SJ-1491_Systems_Integration_Estimate_Rev1.pdf

PDF 132 KB Posted

Attached to
Contract No. 1: Well SJ-1491 Building and Equipping (Re-Bid)
Solicitation number
2025-ITB-003
Issued by
Polk County, New Mexico

About this file

This document is a project proposal from SKM for Systems Integration services for the SJ-1491 Well project for the City of Gallup, New Mexico. The proposal outlines a comprehensive systems integration plan that includes providing an RTU (Remote Terminal Unit) panel with PLC equipment and radio communication capabilities for a new well site. The project involves installing a 36"x24"x12" NEMA 12 enclosure, a Modicon M340 PLC, MDS TransNet radio, antennas, and necessary panel components. SKM plans to spend three 10-hour days on-site to complete the work, which includes panel design, PLC and HMI programming, radio configuration, and startup and commissioning.

The total project cost is $38,120, broken down into two primary tasks: $20,000 for equipment and $18,120 for labor and startup. The cost includes rates for a Project Manager/Professional Engineer at $195/hour, a Senior Programmer at $155/hour, and a Draftsman at $125/hour. The proposal assumes the Electrical Contractor will handle panel installation, conduit, wiring, and instrumentation connections. SKM will provide labor to integrate the well into the overall SCADA system and will include an analog display for well discharge pressure. The proposal notes potential communication challenges, with a contingency to explore alternative communication methods if the current radio link between well sites proves insufficient.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT PROPOSAL

DATE: December 9, 2023

TO: Derek Wright

FROM: Mark Jeppsen

RE: Well SJ-1491 Systems Integration Proposal Revision 1

CC:

SKM is pleased to provide this proposal to provide Systems Integration for the SJ-1491 Well project for the City of Gallup. The proposal is broken down into three parts:

1. Assumed Systems Integration Criteria

2. Project Tasks / Scope of Work

3. Cost Breakdown

1. Assumed Systems Integration Criteria

The following assumptions have been made for the Systems Integration Criteria in developing the tasks and cost breakdown for this project:

1. SKM will be providing an RTU panel to be in the new well building. This control panel will have

PLC equipment and Radio Equipment. It is assumed that a radio link is achievable to this site.

2. SKM will provide a 10dB Yagi antenna and a 100-foot antenna cable. The Electrical Contractor will be responsible for installing the antenna mast, antenna and cabling and any necessary conduit to the RTU panel. The current Junker 1 Well communicates through Junker 2, to Lewis

Well and then to Yah-ta-Hey booster and this link between Junker 1 and Junker 2 is poor. If the radio path is too poor, we will need to cost and come up with an alternative approach (either repeat through a nearby site such as Tohlakai Pump Station or use cellular).

3. The Electrical Contractor will install the RTU panel and all corresponding conduit, wire and instrumentation connections. All wiring terminations will be by the Electrical Contractor.

4. SKM will be providing the labor to add the Well to the overall SCADA System.

5. SKM will provide an analog display for the well discharge pressure to be mounted on the door of the panel. The pressure transmitter, flow meter, and door switch will be provided by others.

2. Project Tasks / Scope of Work

Task #1 – Equipment

1.1 Well SJ-1491 RTU Panel completely built and assembled which includes the following:

• 36”h x 24”w x 12”d NEMA 12 Enclosure and backpanel

• Modicon M340 PLC

• MDS TransNet radio for communications with Junker 2.

• All necessary antennas, coaxial and lightning arrestors.

• All other necessary panel components

Task #2 – Labor and Startup

2.1 Well SJ-1491 RTU Panel Design

2.2 PLC and HMI Programming for the SJ-1491 Well

2.3 Radio configuration

2.4 Startup and Commissioning

3. Cost Breakdown

This project will be performed on a fixed fee basis in accordance with the costs shown herein. Invoices will be based on a percentage of completion. I have planned on three days on site to complete the work. For this trip I have budgeted for three 10-hour days for one individual with flights, rentals, hotels, and travel time. These costs are shown as a line item for each task. The cost breakdown is associated with the tasks described above and with the following rates:

1. Project Manager / Professional Engineer - $195/Hour

2. Senior Programmer - $155/Hour

3. Draftsman - $125/Hour.

Task Information Hours of Service Required Equipment Per

Diem Cost

Task # Description

PM /

Engineer

Senior

Programmer Draftsman

1 Equipment $20,000 $20,000

2 Labor and Startup 16 60 24 $200 $2,500 $18,120

Total

Cost:

$38,120

- END -

File details come from the government source that posted it. Updated .