Section J_Attachment 1-12.pdf
PDF 2 MB Posted
- Solicitation number
- N3319121R4002
About this file
This is a solicitation for a Job Order Contract (JOC) for construction services in Souda Bay, Greece. The indefinite-delivery, indefinite-quantity contract has a maximum value of $40,000,000 over its 60-month period consisting of a 12-month base period and four potential 12-month option periods. The work will consist primarily of renovation, repair, maintenance, replacement, alteration, demolition, and construction tasks. The minimum guaranteed value is $5,000. Proposals are due by 1 June 2021 at 14:00 Central European Time to the Naval Facilities Engineering Command. Points of contact are Alex Wingert at alex.wingert@eu.navy.mil and Michelle Ruiz at Michelle.Ruiz@eu.navy.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 0003_Final.pdf | ||
| Revised Section J_Attachment.pdf | ||
| Amend 0002 (5) Cst MA 2020JUL.pdf | ||
| Amend 0002 (3) AREAS OUTAGE REQUEST FORM NEW.DOCX | DOCX document | |
| Amend 0002 (4) UTILITIES OUTAGE REQUEST FORM NEW.DOCX | DOCX document | |
| Amend 0002 (6) D Bm MZ JUL20.pdf | ||
| N3319121R4002 SOUDA BAY JOC Amendment 0002.pdf | ||
| Amend 0002 (2) EXCAVATION REQUEST FORM NEW.DOCX | DOCX document | |
| Amend 0002 (1) ATTACHMENT B (REV 1 for Amend 0002).docx | DOCX document | |
| N3319121R4002 SOUDA BAY JOC Amendment 0001.pdf | ||
| Attachments A-D.docx | DOCX document | |
| N3319121R4002 SOUDA BAY JOC.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment Spec Item Description
Section J - Attachment 1 C.3.3
PWD-UTILITY
CONNECTION-01
Section J - Attachment 2 C.3.3
Utility Permit
Applications
Section J - Attachment 3 C.16.6
PWD-OUTAGE-
Section J - Attachment 4 C.16.6
Outage Request
Form
Section J - Attachment 5 C.16.6
PWD-HYDRANT
CONNECTION-01
Section J - Attachment 6 H.11.12
PWD-
EXCAVATION-01
Section J - Attachment 7 H.11.12
Excavation
Request Form
Section J - Attachment 8
Marathi Base Map
2015 & NSA GDM
Complete Jan2016
Section J - Attachment
JC6 C.6
Coefficient
Schedule
Section J - Attachment 9 C.19
Environmental
Checklist
Section J - Attachment 10 L.2
Pre-Proposal
Inquiry (PPI)
Section J - Attachment 11 M
Past Performance
Questionnaire
(PPQ)
Section J - Attachment 12 M
Construction and
Design Experience
Data Sheet
Section J: Attachment
UTILITY CONNECTION PERMIT INSTRUCTIONS
All questions must be answered. DO NOT LEAVE BLANKS. If a question is not applicable, indicate it on the application. The following are instructions for the questions on the permit application.
SECTION A - GENERAL INFORMATION
1. Enter the name of the activity having financial responsibility for the facility being serviced by the proposed utility work.
2. Enter the name and phone number of an activity point of contact responsible for the proposed utility work.
3. Enter the building number and name that is serviced by the proposed utility work.
4. Check the categories that correspond to the majority of the work. Abandonment of utilities should be considered demolition. Check all that apply.
5. Check each utility being altered, added, or upgraded. For each utility checked, complete the appropriate section in the application.
6. Indicate the activity performing the construction or responsible for the administration of the construction contract.
7. Indicate the project title. Enter the construction contract number or job order number that identifies the construction project. Enter COMNAVFACENGCOM, NAVFAC XXXXXX, and/or design activity drawing number. Indicate the type of drawing. Attach all existing design drawings or sketches showing proposed work to the utility systems. Indicate if specifications are included.
8. Enter the name of the organization, a point of contact, and a phone number for the party responsible for the design of the proposed work.
9. Enter the name, job title, application submission date, phone number, and signature of the
Engineer in Charge (EIC) or Architect in Charge (AIC) completing the application.
10. Provide all design analyses performed along with drawings and specifications.
SECTION B - WATER
PART A - DOMESTIC WATER SERVICE CONNECTIONS
1. Enter the number of:
a. Existing domestic water service connections/laterals disconnected from the Utilities and Energy Management Product Line-owned water distribution system involved in the proposed work.
b. New domestic water service connections/laterals connected to the Utilities and Energy Management Product Line-owned water distribution system involved in the proposed work.
2. Indicate the:
a. Size(s) of the water pipe to be tied into the domestic water distribution system.
b. Type(s) of water pipe material to be tied into the domestic water distribution system (e.g. ductile iron, PVC, copper).
c. Class of water pipe that is to be tied into the domestic water distribution system (e.g. Class 150, Class 250, Schedule 40, and Schedule
80).
d. Design capacity for all new domestic water service connections tying into Utilities and Energy Management Product Line-owned water lines.
e. The design pressure for all new domestic water service connections tying into Utilities and Energy Management Product Line-owned water lines.
f. Size(s) of the water meter to be installed.
g. Type(s) of water meter to be installed (e.g. positive displacement, turbine, dual flow).
h. Indicate whether or not a backflow prevention device is to be installed.
PART B - FIRE PROTECTION (HIGH PRESSURE/NON-POTABLE) WATER
SERVICE CONNECTIONS
1. Enter the number of:
a. Existing fire protection (high pressure/non-potable) water service connections disconnected from the Utilities and Energy
Management Product Line-owned fire protection water distribution system involved in the proposed work.
b. New fire protection (high pressure/non-potable) water service connections connected to the Utilities and
Energy Management Product Line-owned fire protection water distribution system involved in the proposed work.
2. Indicate the:
a. Size(s) of the water pipe to be tied into the fire protection (high pressure/non-potable) water distribution system.
b. The type(s) of water pipe material to be tied into the fire protection (high pressure/non-potable) water distribution system (e.g. ductile iron, PVC, copper).
c. The class of water pipe that is to be tied into the fire protection (high pressure/non-potable) water distribution system (e.g. Class 150, Class 250, Schedule 40, and Schedule 80).
d. The design capacity for all new fire protection (high pressure/non-potable) water service connections tying into the Utilities and Energy Management Product Line-owned fire protection water lines.
e. The design pressure for all new fire protection (high pressure/non-potable) water service connections tying into the Utilities and Energy Management Product Line-owned fire protection water lines.
f. Whether or not a backflow prevention device is to be installed.
SECTION C – SANITARY SEWER
Note: If a permanent sewer connection is required and construction is involved, a Certificate to
Construct (CTC)/ Certificate to Operate (CTC) from Virginia Department of Environmental
Quality (VDEQ) may be necessary. Please contact the NAVFAC XXXXXX Environmental
Business Line (Code EV) to ensure compliance with this regulation.
PART A - SANITARY SEWER LATERAL CONNECTIONS
1. Enter the number of:
a. Existing sanitary sewer laterals disconnected from the Utilities and Energy
Management Product Line-owned sanitary sewer collection system involved in the proposed work.
b. New sanitary sewer laterals connected to the Utilities and Energy Management Product Line-owned sanitary sewer collection system involved in the proposed work.
2. Indicate the:
a. Size(s) of the sanitary sewer pipe to be tied into the sanitary sewer collection system.
b. Type(s) of sanitary sewer pipe material to be tied into the sanitary sewer collection system (e.g. ductile iron, PVC).
c. Class or schedule of sewer pipe that is to be tied into the sanitary sewer collection system (e.g. DR 35, DR 18, SDR 32.5, SDR 17).
d. Design capacity for all new sewer laterals connected to Utilities and Energy
Management Product Line-owned sanitary sewer collection system.
3. Check all that apply:
a. Building types that will be served by the proposed sanitary sewer connections. If there is a building type that applies and is not listed, check "Other" and indicate type of building.
b. Choices that may discharge to the sanitary sewer through the proposed connections. If none of these apply, check "N/A”.
PART B - SANITARY SEWER MAINS
1. Enter the number and/or quantity of:
a. Sanitary sewer manholes abandoned in the proposed work.
b. Sanitary sewer manholes installed in the proposed work.
c. In linear feet, of sanitary sewer main abandoned in the proposed work.
d. In linear feet, of sanitary sewer main abandoned in the proposed work.
e. In linear feet, of sanitary sewer main installed in the proposed work.
2. Indicate the:
a. Size(s) of the sanitary sewer pipe to be used for the new sanitary sewer main.
b. Type(s) of the sanitary sewer pipe material to be used for the new sanitary sewer main (e.g. ductile iron, PVC).
c. Class of pipe that is to be used for the new sanitary sewer main (e.g. DR 35, DR 18, SDR 32.5, SDR 17).
PART C - SANITARY SEWER PUMP STATIONS
1. Enter the number of:
a. Sanitary sewer pump stations abandoned in the proposed work.
b. Sanitary sewer pump stations installed in the proposed work.
2. Indicate the:
a. The number of pumps for each pump station installed in the proposed work.
b. The size, including horsepower (hp) and rated flow, of each pump for each pump station in the proposed work. Include a manufacturer’s cut sheet and pump/system curve for each pump.
3. Provide details for:
a. The visible and audible alarms and channels.
b. The bypass pump connections.
c. The valve and check valve specifications.
d. The wet well level monitoring system.
SECTION D - ELECTRIC
PART A - PRIMARY ELECTRICAL SYSTEM
Complete this section when any additions, modifications, or deletions are being made to the electrical distribution system.
1. Indicate the voltage rating of the system being modified.
2. Indicate the type of work to be performed (e.g. New transformer installation, switch removal, cable splicing, etc.)
3. Indicate the type of equipment being installed or removed.
4. If new equipment is being installed, indicate the equipment
Basic Impulse Levels (BIL) rating (primary and secondary for transformers).
5. Indicate the transformer rating in Kilovolt Amperes (KVA).
Indicate other equipment ratings as applicable (e.g. KVA for transformers, amperage for switches and cables).
6. If installing a new transformer, indicate the type of transformer primary termination being made.
7. Indicate if primary connection is overhead or underground.
8. Indicate the size of the conductors to be installed.
9. Indicate the type of conductors (e.g. ERP, XLP).
10. Indicate the cable insulation level.
11. Indicate if the connection to the utility is to be a termination on an existing distribution switch, a primary cable splice in a manhole, a tap to an existing overhead circuit, or a new distribution switch. If the connection to the utility is by some means other than those listed, check other and indicate the proposed method. Indicate primary circuit to be tapped, if known. Use the Utility and Energy Management Product Line circuit designations.
PART B - SECONDARY ELECTRICAL SYSTEM
1. Indicate if work is to install a new transformer and secondary load, or if work is to upgrade or repair an existing transformer due to a secondary load addition.
2. Indicate if a load study has been performed on the transformer that is having the secondary load increased. If yes, provide a copy of the study. If no, indicate when the study will be completed.
3. Indicate the watt-hour meter form and type to be provided.
SECTION E - STEAM
1. Check all services to be supplied by the proposed connection and indicate the:
a. Size of the new steam line.
b. Size of the existing steam line to which service is to be connected.
c. Design capacity for the system to be supplied by the new connection.
d. Design pressure of the system to be supplied by the new connection.
e. Model and size of meter being installed.
SECTION F - NATURAL GAS
1. Indicate the:
a. Pipe size of the new gas line.
b. Pipe size of the existing gas line to which service is to be connected.
c. Pipe material of the new gas line to which service is to be connected.
d. Design capacity for the system to be supplied by the new connection.
e. Required service pressure for the system to be supplied by the new connection.
f. Meter manufacturer, model, and size to be installed.
UTILITY CONNECTION PERMIT APPLICATION Tracking #:
SECTION A - GENERAL INFORMATION
1. Requesting Activity:
2. Point of Contact: Phone Number:
3. Project Location:
4. Type of Work: (Check all that apply.)
New Construction Building Addition Renovation
Demolition/Utility Disconnection Repair Utility Upgrade
5. Work will involve the following utilities: (Check all that apply.)
Water Sewer Electric Steam Gas
a. If Sewer is checked, will the connection be permanent or temporary?
Permanent Temporary (Proceed to question 6)
b. If a permanent connection is required and this project involves construction, contact the
NAVFAC XXXXXX Environmental Business Line (Code EV) to determine if CTC/CTO is required before proceeding.
6. Work to be performed by:
ROICC Contract NAVFAC XXXXXX Maintenance Department
Contract NAVFAC XXXXXX Utilities and Energy
Management Product Line
Other:
7. Contract Title:
Contract/J.O./MAXIMO Number: Drawing Number:
NAVFAC NAVFAC XXXXXX Design Activity Other:
NOTE: Submit a complete set of drawings with the application. Include specifications if available.
SPECIFICATIONS INCLUDED: YES NO
DESIGN CALCULATIONS INCLUDED: YES
NO
8. Designed by Firm/Activity:
Point of Contact: Phone:
9. Submitted by: (This is usually the Engineer in Charge (EIC) or AIC.):
Name: Signature:
Title: Request Date: Phone:
10. Reviewed by: Date:
Approved Disapproved
SECTION B - WATER
PART A - DOMESTIC WATER SERVICE CONNECTIONS
Complete the following for all domestic water service connections to water distribution system lines.
1. Number of Domestic Water Service Connections
(a) Existing service connections disconnected from water line
(b) New service connections connected to water line
2. List the following for all new domestic water service connections to water distribution system lines. See Instructions for clarification.
(a) Pipe Size(s)
(b) Pipe Material(s)
(c) Pipe Class or Schedule
(d) Required Capacity (in gpm)
(e) Required Pressure (in psi)
(f) Meter Size(s)
(g) Meter Type(s)
(h) Backflow Preventer (Yes/No)
PART B - FIRE PROTECTION (HIGH PRESSURE/NON-POTABLE) WATER SERVICE
CONNECTIONS
Complete the following for all fire protection (high pressure/non-potable) water service connections to fire protection system lines.
1. Number of Fire Protection (High Pressure/Non-Potable) Water Service Connections
(a) Number of existing service connections disconnected from fire protection line
(b) Number of new service connections connected to fire protection line
2. List the following for all new fire protection (high pressure/non-potable) water service connections to fire protection system lines. See Instructions for clarification.
(a) Pipe Size(s)
(b) Pipe Material(s)
(c) Pipe Class or Schedule
(d) Required Capacity (in gpm)
(e) Required Pressure (in psi)
(f) Backflow Preventer (Yes/No)
SECTION C - SANITARY SEWER
PART A - SANITARY SEWER LATERAL CONNECTIONS
Complete the following information for work involving all sanitary sewer lateral connections to sanitary sewer mains.
1. Number of Sanitary Sewer Laterals
(a) Existing laterals disconnected from sanitary sewer main _
(b) New laterals connected to sanitary sewer main
2. List the following for all new sanitary sewer lateral connections. See Instructions for clarification.
(a) Pipe Size(s)
(b) Pipe Material(s)
(c) Pipe Class or Schedule
(d) Total Added Design Capacity (gpm)
3. Type of Discharge from New Sanitary Sewer Laterals
(a) Building Type: (Check all that apply)
Office Residential Housing Recreational
Warehouse Food Service Fuel Depot
Commercial Barracks Trng. Facility
Medical Industrial Aircraft Hangar
Other (Specify)
(b) Indicate below any of the operations occurring in the above buildings: (Please check all that apply. If none of these apply, check N/A.)
N/A
Food Preparation Operations
Photo Processing or X-Ray Operations
Laboratory or Clinics
Industrial Laundry or Dry Cleaning
Printing Operations (other than copy machines for office use)
Handling or Collecting Used Oils, Solvents, Degreasers, or HW
Grease Traps
PART B - SANITARY SEWER MAINS
Complete the following information for work involving all sanitary sewer mains.
1. Number of sanitary sewer manholes abandoned
2. Number of sanitary sewer manholes installed _
3. Linear feet of sanitary sewer main abandoned _
4. Linear feet of sanitary sewer main installed
5. List the following for all new sanitary sewer mains:
(a) Pipe Size(s)
(b) Pipe Material(s)
(c) Pipe Class or Schedule
PART C - SANITARY SEWER PUMP STATIONS
Complete the following information for work involving all sanitary sewer pump stations.
1. Number of sanitary sewer pump stations abandoned
2. Number of sanitary sewer pump stations installed
3. Number of pumps installed at each pump station
4. Size of each pump installed
5. Attach details for pump station cut sheets, pump/ system curves, visible and audible alarms/ channels, bypass pump connections, valve and check valve connections, and wet well level monitoring systems.
SECTION D - ELECTRIC
PART A - PRIMARY
If the work involves the primary, complete the following:
1. System Voltage: 34.5 KV 19.9KV 13.2 KV 11.5 KV
4.16 KV 2.4 KV 2.3 KV
TRANSFORMER:
2. Installation: New Upgrade Existing Repair
3. Type: Pad mount Unit Substation Pole mount Station
4. Primary BIL: 200 KV 150 KV 95 KV 60 KV
Secondary BIL: 150 KV 95 KV 60 KV 30 KV
5. Rating: KVA
6. Primary Connection: Live Front Dead Front
PRIMARY CONNECTION:
7. Overhead Underground
8. Conductor Size: Copper Aluminum
9. Type:
10. Insulation Level: 133% 100%
11. Point of Connection to Utility: (Check all that apply)
Existing Distrib. Switch Splice in Manhole Overhead Line Tap
New Distribution Switch Other. (Specify.)
Primary Circuit to be connected to (if known):
PART B - SECONDARY
If the work involves the secondary, complete the following:
12. Installation: New Upgrade (Load study required) Repair
13. Transformer Load Study Performed: Yes (Provide) No - Date expected:
14. Watt-hour meter: Form
Type: Transformer rated Self-contained
SECTION E - STEAM
1. Purpose of new line/service: (Please check all that apply.)
Building Heating Water Heating AC/Humidity Control
Other (Specify)
2. Size of New Line
3. Size of Existing Line at Connection Point
4. Required Capacity (lbs./hr.)
5. Required Pressure (psi)
6. Meter model/size:
SECTION F - NATURAL GAS
1. Size of New Line
2. Size of Existing Line at Connection Point
3. Pipe Material
4. Required Capacity
5. Required Service Pressure
6. Meter model/size:
Section J Attachment
1. Purpose
Establish a standard operating procedure (SOP) for managing outages both planned and unplanned.
2. Enclosures
2.1. Outage Request Form
2.2. Outage Planning Sheet
2.3. Department Head List by Building
2.4. Building Monitor List
2.5. Substation Service List
2.6. Water System Emergency Response Plan
3. Definitions
3.1. AMI – Advanced Meter Infrastructure
3.2. BH – Branch Head
3.3. BM – Building Monitor
3.4. CE – Construction Electrician
3.5. DEH – Electric Company
3.6. DEYACh – Chania Water Authority
3.7. DH – Department Head
3.8. DWPM – Installation Drinking Water Program Manager who reports to the IEPD
3.9. DWS – Duty Public Works Watch Stander
3.10. ESAFE – NAVFAC Electrical Safety Program
3.11. FEAD – Facilities Engineering and Acquisition Division
3.12. FM&S – Facilities Management and Sustainment
3.13. IEPD – Installation Environmental Program Director
3.14. LOTO – Lock Out/Tag Out
3.15. Maximo – NAVFAC’s standard asset life cycle management system
3.16. NAVFAC EURAFSWA – Naval Facilities Engineering Command Europe, Africa, Southwest Asia
3.17. OC – Outage Coordinator
3.18. OPS – Outage Planning Sheet
3.19. ORC – Water Operator Responsible in Charge
3.20. ORF – Outage Request Form (Rev 3)
3.21. PAO – Public Affairs Officer
3.22. PC – Production Controller
3.23. PDD – Production Division Director
3.24. PM – Preventative Maintenance
3.25. PMA – Preventative Medicine Authority
3.26. PPE – Personal Protective Equipment
3.27. PWD – Public Works Department
3.28. PWO – Public Works Officer
3.29. SAIDI/SAIFI – Duration and Frequency of Electrical Outages
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE MOST
CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 1 of 10
DOCUMENT OWNER: PWD AUTHORIZED BY: PWO
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
3.30. SBFD – Souda Bay Fire Department
3.31. SD –Service Desk
3.32. SOP – Standard Operating Procedure
3.33. STP – Sewage Treatment Plant
3.34. UICAP – Utilities Infrastructure Condition Assessment Program
3.35. UEM – Utility and Energy Management Branch Head
4. General Requirement
4.1. To provide the best procedure possible for notification of outages, both planned and unplanned, to our customers and our workforce.
4.2. Primary roles and responsibilities
4.2.1. FEAD
4.2.1.1. For contractor requested outages FEAD will submit the ORF with the top portion through item 5 completed to PC at least 15 business days prior to requested outage date.
4.2.2. PD
4.2.2.1. PC accepts the ORF from FEAD or PD BH and assigns serial number and OC for the outage.
4.2.2.2. OC processes the outage request form and gets the PWO signature.
4.2.2.3. PC serializes the signed requests and submits to SD.
4.2.2.4. PD staffs required technicians (ESAFE, PC, OC, Shops support).
4.2.3. Requirements
4.2.3.1. SD informs customers by email three business days prior to the outage.
4.2.3.2. SD informs customers when service is restored.
5. General Procedures for All Planned Outages
5.1. Outage Request Form Top Part (Enclosure 2.1):
5.1.1. See Table 1 below for timeline.
5.1.2. All requests for outages will be provided with 15 business days minimum notice to the PWD
Production Division by submitting the ORF to the PC.
5.1.3. PC cognizes the ORF and assigns an OC for the outage.
5.1.4. FEAD assists contractors in completing items 1through 5 of the ORF and submit the outage on their behalf.
5.1.5. A separate ORF will be required for each work site.
5.1.6. If a scheduled outage is rescheduled a new ORF is required from the requestor with the new outage date.
5.1.7. OC briefs PWO with proposed dates and affected buildings.
5.1.8. PWO notifies Department Heads of proposed dates and affected buildings.
5.2. Outage Planning Sheet (Enclosure 2.2)
The OC meets with the appropriate PD BH (UEM for utility outages, FM&S for road/parking outages, PDD for other outages) and Shop Supervisors and:
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 2 of 10
5.2.1.
5.2.2. Reviews all drawings and prepare the OPS.
5.2.3. Determines if a work order or work orders are required to pay for shop personnel to plan and execute the outage.
5.2.4. If the outage involves electrical work within a facility, assigns lock out / tag out team (CE Shop).
5.2.5. If the outage involves medium or high voltage works, assigns ESAFE Coordinator and Operations
Center.
5.2.6. Determines the affected buildings.
5.2.7. If working in a permit required confined space, schedules gas free testing for permit.
5.2.8. Consults with SBFD to determine if fire watches are needed.
5.2.9. Determines if overtime will be needed to support the outage.
5.2.10. Notes any other requirements for the outage.
5.2.11. Completes items 6 and 7 on the ORF.
5.3. Outage Request Form Routing (Enclosure 2.1):
OC:
5.3.1. Routes the ORF to all the branches of PDD for signature of each shop supervisor within 3 business days of receiving request.
5.3.2. Notifies the BMs of the effected buildings by email and telephone within 10 business days prior to the outage using the BM List by Building (Enclosure 2.4) and record the contact in the notification section of the ORF.
5.3.3. Notifies emergency services, security, dispatch, and environmental (as appropriate) by telephone.
5.3.4. Briefs the PWO or DPWO (in the PWO’s absence) to explain the outage planning.
5.3.5. Obtains the PWO or DPWO signature on the ORF.
5.3.6. If disapproved, works with all parties to resolve issues, coordinate an acceptable time and date, restart routing procedure.
5.3.7. Returns the approved ORF to the PC for serialization and filing within 4 business days of the outage date.
5.4. Notification of the Outage by the Service Desk:
5.4.1. PC submits the serialized ORF to the Service Desk within 1 business day of receiving the signed
ORF.
5.4.2. Service Desk notifies the effected buildings three business days before the outage by email.
5.5. Pre-Outage Meeting
OC and outage personnel (including PD shops, FEAD ETs and contractors):
5.5.1. Review the OPS and confirm that all conditions are met for the outage.
5.5.2. Review any Work Orders that were placed in support of the outage.
5.6. During the Outage
OC will confirm:
5.6.1. ESAFE personnel on site if required.
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 3 of 10
5.6.2. Control points are secured.
5.6.3. Lock out/ tag out has been performed if required.
5.6.4. Gas free has been performed if required.
5.6.5. ORC is notified of main water valves status (on/off)
5.6.6. Utility service is out at the effected buildings.
5.6.7. Site perimeter is secured (caution tape, traffic cones, etc.).
5.6.8. PPE is properly utilized.
OC will notify the UEM or PDD if the following occur:
5.6.9. Unexpected buildings are experiencing an outage.
5.6.10. The outage will extend beyond approved hours.
5.6.11. Subsurface utilities are compromised.
5.6.12. Unforeseen conditions or safety concerns arise.
5.6.13. A breach of protocol occurs.
If the UEM or PDD decide to continue the outage in spite of 5.6.8 and 5.6.9 the Service Desk will be notified and the effected customers will be informed.
If the UEM or PDD decide to postpone the outage, the utility will be restored following the post-outage procedures.
5.7. Post-Outage Procedures
OC will confirm:
5.7.1. Control points are cleared.
5.7.2. Lock out/ tag out has been removed if installed.
5.7.3. Utility service is restored at the effected buildings.
5.7.4. OC informs Service Desk and PWO of utility restoration.
5.7.5. Service Desk notifies effected buildings by email.
5.7.6. Notify UEM of the outage duration and affected buildings.
5.7.7. UEM will record outage date, duration and number of buildings affected on the Maximo work order for SAIDI/SAIFI reporting purposes.
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 4 of 10
Multi-Building Outage
Business Days to Outage 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
Outage
Day
5.1.1 OC Submit Completed ORF to PC
5.1.6 OC Brief PWO
5.1.7 PWO Notifies DHs of
effected buildings
5.2 PD BHs/OC Prepare the OPS
5.3.1 PC Route the ORF to PD BH
5.3.1 PC Returns the ORF to the OC
5.3.2 OC Notifies BMs of effected buildings
5.3.4 OC Briefs PWO (DPWO) of
outage planning
5.3.7 OC Returns the ORF to PC
for serialization
5.4.1 PC Submits the Serialized ORF to SD
5.4.2 SD notifies effected buildings by email
5.5 OC holds pre-outage meeting
Outage takes place
5.7.4 OC Informs SD of Utility Restoration
5.7.5 SD Notifies Effected Buildings by email
5.7.6 OC Notifies UEM of Duration
Table 1
6. Single Building Outage
Planned single building outages can be streamlined from guidelines in section 5 of this SOP as follows:
6.1 Planning
6.1.1. See Table 2 below for time line.
6.1.2. The OC can be the FEAD ET for the project.
6.1.3. OC briefs PWO with proposed dates and affected building 5 business days before the outage date.
6.1.4. PWO notifies DHs of proposed dates and affected building.
6.1.5. OC Prepare the ORF and OPS in conjunction with the PD and routes the ORF.
6.1.5.1. Determine if a work order or work orders are required to pay for shop personnel to plan, coordinate ESAFE/LOTO, and execute the outage.
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 5 of 10
6.1.5.2. If the outage involves electrical work within a facility, assign LOTO team (CE Shop).
6.1.5.3. If the outage involves medium or high voltage works, assign ESAFE Coordinator and Operations
Center.
6.1.5.4. If working in a permit required confined space, schedule gas free testing for permit.
6.1.5.5. If work requires securing main water distribution notify ORC
6.1.5.6. Consult with SBFD to determine if fire watches are needed.
6.1.5.7. Determine if overtime will be needed to support the outage.
6.1.5.8. Note any other requirements for the outage.
6.1.6. OC notify the BM by email and telephone within 4 business days prior to the outage using the
Building Monitor List by Building (Enclosure 2.4).
6.1.7. OC notify emergency services and dispatch by telephone.
6.1.8. Brief the PWO or DPWO (in the PWO’s absence) to explain the outage planning.
6.1.9. If disapproved, work with all parties to resolve issues.
6.2. Pre-Outage Meeting
OC and outage personnel (including PD shops, FEAD ETs and contractors):
6.2.1. Review the OPS and confirm that all conditions are met for the outage.
6.2.2. Review any Work Orders that were placed in support of the outage.
6.3. During the Outage
OC will confirm:
6.3.1. ESAFE personnel on site if required.
6.3.2. Control points are secured.
6.3.3. Lock out/ tag out has been performed if required.
6.3.4. Gas free has been performed if required.
6.3.5. Utility service is out.
6.3.6. ORC is notified of main water valves status (on/off)
6.3.7. Site perimeter is secured (caution tape, traffic cones, etc.).
6.3.8. PPE is properly utilized.
6.3.9. Notify the BM when the outage starts and when service is restored.
OC will notify the UEM or PDD if the following occur:
6.3.10. Unexpected buildings are experiencing an outage.
6.3.11. The outage will extend beyond approved hours.
6.3.12. Subsurface utilities are compromised.
6.3.13. Unforeseen conditions or safety concerns arise.
6.3.14. A breach of protocol occurs.
The OC will decide to continue the outage in spite of 10.8 and 10.9 and notify Building Monitor.
If the OC decide to postpone the outage the utility will be restored following the post-outage procedures.
6.4. Post-Outage Procedures
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 6 of 10
OC will confirm:
6.4.1. Control points are cleared.
6.4.2. Lock out/ tag out has been removed if installed.
6.4.3. Utility service is restored at the effected buildings.
6.4.4. UEM is notified of the outage duration and affected buildings..
6.4.5. UEM will record outage date, duration and number of buildings affected on the Maximo work order for SAIDI/SAIFI reporting purposes.
Single-Building Outage
Business Days to Outage 5 4 3 2 1 Outage Day
7.1.1 OC Brief PWO
7.1.2 PWO Notifies DHs of effected building
7.1.3 PD BH/OC Prepare the OPS
7.1.4 OC Notifies BMs of effected buildings
7.1.5 OC Notifies emergency service and dispatch
7.1.6 Brief PWO (DPWO) of outage planning
7.2 OC holds pre-outage meeting
7.3.8 OC Notifies BM of outage start
Outage takes place
7.3.8 OC Notifies BM of restored service
7.4.4 OC Notify the UEM of Duration
Table 2
7. Unplanned Utility Outage and Emergency Contingency Plan
7.1. General Guidelines, Electrical Emergency:
7.1.1. During a loss of commercial power, the Building 28 Generator System should provide backup power to all of NSA. Should backup power at Building 28 fail to initiate automatically within 15 minutes, the primary effort of the UEM Branch will be to determine the cause of the failure and attempt to perform corrective actions.
7.1.2. If corrective actions are not completed with 1 hour, the UEM Branch will divert staff to provide backup power to critical facilities by placing temporary generators or initiating switchover to tertiary generators if the transfer switch capability exists and generators are available .
7.1.3. Critical Customer Listing: The following is a listing of customers, which have been identified as having critical service needs.
7.1.3.1. Critical Public Service:
7.1.3.1.1. Building 93 Public Safety Building (Police, Fire, EMO) (has generator, manual startup).
7.1.3.1.2. Building 14 Potable Water Pump House (has generator, manual startup).
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 7 of 10
7.1.3.1.3. Building 1 Admin & Command Suite.
7.1.3.1.4. Building 54 &95 Public Works.
7.1.3.1.5. Building 19 Medical Clinic.
7.1.3.1.6. Lift Station adjacent to STP.
7.1.3.2. Critical Mission Service:
7.1.3.2.1. Building 4 NCTAMS (has generator, automatic startup).
7.1.3.2.2. Building 50 CROF.
7.1.3.2.3. Building 22 Air Operations.
7.1.4. Temporary generators would be placed until NSA and local supplies are exhausted. Requests for additional generators shall be placed through Mutual Aid Agreements, other installations in theatre and the EXWC MUSE Program.
7.1.5. In the event of a failure of the transmission line, the commercial provider (DEH) will be contacted to perform repairs. UEM Branch would proceed with steps 6.1.1 to 6.1.4.
7.1.6. In the event of a failure of a component of our distribution system (distribution line, substation, etc.), PW High Voltage Electrician will isolate the failed component and attempt to restore power to the remainder of NSA.
7.1.7. UEM will record a Maximo work order for SAIDI/SAIFI reporting purposes to report the outage date, duration and number of effected buildings.
7.2. General Guidelines, Water Emergency: See WATER SYSTEM EMERGENCY RESPONSE PLAN, U.S.
NAVAL SUPPORT ACTIVITY SOUDA BAY, CRETE, GREECE, JULY 2011, Attachment 2.6
8. Grid Loss Notification Procedure
8.1. Planned
8.1.1. Service desk receives notification from utility provider (DEH, HAF, DEYACh, etc.).
8.1.2. Service desk notifies UEM and PWO.
8.1.3. PWO notifies NSA Command Suite.
8.1.4. For planned water outages, UEM ensures water storage tanks are at maximum level. Prepares for possible water conservation measures.
8.1.5. For planned electrical outages, UEM ensures generator plant is fully fueled and ready for operation.
This includes all generator sets, NSA, Marathi, Malaxa, etc.
8.1.6. UEM monitors utility systems during outage and informs PWO of status to include restoration of utility service from provider.
8.1.7. UEM will record outage date, duration and number of buildings affected on the Maximo work order for SAIDI/SAIFI reporting purposes.
8.2. Unplanned
8.2.1. When a loss of service is detected, Service Desk contacts utility provider and determines cause and duration.
8.2.2. Service desk notifies UEM and PWO.
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 8 of 10
8.2.3. For water outages, UEM ensures water storage tanks are at maximum level. Prepares for possible water conservation measures.
8.2.4. For electrical outages, UEM ensures generator plant is fully fueled and ready for operation. This includes all generator sets, NSA, Marathi, Malaxa, etc.
8.2.5. UEM monitors utility systems during outage and informs PWO of status to include restoration of utility service from provider.
8.2.6. UEM will record outage date, duration and number of buildings affected on the Maximo work order for SAIDI/SAIFI reporting purposes.
9. Road / Parking
OC (can be FEAD):
9.1. Use multi-building outage timeline (Table 1) and ORF for planning.
9.2. Coordinate with Base Security and Fire to plan alternate routes, additional personnel requirements, and cone and barrier placement.
9.3. Brief the PWO or DPWO (in the PWO’s absence) to explain the outage planning.
9.4. Obtain the PWO or DPWO signature on the ORF.
9.5. If disapproved, work with all parties to resolve issues.
9.6. Return the approved ORF to the PC for serialization and filing within 4 business days of the outage date.
9.7.
PC:
9.8. Submit the serialized ORF to the Service Desk within 4 business days prior to the outage.
9.9.
Service Desk:
9.10. Service Desk will notify the effected buildings three business days before the outage by email.
10. Records
10.1. ORF, signed and serialized
10.2. OPS
10.3. Maximo entries for SAIDI/SAIFI
11. References
11.1. Environmental Final Governing Standards for Greece
11.2. OPNAVINST 5090.1D
11.3. Standard Operating Procedure UEM-DW-03 Water Main Disinfection Procedures
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 9 of 10
Responsible Party Responsibilities
PWO 1. Notify CO/DH of the outage
2. Sign ORF
PDD 1. Assign PC and OC from within the PD
UEM 1. Act for PDD when PDD is not available
2. Identify utility configurations needed for the safe performance of the outage
3. Record the outage in Maximo
PC 1. Receive the ORF and cognize (track the progress)
2. Serialize the completed ORF
3. Send ORF to SD four days before the outage
OC 1. Follow procedure as documented in pertinent SOPs and as directed by
PDD/UEM
FEAD 1. Act as OC for single building outages and simple road/parking outages
SD 1. Notify the affected buildings by email three days before the outage
2. Notify the affected buildings when services are restored
ESAFE Coordinator 1. Complete all ESAFE forms before the outage
2. Ensure that all ESAFE procedures/SOPs are followed during the outage
3. Maintain all ESAFE records
12. Approval
ORIGINATED BY:
PWO Date
CONCURRED BY:
PDD Date FEAD Date
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-OUTAGE-01 NAVFAC Public Works Department Souda Bay
OUTAGE SOP DATE: Page 10 of 10
OUTAGE REQUEST FORM
DATE:
FROM: COMPANY CELL
TO: Outage Coordinator, Public Works Department Souda Bay
FEAD POC (if CTR requested):
Complete Items 1 through 6 and then submit to Outage Coordinator 15 days prior to interruption.
1. Request authorization for the scheduled utility interruption involving the following utilities (double click):
2. Location:
3. Interruption Date and Time:
4. Completion Date and Time:
5. Contract Number and/or Job Description:
6. Affected Buildings:
7. Shop Support WO#:
Routing
PWD CE Shop: DATE:
PWD UT Shop: DATE:
PWD UEM: DATE:
ESAFE/Gas Free: DATE:
Building Monitor Notification by Telephone
PERSON NOTIFIED: DATE:
PERSON NOTIFIED: DATE:
PERSON NOTIFIED: DATE:
PERSON NOTIFIED: DATE:
Contact Emergency Services (IF NEEDED)
FIRE DEPT: DATE:
DISPATCH: DATE:
SECURITY: DATE:
ENVIRONMENTAL: DATE:
SIGNATURE (PWO/DPWO)
Rev 2.0 2/6/2016
Electric Water Roads Sewer Parking Other
Establish a standard operating procedure (SOP) for connecting to fire hydrants on the Naval Support Activity (NSA)
Souda Bay water distribution system.
2. Enclosures
2.1. Hydrant Permit Form
2.2. AWWA Standards/Greece Final Governing Standards
3. Definitions
3.1. BFD – Back Flow Device
3.2. DWPM – Installation Drinking Water Program Manager who reports to the IEPD
3.3. FEAD – Facilities Engineering and Acquisition Division
3.4. FGS – Final Governing Standards
3.5. FM&S – Facilities Management and Sustainment
3.6. IEPD – Installation Environmental Program Director
3.7. ORC – Water Operator Responsible in Charge
3.8. PDD – Production Division Director
3.9. PWD – Public Works Department
3.10. SBFD – Souda Bay Fire Department
3.11. SOP – Standard Operating Procedure
3.12. USB – Utility Services Branch
4. General Requirement
4.1. To provide the best procedure possible for notification and permitting of hydrant connection.
4.2. Primary roles and responsibilities
4.2.1. FEAD
4.2.1.1. For contractor requested hydrant connections FEAD will contact the NSA Souda Bay ORC to request a hydrant connection permit on behalf of the contractor.
4.2.2. PD
4.2.2.1. For PWD shops requested hydrant connections the shop supervisor will contact he NSA Souda
Bay ORC to request a hydrant connection permit.
4.2.3. SBFD
4.2.3.1. For emergency connections to hydrants the requirement for a permit is waived.
4.2.3.2. For non-emergency hydrant connections the Fire Department will contact the NSA Souda Bay water system ORC to request a hydrant connection permit.
4.2.4. ORC
4.2.4.1. Issues hydrant connection permits.
4.2.5. FEAD/PD/SBFD
4.2.5.1. Displays permit at the hydrant connection for the duration of the connection.
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-HYDRANT CONNECTION-01 NAVFAC Public Works Department Souda Bay
HYDRANT CONNECTION SOP DATE: Page 1 of 2
5. General Procedures for All Non-Emergency Hydrant Connections
5.1. A permit is required to connect to a fire hydrant. A BACKFLOW PREVENTER IS ALWAYS REQUIRED.
5.2. To obtain a permit the base representative (not contractor) will contact the Utilities Services Branch ORC in advance. The issuance of the permit shall be within the following time frames:
5.2.1. To use a hydrant: 8 hours. The backflow preventer shall be installed and tested by a licensed
Backflow Prevention Testor prior to issuance of the permit.
5.2.2. Permits will be issued without advance notice in non-fire related emergencies.
5.3. A copy of the AWWA Standards/Greece FGS will be issued with the permit.
5.4. Any hydrant connections will be inspected by the water system ORC.
5.5. Back flow devices and hydrant connections shall be sanitized prior to installation.
5.6. For contractor connections, back flow devices shall be installed by the contractor and tested. Test paperwork shall be submitted to the ORC prior to the permit being issued.
5.7. For shops/SBFD connections, back flow devices shall be installed and tested by the ORC.
5.8. Permits will be displayed at the construction site during the work and returned to the Utilities Services Branch when the work is complete.
5.9. Permits expire one year after issuance. Projects that take longer than a year shall reapply for a new permit prior to expiration.
5.10. Failure to have a permit may result in an immediate work stoppage.
Responsible Party Responsibilities
PDD/FEAD/SBFD 1. Request and display hydrant connection permit
2. Ensure backflow device tested and used at all times
USB 1. Maintain log of Hydrant Permits Issued
ORC 1. Issue Hydrant Permits
2. Inspect Hydrant Connection
3. Perform tests on BFDs as needed by contractors, shops and SBFD
6. Approval
ORIGINATED BY:
PWO Date
CONCURRED BY:
PDD Date FEAD Date
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-HYDRANT CONNECTION-01 NAVFAC Public Works Department Souda Bay
HYDRANT CONNECTION SOP DATE: Page 2 of 2
1.1. Establish a standard operating procedure (SOP) to manage excavations and to ensure underground utilities are not damaged during ANY kind of excavation (digging) being performed at Naval Support Activity (NSA)
Souda Bay.
2. Enclosures
2.1. Excavation Permit Request Form
2.2. Excavation Permit
3. Definitions
3.1. BM – Building Monitor
3.2. DEH – Electric Company
3.3. DH – Department Head
3.4. DWPM – Installation Drinking Water Program Manager who reports to the IEPD
3.5. EC - Excavation Coordinator
3.6. EP – Excavation Permit
3.7. ERF – Excavation Request Form
3.8. ESAFE – NAVFAC Electrical Safety Program
3.9. FEAD – Facilities Engineering and Acquisition Division
3.10. FM&S – Facilities Management and Sustainment
3.11. IEPD – Installation Environmental Program Director
3.12. Maximo – NAVFAC’s standard asset life cycle management system
3.13. NAVFAC EURAFSWA – Naval Facilities Engineering Command Europe, Africa, Southwest Asia
3.14. ORC – Water Operator Responsible in Charge
3.15. PD – Production Division
3.16. PDD – Production Division Director
3.17. PMA – Preventative Medicine Authority
3.18. PPE – Personal Protective Equipment
3.19. PWD – Public Works Department
3.20. PWO – Public Works Officer
3.21. SBFD – Souda Bay Fire Department
3.22. SD –Service Desk
3.23. SOP – Standard Operating Procedure
3.24. UICAP – Utilities Infrastructure Condition Assessment Program
3.25. USBL – Utility Services Branch Lead
4. General Requirement
4.1. To prevent damage to underground utilities and infrastructure at NSA Souda Bay.
4.2. To provide the best procedure possible for notification of excavations to our command, customers, and workforce.
4.3. Primary roles and responsibilities
4.3.1. FEAD/PD shop initiating the request (requestor)
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-EXCAVATION-01 NAVFAC Public Works Department Souda Bay
EXCAVATION PERMIT SOP DATE: Page 1 of 5
4.3.1.1. Submit the ERF with items 1-8 completed to EC at least 10 business days prior to requested excavation date.
4.3.2. EC
4.3.2.1. Accepts the ERF from FEAD or PD shop and assigns serial number for the excavation.
4.3.2.2. Validates the data, researches the underground utilities and infrastructure in the excavation area, gets the shops and USBL, and PWO concurrence.
4.3.2.3. Forwards completed EP to requestor and gets the requestors acknowledgement of receipt and the permitting process.
4.3.2.4. Files permit in excavation log book and share drive.
4.3.2.5. Forwards a copy to the SD
4.3.3. SD
4.3.3.1. Cognizes the EP for situational awareness.
4.3.4. Requestor
4.3.4.1. Displays signed permit at the work site.
4.3.5. FEAD/PW Shop
4.3.5.1. Reports any previously unknown utilities found during the excavation to the Utilities Services
Branch immediately upon discovery.
5. General Procedures for All Planned Excavations
5.1. Excavation Permit Request Form (Enclosure 1):
5.1.1. Excavation requests (ERFs) will be submitted at least 10 business days prior to the proposed start date of the excavation.
5.1.2. ERFs will be submitted to the PWD Production Division EC.
5.1.3. If contractor initiated, FEAD assists contractors in completing items 1through 8 of the ERF and submits the excavation permit request to the EC on their behalf.
5.1.4. If PD shop initiated the shop supervisor completes items 1through 8 of the ERF and submits the excavation permit request to the EC.
5.1.5. EC cognizes the ERF and assigns the excavation serial number.
5.1.6. A separate ERF will be required for each work site.
5.1.7. If a scheduled excavation is rescheduled more than 10 days from the originally requested dates a new
ERF is required from the requestor with the new excavation dates.
5.1.8. EC briefs PWO with proposed excavation site and dates.
5.2. Excavation Permit (Enclosure 2)
The EC researches excavation site using the most current utility maps maintained by the Utility Services Branch and
5.2.1. Consults with FEAD/Contractor/PDD shop to visit the site and understand the excavation area boundries and proposed procedure
5.2.2. Consults with Utilities Services and/or FM&S Branch Head for utilities/facilities concerns:
5.2.2.1. Access to roads and facilities
5.2.2.2. Known underground utilities and structures
5.2.2.3. Fire Hydrant accessibility/availability
5.2.3. Consults with Building Monitors (BM)
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-EXCAVATION-01 NAVFAC Public Works Department Souda Bay
EXCAVATION PERMIT SOP DATE: Page 2 of 5
5.2.3.1. Access to building is impaired
5.2.4. Consults with NSA Security for
5.2.4.1. Associated road outage requirements
5.2.4.2. Security fence breaches/issues
5.2.5. Consults with the Fire Department (FD)
5.2.5.1. Access to fire hydrants impared
5.2.6. Determines if shop support is needed and if so initiates Maximo work order
5.2.7. Creates a PDF from the most current utilities maps with all known utilities and other infrastructure clearly marked in excavation site area.
5.2.8. Completes the NSA Souda Bay Excavation Permit form Items 1-15
5.3. Excavation Permit Routing (Enclosure 2):
5.3.1. EC routes EP internally within the PD
5.3.2. EC briefs the PWO or DPWO (in the PWO’s absence) to explain the excavation details.
5.3.3. Obtains the PWO or DPWO signature on the EP.
5.3.4. If disapproved, works with all parties to resolve issues, coordinate an acceptable time and date, restart routing procedure.
5.3.5. Returns the approved EP to the requestor within 4 business days of the excavation start date with copy to
SD for situational awareness.
5.4. Excavation Requestor:
5.4.1. Displays the EP on the job site at all times
5.4.2. Informs the PD/FEAD of any unmarked utilities or underground structures found during the excavation.
5.4.3. Informs the PD/FEAD of any utilities/structures damaged by the requestor during the excavation.
5.4.4. PD/FEAD informs Utility Services Branch in the event of 5.4.2 or 5.4.3.
6. Emergency Excavations
6.1 Emergency excavations are defined as any excavation needed to restore lost utility service. Examples include a break in any underground utility due to infrastructure failure, acts of nature, or contractor/PD shop activity.
6.2. The following points of contact will be notified immediately of the failure:
6.2.1. PWO (who will notify the Duty Officer and/or ICO as needed)
6.2.2. PDD or USBL (UEM)
6.2.3. SBFD/Dispatch
6.2.4. SD
6.3. PDD or USBL will determine the affected buildings/service and the shutdown procedure for the affected utility.
6.4. PDD or USBL take action to notify following:
6.4.1. Critical Customer Listing: The following is a listing of customers, which have been identified as having critical service needs.
6.4.1.1. Critical Public Service:
PRINTED COPIES OF THIS DOCUMENT MAY NOT BE CURRENT THE
MOST CURRENT REVISION IS MAINTAINED ELECTRONICALLY
File location on Production shared drive:
(\\ds\ueusbdfs11) PROD\UEM\Public Read\SOP's\Water
PWD-EXCAVATION-01 NAVFAC Public Works Department Souda Bay
EXCAVATION PERMIT SOP DATE: Page 3 of 5
6.4.1.1.1. Building 93 Public Safety Building (Police, Fire, EMO) (has generator, manual startup).
6.4.1.1.2. Building 14 Potable Water Pump House (has generator, manual startup).
6.4.1.1.3. Building 1 Admin & Command Suite.
6.4.1.1.4. Building 54 &95 Public Works.
6.4.1.1.5. Building 19 Medical Clinic.
6.4.1.1.6. Lift Station adjacent to…
This is the start of the file's text. The full file is on GovTribe.