Scheduling_and_Conditions_for_Delivery_of_Product.docx

DOCX document 19 KB Posted

Attached to
Walk-In Cooler/Freezer Replacement State and local contract opportunity
Solicitation number
25-JG-032
Issued by
Pinellas County, Florida

About this file

This document is a Scheduling and Conditions for Delivery of Product file for the Pinellas County School Board (PCSB), detailing the replacement of walk-in cooler/freezer units at three school locations: Gibbs High, Frontier Elementary, and Palm Harbor Middle. The project involves removing existing walk-in units and installing new cooler/freezer units between June 2 and July 26, 2025, with specific timeline requirements for each school site. The awarded vendor must verify manufacturer delivery schedules by May 2, 2025, and ensure all units are fully operational by July 26, 2025, with the option to provide portable walk-ins if installation deadlines are not met.

The contract requires the vendor to coordinate with the factory for unit delivery, furnish all materials and labor for demolition and installation, and use licensed electricians as needed. The walk-in coolers/freezers must meet specific requirements, including a minimum 2" air gap between unit and building walls, and the vendor must produce and provide accurate drawings for each unit. If the vendor fails to meet the installation schedule or have units operational by the specified date, they will be responsible for leasing ground-level walk-in units from Polar Leasing until full installation is complete. The project is funded through the Pinellas County School Board and is specifically aimed at preparing the schools' food service facilities for the 2025-26 school year.

View the file

Other files for this state and local contract opportunity

Other files attached to Walk-In Cooler/Freezer Replacement, newest first.
File Type Posted
Walk-In_Cooler_Freezer_Replacement.pdf PDF
Bid_Protest_Procedure.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The awarded bidder shall verify no later than May 2, 2025, that the manufacturer is going to meet the below schedule. If the delivery is not going to meet the prescribed schedule, PCSB has the option to cancel the order on the bases that the projects schedule and completion date will not be met and PCSB will not be able to start and complete the projects in time for the opening of the 2025-26 school year. Failure to notify designated District staff, that the manufacturer will not be able to meet the delivery dates and the project is started on June 2, 2025, and if the provided schedule is not strictly adhered too and school has no working walk in cooler/ freezer prior to the opening of the 2025-26 school year, the awarded bidder is to supply portable walk-ins for the location. These conditions apply only if the awarded bidder does not meet the delivery and install of box schedule dates as it is the responsibility of the awarded bidder to assure this schedule is met. The awarded bidder will be held responsible if there is an interruption on the site prep, refrigeration installation or electrical hook-up schedule.

Gibbs High:

· June 2 - 4, 2025
Vendor removes existing walk-in.
· June 5 – 10, 2025
Concrete contractor preps site for delivery and install of walk-in. PCSB will be providing contractor for concrete work.
· June 11 - 20, 2025
Vendor delivers and installs walk-in and refrigeration.
· June 17 - 18, 2025
Protect-All Flooring is installed after PCSB staff has inspected for proper install.
· June 23, 2025
Vendor has box running

Frontier Elementary:

· June 5 - 6, 2025
Vendor removes existing walk-in.
· June 11 -17, 2025
Concrete contractor preps site for delivery and install of walk-in. PCSB will be providing contractor for concrete work.
· June 19 – 26, 2025
Vendor delivers and installs walk-in and refrigeration
· June 27, 2025
Protect-All Flooring installed after PCSB inspects for proper install.
· June 30, 2025
Vendor has box running

SCHEDULING & CONDITIONS FOR DELIVERY OF PRODUCT

Palm Harbor Middle:

· June 9-10, 2025
Vendor removes existing walk-in.
· June 18 - 24, 2025
Concrete contractor preps site for delivery and install of walk-in. PCSB will be providing contractor for concrete work.
· June 25 – July 2, 2025
Vendor delivers and installs walk-in and refrigeration
· July 2, 2025
Protect-All Flooring installed after PCSB inspects for proper install.
· July 3, 2025
Vendor has box running

The above schedule has room for adjustment; however, all walk-in cooler/freezers need to be up and running by July 26, 2025. Any walk-ins that are not up and running, vendor will be responsible to lease ground level walk-ins ( Polar Leasing) and have powered up until the walk in is up and running in full operation.