This document is a Design Schedule for a professional engineering services project by Pinellas County for the South Cross Bayou Advanced Wastewater Treatment Plant (AWWTP), specifically focusing on the replacement of Switchgear BLA and Switchgear BLB. The project is scheduled to begin on March 10, 2023, with a Notice to Proceed, and is anticipated to conclude on July 25, 2025, spanning approximately 620 days. The project is divided into five primary tasks: Project Management and Schedule, Detailed Design, Permitting, Bidding, and Construction Phase. Key milestones include a kickoff meeting on March 24, 2023, design document submissions at 60% and 90% completion, FDEP permitting, bid document preparation and evaluation, and a construction phase lasting 307 days from May 22, 2024, to July 25, 2025.
The schedule outlines a comprehensive project timeline with detailed subtasks, including data collection, site visits, equipment evaluation, design document preparation, bidding processes, and construction activities. The project involves multiple stages of design review, with specific timelines for 60% and 90% design document submissions, cost estimates, and permit acquisitions. The construction phase includes contract administration, pre-construction conference, shop drawing reviews, quality assurance inspections, and will culminate in substantial completion on May 12, 2025, with final completion and permit clearances by July 25, 2025. The schedule provides a granular view of the project progression, highlighting the interconnected nature of each project phase and the critical path for successful project completion.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Duration Start Finish (Work Days) Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jum Jul
Notice to Proceed From County 1 day Fri 03/10/23 Fri 03/10/23
Task 1.0 - Project Management and Schedule 620 Days Mon 03/13/23 Fri 07/25/25
Project Management 620 days Mon 03/13/23 Fri 07/25/25
Schedule Tracking 620 days Mon 03/13/23 Fri 07/25/25
Kickoff Meeting 1 day Mon 03/24/23 Mon 03/24/23
Review Meetings with County 590 days Mon 04/24/23 Fri 07/25/25 *
Task 2.0 - Detailed Design 220 Days Mon 04/24/23 Fri 02/23/24
Data Collection / Site Visits 25 days Mon 04/24/23 Fri 05/26/23
Equipment Evaluation 20 days Mon 05/15/23 Fri 06/09/23
60% Design Documents 80 days Mon 05/22/23 Fri 09/08/23
90% Design Documents and Cost Estimate 90 days Mon 09/11/23 Fri 01/12/24
100% Design Documents and Cost Estimate 30 days Mon 01/15/24 Fri 02/23/24
Task 3.0 - Permitting 15 Days Mon 02/12/24 Fri 03/01/24
FDEP General Construction Permit 15 days Mon 02/12/24 Fri 03/01/24
Task 4.0 - Bidding 62 Days Mon 02/26/24 Tue 05/21/24
Bid Documents 10 days Mon 02/26/24 Fri 03/08/24
Bidders' Responses and Addenda 25 days Mon 03/04/24 Fri 04/05/24
Bid Evaluation 10 days Mon 04/08/24 Fri 04/19/24
Award Recommendation 1 day Tue 04/23/24 Tue 04/23/24
Conformed Documents 10 days Tue 04/23/24 Mon 04/29/24
Notice to Proceed From County to Contractor 15 days Wed 05/01/24 Tue 05/21/24
Task 5.0 - Construction Phase 307 Days Wed 05/22/24 Fri 07/25/25
Contract Administration 1 day Wed 05/22/24 Wed 05/22/24
Pre-Construction Conference 1 day Wed 05/22/24 Wed 05/22/24
Shop Drawing Review and Procurement 140 days Thu 05/23/24 Thu 12/05/24
Construction 230 days Mon 06/24/24 Fri 05/09/25
Request for Information (RFI) 230 days Mon 06/24/24 Fri 05/09/25
Quality Assurance Inspection / Services 230 days Mon 06/24/24 Fri 05/09/25
Substantial Completion 1 day Mon 05/12/25 Mon 05/12/25
Final Completion 30 days Mon 05/12/25 Fri 06/20/25
Record Drawings 15 days Mon 06/23/25 Fri 07/11/25
Permit Clearances 10 days Mon 07/14/25 Fri 07/25/25
Task Name 2023 2024 2025
* 07/25/25 is the anticipated project closeout date after completion of the construction phase.
April 11, 2023
Attachment D Design Schedule
Pinellas County - South Cross Bayou AWWTP Replacement of Switchgear BLA and Switchgear BLB
Professional Engineering Services
| SCB Switchgear BLA-BLB Schedule |
| SCB AWWTP Schedule 04-11-23.pdf |
| Schedule 04-11-23 |
File details come from the government source that posted it. Updated .