This Scope of Construction Services document outlines the construction requirements for Project 1182-2023, a waterway debris collection and removal initiative funded through the USDA's Natural Resources Conservation Service (NRCS) Emergency Watershed Protection Grant and administered by the City of Fort Myers, Florida. The project encompasses minor clearing, bank repair, debris and sediment removal from waterways and canals, repairs to eroded areas, installation of articulated concrete block mats, and vegetative restoration measures. The scope includes ten line item tasks: Non-Vegetative Debris Removal, Vegetative Debris Removal, Tree Removal, Underwater Debris Removal, Sediment Removal, Bank Reshaping, Sediment Transport, Installation of Articulated Concrete Block Mat, Record Drawings, and Mobilization/Remobilization. Most items are measured in cubic yards, linear feet, or mileage on a not-to-exceed basis, with record drawings specified as a lump sum per 200 linear feet of canal.
The contractor must provide comprehensive documentation to support the City's request for grant reimbursement, including invoices for material costs, records documenting material types, quality and quantities, daily time records for employees with wage rates and hours, equipment operating records showing type, size, hourly rates and actual hours of operation, and weekly construction progress reports with on-site inspections. The contractor is required to submit PE-certified as-built drawings and quantities upon project completion. All contractors and subcontractors must comply with OSHA regulations and the Contract Work Hours and Safety Standards Act (40 USC 3701-3708), as supplemented by Department of Labor regulations (29 CFR Part 5). Equipment idle time is not eligible for reimbursement and must be excluded from equipment operating records.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of construction Services Project 1182-2023
Provide all labor and materials for the construction and required grant documentation based on the plans, specifications, and other contract documents. The following documentation is required to support the City of Fort Myers request for reimbursement of:
a. Invoices covering actual costs of materials used in constructing the eligible EWP project measures.
b. Records documenting the type, quality, and quantities of materials actually used in constructing the eligible EWP project measures.
c. Daily time records for each employee showing name, classification, wage rate, hours, and dates actually employed for constructing the eligible EWP project measures.
d. Equipment operating records showing the type and size of equipment, hourly rate, actual hours of operation and dates used to install the eligible EWP project measures. Equipment idle time is not eligible in-kind construction services, even if on the job site, and should not be included in the equipment operating records.
e. Weekly construction progress reports that include on-site inspections of work accomplished for the period, work planned, problems encountered.
d. Provide PE-certified as-built drawings and quantities for the project.
Construction shall adhere to the following federal requirement: Ensure that all contractors and sub-contractors are performing their work in accordance with OSHA regulations and the
Contract Work Hours and Safety Standards Act (40 USC 3701-3708) as supplemented by
Department of Labor regulations (29 CFR Part 5).
BID TASKS.
Line Item
Description TASK Unit of Measure
1 Non-Vegetative Debris Removal Cubic Yards (NTE)
2 Vegetative Debris Removal Cubic Yards (NTE)
3 Tree Removal Cubic Yards (NTE)
4 Underwater Debris Removal Cubic Yards (NTE)
5 Sediment Removal Cubic Yards (NTE)
6 Bank Reshaping Linear Feet (NTE)
7 Sediment Transport Mileage (NTE)
8 Installation of Articulated Concrete Block mat (ACB Mat) Linear Feet (NTE)
9 Record Drawings Lump sum per 200 LF of Canal (NTE)
10 Mobilization/Remobilization Lump Sum (NTE)