The file's text, extracted by GovTribe without its formatting.
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES
Big Smoky Hybrid Electrical Upgrades & Building Foundation Improvements Sawtooth National Forest Fairfield Ranger District Camas County, Idaho
B.1 Schedule of Items
Base Bid (Big Smoky Work Center Hybrid Electrical – North Site)
| Item No. |
| Description |
| Est. Qty |
| Unit |
| Method of Measure |
| Unit Price |
| Total Price |
| 260000-1 |
| Mobilization |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-2 |
| Demolition and Salvage |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-3 |
| Generator and Pad |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-4 |
| Dual Array and Mounting |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-5 |
| Flexware, Batteries, and Balance of System |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| TOTAL PRICE (ALL ITEMS – Base Bid) |
| $__________________ |
Method of Measurement:
AQ – Actual Quanties; CQ – Contract Quantities; LSQ - Lump Sum Quantities
Option Item #1 (Big Smoky Work Center Building Foundation Construction
| Item No. |
| Description |
| Est. Qty |
| Unit |
| Method of Measure |
| Unit Price |
| Total Price |
| 000050-1 |
| Mobilization |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 000050-2 |
| North Building – Concrete Foundation Construction Including Building Removal, Reinstallation, and Utility Reconnection |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 000050-3 |
| South Building – Concrete Foundation Construction Including Building Removal, Reinstallation, and Utility Reconnection |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| TOTAL PRICE (ALL ITEMS – Option Item #1) |
| $__________________ |
TOTAL PRICE (ALL ITEMS – Base Bid PLUS Option Item #1)
Option Item #2 (Big Smoky Guard Station Hybrid Electrical – South Site)
| Item No. |
| Description |
| Est. Qty |
| Unit |
| Method of Measure |
| Unit Price |
| Total Price |
| 260000-1(1) |
| Mobilization |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-2(1) |
| Demolition and Salvage |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-3(1) |
| Generator and Pad |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-4(1) |
| Array and Mounting |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| 260000-5(1) |
| Flexware, Batteries, and Balance of System |
| 1 |
| Lump Sum |
| LSQ |
| $_________ |
| $__________ |
| TOTAL PRICE (ALL ITEMS – Option Item #2) |
| $__________________ |
TOTAL PRICE (ALL ITEMS – Base Bid PLUS Option Item #1 PLUS Option Item #2)
Method of Measurement:
AQ – Actual Quanties; CQ – Contract Quantities; LSQ - Lump Sum Quantities