1240LT24R0040 AMD 1.pdf

PDF 361 KB Posted

Attached to
Big Smoky Hybrid Electrical System Upgrade and Building Foundation Improvements
Solicitation number
1240LT24R0040
Issued by

About this file

This document is an amendment to a solicitation for the Big Smoky Hybrid Electrical System Upgrade and Building Foundation Improvements project. The amendment makes several changes to the original solicitation, including:

  • Changing the requirement to remove and salvage the existing generator to a requirement to remove and dispose of it.
  • Changing the new diesel generator that was called for to a propane generator that will better suit the site's needs.
  • Extending the period of performance from November 15, 2024 to May 30, 2025, and requiring the existing generator to remain operable through October 18, 2024.
  • Updating various drawings and specifications to reflect the changes to the generator requirements.

The solicitation number is 1240LT24R0040, and it is being issued by the Department of Agriculture Forest Service. The original solicitation included a base bid for the electrical system upgrade and two optional items for building foundation work. The amendment provides additional details and clarifications related to the project.

View the file

Other files

File Type Posted
Big Smoky Pre-bid Sign-in Sheet 05-23.pdf PDF
1240LT24R0040.pdf PDF
SOW.docx DOCX document
Camas County Wage Determination.txt TXT text file
FirePrecautions Plan.docx DOCX document
BigSmokyElectrical Foundations maps.pdf PDF
ScheduleOfItems.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1240LT24R0040

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

40LT

OGDEN UT 84401-2310

324 25TH ST

USDA-FS CSA INTERMOUNTAIN 8

04/11/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

04/11/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The Amendment involves changing language requiring salvaging existing generators to disposing of them, and changing the new diesel generator that is called for to a propane generator that will suit the needs of the site much better

Quote due date has been changed to 06/07/24

Period of Performance: 09/23/2024 to 11/15/2024

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

AMENDMENT #1

Big Smoky Foundation Improvements Project

The following changes have been made to the Schedule of Items, plans and specifications for the above named project. Please incorporate the following information into your bid.

Schedule Of Items:

Part I, Section B, Page 1, Heading B.1, Base Bid Item No. 260000-2 Description

Replace “Demolition & Salvage” with “Demolition and Disposal”

Part I, Section B, Page 2, Heading B.1, Base Bid Item No. 260000-2(1) Description

Replace “Demolition & Salvage” with “Demolition and Disposal”

SOW:

Section C, General Specifications, Page 000001-1, Heading 1.1 SCOPE OF CONTRACT, Paragraph A1a

Replace “a. Removal and salvage of an existing generator from the distribution system and an unused solar array (no electrical connections, salvaged for use at the Big Smoky Guard Station - South Site).”

with “a. Removal and disposal of an existing generator from the distribution system and an unused solar array (no electrical connections, salvaged for use at the Big Smoky Guard Station - South Site).”

Section C, General Specifications, Page 000001-3, Heading 1.9 END DATE, Paragraph A

Replace “November 15, 2024” with “May 30, 2025” and add the following statement “Existing generator shall be operable through October 18, 2024 unless otherwise approved by the Contracting Officer.”

Section 260000, COMMON WORK RESULTS FOR ELECTRICAL, Page 260000-27, Heading 1.6

MEASUREMENT AND PAYMENT, Paragraph A1

Replace “1. Demolition and Salvage – Lump Sum as described on the drawings including repairs noted.”

with “1. Demolition and Disposal – Lump Sum as described on the drawings including repairs noted.”

BigSmokyElectrical+Foundations+maps:

BIG SMOKY NORTH SITE HYBRID ELECTRIC Sheet 2 of 5 (Drawing Sheet No. E-1), GENERATOR NOTES

Replace Note 1 “EXISTING GENERATOR SYSTEM (INCLUDES FLEXIBLE FUEL, EXHAUST, AND VENTILATION SYSTEMS) SHALL BE REMOVED FROM BUILDING AND SHALL

REMAIN THE PROPERTY OF THE GOVERNMENT. THE CONTRACTOR SHALL BE

RESPONSIBLE FOR LOADING IT IN A GOVERNMENT VEHICLE OR PLACING IT AT A

LOCATION NOTED BY THE GOVERNMENT ON THIS SITE.” with “EXISTING GENERATOR

SYSTEM (INCLUDES FLEXIBLE FUEL, EXHAUST, AND VENTILATION SYSTEMS) SHALL BE

REMOVED AND DISPOSED OF”

Replace Note 2 “INSTALL PAD AND KOHLER GENERATOR, MODEL 15REOZK, 60 HZ, 1

PHASE, 120/240 V, 14.0 KW PRIME (105°C RISE), DIESEL, AND WEATHER ENCLOSURE

MOUNTED ON 168 GALLON SUBBASE FUEL TANK. SUPPLY WITH MAIN BREAKER, PRIME

POWER SWITCH, STARTING BATTERY AND CHARGER, STANDARD CONTROL FEATURES,

AND ALL APPURTENANCES READY FOR OPERATION. 2-YEAR WARRANTY. SUBBASE

FUEL TANK INCLUDES I-BEAMS FOR GROUND CLEARANCE, 5 GALLON FUEL FILL SPILL

CONTAINMENT, AND COMBUSTIBLE LIQUIDS DECAL” with “INSTALL PAD AND PDG

GENERATOR, MODEL FORD 15KW PROPANE/NATURAL GAS GENERATOR, 15 KW PRIME,

PROPANE, WITH 2 WIRE AUTOSTART CONTROLLER, AND CRITICALLY SILENCED

ENCLOSURE. SUPPLY WITH MAIN BREAKER, PRIME POWER SWITCH, STARTING

BATTERY AND CHARGER, STANDARD CONTROL FEATURES, AND ALL APPURTENANCES

READY FOR OPERATION.”

BIG SMOKY NORTH SITE HYBRID ELECTRIC Sheet 3 of 5 (Drawing Sheet No. E-2), GENERATOR SHED INTERIOR Detail

Replace callout “EXHAUST SYTEM TO BE REMOVED AND SALVAGED” with “EXHAUST

SYTEM TO BE REMOVED AND DISPOSED OF”

Replace callout “VENT SYSTEM TO BE REMOVED AND SALVAGED” with “VENT SYSTEM TO

BE REMOVED AND DISPOSED OF”

Replace callout “GENERATOR SYSTEM TO BE REMOVED AND SALVAGED” with

“GENERATOR SYSTEM TO BE REMOVED AND DISPOSED OF”

BIG SMOKY NORTH SITE HYBRID ELECTRIC Sheet 5 of 5 (Drawing Sheet No. D-1), GENERATOR PAD NOTES

Replace NOTE-4 “CONTRACTOR SHALL VERIFY THE DIMENSIONS OF THE GENERATOR

AND FUEL TANK TO BE SUPPLIED PRIOR TO BEGINNING CONSTRUCTION. COORDINATE

THE LOCATION OF ANCHOR BOLTS, ELECTRICAL FEEDER, AND AUTOSTART CIRCUIT.

LOCATIONS SHOWN ARE NOT ACCURATE. PAD SIZE IS BASED ON CALLED FOR

GENERATOR AND SHALL BE ADJUSTED LARGER FOR LARGER GENERATOR

SUBSTITUTIONS.” with “CONTRACTOR SHALL VERIFY THE DIMENSIONS OF THE

GENERATOR AND ENCLOSURE TO BE SUPPLIED PRIOR TO BEGINNING CONSTRUCTION.

COORDINATE THE LOCATION OF ANCHOR BOLTS, ELECTRICAL FEEDER, AND

AUTOSTART CIRCUIT. LOCATIONS SHOWN ARE NOT ACCURATE. PAD SIZE IS BASED ON

CALLED FOR GENERATOR AND SHALL BE ADJUSTED LARGER FOR LARGER GENERATOR

SUBSTITUTIONS.”

BIG SMOKY SOUTH SITE HYBRID ELECTRIC Sheet 2 of 5 (Drawing Sheet No. E-1), GENERATOR NOTES

Replace Note 1 “EXISTING GENERATOR SYSTEM (INCLUDES FLEXIBLE FUEL, EXHAUST, AND VENTILATION SYSTEMS) SHALL BE REMOVED FROM BUILDING AND SHALL

REMAIN THE PROPERTY OF THE GOVERNMENT. THE CONTRACTOR SHALL BE

RESPONSIBLE FOR LOADING IT IN A GOVERNMENT VEHICLE OR PLACING IT AT A

LOCATION NOTED BY THE GOVERNMENT ON THIS SITE.” with “EXISTING GENERATOR

SYSTEM (INCLUDES FLEXIBLE FUEL, EXHAUST, AND VENTILATION SYSTEMS) SHALL BE

REMOVED AND DISPOSED OF”

Replace Note 2 “INSTALL PAD AND KOHLER GENERATOR, MODEL 15REOZK, 60 HZ, 1

PHASE, 120/240 V, 14.0 KW PRIME (105°C RISE), DIESEL, AND WEATHER ENCLOSURE

MOUNTED ON 168 GALLON SUBBASE FUEL TANK. SUPPLY WITH MAIN BREAKER, PRIME

POWER SWITCH, STARTING BATTERY AND CHARGER, STANDARD CONTROL FEATURES,

AND ALL APPURTENANCES READY FOR OPERATION. 2-YEAR WARRANTY. SUBBASE

FUEL TANK INCLUDES I-BEAMS FOR GROUND CLEARANCE, 5 GALLON FUEL FILL SPILL

CONTAINMENT, AND COMBUSTIBLE LIQUIDS DECAL” with “INSTALL PAD AND PDG

GENERATOR, MODEL FORD 15KW PROPANE/NATURAL GAS GENERATOR, 15 KW PRIME,

PROPANE, WITH 2 WIRE AUTOSTART CONTROLLER, AND CRITICALLY SILENCED

ENCLOSURE. SUPPLY WITH MAIN BREAKER, PRIME POWER SWITCH, STARTING

BATTERY AND CHARGER, STANDARD CONTROL FEATURES, AND ALL APPURTENANCES

READY FOR OPERATION.”

BIG SMOKY SOUTH SITE HYBRID ELECTRIC Sheet 3 of 5 (Drawing Sheet No. E-2), GENERATOR SHED INTERIOR Detail

Replace callout “EXHAUST SYTEM TO BE REMOVED AND SALVAGED” with “EXHAUST

SYTEM TO BE REMOVED AND DISPOSED OF”

Replace callout “GENERATOR SYSTEM TO BE REMOVED AND SALVAGED” with

“GENERATOR SYSTEM TO BE REMOVED AND DISPOSED OF”

BIG SMOKY SOUTH SITE HYBRID ELECTRIC Sheet 5 of 5 (Drawing Sheet No. D-1), GENERATOR PAD NOTES

Replace NOTE-4 “CONTRACTOR SHALL VERIFY THE DIMENSIONS OF THE GENERATOR

AND FUEL TANK TO BE SUPPLIED PRIOR TO BEGINNING CONSTRUCTION. COORDINATE

THE LOCATION OF ANCHOR BOLTS, ELECTRICAL FEEDER, AND AUTOSTART CIRCUIT.

LOCATIONS SHOWN ARE NOT ACCURATE. PAD SIZE IS BASED ON CALLED FOR

GENERATOR AND SHALL BE ADJUSTED LARGER FOR LARGER GENERATOR

SUBSTITUTIONS.” with “CONTRACTOR SHALL VERIFY THE DIMENSIONS OF THE

GENERATOR AND ENCLOSURE TO BE SUPPLIED PRIOR TO BEGINNING CONSTRUCTION.

COORDINATE THE LOCATION OF ANCHOR BOLTS, ELECTRICAL FEEDER, AND

AUTOSTART CIRCUIT. LOCATIONS SHOWN ARE NOT ACCURATE. PAD SIZE IS BASED ON

CALLED FOR GENERATOR AND SHALL BE ADJUSTED LARGER FOR LARGER GENERATOR

SUBSTITUTIONS.”

Big Smoky Hybrid Electrical System Upgrade & Building Foundation Improvements Project

Pre-Bid Meeting / Site Visit (May 14, 2024, 10:00 AM)

Solicitation # 1240LT24R0040

Meeting notes/comments shown below

1. Introductions

2. Project Overview

Base Bid: North Site hybrid electrical system installation Option #1: North Site building foundation construction Option #2: South Site hybrid electrical system installation

Base Bid Overview:

Create new concrete solar panel site pad & install poles and conduit, install new panel array Install new generator pad and weather enclosure outside existing generator shed, remove & salvage old generator and exhaust system, and install new diesel generator with associated appurtenances

Desire is to remove & dispose of generator, this will be clarified in an Amendment

Install new battery charging station and batteries, and appropriately connect electrical system to solar array, generator, existing double throw disconnect, and distribution panel board

Install required signs, new luminaire, GFCI receptacle, breaker for new lighting, new grounding, etc.

Option #1 Overview:

Verify existing building dimensions, adjust plans as necessary Prepare, form, and pour 2 concrete foundations for 2 existing buildings After waiting appropriate cure time, disconnect all utility systems from existing buildings

(electrical, gas, water, sewer), then move buildings onto new foundations Reconnect all utility systems and clean up existing building sites, and hauling away excavated materials

Option #2 Overview:

Create new concrete solar panel site pad & install poles and conduit, install existing panel array salvaged from north site Install new generator pad and weather enclosure outside existing generator shed, remove & salvage old generator and exhaust system, and install new diesel generator with associated appurtenances

Desire is to remove & dispose of generator, this will be clarified in an Amendment

Install new battery charging station, and appropriately connect electrical system to solar array, generator, existing double throw disconnect, and distribution panel board

Install required signs, new luminaire, GFCI receptacle, breaker for new lighting, new grounding, etc.

Inspections, advance notices, etc.

Give at least 2 days notice in advance of proposed utility interruptions Give at least 2 days notice before placement of concrete to allow for form & steel reinforcement inspection Give proper notice for concrete sampling & testing by independent testing agency Have cold weather plan in place for concrete pouring

3. Project Specifications

Standard Specifications – FP-14 (available online) Forest Service Special Provisions – Included in contract. These supplement the FP-14 CSI Supplemental Specifications – Included in contract. These supplement the FSSS

4. Government-Furnished Items

Existing solar panel array at North Site

5. Work Breakdown & Schedule

Start date September 23, 3024 End date November 15, 2024

6. Questions?

Q: What is the weight rating of the bridge in place between the North Site and South Site?

A: 44.1 Tons.

Q: When are the fire plan, stream/groundwater protection plan, quality control plan, etc.

required for the contract? During bid submission, or after award?

A: These should be after award, but confirm with CO.

Q: For the generator housing/enclosure, will it have or need a snorkel placed up to whatever snow height this site experiences in winter?

A: No, this system is not operational during the winter.

Q: The specification call for heaters to be used to keep the concrete warm during cure time.

Can blankets be used instead?

A: The specification does not call specifically for heaters to be used, as long as the concrete is kept above freezing during the cure time to reach the required strength blankets will suffice, but the contractor is responsible for ensuring the concrete remains at the proper temperature during the cure period.

7. Clarifications:

At the Big Smoky Work Center North Site – the South Building for which the foundation is to be constructed has the following utilities running into the building which will need to be temporarily disconnected and reattached while the building is raised and the foundation constructed: sewer (for washing machines), water, electrical power, propane gas line.

At the Big Smoky Work Center North Site – the North Building for which the foundation is to be constructed has the following utilities running into the building which will need to be temporarily disconnected and reattached while the building is raised and the foundation constructed: electrical power, propane gas line. There is also a radio tower that will need to be left in place and disconnected from the building then reattached while working around it during foundation construction.

At the Big Smoky Work Center North Site South Building, the space existing underneath the building to crawl underneath and disconnect utilities is limited, but it is possible to remove the existing subfloor (no flooring is present inside the building) to access underneath the building and can be reinstalled as necessary.

The Big Smoky Work Center North Site North Building, South Building, and Generator Shed have items stored in them which will be removed by Forest Service personnel prior to work commencing in each building. Contractors must coordinate with the COR/Fire Staff on site to ensure enough time is given for personnel to remove the items.

Two trailer pads are available for the contractor to use during construction. The pads have water hookups (no sewer or electrical hookups), but there is a dump station located less than ½ mile from the Big Smoky Work Center.

Water for construction use is available, but toilets and power will need to be supplied by the contractor for their own use on site.

The Forest Service will identify the utility locations at each building before construction begins.

Final building locations shall match existing

1240LT24R0040 AMT 1