section 01300 and 01700.pdf

PDF 90 KB Posted

Attached to
SE Piedmont Sanitary Extension
Solicitation number
IFB605CO25000817
Issued by
Texas County, Missouri

About this file

This file contains specification sections 01300 (Submittal Requirements) and 01700 (Contract Closeout) from the Missouri Department of Transportation's SE Piedmont Sanitary Extension project, a construction initiative in Texas County, Missouri involving approximately 653 linear feet of 8" SDR-35 PVC gravity sewer line with 6 manholes, 60 linear feet of 12" steel casing for sewer under the Union Pacific Railroad, and approximately 235 linear feet of 6" sewer lateral with cleanouts. The project requires the abandonment of an existing septic tank system and connection to the City of Piedmont sanitary sewer system from the MoDOT Maintenance Facility. A mandatory pre-bid meeting is scheduled for November 13, 2024, at 11:00 AM, with site visit completion required for bid eligibility. Bids are due by 2:00 PM CST on December 20, 2024, submitted electronically through MissouriBUYS or by mail, UPS, or FedEx with advance notification to Michael.Yoder@modot.mo.gov. The anticipated Notice to Proceed is January 1, 2025, with project completion required by December 31, 2025.

The specifications establish comprehensive submittal and closeout procedures including electronic submission of construction progress schedules within 15 days of Notice to Proceed, product data with manufacturer information, shop drawings, samples, and design data for architect/engineer review. Final closeout requirements mandate written certification of work completion, final cleaning of all surfaces and site areas, adjustment of operating equipment, detailed project record documents, operation and maintenance data bound in three D-side ring binders submitted 15 days prior to final inspection with revised copies due within 10 days after inspection, and transferable warranty documents from all subcontractors and suppliers. The base bid must include excavation of 200 cubic yards of rock with additional excavation priced separately per cubic yard, and contractors must include $3,300 for railroad permitting in their lump sum bid. Project requirements include a 5% bid bond or security, 100% performance and payment bond if awarded, prevailing wage rates per Wayne County Annual Wage Order #31, OSHA 10-hour construction safety training for all on-site employees, and comprehensive insurance coverage of $4,000,000 in general and automobile liability. The procurement encourages MBE and WBE participation with goals of 10% and 5% involvement respectively.

View the file

Other files

File Type Posted
IFB605CO25000817_Jun_23_25_solicitation_doc.pdf PDF
IFB605CO25000817_Nov_11_24_solicitation_doc.pdf PDF
IFB605CO25000817_May_15_26_solicitation_doc.pdf PDF
IFB605CO25000817_Aug_28_26_solicitation_doc.pdf PDF
IFB605CO25000817_Dec_30_24_solicitation_doc.pdf PDF
VendorChangeDetailsReport_IFB605CO25000817_v5_Dec_11_24.pdf PDF
IFB605CO25000817_Aug_20_26_solicitation_doc.pdf PDF
IFB605CO25000817_Jan_20_25_solicitation_doc.pdf PDF
IFB605CO25000817_Dec_2_24_solicitation_doc.pdf PDF
Exhibit M - ANTI-DISCRIMINATION AGAINST ISRAEL.pdf PDF
IFB605CO25000817_Aug_25_26_solicitation_doc.pdf PDF
IFB605CO25000817_May_8_26_solicitation_doc.pdf PDF
IFB605CO25000817_May_5_25_solicitation_doc.pdf PDF
Bid Form.pdf PDF
IFB605CO25000817_Feb_10_25_solicitation_doc.pdf PDF
IFB605CO25000817_Sep_23_26_solicitation_doc.pdf PDF
IFB605CO25000817_Apr_21_25_solicitation_doc.pdf PDF
IFB605CO25000817_Feb_24_25_solicitation_doc.pdf PDF
IFB605CO25000817_Apr_24_26_solicitation_doc.pdf PDF
IFB605CO25000817_Nov_4_24_solicitation_doc.pdf PDF
IFB605CO25000817_Mar_10_25_solicitation_doc.pdf PDF
IFB605CO25000817_Sep_15_26_solicitation_doc.pdf PDF
IFB605CO25000817_Mar_31_25_solicitation_doc.pdf PDF
IFB605CO25000817_Mar_17_25_solicitation_doc.pdf PDF
IFB605CO25000817_Feb_17_25_solicitation_doc.pdf PDF
IFB605CO25000817_Apr_17_26_solicitation_doc.pdf PDF
IFB605CO25000817_Nov_2_24_solicitation_doc.pdf PDF
Affidavits - Exhibit A and B.pdf PDF
IFB605CO25000817_Aug_14_26_solicitation_doc.pdf PDF
IFB605CO25000817_Jan_13_25_solicitation_doc.pdf PDF
IFB605CO25000817_Sep_22_26_solicitation_doc.pdf PDF
IFB605CO25000817_Jun_9_25_solicitation_doc.pdf PDF
IFB605CO25000817_Nov_25_24_solicitation_doc.pdf PDF
Piedmont MoDOT Standard Specifications.pdf PDF
IFB605CO25000817_Jan_6_25_solicitation_doc.pdf PDF
IFB605CO25000817_May_12_25_solicitation_doc.pdf PDF
IFB605CO25000817_Nov_18_24_solicitation_doc.pdf PDF
MoDOT_Piedmont_GravitySewer.pdf PDF
IFB605CO25000817_Feb_3_25_solicitation_doc.pdf PDF
IFB605CO25000817_Mar_3_25_solicitation_doc.pdf PDF
IFB605CO25000817_Aug_18_26_solicitation_doc.pdf PDF
IFB605CO25000817_Jan_27_25_solicitation_doc.pdf PDF
IFB605CO25000817_Apr_7_25_solicitation_doc.pdf PDF
IFB605CO25000817_Dec_9_24_solicitation_doc.pdf PDF
WayneAWO31.pdf PDF
IFB605CO25000817_Dec_23_24_solicitation_doc.pdf PDF
IFB605CO25000817_Dec_16_24_solicitation_doc.pdf PDF
IFB605CO25000817_Sep_4_26_solicitation_doc.pdf PDF
IFB605CO25000817_May_19_25_solicitation_doc.pdf PDF
IFB605CO25000817_Aug_7_26_solicitation_doc.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01300

SUBMITTAL REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

A. AGC Associated General Contractors of America publication "The Use of CPM in Construction -

A Manual for General Contractors and the Construction Industry".

1.2 SUBMITTAL PROCEDURES

A. Submittals shall be submitted electronically with Architect/Engineer/Designer accepted form.

B. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number and specification section number, as appropriate.

C. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of

Products required, field dimensions, adjacent construction Work and coordination of information is in accordance with the requirements of the Work and Contract Documents.

D. Schedule submittals to expedite the Project, and deliver to Architect/Engineer/Designer at business address. Coordinate submission of related items.

E. For each submittal for review, allow 15 days excluding delivery time to and from the contractor.

F. Identify variations from Contract Documents and Product or system limitations, which may be detrimental to successful performance of the completed Work.

G. Submittals not requested will not be recognized or processed.

1.3 CONSTRUCTION PROGRESS SCHEDULES

A. Submit initial schedule in duplicate within 15 days after date established in Notice to Proceed.

B. Revise and resubmit as required.

C. Submit revised schedules with each Application for Payment, identifying changes since previous version.

D. Submit a horizontal bar chart with separate line for each major portion of Work or operation, identifying first workday of each week.

1.4 PROPOSED PRODUCTS LIST

A. Within 15 days after date of Notice to Proceed, submit list of major products proposed for use, with name of manufacturer, trade name and model number of each product.

B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation and reference standards.

1.5 PRODUCT DATA

A. Product Data for Review:

1. Submitted to Architect/Engineer/Designer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

2. After review, provide copies and distribute in accordance with SUBMITTAL

PROCEDURES article above and for record documents purposes described in Section

01700 - CONTRACT CLOSEOUT.

B. Product Data for Information:

1. Submitted for the Architect/Engineer/Designer’s knowledge as contract administrator or for the

Owner.

C. Product Data for Project Closeout:

1. Submitted for the Owner's benefit during and after project completion.

D. Submit the number of copies, which the Contractor requires, plus two copies that will be retained by the Architect/Engineer/Designer.

E. Mark each copy to identify applicable products, models, options and other data. Supplement manufacturers' standard data to provide information specific to this Project.

F. After review distribute in accordance with the Submittal Procedures article above and provide copies for record documents described in Section 01700 - CONTRACT CLOSEOUT.

1.6 SHOP DRAWINGS

A. Shop Drawings for Review:

1. Submittals shall be submitted electronically with Architect/Engineer/Designer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

2. After review, produce copies and distribute in accordance with SUBMITTAL

B. Shop Drawings for Information:

1. Submitted for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.

C. Shop Drawings for Project Closeout:

1. Submitted for the Owner's benefit during and after project completion.

D. Indicate special utility and electrical characteristics, utility connection requirements and location of utility outlets for service for functional equipment and appliances.

E. Submit in the form of one reproducible transparency and one opaque reproduction.

1.7 SAMPLES

A. Samples for Review:

1. Submitted to Architect/Engineer/Designer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

2. After review, produce duplicates and distribute in accordance with SUBMITTAL

B. Samples for Information:

1. Submitted for the Architect/Engineer/Designer’s knowledge as contract administrator or for the Owner.

C. Samples for Selection:

1. Submitted to Architect/Engineer/Designer for aesthetic, color, or finish selection.

2. Submit samples of finishes for Architect/Engineer/Designer selection.

3. After review, produce duplicates and distribute in accordance with SUBMITTAL

1.8 DESIGN DATA

A. Submit for the Architect/Engineer/Designer’s knowledge as contract administrator or for the

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.9 TEST REPORTS

A. Submit for the Architect/Engineer/Designer’s knowledge as contract administrator or for the

B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.10 CERTIFICATES

A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or the Contractor to Architect/Engineer/Designer, in quantities specified for Product Data.

B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits and certifications as appropriate.

C. Certificates may be recent or previous test results on material or Product but must be acceptable to

Architect/Engineer/Designer.

1.11 MANUFACTURER'S INSTRUCTIONS

A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, and start-up, adjusting and finishing, to

Architect/Engineer/Designer for delivery to owner in quantities specified for Product Data.

B. Indicate special procedures, perimeter conditions requiring special attention and special environmental criteria required for application or installation.

C. Refer to Section 01400 - Quality Control, Manufacturers' Field Services article.

1.12 MANUFACTURER'S FIELD REPORTS

A. Submit reports for the Architect/Engineer/Designer's benefit as contract administrator or for the

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

1.13 ERECTION DRAWINGS

A. Submit drawings for the Architect/Engineer/Designer’s benefit as contract administrator or for the

B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

C. Data indicating inappropriate or unacceptable Work may be subject to action by the

Architect/Engineer/Designer or Owner.

END OF SECTION

01700

CONTRACT CLOSEOUT REQUIREMENT

PART 1 GENERAL

1.1 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for

Architect/Engineer/Designer’s review.

B. Provide submittals to Owner that is required by governing or other authorities.

C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments and sum remaining due.

D. Owner will occupy portions of the building as specified in Section 01010.

E. Projects shall not be accepted by MoDOT until the vendor has completed all punch list items. The vendor will then have 30 days to submit all required paperwork necessary to close the project.

Failure to submit the required paperwork within 30 days could result in the debarment or suspension of the contractor from future projects.

1.2 FINAL CLEANING

A. Execute final cleaning prior to final project assessment. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

C. Clean or replace filters of operating equipment used during construction and/or adjustment.

D. Clean debris from roofs, gutters, downspouts and drainage systems.

E. Clean site; sweep paved areas, rake clean landscaped surfaces.

F. Remove waste and surplus materials, rubbish and construction facilities from the site.

1.3 ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

1.4 PROJECT RECORD DOCUMENTS

A. Store record documents separate from documents used for construction.

B. Record information concurrent with construction progress.

C. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

D. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

1. Measured depths of foundations in relation to finish main floor datum.

2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

4. Field changes of dimension and detail.

5. Details not on original Contract drawings.

E. Submit documents to Architect/Engineer/Designer’swith claim for final Application for Payment.

1.5 OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11 inch (A4) text pages, three D side ring binders with durable plastic covers.

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE

INSTRUCTIONS", title of project and subject matter of binder when multiple binders are required.

C. Internally subdivide the binder contents with permanent page dividers, logically organized; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Submit 1 draft copy of completed volumes 15 days prior to final inspection. This copy will be reviewed and returned with Architect/Engineer/Designer comments. Revise content of all document sets as required prior to final submission.

E. Submit two sets of revised final volumes, within 10 days after final inspection.

1.6 SPARE PARTS AND MAINTENANCE PRODUCTS

A. Provide spare parts, maintenance, and extra Products in quantities specified individual specification sections.

B. Deliver to Project site; obtain receipt prior to final payment.

C. Examine system components at a frequency consistent with reliable operation. Clean, adjust and lubricate as required.

D. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by the manufacturer of the original component.

E. Maintenance service shall not be assigned or transferred to any agent or Subcontractor without prior written consent of the Owner.

1.7 WARRANTIES

A. Execute and assemble transferable warranty documents from Subcontractors, suppliers and manufacturers.

B. Submit prior to final Application for Payment.

C. For items of Work delayed beyond date of Final Completion, provide updated submittal within 10 days after acceptance, listing date of acceptance as start of the warranty period.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

END OF SECTION