Scope of Work Summary
This is a Scope of Work document for Volusia County's Office of Recovery and Resiliency (ORR) detailing construction services required for Ridgewood Flood Mitigation improvements in Florida. The project encompasses structural flood mitigation enhancements to reduce vulnerability to future flooding events, with specific focus on elevating critical building systems and installing flood barriers and resilience measures at the Ridgewood facility. The project is part of Volusia County's broader Hurricane Ian recovery effort funded through a U.S. Department of Housing and Urban Development (HUD) Community Development Block Grant for Disaster Recovery (CDBG-DR). The scope includes site preparation, construction of flood mitigation infrastructure, installation of mechanical and electrical systems, completion of final finishes, and all work necessary to bring the facility into full operational compliance with state and federal disaster recovery requirements. The contractor must comply with all CDBG-DR regulations, prevailing wage requirements, and federal environmental standards. The project timeline, specific deliverables, inspection requirements, and performance standards are outlined within the scope to ensure quality construction and timely project completion.
The project is funded entirely through HUD CDBG-DR disaster recovery funds allocated to Volusia County for Hurricane Ian recovery. Prevailing wage requirements apply to all construction work as mandated by federal CDBG-DR funding guidelines. Contractors must demonstrate experience with similar flood mitigation projects and compliance with federal procurement standards. All work must meet current Florida Building Code standards and incorporate design specifications developed by the county's engineering consultants to ensure long-term flood resilience and protection for this critical healthcare facility.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VOLUSIA COUNTY
Invitation to Bid – Scope of Work
INVITATION TO BID
SCOPE OF WORK
702 South Ridgewood Avenue – Flood Mitigation Improvements Daytona Beach, Florida | Volusia County, Florida
| Project Title: |
| 702 S. Ridgewood Avenue – Flood Mitigation Improvements |
| Project Location: |
| 702 South Ridgewood Avenue, Daytona Beach, Florida 32114 |
| Owner: |
| SMA Healthcare |
| Administering Div.: |
| Recovery and Resiliency |
| Funding Source: |
| Transform 386 – Ridgewood Flood Mitigation Grant Program |
| Procurement Type: |
| Invitation to Bid (ITB) – Lump Sum, Fixed Price |
| License Required: |
| State of Florida Certified General Contractor (CGC) |
1. Project Overview On September 28, 2022, the outpatient services facility located at 702 South Ridgewood Avenue, Daytona Beach, sustained significant flood damage as a result of Hurricane Ian. The structure is a brick-on-concrete-masonry-unit (CMU) building with a first-floor elevation of 5.14 feet above sea level (NAVD 88), as established by the recorded Elevation Certificate.
The objective of this project is to implement passive flood mitigation improvements that will protect the building to a flood elevation of 8.0 feet above sea level without requiring human intervention prior to a storm event. The design strategy achieves this protection level by adding three (3) feet of waterproofing and flood-resistant construction above the existing first-floor elevation, replacing existing openings with flood-rated assemblies, and elevating mechanical and electrical equipment above the 8.0-foot flood protection datum.
The improvements are consistent with the Transform 386 Ridgewood Flood Mitigation Application and have been developed through site assessment and pre-construction coordination. All work shall be performed in accordance with applicable provisions of the Florida Building Code (FBC), local Volusia County building requirements, and the floodplain management standards of the National Flood Insurance Program (NFIP).
2. Existing Conditions The Contractor shall be responsible for independently verifying existing site and building conditions prior to submission of a bid. The following conditions are provided for informational purposes based on pre-design assessment:
1. Structure: Brick-on-CMU construction, two-story building, inherently capable of withstanding hydrostatic flood loads.
1. First-Floor Elevation: 5.14 feet above sea level (NAVD 88) per the recorded Elevation Certificate.
1. Existing Openings: Multiple storefront doors and windows currently extend to or near finished grade, providing no flood resistance below the 8.0-foot flood protection datum.
1. Existing Doors: A combination of hollow metal (HM) and glass storefront doors are present on the north and south elevations. See Section 4.6 for a complete listing of openings.
1. Existing Windows: Windows on the south elevation currently extend to near grade level and are not flood-rated.
1. Mechanical / Electrical: Exterior air conditioning units and associated electrical connections are located at or below the 8.0-foot flood protection datum on the north elevation. Current equipment pad elevation is approximately 5.36 feet above sea level.
3. General Requirements
3.1 Contractor Qualifications
1. The Contractor shall hold a valid State of Florida Certified General Contractor (CGC) license in good standing at the time of bid submission and throughout the duration of the project.
1. The Contractor shall demonstrate a minimum of five (5) years of verifiable experience in commercial building envelope, masonry, and flood mitigation construction.
1. The Contractor shall provide a list of not fewer than three (3) comparable projects completed within the preceding five (5) years, including project name, owner contact, contract value, and description of scope.
3.2 Permits and Regulatory Compliance
1. The Contractor shall be responsible for obtaining all required building permits from the City of Daytona Beach Building Division and any other applicable regulatory authority having jurisdiction (AHJ). Permit fees shall be included in the lump sum bid price.
1. All work shall comply with the current edition of the Florida Building Code, including the Existing Building volume, the Residential volume (where applicable), and ASCE 7 flood load provisions.
1. The Contractor shall comply with all applicable NFIP floodplain management regulations and Volusia County floodplain ordinance requirements.
1. The Contractor shall be responsible for scheduling and coordinating all required inspections with the AHJ.
3.3 Design and Engineering Services
1. Architectural and engineering services required to prepare construction documents sufficient for permit issuance shall be provided by the Contractor through a licensed Florida design professional (AOR/EOR) and shall be included in the lump sum bid price.
1. Construction documents shall be sealed by a Florida-licensed Professional Engineer or Architect as required by the FBC and AHJ.
1. Shop drawings, product data, and submittals for all flood-rated door assemblies, window systems, and waterproofing systems shall be submitted to the Owner for review prior to procurement and installation.
3.4 Coordination and Scheduling
1. The Contractor shall submit a preliminary construction schedule within ten (10) calendar days of Notice to Proceed (NTP). The schedule shall identify key milestones including demolition, masonry, waterproofing, door/window installation, MEP work, and final inspection.
1. The project site is an occupied or operationally sensitive facility. The Contractor shall coordinate phasing, access restrictions, and noise/dust controls with the Owner's representative in advance of any demolition or construction activity.
1. All work within or immediately adjacent to active occupied areas shall be performed with appropriate dust and noise mitigation measures and in compliance with applicable OSHA standards.
3.5 Temporary Protection and Site Maintenance
1. The Contractor shall provide and maintain temporary weatherproofing protection for all openings during the demolition and construction phases to prevent water intrusion.
1. The Contractor shall maintain the site in a clean and orderly condition throughout the duration of the project. A minimum of four (4) dumpster pulls shall be anticipated for debris removal; associated costs shall be included in the lump sum bid price.
1. The Contractor shall restore all disturbed landscaping and grading to a condition equal to or better than existing conditions at project completion.
4. Scope of Work The Contractor shall furnish all labor, materials, equipment, tools, taxes, insurance, permits, and incidentals necessary to complete the following items of work. Work is organized by construction division for bidding clarity; the Contractor is responsible for coordination across all trades.
4.1 Demolition and Site Preparation
The Contractor shall perform selective demolition of existing doors, windows, and associated frames as identified below, and shall prepare the building envelope to receive new flood-resistant assemblies:
1. Demolish and remove (2) existing 12'-0" x 9'-0" windows, including frames, sills, and associated masonry infill or trim.
1. Demolish and remove (1) existing 10'-0" x 7'-4" storefront door assembly, including frame and threshold.
1. Demolish and remove (2) existing 6'-0" x 7'-4" storefront door assemblies, including frames and thresholds.
1. Demolish and remove (1) existing 5'-0" x 7'-4" storefront door assembly, including frame and threshold.
1. Demolish and remove (4) existing 3'-0" x 7'-4" windows, including frames.
1. Demolish and remove (1) existing 3'-0" x 7'-4" hollow metal (HM) door, including frame and hardware.
1. Demolish and remove (1) existing pair 3'-0" x 7'-4" doors, including frame and hardware.
1. All demolished materials shall be removed from the site and legally disposed of by the Contractor. Salvageable hardware shall be offered to the Owner prior to disposal.
1. Soil around the building base shall be excavated as necessary to expose the building footing for waterproofing application. Excavated areas shall be backfilled and compacted following waterproofing installation.
4.2 Masonry
New masonry infill shall be constructed at locations where existing window openings extended to or near grade and where new window sill heights are to be raised to 3.0 feet above the finished first-floor elevation:
1. Construct new CMU/brick infill at (4) locations with 3'-0" x 3'-0" opening fill-in dimensions and (2) locations with 3'-0" x 12'-0" dimensions, or as dimensioned in the permitted construction documents.
1. New masonry shall match the existing brick-on-CMU construction in bond pattern, joint profile, color, and texture to the greatest extent practicable.
1. All new masonry units shall be solid or fully grouted at the base of the flood-protection zone and shall be installed in accordance with TMS 402/602 and FBC structural provisions.
1. Masonry work shall be coordinated with the concrete column reinforcement specified in Section 4.3.
4.3 Concrete – Structural Reinforcement
Reinforced concrete columns shall be installed at each side of all modified window and door openings to provide lateral resistance against hydrostatic flood loads:
1. Pour reinforced concrete columns (pilasters) at each jamb of all new window and door openings as required by the structural engineer of record (EOR).
1. Reinforcing steel size, spacing, and embedment depth shall be as specified in the permitted structural drawings. At a minimum, columns shall extend from the building footing to a height no less than the top of the flood-protection datum (8.0 feet above sea level).
1. Concrete mix design shall be a minimum of 3,000 psi compressive strength at 28 days. Form removal and curing shall comply with ACI 318.
4.4 Waterproofing – Thermal and Moisture Protection
The building's exterior walls shall be waterproofed from the building footing to a minimum elevation of 8.0 feet above sea level (NAVD 88) to prevent flood water intrusion through the wall assembly:
1. Waterproof approximately 1,715 square feet of exterior wall surface from the existing building footing to the flood protection datum of elevation +8.0 feet NAVD 88.
1. Waterproofing system shall be a below-grade and above-grade rated elastomeric or crystalline waterproofing product specifically listed for use on masonry substrates in flood-prone environments.
1. Product selection shall be submitted for Owner review and approval prior to installation. The system shall be installed in strict accordance with the manufacturer's written application instructions.
1. All penetrations through the waterproofed wall assembly (conduits, piping, anchors) shall be sealed in accordance with the waterproofing manufacturer's requirements and shall not compromise the flood protection rating of the assembly.
1. The completed waterproofing installation shall be inspected and accepted by the Owner's representative and the design professional of record prior to backfill or concealment.
4.5 Doors – Flood-Resistant Assemblies
All new exterior door assemblies shall be flood-rated, waterproof, and installed to perform as passive flood-prevention barriers without requiring pre-storm preparation. All doors shall be set at a threshold elevation of 5.14 feet above sea level (NAVD 88), shall be a minimum of 7'-0" in clear opening height, and shall provide flood protection to 8.0 feet above sea level. The following assemblies are required:
Hollow Metal (HM) Flood Doors – (2) Units:
1. (1) HM Flood Door, 3'-0" x 7'-0", single-leaf
1. (1) HM Flood Door, 6'-0" x 7'-0", double-leaf or single wide-leaf as applicable
1. Location: North elevation, replacing doors behind the building's front screen wall.
Glass Storefront Flood Doors – (4) Units:
1. (1) Glass Flood Door, 3'-0" x 7'-0"
1. (1) Glass Flood Door, 5'-0" x 7'-0"
1. (1) Glass Flood Door, 6'-0" x 7'-0"
1. (1) Glass Flood Door, 10'-0" x 7'-0"
1. Locations: North and south elevations as shown on construction documents.
All flood door assemblies shall meet the following minimum performance requirements:
1. Flood rating: Certified for flood resistance to a minimum hydrostatic head of 2.86 feet (equivalent to 3.0 feet of flooding above threshold), consistent with FEMA Technical Bulletin 3 and ASCE 24 flood-opening requirements.
1. Impact rating: Assemblies shall meet Large-Missile Impact requirements of ASTM E1886/E1996 or FBC High-Velocity Hurricane Zone (HVHZ) equivalent as required by the AHJ.
1. Hardware: All hardware shall be corrosion-resistant, stainless steel or equivalent, and suitable for the coastal marine environment.
1. Manufacturer's certification documentation and a Florida Product Approval (NOA) or FBC product approval number shall be submitted prior to procurement.
4.6 Windows – Impact-Resistant Flood Assemblies
All new window assemblies shall be installed at a sill elevation of not less than 3.0 feet above the finished first-floor elevation (i.e., sill elevation of 8.14 feet above sea level or as dimensioned in permit documents), providing flood protection to the 8.0-foot flood datum through the raised masonry infill. The following units are required:
1. (4) Impact-resistant window units, 3'-0" x 5'-0", with aluminum frames – south elevation
1. (2) Impact-resistant window units, 10'-0" x 5'-0", with aluminum frames – south elevation
1. All window units shall be installed with sealed perimeter frames and flood-rated sill pans in accordance with manufacturer's installation instructions and FBC requirements.
1. Window systems shall carry a Florida Product Approval (NOA) for the applicable wind speed and impact zones and shall meet ASTM E1886/E1996 or equivalent Large-Missile Impact requirements.
1. Product data and Florida Product Approval documentation shall be submitted for Owner review prior to procurement.
4.7 Finishes
Interior and exterior finishes disturbed by demolition and construction activities shall be restored to a condition equal to or better than existing:
1. Interior gypsum wallboard (Sheetrock) repair and replacement shall be performed at all locations where wall assemblies were disturbed by demolition, masonry infill, or column work. Repairs shall be finished to match existing texture and profile.
1. Interior and exterior painting shall be applied at all repaired and new surfaces. Paint color, sheen, and product type shall match existing adjacent finishes. Touch-up of adjacent undisturbed surfaces may be required to achieve a uniform appearance; such work shall be included in the lump sum price.
4.8 HVAC and Electrical – Equipment Elevation
Existing exterior mechanical and electrical equipment currently located below the 8.0-foot flood protection datum shall be permanently elevated:
1. Raise all exterior air conditioning units to a new support elevation above 8.0 feet NAVD 88. Supports shall be engineered aluminum equipment stands or equivalent, designed for the combined weight and wind loads of the HVAC equipment.
1. Raise all associated exterior electrical connections, disconnects, and conduit routing to maintain continuity with elevated equipment. All electrical work shall be performed by a licensed Florida electrical contractor and shall comply with the National Electrical Code (NEC) and FBC Electrical volume.
1. Refrigerant line sets, condensate lines, and equipment disconnects shall be reconfigured and reconnected as required to restore full HVAC system function following relocation.
1. HVAC system shall be placed back in full operational service upon project completion. The Contractor shall provide a functional performance test and confirmation prior to final acceptance.
5. Owner's Contingency An Owner's contingency allowance of $20,000 is included in the project budget to address unforeseen conditions encountered during construction (e.g., concealed deterioration of masonry, footing conditions inconsistent with survey data, or subsurface drainage concerns). This allowance shall not be included by the Contractor in the lump sum bid price. Any work performed against the contingency allowance shall require written authorization from the Owner's representative prior to commencement. Unused contingency shall revert to the Owner at project closeout.
6. Submittals and Closeout Requirements
6.1 Pre-Construction Submittals
Prior to commencement of any construction activity, the Contractor shall submit the following for Owner review:
1. Construction schedule (preliminary, within 10 calendar days of NTP)
1. List of all proposed subcontractors with license numbers
1. Shop drawings and product data for: flood door assemblies, window systems, waterproofing system, and HVAC equipment supports
1. Florida Product Approval (NOA) or FBC approval documentation for all flood-rated and impact-rated assemblies
1. Proof of required insurance coverage meeting Volusia County minimums
6.2 Project Closeout
At project completion, the Contractor shall provide the following:
1. As-built drawings reflecting field conditions for all modified openings, waterproofing limits, column locations, and MEP routing
1. Certificate of Occupancy or Final Inspection approval issued by the AHJ
1. All manufacturer's warranties for flood doors, window systems, and waterproofing in the Owner's name
1. All equipment manuals and cut sheets for elevated HVAC equipment
1. Contractor's warranty against defects in materials and workmanship for a minimum of one (1) year from date of Substantial Completion
1. Final lien waivers from Contractor and all subcontractors and material suppliers
1. Final punch list completion sign-off from Owner's representative
7. Bid Submission Requirements The Contractor's lump sum bid price shall include all labor, materials, equipment, tools, taxes, insurance, permits, architectural/engineering services, and supervision necessary to complete the full scope of work as described herein. The bid price shall also include the following:
1. All demolition, haul-off, and disposal costs
1. All permit and inspection fees
1. Temporary weatherproofing during construction
1. Dumpster service (minimum 4 pulls)
1. Site cleanup and final cleaning
1. Landscaping and grading restoration following waterproofing
1. All subcontractor work (masonry, concrete, electrical, HVAC, waterproofing)
1. All engineering and design professional fees required for permit
The Owner's contingency of $20,000 shall NOT be included in the Contractor's lump sum bid price. The Contractor's Profit and Overhead shall be included in the base bid as a component of the lump sum price.
Questions regarding the scope of work shall be submitted in writing to the Volusia County Purchasing Division no later than the deadline established in the ITB solicitation documents. Responses to questions will be issued as addenda and distributed to all registered bidders.
END OF SCOPE OF WORK