Scope_of_Services.pdf

PDF 117 KB Posted

Attached to
Oberly and Washington Terrace Improvements (Project No. 26005-130)
Solicitation number
RFQ- 26 - 199
Issued by
Pinellas County, Florida

About this file

This is a Scope of Services document for the City of St. Petersburg, Florida, outlining engineering design services for the Oberly and Washington Terrace Improvements project (Project No. 26005-130). The City seeks qualified Architectural/Engineering (A/E) firms to provide comprehensive design services for improvements to two critical potable water pump stations that serve the municipality's water distribution system. The project encompasses six primary capital improvement tasks: a kick-off meeting with project team members, preparation of a Basis of Design Report incorporating resiliency concepts, preparation of 60% design documents with regulatory pre-applications, preparation of 90% design documents with permit applications, finalization of design documents, and construction phase services including shop drawing review and record drawings. The specific infrastructure improvements include rehabilitation of storage tanks, pumps, and valves and yard piping at both the Oberly pump station (64 million gallons per day capacity) and Washington Terrace pump station (30 million gallons per day capacity). The scope is flexible and may be modified based on funding availability, schedule constraints, and other project factors. Construction is planned to be executed by a Construction Manager at Risk delivery method.

The project emphasizes the incorporation of energy efficiency and resiliency elements throughout all design phases. The A/E firm must ensure that all personnel with regular access to the water department facilities comply with criminal background check requirements pursuant to Florida Statute Section 373.6055, with affidavits required prior to site access and maintained throughout the contract term. The City reserves the right to modify, delete, or add tasks based on project needs and discussions with the selected firm. No specific contract term, pricing structure, or award date is identified in the scope document, indicating these details would be addressed in the formal Request for Proposals or contract agreement.

View the file

Other files

File Type Posted
Oberly_and_Washington_Terrace_Improvements_(Project_No._26005-130).pdf PDF
Subcontractor_Utilization_Plan.docx DOCX document
Statement_of_Qualifications_Requirements.pdf PDF
Statement_of_Qualifications_Requirements_.docx DOCX document
SF330.pdf PDF
Base_Agreement.pdf PDF
_Solicitation_Development_Form_AE_Agreements_03.03.2026.docx DOCX document
Light_Construction_Agreement.docx DOCX document
Performance_&_Payment_Bond_.DOCX DOCX document
Public_Construction_Bond.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A-1

Appendix A - Scope of Services Oberly and Washington Terrace Improvements

City of St. Petersburg, Florida Project No. 26005-130

1. INTENT

The City of St. Petersburg, Florida (“City”) is seeking the services of a qualified Architectural/Engineering (“A/E”) firms to provide engineering design services for the Oberly and Washington Terrace Improvements project, located in the City of St. Petersburg.

2. BACKGROUND

The City of St. Petersburg’s primary drinking water source is served by the Cosme Water Treatment Plant in Northern Hillsborough County. The water is transmitted to St. Petersburg through two larger diameter transmission mains (one 48-inch-diameter and one 36-inch-diameter), a booster pump station [Gulf-to-Bay (GTB)], and two pump stations: Oberly and Washington Terrace. The Oberly (OBE) and Washington Terrace (WAS) pump stations serve as the high-pressure pump stations delivering potable water to the City’s service area.

The 48-inch transmission main delivers water to OBE, which has a firm pumping capacity of 64 million gallons per day (MGD), while the 36-inch transmission main directs water to WAS, with a firm pumping capacity of 30 MGD. Additionally, GTB is available to boost pressure in the 36-inch main, when necessary, though its use is limited to specific, infrequent conditions.

The pump stations have above ground storage and chemical treatment.

In 2025, HDR Engineering, Inc. completed a “Treated Water Transmission, Storage, and Pumping Facilities Plan” (Facility Plan) for the City of St. Petersburg. The plan outlined a strategic roadmap for the rehabilitation and sustainability of water services for the City. The Facility Plan identified and prioritized capital improvement projects to allow the City to mitigate risks, enhance operational efficiency, and meet future demands.

The Oberly and Washington Improvements includes the following capital projects that were included in the Facility Plan:

OBE-1 Oberly Storage Tanks OBE-2 Oberly Pumps OBE-5 Oberly Valves and Yard Piping

WAS-1 Washington Terrace Storage Tanks WAS-2 Washington Terrace Pumps WAS-5 Washington Terrace Valves and Yard Piping

Although no additional projects are planned to be included at this time, the scope of the Oberly and Washington Terrace Improvements project may be added to or subtracted from depending on various factors including funding, schedule, and other constraints and opportunities.

The project is planned to be completed by a Construction Manager at Risk.

A-2

3. SCOPE

TASK 1 KICK-OFF MEETING WITH THE A/E AND CITY STAFF

Under this task, the A/E shall have a kickoff meeting and complete the following services:

a. Introduce team members.

b. Establish roles and responsibilities.

c. Discuss preliminary design options (including energy efficiency and resiliency elements), budget, and schedule.

TASK 2 PREPARE BASIS OF DESIGN REPORT

a. Incorporate resiliency concepts.

b. Develop a Basis of Design Report including drawings, schematics, tables, calculations, details, construction cost estimates, etc. for evaluation of options and recommendations.

c. Prepare outline of technical specifications.

d. Provide funding support.

TASK 3 PREPARE 60% DESIGN DOCUMENTS

a. Prepare design drawings including plans, sections, notes, schematics, tables, etc. for construction.

b. Prepare draft technical specifications.

c. Continue incorporating energy efficiency and resiliency concepts.

d. Conduct pre-application meetings with regulatory agencies.

e. Prepare draft permit applications.

f. Review CMAR cost estimates.

g. Conduct or attend value engineering workshops.

h. Conduct public meetings and workshops.

i. Continued funding support.

TASK 4 PREPARE 90% DESIGN DOCUMENTS

a. Prepare design drawings including plans, sections, notes, schematics, tables, details, etc. for construction.

b. Continue incorporating energy efficiency and resiliency concepts.

c. Incorporate 60% design document review comments.

d. Prepare technical specifications.

e. Prepare construction cost estimate.

f. Apply for permit approvals.

g. Continued funding support.

TASK 5 PREPARE FINAL DESIGN DOCUMENTS

a. Incorporate 90% design document review comments.

b. Finalize incorporating energy efficiency and resiliency concepts.

c. Incorporate permit agency comments.

d. Prepare final design drawings, technical specifications, and construction cost estimate.

A-3

TASK 6 CONSTRUCTION SERVICES

a. Attend construction progress meetings.

b. Review shop drawings.

c. Respond to requests for information.

d. Observe construction.

e. Review change orders.

f. Attend final inspections.

g. Prepare record drawings.

h. Support with potential funding implementation.

TASK 7 ADDITIONAL SERVICES NEEDED

The City reserves the right to delete, alter or add to any of the above tasks based on City needs and/or discussions with the selected A/E.

4. CRIMINAL BACKGROUND CHECKS

Water Resources Department - Criminal background checks in accordance with state statute are required for persons having regular access to the Water Department's buildings, facilities and structures.

The A/E shall conduct a criminal history check (“Background Check”) for each A/E, subconsultant/subcontractor employee that will have regular access to the work site in accordance with the background check requirements set forth in Florida Statute Section 373.6055.

Prior to allowing an A/E, subconsultant/subcontractor employee regular access to the work site, the A/E shall submit to the City's Design Manager an affidavit certifying that each such employee is qualified to regularly access the work site in accordance with Florida Statute Sections 373.6055(2), (3)(b) and (3)(c). If any A/E, subconsultant/subcontractor employee’s Background Check identifies criminal convictions or other criminal history factors that disqualify that employee from regular access to the work site, A/E shall not allow that employee to have regular access to the work site, and an appeal process is not available. In the event A/E becomes aware that any A/E, subconsultant/subcontractor employee has been arrested or convicted for disqualifying offense, A/E shall immediately remove that employee from the work site.

An updated list of all A/E, subconsultant/subcontractor employees with regular access to the work site shall accompany the affidavit and be provided to the City's Design Manager along with the cell phone number of the A/E's representative responsible for those employees. At any time, the City may request to view the Background Checks of A/E, subconsultant/subcontractor employees working at the work site. A/E shall make the Background Checks available for viewing as soon as possible, but no later than twenty-four

(24) hours after the request. If the A/E fails to provide the requested documentation, the employee(s) in question will not be allowed to continue work until the appropriate documentation has been received. The A/E shall not be allowed an extension of the Contract Time due to any delay in the performance of the Work attributable to an employee’s inability to perform Work due to a Background Check being unavailable for inspection. The failure of the A/E to submit an appropriate affidavit or the submission of an affidavit containing false information shall be considered a substantial violation of the terms and conditions of the Contract Documents and shall provide a basis for termination of the Contract.

Oberly and Washington Terrace Improvements
Project No. 26005-130