SCB_AWRF_Generator_Controls_Switchgear_-_Bid_Form_(BLA_BLB)_Contracts_10-29-24.xlsx
XLSX spreadsheet 20 KB Posted
- Solicitation number
- 25-0073-ITB-C STEP 2
- Issued by
- Pinellas County, Florida
About this file
This document is a Bid Form for the Pinellas County South Cross Bayou Advanced Waste Reclamation Facility (AWRF) in Florida, specifically for the Generator Controls and Switchgear Replacement project (PID No. 004906DE, Bid No. 25-0073-ITB-C). The project involves the comprehensive removal and replacement of two switchboard line-ups, including utility circuit breakers, generator circuit breakers, feeder circuit breakers, group mounted devices, and automatic failover systems. The bid form details nine primary work items, ranging from mobilization/demobilization to project closeout documents, with quantities specified as lump sum (LS) for most line items.
The total engineer's estimated project cost is $2,032,000, with major cost components including $1,854,000 for switchgear replacement and demolition, $113,000 for utilities, $15,000 for building permit allowances, and $50,000 in unspecified funds. Key line items include switchgear replacements for BLA and BLB sections, demolition of existing switchgear, plant SCADA HMI modification, temporary engine/generator sets, arc flash risk assessment, and documentation preparation. The project is focused on creating fully operational and tested electrical systems at the South Cross Bayou Advanced Waste Reclamation Facility, with a comprehensive approach to equipment replacement and system integration.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Form BID NAME: SOUTH CROSS BAYOU AWRF GENERATOR CONTROLS AND SWITCHGEAR REPLACEMENT (BLA&BLB)
PID NO. 004906DE
BID NO. 25-0073-ITB-C
| Engineer's Estimate | |||||
| Pay Item No. | Description | Quantity | Unit | Unit Price | Amount |
| Utilites | |||||
| 1 | Mobilization / Demobilization | 1 | LS | 113,000.00 | $ 113,000.00 |
| Utilities Subtotal | $ 113,000.00 | ||||
| Switchgear Replacement/Demolition | |||||
| 3.1 | 3-1: Switchgear BLA | 1 | LS | 773,000.00 | $ 773,000.00 |
| 3.2 | 3-2: Switchgear BLB | 1 | LS | 773,000.00 | $ 773,000.00 |
| 3.3 | 3-3: Demolition of Exisiting Switchgear BLA | 1 | LS | 44,000.00 | $ 44,000.00 |
| 3.4 | 3-4: Demolition of Exisiting Switchgear BLB | 1 | LS | 44,000.00 | $ 44,000.00 |
| 3.5 | 3-5: Plant SCADA HMI Modification | 1 | LS | 20,000.00 | $ 20,000.00 |
| 3.6 | 3-6: Temporary Engine/Generator Sets, Fuel Tank and Cabling | 1 | LS | 86,000.00 | $ 86,000.00 |
| 3.7 | 3-7: Arc Flash Risk Assessment and Labeling | 1 | LS | 63,000.00 | $ 63,000.00 |
| 3.8 | 3-8: O&M Manuals and As-Built Drawings | 1 | LS | 25,000.00 | $ 25,000.00 |
| 3.9 | 3-9: Project Closeout Documents | 1 | LS | 26,000.00 | $ 26,000.00 |
| Switchgear Replacement/Demolition Subtotal | $ 1,854,000.00 | ||||
| Permits | |||||
| 2 | Building Permit Allowance | 15000 | EA | 1.00 | $ 15,000.00 |
| Permits Subtotal | $ 15,000.00 | ||||
| Unspecified Work | |||||
| 4 | Unspecified Funds | 50000 | EA | 1.00 | $ 50,000.00 |
| Unspecified Work Subtotal | $ 50,000.00 | ||||
| TOTAL | $ 2,032,000.00 |