About this file

This is a Performance Bond form issued by the State of Colorado Office of the State Architect State Buildings Program for construction projects managed by Colorado state agencies and institutions. The bond serves as a guarantee that the contractor will complete the contracted project in accordance with all terms, conditions, and specifications outlined in the underlying construction contract. The bond is executed simultaneously with a payment bond covering labor and material costs and requires submission with a power of attorney document. Upon contractor default as declared by the Principal Representative, the surety agrees to either complete the contract directly or arrange for completion through competitive bidding, providing sufficient funds throughout the completion process up to the bond amount.

The performance bond amount is set equal to the full contract price and protects the State of Colorado against contractor non-performance and breach of contract obligations. The bond remains in effect throughout the original contract term, any authorized extensions, and the life of any guaranties required under the contract. The surety's liability is capped at the bond amount and covers all costs associated with contract completion and damages resulting from default. No private parties have rights of action under this bond; only the State of Colorado may make claims. The form explicitly prohibits modifications to the bond language and is standardized across Colorado's state building projects as State Form SC-6.22.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

PERFORMANCE BOND

Institution/Agency:

Project No./Name:

BONDING COMPANY: DO NOT MAKE ANY CHANGES TO THE LANGUAGE IN THIS BOND.

KNOW ALL PERSONS BY THESE PRESENTS:

That the Contractor as Principal and hereinafter called “Principal,” and

as Surety and hereinafter called “Surety,” a corporation organized and existing under the laws ofare held and firmly bound unto the STATE OF COLORADO acting by and through
(AGENCY OR INSTITUTION)

hereinafter called the “Principal Representative”, in the sum of Dollars ($ ) for the payment whereof the Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly, by these presents.

WHEREAS, the Principal and the State of Colorado acting by and through the Principal Representative have entered into a certain Contract, hereinafter called “Contract,” dated , 20 , for the construction of a PROJECT described as which Contract is hereby by reference made a part hereof;

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION, is such that, if the Principal shall promptly, fully and faithfully perform all the undertakings, covenants, terms, conditions and agreements of said Contract during the original term of said Contract any extensions thereof that may be granted by the Principal Representative with or without notice to the Surety, and during the life of any guaranty required under the Contract, and shall also well and truly perform and fulfill all undertakings, covenants, terms, conditions and agreements of any and all duly authorized modifications of said Contract that may hereafter be made, notice of which modifications to the Surety being hereby waived, then this obligation shall be null and void; otherwise it shall remain in full force and effect.

AND THE SAID SURETY, for value received hereby stipulates and agrees that whenever the Principal shall be, and declared by the Principal Representative to be in default under said Contract, the State of Colorado having performed its obligations thereunder, the Surety may promptly remedy the default or shall promptly (1) Complete the Contract in accordance with its terms and conditions, or (2) Obtain a bid or bids for submittal to the Principal Representative for completing the Contract in accordance with its terms and conditions, and upon determination by the Principal Representative and Surety of the lowest responsible bidder, arrange for a contract between such bidder and the State of Colorado acting by and through the Principal Representative and make available as work progresses (even though there should be a default or a succession of defaults under the contract or contracts of completion arranged under this paragraph) sufficient funds to pay the cost of completion, less the balance of the contract price but not exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount hereinbefore set forth. The term “balance of the contract price” as herein used shall mean the total amount payable to the Principal under the Contract and any amendments thereto, less the amount properly paid by the State of Colorado to the Contractor.

No right of action shall accrue on this bond to or for the use of any person or corporation other than the State of Colorado.

IN WITNESS WHEREOF said Principal and Surety have executed this Bond, this day of , A.D., 20 .

(Corporate Seal)

THE PRINCIPAL

ATTEST:

By:

Title:

Secretary

(Corporate Seal)

SURETY

By:

Attorney-in-fact

THIS BOND MUST BE ACCOMPANIED BY POWER OF ATTORNEY, EFFECTIVELY DATED

Note:
This bond is issued simultaneously with another bond conditioned for the full and faithful payment for all labor and material of the contract.

State Form SC-6.22 Page 2 of 2 (Rev. 9/2006) image1.png