Sector Detroit Elevator Maintenance_Statement of Work (SOW) .docx
DOCX document 49 KB Posted
- Attached to
- Coast Guard Sector Detroit Elevator Maintenance Federal contract opportunity
- Solicitation number
- 70Z03026QCLEV0054
About this file
This is a Statement of Work (SOW) for elevator maintenance services at U.S. Coast Guard Sector Detroit, located at 110 Mt. Elliott Street, Detroit, Michigan. The contract covers preventive maintenance, emergency response, standard service calls, mandatory safety testing, and documentation for a Dover Systems Inc. elevator with 2,000 lb capacity serving three floors. The contractor must perform all work in accordance with manufacturer specifications, American Society of Mechanical Engineers (ASME) A17.1 guidelines, Occupational Safety and Health Administration (OSHA) standards, and Michigan elevator safety regulations. Key performance requirements include completing 95% of scheduled monthly preventive maintenance inspections by manufacturer specifications, responding to passenger entrapments within one hour (100% compliance required), responding to routine equipment failures within two hours (90% compliance), executing all Category 1 annual and Category 5 five-year safety tests before certification expiration (100% compliance), and submitting accurate monthly reports by the 5th business day of the following month (95% compliance). The contractor must provide qualified personnel including designated key contacts for billing, emergency maintenance, and general contracting officer communication, and all contractor employees must wear identification badges and comply with Department of Homeland Security security, safety, and conduct regulations.
The contract period runs from August 15, 2026 through March 31, 2027 (base period), with four one-year option periods extending through March 31, 2031. Work must be performed between 0800 and 1500 Eastern Standard Time, Monday through Friday, except Federal holidays, though emergency response may require weekend and holiday availability. The contractor must furnish all facilities, materials, equipment, and services necessary to fulfill requirements, with the exception of any government-furnished resources. The contracting officer is Kara Davis (Kara.A.Davis@uscg.mil), and site coordination contacts include Site Supervisor Justin Stanley and Site Lead Joseph Cendejas. This is a small business set-aside with NAICS code 238290 and PSC code J039, utilizing firm-fixed price acquisition procedures under FAR Part 12 for commercial services.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Standard Form 1449 - Solicitation_Sector Detroit Elevator Maintenance.pdf | ||
| RFQ for Sector Detroit Elevator Maintenance 70Z03026QCLEV0054.docx | DOCX document | |
| References.pdf | ||
| Request for Information.pdf | ||
| Wage Determination Wayne County.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #: 37220PR260000247
STATEMENT OF WORK
STATEMENT OF WORK (SOW)
FOR
Sector Detroit’s Elevator Maintenance
1.0 GENERAL
1.1 BACKGROUND
U.S. Coast Guard Sector Detroit, MI operates a facility where the elevator system is a critical infrastructure component supporting daily mission operations, personnel movement, and logistics. Due to the high operational tempo, elevator downtime directly impacts mission readiness and facility accessibility. Historically, these systems require consistent, proactive oversight to mitigate mechanical fatigue and electrical failures. This contract establishes a comprehensive maintenance program to identify and correct potential deficiencies before they result in equipment failure or safety hazards.
1.2 SCOPE
This contract covers the provision of monthly preventive maintenance, emergency response, standard service calls, mandatory safety testing, and reporting/documentation for a Dover Systems Inc. elevator with a 2000 lb capacity serving three floors at Sector Detroit. The contractor must perform all tasks in accordance with manufacturer specifications and applicable safety standards. The scope does not include provision of food, drinks, parking, tools, safety equipment, or labor by Sector Detroit.
1.3 OBJECTIVE
The objective of this contract is to ensure uninterrupted, safe, and reliable elevator operation at Sector Detroit through scheduled monthly maintenance, prompt response to emergencies, and compliance with all safety certification requirements. The contractor’s work will support mission readiness and facility accessibility.
1.4 APPLICABLE REFERENCES
1.4.1 Compliance References
The following documents provide specifications, standards, or guidelines that must be complied with in order to meet the requirements of this contract:
· American Society of Mechanical Engineers (ASME) Guidelines
· Occupational Safety and Health Administration (OSHA) Standards
· State of Michigan elevator safety regulations
· OEM Operation and Maintenance manuals
1.4.2 Reference Documents
The following documents may be helpful to the Contractor in performing the work described in this document:
· Previous maintenance logs (Sector Detroit archives)
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 Preparation
2.1.1 The Contractor must stage equipment and supplies as needed for elevator maintenance activities.
2.1.2 The Contractor must remove all material from the site after completion of work.
2.2 Elevator Monthly Maintenance
2.3.1 The Contractor must perform all scheduled monthly preventive maintenance inspections and tasks in accordance with the manufacturer’s specifications and ASME A17.1.
2.2.2 The Contractor must document all maintenance activities and deficiencies, and submit monthly reports by the 5th business day of the following month
2.3 Operation Inspection
2.3.1 The Contractor must inspect the proper operation of all elevator systems after maintenance is completed.
2.3.2 The Contractor must conduct a site inspection with the Contracting Officer’s Representative (COR) to verify completion and compliance.
2.4 Emergency Response
2.4.1 The Contractor must respond on-site to passenger entrapments within one (1) hour of notification.
2.4.2 The Contractor must respond on-site to routine, non-emergency equipment failures within two (2) hours of notification.
2.5 Mandatory Safety Testing
2.5.1 The Contractor must execute and document all Category 1 (Annual) and Category 5 (Five-Year) safety tests before prior certifications expire.
2.5.2 The Contractor must ensure no elevators operate with expired safety certifications.
2.6 Critical Performance Objectives
The following table dictates the critical performance objectives, the required standards, the allowed margin of error (AQL), and how the government will monitor compliance.
| Performance Objective |
| Performance Standard |
| Acceptable Quality Level (AQL) |
| Method of Surveillance |
| 1. Preventive Maintenance (PM) |
| Complete all scheduled monthly PM inspections and tasks in accordance with the manufacturer's specifications and ASME A17.1. |
| 95% of all scheduled PMs completed within the designated month. No critical safety deficiencies left unaddressed. |
| COR review of monthly PM logs and random on-site inspections. |
| 2. Emergency Response (Entrapment) |
| Contractor must respond on-site to passenger entrapments within one (1) hour of notification. |
| 100% compliance. Zero deviation allowed for life-safety incidents. |
| Facility dispatch records, security logs, and COR verification. |
| 3. Standard Service Calls |
| Contractor must respond on-site to routine, non-emergency equipment failures within two (2) hours of notification. |
| 90% compliance. Response times must not exceed the standard by more than one hour in any instance. |
| Help desk ticket timestamps and contractor service reports. |
| 4. Mandatory Safety Testing |
| Execute and document all Category 1 (Annual) and Category 5 (Five-Year) safety tests before prior certifications expire. |
| 100% compliance. No elevators shall operate with expired safety certifications. |
| COR review of testing documentation and state/federal safety certificates. |
| 5. Reporting and Documentation |
| Submit accurate, timely monthly performance and deficiency reports by the 5th business day of the following month. |
| 95% compliance. Reports must be complete and free of material errors. |
| Direct COR receipt and review of monthly deliverables. |
3.0 CONTRACTOR PERSONNEL
3.1 QUALIFIED PERSONNEL
The Contractor must provide qualified personnel to perform all requirements specified in this SOW.
3.2 CONTINUITY OF SUPPORT
The Contractor must ensure that the contractually required level of support for this requirement is maintained at all times.
3.3 KEY PERSONNEL
Before replacing any individual designated as Key by the Government, the Contractor must notify the Contracting Officer no less than 5 business days in advance. The following Contractor personnel are designated as Key for this requirement.
3.3.1 US Coast Guard Key Personnel
The following positions will be assigned by the US Coast Guard and are considered Key Personnel for this requirement:
· Contracting Officer Kara Davis, SKC Kara.A.Davis@uscg.mil Subject to change
· Sector Detroit Supply Officer Darnell N. Geralds, CWO Darnell.N.Geralds@uscg.mil Subject to change
· Sector Detroit Facilities Engineer Cody C. Cates, DCC Cody.C.Cates@uscg.mil Subject to change
3.3.2 Contractor Key Personnel
The following positions must be assigned by the Contractor and are considered Key Personnel for this requirement:
· Contracting Officer
· Billing Point of Contact (if different from the Contracting Officer)
· Emergent Maintenance Point of Contact
3.4 EMPLOYEE IDENTIFICATION
3.4.1 Contractor employees visiting Government facilities must wear an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees must comply with all Government escort rules and requirements. All Contractor employees must identify themselves as Contractors when their status is not readily apparent and always display identification and visitor badges in plain view above the waist.
3.5 EMPLOYEE CONDUCT
Contractor’s employees must comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees always present a professional appearance and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.6 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract.
4.0 OTHER APPLICABLE CONDITIONS
4.1 SECURITY
Contractor access to classified information is not currently required under this SOW.
4.2 PERIOD OF PERFORMANCE
The period of performance for this contract is a base period with four one-year option periods as follows:
| Base Period | August 15, 2026 through March 31, 2027 | |
| Option Period One | April 1, 2027 through March 31, 2028 | |
| Option Period Two | April 1, 2028 through March 31, 2029 | |
| Option Period Three | April 1, 2029 through March 31, 2030 | |
| Option Period Four | April 1, 2030 through March 31, 2031 |
4.3 PLACE OF PERFORMANCE
The primary place of performance will be at United States Coast Guard Sector Detroit located at 110 Mt. Elliott St., Detroit, MI 48207.
4.4 HOURS OF OPERATION
Contractor employees must generally perform all work between the hours of 0800 and 1500 EST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
4.5 TRAVEL
Contractor travel must be required to support this requirement. All travel required by the Government will not be outside the local commuting area(s) and will not be reimbursed to the Contractor.
4.6 PROTECTION OF INFORMATION
Contractors’ access to proprietary information is required under this SOW. Contractor employees must safeguard this information against unauthorized disclosure or dissemination in accordance with DHS MD 11042.1, Safeguarding Sensitive but Unclassified (For Official Use Only) Information. The Contractor must ensure that all Contractor personnel having access to business or procurement sensitive information sign a non-disclosure agreement (DHS Form 11000-6).
5.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
6.0 CONTRACTOR FURNISHED PROPERTY
The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0 and SOW 5.0.
7.0 SITE VISITS
7.1 Questions regarding the contract, or project SHALL be directed to the Contracting Officer.
7.2 Site visits can be coordinated with the following members located at Sector Detroit:
· Site Supervisor Justin Stanley, MKCS
(415) 399-7427 justin.s.stanley@uscg.mil
· Site Lead Joseph Cendejas, DCC W: (206) 820-1378 C: (714) 336-5734 joseph.cendejas@uscg.mil
LAST UPDATED: 07/09/2026 PAGE 8/17