Scope of Work.docx.docx

DOCX document 17 KB Posted

Attached to
Cooling Tower On Site Repair - SEE DESCRIPTION & ATTACHMENTS (G4-324032. 1)
Solicitation number
5-B193-Q-00154-00
Issued by

About this file

This is a Scope of Work document for cooling tower repairs at Building 371 for Argonne National Laboratory, accompanied by a related solicitation for parts and labor. The scope requires contractor Facility Solutions Partners (FSP) to perform structural repairs including removal and reinstallation of mechanical equipment, replacement of oil seals, and installation of new mechanical equipment supports with stainless steel hardware. Work must be performed Monday through Friday, 7:00 AM to 3:30 PM.

The associated solicitation specifies required parts including S300 and S304 branded components, mechanical vibration switches, flex element kits, seal spacer O-rings, and stainless steel stiffeners. Labor requirements include parts installation, crane rental, and angle modification work. Contractors must have OSHA 10-hour Safety Construction Training, CSO Service Training, and Lockout Tag out Training. Responses are due by January 28, 2025 at 11:30 PM CST. The solicitation requires signed documentation and firm fixed pricing in US dollars for each line item. The contract opportunity is being managed by the Department of Energy Office of Science.

View the file

Other files

File Type Posted
Appendix A-71COM-13-FEB-2023.PDF PDF
ANL-366H (on-site high risk)-01-OCT-2024.PDF PDF
ANL-70 Request for Quotation (01D).doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 371 Cooling Tower Repairs Scope of Work

December 3, 2024 Contractor to provide labor and materials for structural repair of damaged cooling towers.

Facility Solutions Partners Services and Duties:

· FSP crew to remove couplings, flex oil lines, vent lines and all hold down hardware from mechanical.

· FSP crew will drain oil from gearboxes and dispose of in EPA approved facility.

· Rig all mechanical equipment for removal via crane supplied by FSP thru Stevenson Crane company.

· Remove motor, gearbox and fan assembly from tower and set aside for later re-installation.

· Our crew to remove 100% of the mechanical equipment support system including all hardware.

· Install 100% new ME supports w/ new SS hardware.

· Remove oil seal on cell 3 GRDR and replace with new seal, and O-ring.

· Remove and replace oil in both gearboxes and replace with customer supplied oil.

· Hoist all mechanical equipment back into the tower.

Service Hours:

· All work is to be performed during normal business hours. Business hours for service are Monday through Friday, 7:00 AM to 3:30 PM.

· Tools and Equipment:

· Provide all necessary tools and equipment for service and repair work.

· Allow inspection of tools and equipment by an Argonne technical representative before use on-site.

Training:

OSHA 10-hour Safety – Construction Training CSO Service Training – Provided by BM Technical Rep at the ANL site Lockout Tag out Training Technicians to be up to date on Argonne Contractor Safety Orientation training. All technicians must review and sign the Argonne Job Safety Analysis before the start of work.

ANL Responsibilities

· Disconnect electrical from tower motor before work starts and reconnect after completion of work.

· Coordinate technician access to the ANL Site.

· Provide the ANL Contractor Safety Orientation (CSO).