SBP-6.133 Unit Pricing_2025 (2).docx

DOCX document 37 KB Posted

Attached to
LCC 26-9 Replace Natural Gas Line-Bowman & Trustees Bldgs
Solicitation number
IFB1 GJFA 2026000120 2
Issued by
Pitkin County, Lakewood City, Colorado

About this file

This is a Unit Pricing Form issued by the State of Colorado Office of the State Architect State Buildings Program for the project LCC 26-9 Replace Natural Gas Line-Bowman & Trustees Buildings. The form is designed to establish unit prices for potential change orders during the execution of the contract. The document provides nine numbered line items (U1 through U9) for unit pricing entries, with columns designated for description, unit of measure, and unit price. Bidders are required to complete the form with detailed descriptions based on specifications provided in Division 01 of the project specifications before submission with their bids. The unit prices established through this form will remain valid until the date of contract completion as established on the Notice to Proceed.

All unit prices submitted must include the pro-rata share of materials, equipment, and disposal costs required to complete each work item. Overhead, profit, and bond will be calculated separately on a Change Order Proposal form (SC-6.312) rather than being incorporated into the unit prices. The form requires the bidder's company name, authorized signature, and date of submission. This pricing mechanism allows the state to adjust contract sums for authorized changes to the work scope while maintaining consistency in pricing methodology throughout the project duration.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

UNIT PRICING FORM

Institution or Agency:

Project No./Project Name:

INSTRUCTIONS:

The unit prices below shall be used to determine adjustment to the contract sum when changes in the work involving said items are deemed necessary.

Unit Prices shall apply until the date of contract completion established on the Notice to Proceed.

All unit prices shall include the pro-rata share of all costs of materials, equipment and disposal required to complete the work item. Overhead, profit and bond will be calculated on a Change Order Proposal (SC-6.312).

(Architect/Engineer should complete a brief description below based on their complete description provided in Division 01 of their specification before inserting into the solicitation)

UNIT PRICING

Number
Description

Unit of Measure

Unit Price

U1

U2

U3

U4

U5

U6

U7

U8

U9

THE BIDDER

BY_________________________________________________________________

Company Name

BY__________________________________________________________________

Signature Date

SBP-6.131

Rev 7/2025 image1.jpeg

File details come from the government source that posted it. Updated .