Attachment 13 - RFIs.pdf
PDF 74 KB Posted
- Solicitation number
- 12505B24R0016
About this file
This document appears to be a set of questions and answers related to a Request for Proposal (RFP) for the National Center for Animal Health Concrete Repairs and Pavement Painting project. The RFP solicitation number is 12505B24R0016, and the applicable NAICS code is 238990 (All Other Specialty Trade Contractors) with a small business size standard of under $19 million. The project involves concrete repairs and pavement painting at the National Center for Animal Health facility.
The key details from the Q&A document include: the required depth of the concrete is 8 inches per the Statement of Work; soil boring reports are not available, and contractors are responsible for their own locates; a topo survey is provided for Alt 2 Area 3; the Superintendent, SSHO, and QC Manager can be the same individual; modifications to the period of performance can be discussed with the Contracting Officer after award; the contractor shall recommend an industry standard base thickness for the 8-inch concrete paving; weekend hours are permitted for the painting work; and the Statement of Work includes a base bid and 3 CLIN options. The proposal is due by 11:00 AM CT on August 6, 2024.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Response 1 What does the depth of the concrete need to be on the 40x200 8" As per the statement of work.
2 Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.
Reports are not available. Contractors are responsible for their own locates.
3 Please provide a map for vehicle traffic control. See Attachment 6 4 Is grading required to match existing conditions? If so, please provide bidding quantities.
Grading is required for Alt 2 Area 3 and Alt 1 Area 2.
Contractor will need to identify cut/fill quantities. A topo survey is provided for Alt 2 Area 3 for the contractor. See Attachment 5 - TOPO
5 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
No
6 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
Modifications can be discussed with Contracting Officer after award
7 Please provide bidding quantities for the base course (paving). Contractor to remove concrete to existing base as per statement of work. For Alt 2 Area 3 and Alt 1 Area 2, contractor shall recommend a industry standard base thickness for 8" concrete paving. Existing spoil pile may be used for base if it complies with necessary industry standards
8 Please provide the site visit attendee sign in sheet. Attachment 7 and Attachment 8 9 Are weekend hours permitted for the completion of the project? As per Attachment 11 - SOW Addendum 001, the painting needs to be accomplished during weekend hours. Concrete work to be accomplished during normal business hours as per statement of work.
10 The Statement of Work includes the base bid and 2 CLIN options while the solicitation includes the base bid and 3 CLIN options. Please confirm if option #3 is to be included in the proposal.
Statement of work includes three options. Please include #3.
FY24 Concrete Repairs and Pavement Painting
Sheet1
File details come from the government source that posted it. Updated .