SCB_AWRF_Generator_Controls_Switchgear_-_Bid_Form_(BLA_BLB)_Contracts_10-29-24.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
SCB Replacement of Generator Controls and Switchgear (PID 004906DE) STEP 2
Solicitation number
25-0073-ITB-C STEP 2
Issued by
Pinellas County, Florida

About this file

This document is a Bid Form for the Pinellas County South Cross Bayou Advanced Waste Reclamation Facility (AWRF) in Florida, specifically for the Generator Controls and Switchgear Replacement project (PID No. 004906DE, Bid No. 25-0073-ITB-C). The project involves the comprehensive removal and replacement of two switchboard line-ups, including utility circuit breakers, generator circuit breakers, feeder circuit breakers, group mounted devices, and automatic failover systems. The bid form details nine primary work items, ranging from mobilization/demobilization to project closeout documents, with quantities specified as lump sum (LS) for most line items.

The total engineer's estimated project cost is $2,032,000, with major cost components including $1,854,000 for switchgear replacement and demolition, $113,000 for utilities, $15,000 for building permit allowances, and $50,000 in unspecified funds. Key line items include switchgear replacements for BLA and BLB sections, demolition of existing switchgear, plant SCADA HMI modification, temporary engine/generator sets, arc flash risk assessment, and documentation preparation. The project is focused on creating fully operational and tested electrical systems at the South Cross Bayou Advanced Waste Reclamation Facility, with a comprehensive approach to equipment replacement and system integration.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form BID NAME: SOUTH CROSS BAYOU AWRF GENERATOR CONTROLS AND SWITCHGEAR REPLACEMENT (BLA&BLB)

PID NO. 004906DE

BID NO. 25-0073-ITB-C

Engineer's Estimate
Pay Item No.DescriptionQuantityUnitUnit PriceAmount
Utilites
1Mobilization / Demobilization1LS113,000.00$ 113,000.00
Utilities Subtotal$ 113,000.00
Switchgear Replacement/Demolition
3.13-1: Switchgear BLA1LS773,000.00$ 773,000.00
3.23-2: Switchgear BLB1LS773,000.00$ 773,000.00
3.33-3: Demolition of Exisiting Switchgear BLA1LS44,000.00$ 44,000.00
3.43-4: Demolition of Exisiting Switchgear BLB1LS44,000.00$ 44,000.00
3.53-5: Plant SCADA HMI Modification1LS20,000.00$ 20,000.00
3.63-6: Temporary Engine/Generator Sets, Fuel Tank and Cabling1LS86,000.00$ 86,000.00
3.73-7: Arc Flash Risk Assessment and Labeling1LS63,000.00$ 63,000.00
3.83-8: O&M Manuals and As-Built Drawings1LS25,000.00$ 25,000.00
3.93-9: Project Closeout Documents1LS26,000.00$ 26,000.00
Switchgear Replacement/Demolition Subtotal$ 1,854,000.00
Permits
2Building Permit Allowance15000EA1.00$ 15,000.00
Permits Subtotal$ 15,000.00
Unspecified Work
4Unspecified Funds50000EA1.00$ 50,000.00
Unspecified Work Subtotal$ 50,000.00
TOTAL$ 2,032,000.00

File details come from the government source that posted it. Updated .