement Painting
(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;
(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but
(3) Does not include any equipment acquired by a Federal contractor incidental to a Federal contract.
(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, “No TikTok on Government Devices” Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor’s employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that an exception has been granted in accordance with OMB Memorandum M-23-13.
(c) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts, including subcontracts for the acquisition of commercial products or commercial services.
(End of clause)
52.204-30 Federal Acquisition Supply Chain Security Act Orders—Prohibition.
Federal Acquisition Supply Chain Security Act Orders—Prohibition (Dec 2023)
(a) Definitions. As used in this clause—
Covered article, as defined in 41 U.S.C. 4713(k), means—
(1) Information technology, as defined in 40 U.S.C. 11101, including cloud computing services of all types;
(2) Telecommunications equipment or telecommunications service, as those terms are defined in section 3 of the Communications Act of 1934 ( 47 U.S.C. 153);
(3) The processing of information on a Federal or non-Federal information system, subject to the requirements of the Controlled Unclassified Information program (see 32 CFR part 2002); or
(4) Hardware, systems, devices, software, or services that include embedded or incidental information technology.
FASCSA order means any of the following orders issued under the Federal Acquisition Supply Chain Security Act (FASCSA) requiring the removal of covered articles from executive agency information systems or the exclusion of one or more named sources or named covered articles from executive agency procurement actions, as described in 41 CFR 201–1.303(d) and (e):
(1) The Secretary of Homeland Security may issue FASCSA orders applicable to civilian agencies, to the extent not covered by paragraph (2) or (3) of this definition. This type of FASCSA order may be referred to as a Department of Homeland Security (DHS) FASCSA order.
(2) The Secretary of Defense may issue FASCSA orders applicable to the Department of Defense (DoD) and national security systems other than sensitive compartmented information systems. This type of FASCSA order may be referred to as a DoD FASCSA order.
National Centers for Animal Health Concrete Repairs and Pavement Painting
(3) The Director of National Intelligence (DNI) may issue FASCSA orders applicable to the intelligence community and sensitive compartmented information systems, to the extent not covered by paragraph (2) of this definition. This type of FASCSA order may be referred to as a DNI FASCSA order.
Intelligence community, as defined by 50 U.S.C. 3003(4), means the following—
(1) The Office of the Director of National Intelligence;
(2) The Central Intelligence Agency;
(3) The National Security Agency;
(4) The Defense Intelligence Agency;
(5) The National Geospatial-Intelligence Agency;
(6) The National Reconnaissance Office;
(7) Other offices within the Department of Defense for the collection of specialized national intelligence through reconnaissance programs;
(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of Energy;
(9) The Bureau of Intelligence and Research of the Department of State;
(10) The Office of Intelligence and Analysis of the Department of the Treasury;
(11) The Office of Intelligence and Analysis of the Department of Homeland Security; or
(12) Such other elements of any department or agency as may be designated by the President, or designated jointly by the Director of National Intelligence and the head of the department or agency concerned, as an element of the intelligence community.
National security system, as defined in 44 U.S.C. 3552, means any information system (including any telecommunications system) used or operated by an agency or by a contractor of an agency, or other organization on behalf of an agency—
(1) The function, operation, or use of which involves intelligence activities; involves cryptologic activities related to national security; involves command and control of military forces; involves equipment that is an integral part of a weapon or weapons system; or is critical to the direct fulfillment of military or intelligence missions, but does not include a system that is to be used for routine administrative and business applications (including payroll, finance, logistics, and personnel management applications); or
(2) Is protected at all times by procedures established for information that have been specifically authorized under criteria established by an Executive order or an Act of Congress to be kept classified in the interest of national defense or foreign policy.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of any covered articles, or any products or services produced or provided by a source. This applies when the covered article or the source is subject to an applicable FASCSA order. A reasonable inquiry excludes the need to include an internal or third-party audit.
National Centers for Animal Health Concrete Repairs and Pavement Painting
Sensitive compartmented information means…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .