Scope of Work - Small~89.docx
DOCX document 686 KB Posted
- Attached to
- DNR Dixon Springs - Stream Bank Stabilization
- Solicitation number
- 22-422DNR-REALT-B-30330
- Issued by
- Richland County, Illinois
About this file
This document is a Scope of Work for a small purchase procurement contract with the Illinois Department of Natural Resources for a Stream Bank Stabilization project at Dixon Springs State Park. The project involves removing the remnants of an existing failed concrete retaining wall and constructing a new reinforced concrete retaining wall along the stream bank near the park's swimming pool facility. The new wall will have a sandstone cap. The project has specific requirements related to excavation, concrete, reinforcement, and sandstone work. The contractor must have 3 years of construction experience and provide documentation of at least 5 similar projects. The contract will follow IDOT Standard Specifications, and the contractor is responsible for obtaining all necessary permits and licenses. The project must be completed by September 30, 2022. Certified payroll records must be submitted, and the contractor must comply with state requirements for hiring Illinois laborers on public works projects. The contract will be awarded to the lowest responsible, responsive bidder.
The document outlines detailed project specifications, instructions, and requirements, including insurance, bonds, warranties, change orders, and payment terms. It also notes that all or a portion of the project may be funded by tax-exempt bonds. Contractors must be registered as a small business and participants in approved apprenticeship programs. The document provides contact information for questions during the bidding process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Dowel Locations.pdf | ||
| Attachment 3 - Rebar Locations.pdf | ||
| Dixon Springs Stream Bank QUESTIONS AND ANSWERS 1.docx | DOCX document | |
| 2SMALL CONSTRUCTION BID FORM~1.docx | DOCX document | |
| Attachment 4 - Detail Views.pdf | ||
| 1Standard Terms and Conditions1~90.pdf | ||
| Attachment 1 - Dixon Springs Map.pdf | ||
| 1Standard CertificationsV.18.1~53.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SMALL PURCHASE PROCUREMENT
SCOPE OF WORK & PROJECT REQUIREMENTS
Date: 6/7/2022 File# 5-22-034
| LOCATION: | Dixon Springs State Park | |
| 982 IL. 146 | ||
| Golconda, IL 62938 |
PROJECT TITLE: Stream Bank Stabilization
PROJECT NARRATIVE:
Dixon Springs State Park is one of several state parks in the Illinois Shawnee Hills. The 801-acre Pope County park is located approximately 12 miles east of I-57, on Illinois Rt. 146. One of the amenities that the park offers visitors is a large outdoor swimming pool with an adjacent pool house/concession area. Hills Branch stream, which conveys a watershed of approximately 800 acres, runs along the west side of the swimming pool facility. The stream runs in a southeasterly direction in this area and then makes a 90o turn to the southwest. Given the contribution of a large watershed area, significant flow rates during large storm events, and the directional change of the stream, the eastern-most streambank (nearest to the swimming pool facility) has failed. The former concrete wall that stabilized the bank has broken off exposing soil that has led to significant erosion. This erosion has impacted the pool drain system and has caused extensive foundation instability on the pool house/concession area building, which is the reason for this project.
SCOPE OF WORK:
This project will consist of the Contractor providing all labor, equipment and materials required to remove the remnants of the former concrete wall that has failed and constructing a new CIP reinforced concrete retaining wall with a sandstone cap in the same location.
Excavation: Must be done in accordance with Section 202. Minor earthwork will be required to expose the existing footing to the retaining wall and to remove any loose material from the rock strata on the backside. The removal of a 6” diameter Ash tree will be required and will be hauled and disposed off-site at the Contractor’s expense.
Removal of Existing Wall: The Contractor is required to remove the remnants of the existing stone/concrete wall and dispose of on-site at locations specified by the Site Superintendent/Engineer. A full-depth vertical saw cut shall be made at the north end of the proposed wall.
Retaining Wall: The new retaining wall shall be constructed in accordance with Section 522.00 and per enclosed plans. The front face of the wall shall be formed. The rear shall not be formed to allow for anchoring into the existing rock strata and filling of all voids with concrete. There are existing pipes protruding from the stream bank that serves as drains for the pool system. These pipes shall be extended through the new concrete wall to ensure continual operation.
Mechanical Fasteners: The Contractor will be required to core drill 6” deep holes into the existing footing, existing east wall, and transversely into the rock strata behind the proposed wall on the existing eastern face of the streambank. Locations are shown on the plan drawing. The holes will be cleaned to receive 12” and 24” long, #4 bars that will be grouted/epoxied in accordance with Section 442.06.
Concrete: Will be in accordance with Table 1, Article 1020.04, Class SI Concrete, not less than 3,500 psi minimum compressive strength, as referenced in Specification Section 522.00 for retaining walls.
Reinforcement: Reinforcement bars (#4 Rebar) will be installed per plan drawing and in accordance with Section 508.00. Reinforcement will be placed within 6” clearance of the wall face. The horizontal bars will be spaced on 1’ centers with two (2) rows in the 18’ section where the depth of the concrete is 2 feet. The vertical bars will be spaced at 2’ centers.
Sandstone Cap: The sandstone cap shall be placed on top of the concrete retaining wall and properly mortared in place and tuck-pointed. There should be three (3) layers of sandstone slabs to match the existing cap. The Contractor may salvage and reuse the existing sandstone to the extent possible, but shall also provide additional sandstone - with similar characteristics - as necessary to complete the project.
ATTACHMENTS:
The following documents are included:
Attachment 1 – Dixon Springs State Park Map Attachment 2 – Rebar Dowel Locations Attachment 3 – Rebar Locations Attachment 4 – Detail Views
Photo Documentation of Damaged Wall
PROJECT SPECIFICATIONS & REQUIREMENTS:
A. Project Specifications:
1) The awarded contractor must have 3 years of experience in the general construction industry and be able to provide documentation of completion of at least 5 projects similar in size and scope to this one prior to starting work.
2) This project will follow the guidelines set forth by the IDOT Standard Specifications for Road and Bridge Construction, adopted January 1, 2022 and Supplemental Specifications and Recurring Special Provisions dated January 1, 2022.
3) Contractor is responsible to verify all measurements prior to bidding. Once construction is complete, the Contractor is required to clean-up all construction debris and haul off-site.
4) All disturbance caused by the construction activities shall be repaired by the Contactor with the area disturbed being seeded and mulched.
B. Project Instructions and Notes:
1) Work Completed by Prime Contractor:
A minimum of fifty percent (50%) of the work shall be completed by the Prime Contractor on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.
2) Coordination of Work Activities:
The Contractor will be required to abide to all site regulations and work with Site Superintendent and site staff regarding working hours, staging areas and securing the work site.
| 3) | Deliverables and Staff Training: |
| N/A |
4) Independent Testing:
The Contractor shall pay all independent laboratory testing, if required.
5) Contractor’s Licensing and/or Certifications:
Contractor shall be responsible for compliance with all applicable contractor and trades person licensing with the appropriate State agency.
6) Product Data:
Submit for the approval of the DNR Project Architect/Engineer product data for the following items prior to starting work:
a. Epoxy
b. Reinforcement Bars
c. Concrete Mix
d. Supplemental sandstone material
7) As-Built Markups:
The Contractor shall hand mark one set of drawings with corrections, dimensions, and "As-Built" notes. These Drawings shall be delivered to the DNR Project Architect/Engineer upon construction completion and prior to final payment request.
| 8) | Extended Warranty: |
| a) | Workmanship and materials will be in conformance with the contract and free from defects for a period of (2) two years, commencing from the goods acceptance date. |
9) Contractor’s Schedule of Values:
The Contractor shall provide to the DNR Project Architect/Engineer, a cost breakdown of each item of work required to fulfill the contract. The breakdown shall be identified on the Contractor’s Schedule of Values (CSV) form.
C. Project Requirements:
| 1) | Project Meeting |
| PROJECT MEETING TO BE HELD: YES | |
| MANDATORY ATTENDANCE: NO |
Refer to the BidBuy solicitation for meeting date and time.
| 2) | COVID-19 Requirements |
| In response to the COVID-19 pandemic, Governor J.B. Pritzker issued Executive Order 2021-22 and 2021-23. These Executive Orders mandate certain contractors shall use face coverings, have COVID-19 vaccinations, or undergo testing for COVID-19 when in indoor public places, Health Care Facilities, Schools, Institutions of Higher Education, and State-owned and operated congregate facilities. Vendor shall adhere to the requirements of these Executive Orders as applied by the Agency. The Agency may also implement vaccination or testing requirements that exceed those in the Executive Orders. |
3) Duration Bids shall be good for ninety (90) calendar days after the Bid Opening Date.
| 4) | Prevailing Wage Rates |
| This contract [or agreement] calls for the construction of a “public work,” within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires contractors and subcontractors to pay laborers, workers and mechanics performing services on public works projects no less than the current “prevailing rate of wages” (hourly cash wages plus amount for fringe benefits) in the county where the work is performed. The Illinois Department of Labor (IDOL) publishes the prevailing wage rates on its website at https://www2.illinois.gov/idol/laws-rules/conmed/pages/rates.aspx. IDOL revises the prevailing wage rates and the contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to IDOL’s website. All contractors and subcontractors rendering services under this contract must comply with all requirements of the Act, including but not limited to, all wage requirements and notice and record keeping duties. |
| 5) | Certified Payroll |
| State law 820 ILCS 130/5 requires all contractors and sub-contractors working on state construction projects to submit certified payroll records to the Department of Natural Resources. The payroll records must include all workers employed by contractors on the project. |
In accordance with 820 ILCS 130/5, the contractor and sub-contractor(s) shall make and keep, for a period of 5 years from the date of the last payment made on or after January 1, 2014 (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.
No later than the 15th day of each calendar month, the contractor shall file a certified payroll for the immediately preceding month with the Department of Natural Resources.
6) Employment of Public Workers on Public Works:
In a period of excessive unemployment rates, State contractors (1) constructing or building any public works or (2) cleaning-up and disposing on-site of hazardous waste, and that clean-up or on-site disposal is funded or financed in whole or in part with State funds or funds administered by the State, are required to employ at least 90% Illinois laborers on such project. For projects involving clean-up and on-site disposal of hazardous waste, emergency response or immediate removal activities are excluded. This requirement applies to all labor whether skilled, semi-skilled or unskilled, whether manual or non- manual.
A period of excessive unemployment rates is defined as any month immediately following two consecutive calendar months during which the level of unemployment in the State of Illinois has exceeded 5% as measured by the United States Bureau of Labor Statistics in its monthly publication of employment and unemployment figures.
Any public works project financed in whole or in part by federal funds administered by the State of Illinois is covered under the provisions of this requirement, to the extent permitted by any applicable federal law or regulation. 30 ILCS 570.
Contractors may receive an exception from this requirement by submitting a request and supporting documents certifying that Illinois laborers are either not available or are incapable of performing the particular type of work involved. The certification must: (a) be submitted to the agency within the first quarter of the Contract Term; (b) provide sufficient support that demonstrates the exception is met; (c) be signed by an authorized signatory of the contractor; and (d) be approved by the agency.
7) Small Business Set-Aside The Contractor awarded the project must be registered as a small business, as required by the Small Business Set-Aside Program. (For complete requirements, to become registered, or to certify your business is in the Small Business Set-Aside Program, visit the Illinois Procurement Gateway (IPG) at https://ipg.vendorreg.com/ or call (217) 782-1270.
8) Apprenticeship-in-Training When applicable, the contractor and all subcontractors must be participants in apprenticeship and training programs that are both approved by and registered with the U.S. Department of Labor’s Bureau of Apprenticeship and Training. The program(s) must be in the same trade(s) in which the contractor or subcontractor performs work. For information on how to participate in or set up a program, contractors may call the U.S. Department of Labor at 312/596-5508 or visit their website http://www.doleta.gov/oa/ .
9) Illinois Office The bidder must certify that the bidder will maintain an Illinois office as the primary place of employment for persons employed in the construction authorized by the contract.
| 10) | Subcontractors |
| The Contractor shall identify the names of all subcontractors to be utilized by them in the performance of this contract, together with the anticipated amount of money that each subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only Provides goods or supplies that are incidental to the performance of a contract by a person who has a contract subject to the Code. |
| 11) | Insurance |
| Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims. |
12) Performance Bond/Labor and Material Payment Bond Pursuant to the Public Construction Bond Act (30 ILCS 550/), a performance bond and a labor and material payment bond covering the faithful performance of the contract and the payment of all obligations arising thereunder, shall be required if the project cost exceeds $50,000. Each bond shall be in the full amount of the contract. The bond must be from a surety licensed to do business within the State of Illinois and acceptable to IDNR.
13) Minority Contractor Opportunity Initiative The State requires a fee of $15 to cover Expenses related to the administration of the Minority Contractor Opportunity Initiative. Any Vendor awarded a contract under Section 20-10, 20-15, 20-25 or 20-30 of the Illinois Procurement Code (30 ILCS 500) of $1000 or more is required to pay a fee of $15. The Comptroller shall deduct the fee from the first check issued to the Vendor under the contract and deposit the fee in the Comptroller’s Administrative Fund.
14) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.
15) Utilities Before starting excavation, establish location and extent of underground utilities occurring in the work area. Contractor shall contact Joint Utility Locating Information for Excavators (J.U.L.I.E.) 800-892-0123.
16) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.
17) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.
| 18) | Steel Products |
| Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/). |
19) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.
20) Final Cleaning Contractor shall clean-up all work related debris and construction materials and properly dispose off-site. The Contractor shall repair and otherwise make good any damage caused by the work and leave the premises in the equivalent of the original condition.
21) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of two years from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.
22) Change Orders Change order shall be defined as a change in a contract term, other than as specifically provided for in the contract, which authorizes or necessitates any increase or decrease in the cost of the contract or the time for completion. A change order shall be executed by the State agency and vendor evidencing the change. All changes shall be approved by the CPO, or designee, and be accompanied by a written determination that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed and the change is germane to the original contract as signed. Change orders that increase or decrease the cost of a contract or an estimated contract by a total of $10,000 or more or the time of completion by more than 30 days shall be published on the Illinois Procurement Bulletin, pursuant to Section 15-25 of the Code and documented pursuant to Section 33E-9 of the Criminal Code of 2012, in advance of execution of the change order.
23) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.
24) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.
| 25) | Contract Award |
| Contract award will be made to the lowest, responsible, responsive bidder. The Department of Natural Resources reserves the right to reject any or all bids. |
| 26) | Term of Contract |
| All work shall be completed by September 30, 2022. |
27) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form.
| 28) | Bid Submittal Date and Time |
| Refer to the BIDBUY solicitation for the bid date and time. |
29) Questions ALL QUESTIONS PERTAINING TO THE SCOPE OF WORK OR THE BIDBUY PROCEDURES, MUST BE DIRECTED TO Frederick.Murphy@Illinois.gov ALL QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN THREE (3) BUSINESS DAYS BEFORE THE BID DATE.
30) Project Contacts: The following individuals are listed as project contacts during the construction phase. The Bidder may not communicate directly with any of these individuals during the bidding process. All communication during the bidding phase must be directed to the Frederick.Murphy@Illinois.gov email address.