SL2_SOW ATCH G_DELIVERABLES TABLE.pdf
PDF 268 KB Posted
- Attached to
- ENVIRONMENTAL ASSESSMENT FOR REPAIR OF OVERHEAD 70kV TRANSMISSION LINE South Loop 2 VSFB, CA
- Solicitation number
- FA461026_EA_SL2
About this file
This is SOW Attachment B, an Environmental Assessment (EA) Deliverables Table that outlines contractor requirements for a federal environmental analysis project, likely for the Department of the Air Force (DAF) at Vandenberg Space Force Base (VSFB).
The deliverables are organized into ten major task categories spanning project management, meetings, coordination, cultural resources fieldwork, natural resources fieldwork, coastal zone management, construction noise analysis, and EA/FONSI/FONPA development. Task 1 requires monthly status reports due within 30 days of award and thereafter within 20 calendar days of each cost accounting period end, not to exceed 20 pages. Task 2 mandates a post-award kickoff meeting, data gap identification, bi-weekly coordination meetings with agendas provided two days in advance, a three-day DOPAA Development Workshop at VSFB, and up to five on-board reviews. Task 3 addresses regulatory coordination and stakeholder engagement. Tasks 4 through 9 detail progressive development of technical reports and the Draft EA/FONSI/FONPA, with multiple review cycles (Preliminary Draft, Check Draft, Interim Draft, and Final versions) submitted electronically with clean and red-lined copies as needed. Task 5 requires cultural resources fieldwork including pedestrian surveys and archaeological excavation, with fieldwork commencing no later than 15 days after award and completion within 40 days. Task 6 addresses natural resources analysis including wetlands assessment, ESA Section 7 consultation, and biological evaluation. Task 7 covers Coastal Zone Management Act compliance documentation. Task 10 requires development of an Administrative Record outline and final organization. Resource-specific analyses in Section 7 include air quality EIAP screening, greenhouse gas assessment, and construction noise technical reporting. All deliverables are submitted electronically to the Contracting Officer's Representative (COR), NEPA Planner POC, and Proponent POC, with most major documents due within specific business day timeframes (typically 3-10 business days for various review stages). The note specifies that all referenced days are working/business days excluding weekends and federal holidays unless otherwise authorized.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW Attachment B – EA Deliverables Table
Task Deliverable # Deliverable Description Frequency # of Copies & Format Submit To
Task 1: Project Management
Task 1.1 - Contractor’s Progress, Status, and Management Report
Deliverable 1.1
Monthly Status Report (no more than twenty [20] pages) that includes the status of the project and billing/percent complete estimates.
• First submittal due no later than thirty (30) calendar days after award.
• Subsequent submittals shall be monthly and are due no later than twenty [20] calendar days after the end of the Contractor's cost accounting period.
Electronic • Contracting Officer’s Representative (COR)
Task 1.2 –– Project Schedule
Deliverable 1.2
Initial project schedules and updates that include identification of planned and actual dates.
• Initial project schedules will be presented during the post award/kickoff meeting.
• Updated as needed
Electronic as needed • COR
• NEPA Planner POC
Task 2: Meetings
Task 2.1 - Post-Award Kickoff / Planning Meeting
Deliverable 2.1
Virtual kickoff/planning meeting to initiate the contract, obtain project POCs; and plan for data gap identification/data collection, project coordination meetings, and in-person DOPAA Development Workshop/data collection visit.
• Once
• Agenda items and presentation materials will be provided at least three (3) days prior to kick-off meeting.
Virtual Meeting
Electronic data/presentation as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 2.2 - Data Gap Identification / Data Collection
Deliverable 2.2
Identify and collect all relevant data.
Upon conclusion of the project site review and data collection effort, and if necessary, the Contractor shall submit a list of data gaps needing to be supplied by DAF personnel.
• Once following Post-Award Kickoff / Planning Meeting Electronic as needed
• COR
• NEPA Planner POC
• Proponent POC
Format Submit To
Task 2.3 - Coordination Meetings / Teleconferences
Deliverable 2.3
The Contractor shall coordinate and participate in project coordination review meetings/teleconferences at least twice (2) per month.
Contractor will prepare agenda, minutes, and presentation materials.
• Bi-weekly
• Agenda and presentation materials will be provided at least two (2) days prior to meeting.
• Meeting minutes will be provided within three (3) days of meetings.
Electronic as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 2.4 – DOPAA Development Workshop / Data Collection
Deliverable 2.4
No more than five (5) Contractors shall travel to VSFB for a three (3) day DOPAA Development Workshop.
• Once, as scheduled
• Agenda and presentation materials will be provided three (3) business days prior to the meeting
Electronic as needed
Site Visit
• COR
• NEPA Planner POC
• Proponent POC
Task 2.5 - On-Board Reviews Deliverable 2.5
Contractor will support up to five
(5) OBRs. Contractor shall conduct the OBRs in a manner that allows for live, on-screen edits during the discussions, as necessary.
• Up to five (5) OBRs, as needed
• OBRs will be conducted no more than three (3) business days after reviews are completed.
• Contractor to provide agendas, minutes, and presentation materials at least three (3) business days prior to the meeting.
• Any meeting minutes will be provided to the DAF no more than three (3) business days after OBR.
• NEPA Planner POC
• Proponent POC
Task 3: Project Coordination and Consultations
Task 3.1 – Regulatory and Professional Interface Deliverable 3.1
The Contractor shall assist with oral/written interaction with interested parties related to the project.
• As required Electronic as needed
• COR
Format Submit To
Task 3.2 – Coordination and Consultation POC List
Deliverable 3.2 The Contractor shall identify key stakeholders and create a project POC list.
• As needed / required by project schedule Electronic as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 3.3 – Interagency / Intergovernmental / Government-to- Government Coordination and Consultation
Deliverable 3.3
The Contractor shall prepare appropriate coordination and consultation letters and mail letters requiring read receipts.
• As required by SOW and project schedule
Hardcopies for mailing
• COR
• NEPA Planner POC
• Pertinent SLD 30
Environmental SME
• Proponent POC
Task 4: DOPAA Task 4.1 – Preliminary Draft DOPAA for SME Review
Deliverable 4.1 The Contractor shall provide a Preliminary Draft DOPAA for review and comment.
• Once, as required by project schedule Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 4.2 – Preliminary Draft DOPAA OBR Deliverable 4.2
Contractor shall prepare for and conduct an OBR to resolve comments.
• Once, no more than five (5) business days after receiving review comments.
Electronic Clean and Red-lined copies
• COR
• NEPA Planner POC
• Proponent POC
Task 4.3 – Check Preliminary Draft DOPAA Backcheck for DAF Review
Deliverable 4.3
Contractor shall submit the Check Draft DOPAA with a CRM to the DAF for backcheck. Contractor shall submit two (2) versions of Check Draft DOPAA.
• Once, within five (5) business days of OBR Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 4.4 – Interim Draft DOPAA for Legal & AFCEC Review
Deliverable 4.4
Contractor shall submit Interim Draft DOPAA with a CRM to the SLD30 NEPA POC for Legal & AFCEC Review.
• Once, within ten (10) business days of receiving comments from Check Preliminary Draft
DOPAA.
Electronic Clean and Red-lined copies as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 4.5 – Interim Draft DOPAA OBR Deliverable 4.5
Contractor shall prepare for and conduct an OBR to resolve comments
• OBR will be conducted no more than three (3) business days after receiving new comments.
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 4.6 – Stabilized DOPAA Deliverable 4.6
Contractor shall submit Stabilized DOPAA. Contractor shall submit two (2) versions.
• Within five (5) business days of Interim Draft DOPAA
OBR
Electronic
• COR
• NEPA Planner POC
Task 5: Cultural Resources Fieldwork & Consultations
Format Submit To
Task 5.1 – Kick-off Meeting Deliverable 5.1
Contractor shall coordinate and hold max 90-min kick-off meeting with SLD30 POC. Contractor shall be responsible for capturing meeting minutes.
• Within three (3) business days following contract award Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 5.1 – Kick-off Meeting Deliverable 5.1 Contractor shall deliver meeting minutes to SLD30 POC.
• Withing five (5) days following contract award. Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 5.2 – Background Research Deliverable 5.2
Contractor shall perform background research consisting of the examination of existing documentation for each archaeological site subject to NR evaluation and/or an assessment of effect.
• Refer to Task 5.2.
• NEPA Planner POC
• Proponent POC
Task 5.4 – Fieldwork Deliverable 5.4 Contractor shall submit a summary email on the progress of fieldwork to SLD30 POC.
• Fieldwork to begin no later than fifteen (15) days following contract award.
• Weekly summary
• All fieldwork tasks to be completed within forty (40) days of contract award.
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 5.4.1 – Pedestrian Survey
Deliverable
5.4.1 Refer to Task 5.4.1 • Once, per project
requirements Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 5.4.2 – Archaeological Excavation
Deliverable
5.4.2 Refer to Task 5.4.2 • Once, per project
requirements Electronic
• COR
Format Submit To
Task 5.7 – Preliminary Draft Technical Report Deliverable 5.7
Contractor shall develop a Preliminary Draft Technical Report.
Contractor shall submit two (2) copies of the draft report to the
SLD30 POC.
• No later than four (4) months from award of contract.
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 5.8 – Interim Draft Technical Report Deliverable 5.8
Contractor shall DAF’s Preliminary Draft Technical Report comments and submit Preliminary Final Technical report.
• Within ninety-six (96) business days from date of contract award.
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 5.9 – Final Technical Report Deliverable 5.9
Contractor shall submit a Final Technical Report to the DAF. Refer to Task 5.9.
• Within five (5) months from date of contract award.
CD/DVD and hard copy.
• COR
• NEPA Planner POC
• Proponent POC
Task 6: Natural Resources Fieldwork & Consultations
Task 6.1 – Wetlands and Potential Jurisdictional Waters Analysis
Deliverable 6.1 Contractor shall participate in a kick-off meeting with SLD30 POC and submit meeting minutes.
• Once, within five (5) business days of contract award.
• Minutes to be submitted within three (3) business days of kick-off meeting.
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 6.1.1 – Preliminary Draft Potential Jurisdictional Waters Analysis Report
Deliverable 6.1.1
Contractor shall develop a Preliminary Draft Report based on at least 35% design.
• Once, per project requirements. Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 6.1.2 – Interim Draft Potential Jurisdictional Waters Analysis Report
Deliverable 6.1.2
Contractor shall submit an Interim Draft potential Jurisdictional Waters Analysis Report with a CRM for DAF backcheck review. Contractor shall submit two (2) versions.
• Once, as required by project requirements
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 6.1.3 – Final Potential Jurisdictional Waters Analysis Report
Deliverable 6.1.3
Contractor shall submit a Final Potential Jurisdictional Waters Analysis Report to DAF. Refer also to Task 9.5.
• With Interim Draft EA/FONSI/FONPA Review. Electronic
• COR
Format Submit To
Optional Task: 6.1.4 – Compensatory Mitigation and Monitoring Plan
Deliverable
6.1.4 Refer to Optional Task 6.1.4. • Once, as required by project schedule Electronic
• COR
• NEPA Planner POC
• Proponent POC
Optional Task: 6.1.5 – Compensatory Mitigation and Monitoring Plan
Deliverable 6.1.5
Contractor shall incorporate comments and return two (2) versions of Draft CMMP to SLD30 POC for backcheck.
• Within three (3) weeks of receiving comments.
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Optional Task 6.1.6 – Preliminary Final CMMP
Deliverable 6.1.6
Contractor shall provide the Preliminary Final CMMP. Refer to Task 9.5.
• With Interim Draft EA/FONAI/FONPA Review. Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 6.3 – ESA Section 7 Consultation Deliverable 6.3
Contractor shall participate in a kick-off meeting with SLD30 POC and record meeting minutes.
• Meeting held within five (5) days of contract award
• Minutes submitted within three (3) days of kick-off meeting.
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Optional Task 6.3.1 – Formal Consultation – Final Biological Assessment
Deliverable 6.3.1
Contractor shall complete a Draft Biological Assessment for DAF review.
• Within thirty (30) days of contract award. Electronic
• COR
• NEPA Planner POC
• Proponent POC
Optional Task 6.3.2 – Formal Consultation – Final Biological Assessment
Deliverable 6.3.2
Contractor shall submit the Final Section 7 Consultation Report, government CRM, and contractor responses to SLD30 POC.
• With Interim Draft EA/FONSI/FONPA Electronic (CD)
• COR
• NEPA Planner POC
• Proponent POC
Optional Task 6.3.3 – Informal Consultation – Draft Biological Evaluation
Deliverable 6.3.3
Contractor shall complete a draft Section 7 Biological Evaluation for DAF review.
• Within sixty (60) days of contract award Electronic
• COR
• NEPA Planner POC
• Proponent POC
Optional Task 6.3.4 – Informal Consultation – Final Biological Evaluation
Deliverable 6.3.4
Contractor shall submit Final Section 7 Consultation Report, government CRM, and contractor comment responses.
• With Interim Draft EA/FONSI/FONPA Electronic
• COR
Format Submit To
Task 6.3.5 – Preliminary Draft Survey Report
Deliverable 6.3.5
Contractor shall develop a Preliminary Draft Survey Report documenting the potential effects of proposed action on federally-listed species.
• Once, per project requirements Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 6.3.6 – Check Draft Survey Report
Deliverable 6.3.6
Contractor shall submit a Check Draft Survey Report with a CRM for DAF backcheck review.
Contractor shall submit two (2) versions.
• Once, per project requirements
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 6.3.7 – Final Survey Report
Deliverable 6.3.7
Contractor shall submit a Final Survey Report to DAF.
• Within XX days of contract award. Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 7: Coastal Zone Management Act
Task 7.1 – Preliminary Draft CD Deliverable 7.1
Contractor shall develop and submit a Preliminary Draft CD with a CRM for DAF review.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.2 – Check Preliminary Draft CD Deliverable 7.2
Contractor shall submit a Check Draft CD with a CRM for DAF backcheck review.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.3 – Draft CD Package for Legal Review Deliverable 7.3 Contractor shall submit a Draft CD for Legal review.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 7.4 – Check Draft CD Deliverable 7.4
Contractor shall incorporate necessary changes and then submit a Check Draft CD for Legal backcheck review. Contractor shall submit two (2) versions.
• Once, as required by project schedule
Electronic clean and red-lined versions as needed
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
JACOBS, KATHARINE L CTR USAF SSC 30 CES/BAH
No timeline specified in SOW
Format Submit To
Task 7.5 –Final CD Deliverable 7.5 Contractor shall submit a final CD to the DAF.
• Once, as required by project schedule Electronic
• COR
• Proponent POC
• Installation POC
• AFCEC/CIE POC
Task 8: Construction Noise Analysis
Task 8.1 – Technical Report & Modeling Files Deliverable 8.1
Contractor shall prepare a detailed technical report documenting and describing methods, findings and analysis results for existing conditions, No Action Alternative, noise impact criteria, and construction noise.
• Once, as required by project schedule, to be incorporated into EA
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 8.1 – Technical Report & Modeling Files Deliverable 8.2
All construction noise files shall be delivered for archiving to the SLD30 NEPA POC as part of administrative record.
• Once, as required by project schedule Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 9: Draft EA/FONAI/FONPA
Task 9.2 – Preliminary Draft EA/FONSI/FONPA Deliverable 9.2
Contractor shall develop a Preliminary Draft EA and FONSI/FONPA for DAF review.
Contractor shall submit with a CRM for DAF comments.
Once, as required by project schedule Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 9.3 – Preliminary Draft EA/FONSI/FONPA
OBR
Deliverable 9.3 Contractor shall prepare for and conduct an OBR to resolve comments
Once, no more than five (5) business days after receiving review comments.
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 9.4 – Check Preliminary Draft
EA/FONSI/FONPA
Deliverable 9.4
Contractor shall submit the Check Draft EA/FONSI/FONPA with a CRM for DAF backcheck.
Contractor shall submit two (2) versions of the Check Draft
EA/FONSI/FONPA.
Electronic clean and red-lined versions as needed
• COR
Format Submit To
Task 9.5 – Interim Draft EA/FONSI/FONPA for Legal and AFCEC Review
Deliverable 9.5 Contractor shall submit the Interim Draft EA/FONSI/FONPA with a CRM for Legal and AFCEC review
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 9.6 – Interim Draft EA/FONSI/FONPA OBR Deliverable 9.6
Contractor shall prepare for and conduct an OBR to resolve comments
Conducted no more than three
(3) business days after receiving review comments
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 9.7 – Check Interim Draft EA/FONSI/FONPA Deliverable 9.7
Contractor shall submit the Check Interim Draft EA/FONSI/FONPA with a CRM for Legal and AFCEC backcheck. The Contractor shall submit two (2) versions of the Check Draft EA/FONSI/FONPA
Electronic clean and red-lined versions as needed
• COR
• NEPA Planner POC
• Proponent POC
Task 9.8 – Draft Final EA/FONSI/FONPA for OPSEC Review
Deliverable 9.8
Contractor shall submit a clean copy of the Final EA with a CRM for the SLD 30 Public Affairs Office OPSEC review.
OPSEC review must be complete before the Final EA is released to the VSFB public webpage
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 9.9 – Draft Final EA/FONSI/FONPA OBR Deliverable 9.9
Contractor shall prepare for and conduct an OBR to resolve comments
Conducted no more than three
(3) business days after receiving review comments
Electronic
• COR
• NEPA Planner POC
• Proponent POC
Task 9.10 – Final EA/FONSI/FONPA for Signature
Deliverable 9.10
Contractor shall submit the Final EA/FONSI/FONPA for DAF signature signature timeframe will be approximately twenty-eight (28) business days
• Proponent POC
Task 9.11 – Final EA/FONSI/FONPA for DAF Record
Deliverable 9.11
Contractor shall provide an electronic file combining Final EA with Appendices and signed FONSI/FONPA for DAF record.
Electronic (?)
• COR
• NEPA Planner POC
• Proponent POC
Task 10: Administrative Record
Task 10.1 – Draft AR Outline
Deliverable 10.1
Contractor shall develop a Draft AR Outline illustrating the planned organization and order of the AR for this EA. The Contractor shall submit the Draft AR Outline for DAF review
Once, to be provided no later than at the onsite DOPAA Development Workshop/On- Site Data Collection task
Format Submit To
Task 10.2 – Final AR Outline
Deliverable 10.2
Contractor shall submit the Final AR Outline.
• COR
• NEPA Planner POC
• Proponent POC
7.0 Instructions for EA Resource Area – Specific Analysis
7.1 Air Quality
7.1.1 – Air Quality EIAP Screen Analysis
Contractor shall perform an air quality EIAP screening assessment at the lowest level possible. Refer to 7.1.1
• Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
• Proponent POC
7.1.2 – Greenhouse Gas Contractor shall ensure that the analysis includes an assessment of GHG emissions. Refer to 7.1.2
• Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
• Proponent POC
7.2 Construction Noise Analysis
7.2.1 – Existing Conditions & Noise Analysis of No Action Alternative
Contractor shall conduct an analysis that describes the existing conditions in the study area at and around the proposed construction site. Refer to 7.2.1
Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
• Proponent POC
7.2.2 – Construction Noise Impact Criteria
Contractor shall define and/or develop criteria for assessing construction noise impacts for the project.
Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
• Proponent POC
7.2.3 – Construction Noise Analysis of Proposed Action & Alternatives
Contractor shall conduct analysis to assess potential noise impact resulting from the construction activities under the Proposed Action and Alternatives. Refer to 7.2.3
Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
Format Submit To
7.2.4 – Technical Report & Modeling Files Deliverable
A detailed technical report documenting and describing methods, findings and analysis results for the existing conditions, No Action Alternative, noise impact criteria, and construction noise for Proposed Action Alternative and other study Alternatives will be prepared and submitted
Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
• Proponent POC
7.3 Natural Resource Analysis
7.3 – Natural Resource Analysis
Contractor shall comply with DAFMAN 32-7003, Environmental Conservation. Refer to 7.3
Once, per project requirements Electronic
• COR
• NEPA Planner POC
• SLD30 SME/POC
• Proponent POC
7.4 Installation Restoration Program (IRP)
8.0 Compliance Requirements
8.1 – Fiscal Regulatory Compliance Refer to 8.1. Once, per project requirements •
8.2.1 – Data Deliverable 8.2.1
Contractor shall collect applicable environmental baseline data for the surrounding geographical areas and site-specific data for the project areas necessary to identify and address the environmental issues associated with each Proposed Action and its alternatives. Refer to 8.2.1
Per project requirements. •
8.2.2 – Document Instructions Refer to 8.2.2 Per project requirements. •
8.2.3 – Comment Responses
Contractor shall respond to all comments and corrections resulting from government reviews. Refer to 8.2.3
Per project requirements. •
Format Submit To
8.2.4 – Site Visits Deliverable 8.2.4
Contractor shall coordinate all visits to any location under this TO with Installation and DAF POCs
At least five (5) working days prior to any visit •
8.3 – Spatial Data
Contractor shall prepare maps and other graphics, as appropriate, to support the activities required under this TO. Refer to 8.3
Per project requirements. •
Note: Days refer to working / business days and exclude Saturdays, Sundays, and Federal holidays unless otherwise authorized by the Contracting Officer.