SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
SAQMMA16R0310 SEALED BID (IFB)
X NEGOTIATED (RFP)
2. TYPE OF SOLICITATION 3. DATE ISSUED
06/27/2016
RATING
IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
CODE LMAQM
OFFICE OF ACQUISITION MANAGEMENT (A/LM/AQM)
PO BOX 9115, ROSSLYN STATION
US DEPARTMENT OF STATE
ARLINGTON, VA 22219
7. ISSUED BY 8. ADDRESS OFFER TO
9. FOR INFORMATION EMAIL: a. NAME
Tracie N. Hardy
b. TELEPHONE NO. (Include area code)(NO COLLECT CALLS)
703-875-6897
c. EMAIL hardytn@state.gov
SOLICITATION
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The Contractor shall begin performance within ______ calendar days and complete it within ______ calendar days after receiving award, X notice to proceed. This performance period is X mandatory negotiable. ( (See __.)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).
X YES NO
12b. CALENDAR DAYS
Sealed offers in original and ____ copies to perform the work required are due at the place specified in item 8 by __12:00:00__ (hour) local time __07/26/2016 __ (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
a.
b. An offer guarantee is, X is not required.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.
d.
Offers providing less than ____ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
13. ADDITIONAL SOLICITATION REQUIREMENTS:
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA - FAR (48 CFR) 53.236-1(e)
SAQMMA16R0310
OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
CONTACT: DUNS:
CODE FACILITY CODE
The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
17.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY
FISCAL OPERATIONS BRANCH CHIEF (OBO/RM/FM/FO)
SEE SPECIAL INVOICE SUBMISSION INSTRUCTIONS
ARLINGTON, VA 22209
27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No futher contractual document is necessary.
30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
John Hite 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA
BY
31c. DATE
STANDARD FORM 1442 (REV. 4-85) BACK
Table of Contents
Section Description Page Number
B Supplies or Services and Prices/Costs
1.1 TYPE OF CONTRACT
C Descriptions/Specifications/Statement of Work
1.2 DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
D Packaging and Marking
1.3 PLACE OF DELIVERY
1.4 PACKING AND MARKING
E Inspection and Acceptance 52.246-2 Inspection of Supplies - Fixed-Price (Aug 1996) 52.246-12 Inspection of Construction (Aug 1996)
1.5 QUALITY ASSURANCE
1.6 INSPECTION BY GOVERNMENT
1.7 DEFINITIONS
F Deliveries or Performance 52.242-15 Stop-Work Order (Aug 1989) 52.242-17 Government Delay of Work (Apr 1984)
G Contract Administration Data
02INV OFFICE OF OVERSEAS BUILDING OPERATIONS INVOICE INSTRUCTIONS
G-002 CONTRACT ADMINISTRATION DATA
652.242-70 CONTRACTING OFFICER'S REPRESENTATIVE (COR) (AUG 1999)
I Contract Clauses 52.242-14 Suspension of Work (Apr 1984) 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-12 Liquidated Damages - Construction (Sept 2000) 52.202-1 Definitions (Nov 2013) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-7 Anti-Kickback Procedures (May 2014) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2015) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Oct 2015) 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data - Modifications (Aug 2011) .24 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data - Modifications (Oct 2010) 52.216-7 Allowable Cost and Payment (Jun 2013) 52.219-8 Utilization of Small Business Concerns (Oct 2014) 52.222-19 Child Labor--Cooperation with Authorities and Remedies (Feb 2016) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment Exceeding $15,000 (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Apr 2015) 52.222-29 Notification of Visa Denial (Apr 2015) 52.222-35 Equal Opportunity for Veterans (Oct 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (Jul 2014) 52.222-37 Employment Reports on Veterans (Feb 2016) 52.222-50 Combating Trafficking in Persons (Mar 2015) 52.223-6 Drug Free Workplace (May 2001) 52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving (Aug 2011) 52.225-5 Trade Agreements (Feb 2016) 52.225-13 Restrictions on Certain Foreign Purchases (June 2008) 52.225-14 Inconsistency Between English Version and Translation of Contract (Feb 2000) 52.228-3 Workers' Compensation Insurance (Defense Base Act) (July 2014) 52.228-4 Workers' Compensation and War-Hazard Insurance Overseas (Apr 1984) 52.228-5 Insurance - Work on a Government Installation (Jan 1997) 52.228-11 Pledges of Assets (Jan 2012) 52.228-13 Alternative Payment Protections (July 2000)
52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.229-6 Taxes - Foreign Fixed-Price Contracts (Feb 2013) 52.232-8 Discounts For Prompt Payment (Feb 2002) 52.232-11 Extras (Apr 1984) 52.232-17 Interest (May 2014) 52.232-18 Availability Of Funds (Apr 1984) 52.232-22 Limitation Of Funds (Apr 1984) 52.232-24 Prohibition of Assignment of Claims (May 2014) 52.232-25 Prompt Payment (Jul 2013) 52.232-27 Prompt Payment for Construction Contracts (May 2014) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Jul 2013) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-13 Bankruptcy (July 1995) 52.243-1 Changes - Fixed-Price (Aug 1987) 52.243-4 Changes (June 2007) 52.245-1 Government Property (Apr 2012) 52.245-2 Government Property Installation Operation Services (Apr 2012) 52.245-9 Use and Charges (Apr 2012) 52.246-17 Warranty of Supplies of a Noncomplex Nature (June 2003) 52.246-19 Warranty of Systems and Equipment under Performance Specifications or Design Criteria (May 2001) 52.246-21 Warranty of Construction (Mar 1994) 52.246-23 Limitation of Liability (Feb 1997) 52.246-25 Limitation of Liability - Services (Feb 1997) 52.247-63 Preference for U.S.-Flag Air Carriers (June 2003) 52.248-1 Value Engineering (Oct 2010) 52.248-3 Value Engineering--Construction (Oct 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (Apr 2012) 52.249-8 Default (Fixed-Price Supply and Service) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.204-14 Service Contract Reporting Requirements (Jan 2014) 52.215-13 Subcontractor Certified Cost or Pricing Data - Modifications (Oct 2010) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Jul 2013)
652.243-70 NOTICES (AUG 1999)
652.229-70 EXCISE TAX EXEMPTION STATEMENT FOR CONTRACTORS WITHIN THE
UNITED STATES (JUL 1988)
652.229-71 PERSONAL PROPERTY DISPOSITION AT POSTS ABROAD (AUG 1999)
652.242-73 AUTHORIZATION AND PERFORMANCE (AUG 1999)
652.225-71 SECTION 8(a) OF THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED
(AUG 1999)
52.228-15 Performance and Payment Bonds - Construction (Oct 2010) 52.217-7 Option for Increased Quantity - Separately Priced Line Item (Mar 1989) 52.209-1 Qualification Requirements (Feb 1995) 52.244-6 Subcontracts for Commercial Items (June 2016)
52.252-2 Clauses Incorporated by Reference (Feb 1998) 52.216-25 Contract Definitization (Oct 2010)
K Representations, Certifications, and Other Statements of Offerors or Respondents 52.250-2 SAFETY Act Coverage Not Applicable (Feb 2009) 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran--Representation and Certifications (Oct 2015) 52.236-28 Preparation of Proposals - Construction (Oct 1997) 52.222-56 Certification Regarding Trafficking in Persons Compliance Plan (Mar 2015)
652.228-70 DEFENSE BASE ACT - COVERED CONTRACTOR EMPLOYEES (FEB 2015)
52.204-8 Annual Representations and Certifications (Apr 2016) 52.203-11 Certification And Disclosure Regarding Payments To Influence Certain Federal Transactions (Sept 2007) 52.204-3 Taxpayer Identification (Oct 1998) 52.209-5 Certification Regarding Responsibility Matters (Oct 2015) 52.225-18 Place of Manufacture (Mar 2015)
652.225-70 ARAB LEAGUE BOYCOTT OF ISRAEL (AUG 1999)
52.222-22 Previous Contracts and Compliance Reports (Feb 1999) 52.222-25 Affirmative Action Compliance (Apr 1984)
L Instructions, Conditions, and Notices to Offerors and Respondents 52.204-16 Commercial and Government Entity Code Maintenance (Jul 2015) 52.215-1 Instructions to Offerors - Competitive Acquisition (Jan 2004) 52.237-1 Site Visit (Apr 1984)
652.206-70 ADVOCATE FOR COMPETITION/OMBUDSMAN (FEB 2015)
1.10 INSTRUCTION TO OFFERORS
52.216-1 Type of Contract (Apr 1984) 52.233-2 Service of Protest (Sept 2006)
M Evaluation Factors for Award
1.11 EVALUATION OF PROPOSALS
001 Active Anti-Ram Vehicle Barriers 3.00 EA Doc Ref No:
Delivery Date
FOB:
03/31/2017 Destination
002 Barrier Removal 3.00 EA The Contractor shall remove the three (3) existing Delta vehicle barriers in accordance with the Statement of Work.
Doc Ref No:
Delivery
Date
FOB:
03/31/2017 Destination
003 Barrier Installation 3.00 EA The Contractor shall install three (3) new Electro-Mechanical vehicle barriers their controls, and support equipment in accordance with the Statement of Work.
Doc Ref No:
Delivery
Date
FOB:
03/31/2017 Destination
004 Value Added Tax (VAT) 1.00 LT Doc Ref No:
Delivery Date
FOB:
03/31/2017 Destination
005 Defense Base Act (DBA) Insurance 1.00 LT Effective July 22, 2012, the Department of State does not have a Department-wide contract for DBA insurance.
Contractors may continue using DBA policies until they expire. Contractors requiring new DBA insurance may purchase new insurance policies directly from any Department of Labor (DOL) approved insurance provider. Approved providers can be found at the DOL website http:// www.dol.gov/owcp/dlhwc/lscarrier.htm
The Contractor shall provide proof of insurance no later than ten (10) days after contract award.
Doc Ref No:
Delivery
Date
FOB:
03/31/2017 Destination
006 Shipping to US Embassy Kingston, Jamaica 1.00 LT Doc Ref No:
Delivery Date
FOB:
03/31/2017 Destination
1.1 TYPE OF CONTRACT
This is a firm-fixed price contract. The Government will not pay additional sums due to any escalation in the cost of materials, equip-
SAQMMA16R0310
Line Item Summary
Solicitation Number:
SAQMMA16R0310
Contract Number: Title: Vehicle Barrier Replacement - Kingston
Date of Solicitation:
06/27/2016
Line Item No. Description Quantity Unit Unit Price Total Cost ment or labor, or the Contractor's failure to properly estimate or accurately predict the cost or difficulty of achieving the results re-quired. The Government will also not adjust the contract price due to fluctuations in the currency exchange rates. The Government may make changes in the contract price or time to complete only due to changes made by the Government in the work to be per-formed, or by delays caused by the Government.
Section C- Descriptions/Specifications/Statement of Work
1.2 DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
1.0 General.
The purpose of the contract is to remove the two (2) existing hydraulic vehicle barriers and replace with two (2) new Diplomatic Se-curity (DS) approved, contractor provided hydraulic vehicle barriers at the US Embassy Kingston, Jamaica.
2.0 Requirements.
2.1 The contractor shall provide two (2) Hydraulic vehicle barriers that meet all the Department of State (DoS) requirements including DS crash rating and Overseas Building Operations (OBO) cycle testing at the US Embassy Kingston, Jamaica.
2.2 The contractor shall remove the two (2) existing vehicle barriers installed at the main entrance and exit gates (one on each lane) at the US Embassy Kingston, Jamaica.
2.3 The contractor shall install two (2) new Hydraulic shallow mount vehicle barriers at the same general locations as the removed ones – one (1) at the main gate and one (1) at the exit gate. The installation must be in compliance with the manufacturer’s specifica-tions, the National Electrical Code, and Department of State standards.
3.0 Removal of Existing Barriers.
3.1.1 The contractor shall remove the two (2) existing vehicle barriers located at the Embassy main and exit gates.
3.1.2 The contractor shall remove the concrete foundation and dispose of all waste concrete, barrier road plate(s), reinforcing steel rebar(s), PVC conduit piping, electrical wiring, and waste materials associated with the existing vehicle barriers.
3.1.3 The contractor shall remove all hydraulic lines, electrical wiring, and PVC conduit piping as connected underground from the two (2) existing vehicle barriers and back to the hydraulic pumping units in the embassy compound.
3.1.4 The contractor shall remove the electrical wiring as connected underground and back to the hydraulic powering units (HPU) and the vehicle barrier for each location.
3.1.5 The contractor shall remove existing water drainage piping for rerouting the flow of drainage water through and/or around each vehicle barrier construction sites.
3.1.6 The contractor shall remove existing fresh water piping for the rerouting of fresh water and piping through and/or around each vehicle barrier construction sites.
3.1.7 Notice of Construction and/or Repair around any gas line(s) or local power, data or similar utilities must be submitted to the loc-al responsible oil, power, telephone, and/or gas commission before the start of any construction or repairs. Construction and/or repairs must be under the authority and probably the supervision of the local commission(s), if applicable.
3.1.8 The contractor shall remove electrical lines or wiring for the rerouting of electrical lines or wiring through and/or around each vehicle barrier construction site.
3.1.9 Notice of Construction and/or Repair for any electrical line(s) must be submitted to the local electric cooperative before the start of any construction or repairs. Construction and/or repairs must be under the authority and supervision of the local electric co-operative.
3.1.10 The contractor shall conduct a damage restoration improvement associated with the two (2) vehicle barriers removal process.
3.1.11 The contractor shall provide a rental service and/or use, pickup and delivery of a dumpster(s) as necessary to the project cleanup and waste removal, including removal of the existing barriers.
3.1.12 The contractor shall provide a rental service and/or use of a vehicle blocking barrier(s) to ensure construction site security. The blocking barrier(s) must be approved by the post Regional Security Officer (RSO) and Contracting Officer Representative (COR) pri-or to use.
3.1.13 The contractor shall provide a steel plate able to carry the weight of an oversized vehicle passing over it while crossing the working area. The contactor should be able to move this plate back and forth to allow vehicle to pass over the excavation area, as re-quired by post management.
3.1.14 The contractor shall identify, address, and resolve any areas of concern.
3.2 Excavation for replacement barriers.
3.2.1 The contractor shall excavate for the installation of two (2) new K12 crash rated; DS approved Hydraulic vehicle barriers at the main and exit gates.
3.2.2 The contractor shall excavate for the installation of all hydraulic lines, electrical wiring, and PVC conduit piping underground connecting each new vehicle barrier to its new hydraulic pumping units, and back.
3.2.3 The contractor shall excavate for the installation of the hydraulic pumping units, if applicable.
3.2.4 The contractor shall excavate for the installation of the vehicle detector circuits, associated concrete foundation(s), all electrical wiring, and PVC conduit piping as connected underground and back to the control circuits for each new vehicle barrier.
3.2.5 The contractor shall excavate for the installation of the vehicle barrier drainage water (for each barrier) to include the appro-priate disposal of water to the nearest water drainage or sewer including all associated electrical wiring and PVC conduit piping un-derground and connecting from the each new vehicle barrier and back to the water drainage or sewer .
3.2.6 The contractor shall excavate for the installation of fresh water piping for the rerouting of fresh water and piping through and/or around each vehicle barrier construction site, if applicable.
3.2.7 The contractor shall excavate for the installation of gas piping for the rerouting of gas and piping through and/or around each vehicle barrier construction sites, if applicable.
3.2.8 The contractor shall excavate for the installation of electrical lines or wiring for the rerouting of electrical lines or wiring through and/or around each vehicle barrier construction sites.
3.2.9 The contractor shall excavate for the installation of a sump pump well(s), if required, for the installation of a sump pump (s) for each barrier.
3.2.10 The contractor shall conduct damage restoration improvements as associated with the vehicle barrier(s) excavation process.
3.3 Installation of replacement barriers.
3.3.1 The contractor is totally responsible for ensuring that the two (2) vehicle barriers are fully functional barriers, installed per the requirements of the design, and the manufacturer guidelines and installation specifications.
3.3.2. The contractor is responsible for ensuring the safety of the workers and site personnel during the project.
3.3.3 The contractor shall verify and be responsible for all dimensions and conditions at the job site.
3.3.4 The contractor shall conduct the installations of all the concrete foundations, reinforcing steel rebars, and aggregate materials, per the manufacturer’s instructions.
3.3.5 The contractor shall provide spacer bars, chairs, spreaders, blocks, etc. as required to positively hold the steel in place before concrete is poured.
3.3.6 The contractor shall ensure the concrete is conveyed from the mixer to final deposit by methods that will prevent separation and loss.
3.3.7 The contractor shall ensure the concrete is thoroughly consolidated by suitable means during placement and shall be thor-oughly worked around reinforcement and embedded fixtures and corners of forms.
3.3.8 The contractor shall ensure the concrete is maintained above 50°F (10°C) and in a moist condition for at least seven (7) days after placement. And that adequate equipment shall be provided for heating concrete materials and protecting concrete during freez-ing or near freezing weather.
3.3.9 The contractor shall install all new hydraulic lines, electrical wiring, and PVC conduit piping underground and connecting to/ from each vehicle barrier, back to its hydraulic pumping units and the control panels per the manufacturer’s instructions.
3.3.10 The contractor shall install the foundation, all electrical wiring, and PVC conduit piping as connected underground and back to the control circuits for each new vehicle barrier.
3.3.11 The contractor shall install hydraulic pumping units per the manufacturer’s instructions.
3.3.12 The contractor shall install vehicle detector circuits, associated concrete foundation(s), traffic lights, and all electrical wiring, and PVC conduit piping as connected underground and back to the control circuits for each vehicle barrier per the manufacturer’s in-structions.
3.3.13 The contractor shall install vehicle barrier drainage water sump pump(s) to include the appropriate disposal of water to the nearest water drainage or sewer including all associated electrical wiring and PVC conduit piping underground and connecting from each vehicle barrier and back to its sump pump and water drainage or sewer.
3.3.14 The contractor shall install water drainage piping for rerouting the flow of drainage water through and/or around each vehicle barrier construction sites.
3.3.15 The contractor shall install fresh water piping for the rerouting of fresh water and piping through and/or around each vehicle barrier construction sites.
3.3.16 The contractor shall install gas piping, if required, for the rerouting of gas and piping through and/or around each vehicle bar-rier construction sites.
3.3.17 The contractor shall install electrical lines or wiring for the rerouting of electrical lines or wiring through and/or around the vehicle barrier construction site(s) including the wires and any conduit required from the hydraulic pump to the master control units in Post One.
3.3.18 The contractor shall conduct damage restoration improvements as associated with each vehicle barrier installation process.
3.4 Trucking & Equipment.
3.4.1 The contractor shall provide concrete mixer trucking and delivery of concrete for the installation of two (2) vehicle barriers, to include the concrete foundations for each vehicle barrier, hydraulic pumping units, vehicle detector circuits, traffic lights, and water sump pump (if required) for the installation project per the manufacturer’s instructions.
3.4.2 The contractor shall provide the trucking and delivery of reinforcing steel rebar(s) for the installation of two (2) hydraulic vehicle barriers, the concrete foundation for each vehicle barrier, hydraulic pumping units, the water sump pump (if required), and the water drainage for the installation project per the manufacturer’s instructions.
3.4.3 The contractor shall provide the trucking and delivery of aggregate materials for the installation of two (2) vehicle barriers, the concrete foundation for each vehicle barrier, the hydraulic pumping units, the vehicle detector circuits, the water sump pump, and the water drainage for the installation project per the manufacturer’s instructions.
3.4.4 The contractor shall provide the rental and/or use of all heavy duty equipment (i.e., forklift, front loader, excavator with hoe ram and bucket attachments) and/or other equipment for the removal and installation process to include the concrete foundations, re-inforcing steel rebar and excavations necessary to the installation project per the manufacturer’s instructions.
3.4.5 The contractor shall provide a rental service and/or use, pickup and delivery of a dumpster(s) as necessary to the project cleanup and waste removal, including removal of the existing barrier.
3.5 Site Condition, Clean-Up and Waste Disposal.
3.5.1 The contractor shall dispose of the removed barriers, HPU and control panels. The contractor shall remove and dispose of all waste materials including concrete, aggregate materials, reinforcing steel rebars, steel barrier road plate(s), conduit piping, and all electrical wiring associated with the removal and installation process pertaining to the new and existing barriers.
3.5.2 The contractor shall maintain the site in a safe, neat, clean and secure condition at all times.
3.5.3 The contractor shall remove and dispose of all waste materials including old barriers and equipment, concrete, aggregate ma-terials, reinforcing steel rebar(s), conduit, piping, and all electrical wiring associated with the removal and installation process as iden-tified in Sections 3.1, 3.2 ad 3.3 above.
3.5.5 The contractor shall provide a vehicle blocking barrier(s) to ensure construction site security. The blocking barrier(s) must be approved by the post Regional Security Officer, RSO prior to use.
3.5.6 The contractor shall provide a pedestrian fencing and/or netting for pedestrian safety and access control.
3.5.7 The contractor shall provide a construction site Portable Restroom for contractor personnel (may be waived by Post).
3.5.8 The contractor shall identify, address, and resolve any areas of concern.
3.5.9 The contractor shall return the construction site back into the same condition or better, as it was found prior to the start of the project.
3.6 Project Time Line.
3.6.1 The contractor shall coordinate with OBO’s vehicle barrier program and Post to determine the project time line required for the initiating and completing the removal, excavation, and installation of two (2) vehicle barriers as fully operational barriers.
3.6.2 The contractor shall provide a construction schedule with defined timelines for the major project activities (i.e. project mobiliz-ation, demolition, barriers installation, cable/conduit installation, equipment installation, concrete curing, start-up, testing, etc.) for the removal of the existing system and installation of a new fully operational vehicle arrest system.
3.6.3 The schedule shall reflect a total elapsed time not to exceed five (5) weeks per barrier for the installation of the barrier, from the time the personnel and equipment arrival at site to turn-over of barrier system to post.
3.6.4 The contractor will have access to the site six (6) days a week, 10 hours per day. All work outside of this time frame will re-quire prior approval from the Government project representative.
(a) The Department of State observes the following days* as holidays:
U.S. / J New Year Holiday (January 1st)
U.S. Birthday of Martin Luther King, Jr (January 18th)
J Ash Wednesday (February 10th)
U.S. Washington’s Birthday (February 15th)
J Good Friday (March 25th
J Easter Monday (March 28th)
J Labor Day (May 23rd)
U.S. Memorial Day (May 30th)
U.S Independence Day (Jul 4th)
J Emancipation Day (August 1st)
J Independence Day (August 6th)
U.S. Labor Day (September 5th)
U.S. Columbus Day (October 10th)
J National Heroes Day (October 17th)
U.S. Veterans' Day (November 11th)
U.S. Thanksgiving (November 24th)
U.S. / J Christmas Day (December 26th)
J Boxing Day (December 27th)
* U.S. or Jamaican (J) or both (U.S. / J) holiday
When any such day falls on a Saturday, the preceding Friday is observed; when any such day falls on a Sunday, the following Monday is observed. Observance of such days by Government personnel shall not be cause for additional period of performance or entitlement to compensation except as set forth in the contract. If the Contractor's personnel work on a holiday, no form of holiday or other premium compensation will be reimbursed either as a direct or indirect cost, unless authorized pursuant to an overtime clause else-where in this contract.
4.0 Contractor Provided Materials.
The contractor must provide the following materials to include but not limited to:
4.1.1 Two (2) vehicle barriers delivered to post.
4.1.2 Six (6) control panels (one Masters and one Slave for each barrier).
4.1.3 Two (2) hydraulic power units (HPU). (This could be modified without Change Work Order, if approved by OBO).
4.1.4 All sump pumps, as require.
4.1.5 All vehicle detector circuits as require for each barrier.
4.1.6 The hydraulic oil 46 Grade or equivalent for all HPUs.
4.1.7 The dry nitrogen, 2000 PSI for all HPUs
4.1.8 Safety yellow spray paint, for each barrier location.
4.1.9 Gloss black spray paint.
4.1.10 The vehicle barrier barricade for each site for the duration of the project.
4.1.11 The contractor shall provide any items or services for the barrier installation not previously identified.
4.1.12 The contractor shall identify, address, and resolve any areas of concern.
5.0 Contractor Responsibilities.
5.1.0 In addition to furnishing the two (2) new barriers to the Embassy compound and before starting the removal and the installa-tion of the new barrier, the contractor shall conform to the following:
5.1.1 The contractor shall conform to the manufacturer’s guidelines, National Electrical Code requirements, Department of State regulations, and installation technical, physical and safety specifications.
5.1.2 The contractor shall verify and be responsible for all dimensions and conditions at the job site.
5.1.3 The contractor shall verify that the foundation concrete will be placed directly into neat excavations. Where sides of the ex-cavation are not stable the contractor shall provide shoring. Type and method of shoring shall be at the contractor’s discretion in ac-cordance with standard trade practices.
5.1.4 The contractor shall ensure the excavation is kept dry at all times.
5.1.5 The contractor shall ensure the concrete is laboratory designed, machine mixed, producing 3,000 PSI (20.68 MPA) at 28 days.
5.1.6 The contractor shall ensure the cement is tested Portland cement conforming to ASTM C150, Type II Only.
5.1.7 The contractor shall ensure the aggregates conform to ASTM C33 & B GRADE per standard specifications. Maximum size of aggregate shall be 1-1/2 inches (38mm).
5.1.8 The contractor shall ensure the reinforcing steel bars when/if deformed conform to ASTM A615, grade 60 (60,000 PSI or
413.7MPA).
5.1.9 The contractor shall ensure that all hooks and bends conform to ACI STANDARD 318 (Latest revision). Inside diameter of hooks and bends shall be at least six (6) bar diameters.
5.1.10 The contractor shall provide spacer bars, chairs, spreaders, blocks, etc. to positively hold the steel in place before concrete is poured.
5.1.11 The contractor shall ensure the concrete is conveyed from the mixer to final deposit by methods that will prevent separation and/or loss of material.
5.1.12 The contractor shall ensure the concrete is thoroughly consolidated by suitable means during placement and shall be thor-oughly worked around reinforcement and embedded fixtures and corners of forms.
5.1.13 The contractor shall ensure the concrete is maintained above 50°F (10°C) and in a moist condition for at least seven (7) days after placement.
5.1.14 The contractor shall ensure that where exterior wall face requires shoring and/or forming, the forms shall be substantial and suf-ficiently tight to prevent leakage, and that forms shall not be removed until the concrete is seven (7) days old.
5.1.15 The contractor shall back fill by depositing and tamping into place clean sand or pouring lean concrete to 95% percent com-paction. Water jetting shall not be allowed.
5.1.16 The contractor must not use aluminum conduit and pipes.
5.1.17 The contractor shall be responsible for the protection of all adjacent areas against damage and shall repair all damaged areas to match existing improvements.
5.1.18 The contractor shall be responsible for the protection of all electrical, data, video, fiber, communications, or similar utility lines and/or wiring located in the adjacent areas against damage and shall repair all damaged electrical lines and/or wiring.
5.1.19 The contractor shall be responsible for the protection of all water, gas, and sewage lines located in the adjacent area against damage and shall repair all damaged water, gas and/or sewage lines.
5.1.20 The contractor shall be responsible for notifying the local Oil and Gas Commission before the commencement of any construc-tion and/or repairs of gas lines.
5.1.21 The contractor shall be responsible for determining the location of underground power lines, water, gas, and sewer mains to prevent damage during construction.
5.1.22 The contractor shall keep the construction area clean at all times and at completion of work remove all surplus materials, equipment and debris leaving the premises in a clean condition acceptable to the Contracting Officer (CO) or Contracting Officer’s Representative (COR).
5.1.23 The contractor shall perform damage restoration improvements as associated with the vehicle barrier installation.
5.1.24 The contractor shall identify, address, and resolve any areas of concern.
6.0 Reporting Requirements.
6.1.1 The contractor shall provide daily oral progress reports (as requested) to the US Government project representative.
6.1.2 The contractor shall provide weekly written progress reports to the US Government project representative. The contractor shall provide verbal notice, to the Government project representative, two week in advance of the delivery of any and all materials and equipment to site.
6.1.3 The contractor shall provide written notice to the Government project representative, at least two (2) weeks in advance, of the need of access to the site of any additional construction personnel after the start of the project. This also pertains to delivery personnel who will need to be on site for an extended period of time, more than simply dropping off materials (i.e. operators of rental equipment, driver of the concrete delivery truck, etc.)
6.1.4 The contractor shall provide availability to at least one person that can communicate (write, read and speak) in English to clari-fy and resolve any issues involving US Government specifications or requirements.
6.1.5 The contractor shall identify and immediately bring to the attention of the Government project representative any anomalies of concern.
6.1.6 The contractor shall identify, address, and resolve any areas of concern.
7.0 General Information.
7.1.1 Throughout the installation process there will be a US Government Project Representative on site to assist the contractor with any anomalies or areas of concern.
7.1.2 The contractor, upon completion of the project shall remand all documentation for the project by post Regional Security Of-ficer.
7.1.3 The contractor will provide training and demonstrations sessions to post staff members, as required by post management.
7.1.4 The project will not be considered completed until technical review and acceptance from the Government.
Section D- Packaging and Marking
1.3 PLACE OF DELIVERY
All deliverables shall be delivered to the following address:
US Embassy Kingston, Jamaica.
1.4 PACKING AND MARKING
Materials delivered to the site shall be export packed for surface shipment and marked as follows:
US Embassy Kingston, Jamaica.
Section E- Inspection and Acceptance
52.246-2 Inspection of Supplies - Fixed-Price (Aug 1996)
(a) Definition. "Supplies," as used in this clause, includes but is not limited to raw materials, components, intermediate assemblies, end products, and lots of supplies.
(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering supplies under this con-tract and shall tender to the Government for acceptance only supplies that have been inspected in accordance with the inspection sys-tem and have been found by the Contractor to be in conformity with contract requirements. As part of the system, the Contractor shall prepare records evidencing all inspections made under the system and the outcome. These records shall be kept complete and made available to the Government during contract performance and for as long afterwards as the contract requires. The Government may perform reviews and evaluations as reasonably necessary to ascertain compliance with this paragraph. These reviews and evaluations shall be conducted in a manner that will not unduly delay the contract work. The right of review, whether exercised or not, does not relieve the Contractor of the obligations under the contract.
(c) The Government has the right to inspect and test all supplies called for by the contract, to the extent practicable, at all places and times, including the period of manufacture, and in any event before acceptance. The Government shall perform inspections and tests in a manner that will not unduly delay the work. The Government assumes no contractual obligation to perform any inspection and test for the benefit of the Contractor unless specifically set forth elsewhere in this contract.
(d) If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and con-venient performance of these duties. Except as otherwise provided in the contract, the Government shall bear the expense of Govern-ment inspections or tests made at other than the Contractor's or subcontractor's premises; provided, that in case of rejection, the Gov-ernment shall not be liable for any reduction in the value of inspection or test samples.
(e)(1) When supplies are not ready at the time specified by the Contractor for inspection or test, the Contracting Officer may charge to the Contractor the additional cost of inspection or test.
(2) The Contracting Officer may also charge the Contractor for any additional cost of inspection or test when prior rejection makes re-inspection or retest necessary.
(f) The Government has the right either to reject or to require correction of nonconforming supplies. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements. The Government may reject nonconforming supplies with or without disposition instructions.
(g) The Contractor shall remove supplies rejected or required to be corrected. However, the Contracting Officer may require or permit correction in place, promptly after notice, by and at the expense of the Contractor. The Contractor shall not tender for acceptance cor-rected or rejected supplies without disclosing the former rejection or requirement for correction, and, when required, shall disclose the corrective action taken.
(h) If the Contractor fails to promptly remove, replace, or correct rejected supplies that are required to be removed or to be replaced or corrected, the Government may either (1) by contract or otherwise, remove, replace, or correct the supplies and charge the cost to the Contractor or (2) terminate the contract for default. Unless the Contractor corrects or replaces the supplies within the delivery sched-ule, the Contracting Officer may require their delivery and make an equitable price reduction. Failure to agree to a price reduction shall be a dispute.
(i)(1) If this contract provides for the performance of Government quality assurance at source, and if requested by the Government, the Contractor shall furnish advance notification of the time--
(i) When Contractor inspection or tests will be performed in accordance with the terms and conditions of the contract; and
(ii) When the supplies will be ready for Government inspection.
(2) The Government's request shall specify the period and method of the advance notification and the Government representative to whom it shall be furnished. Requests shall not require more than 2 workdays of advance notification if the Government representative is in residence in the Contractor's plant, nor more than 7 workdays in other instances.
(j) The Government shall accept or reject supplies as promptly as practicable after delivery, unless otherwise provided in the contract.
Government failure to inspect and accept or reject the supplies shall not relieve the Contractor from responsibility, nor impose liability on the Government, for nonconforming supplies.
(k) Inspections and tests by the Government do not relieve the Contractor of responsibility for defects or other failures to meet con-tract requirements discovered before acceptance. Acceptance shall be conclusive, except for latent defects, fraud, gross mistakes amounting to fraud, or as otherwise provided in the contract.
(l) If acceptance is not conclusive for any of the reasons in paragraph (k) hereof, the Government, in addition to any other rights and remedies provided by law, or under other provisions of this contract, shall have the right to require the Contractor (1) at no increase in contract price, to correct or replace the defective or nonconforming supplies at the original point of delivery or at the Contractor's plant at the Contracting Officer's election, and in accordance with a reasonable delivery schedule as may be agreed upon between the Contractor and the Contracting Officer; provided, that the Contracting Officer may require a reduction in contract price if the Con-tractor fails to meet such delivery schedule, or (2) within a reasonable time after receipt by the Contractor of notice of defects or non-conformance, to repay such portion of the contract as is equitable under the circumstances if the Contracting Officer elects not to re-quire correction or replacement. When supplies are returned to the Contractor, the Contractor shall bear the transportation cost from the original point of delivery to the Contractor's plant and return to the original point when that point is not the Contractor's plant. If the Contractor fails to perform or act as required in paragraph (l)(1) or (l)(2) of this clause and does not cure such failure within a peri-od of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure, the Government shall have the right by contract or otherwise to replace or correct such supplies and charge to the Contractor the cost occasioned the Government thereby.
(End of clause)
52.246-12 Inspection of Construction (Aug 1996)
(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not-
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract re-quirement, nor is the inspector authorized to change any term or condition of the specification without the Con-tracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reas-onably needed for performing such safe and convenient inspections and tests as may be required by the Con-tracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appro-priate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may-
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by re-moving it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(End of clause)
1.5 QUALITY ASSURANCE
The Contractor shall institute an appropriate inspection system including:
(1) Creation of checklists of duties to be carried out;
(2) Periodic inspections to ensure that these duties are carried out by the supervisory staff and senior employ-ees; and,
(3) Weekly inspections to determine whether the various services are being performed according to the con-tract requirements.
The Contractor shall provide copies of the weekly inspection reports to the COR.
The Contractor shall promptly correct and improve upon any areas of shortcomings and/or substandard condi-tions noted in such inspections. The Contractor shall bring to the attention of the Contracting Officer or COR, for disposition, any conditions uncovered which are not the responsibility of the Contractor.
1.6 INSPECTION BY GOVERNMENT
The COR or his/her authorized representatives will periodically inspect the services being performed and supplies being furnished, to determine that all services are being performed in an acceptable manner, and that all supplies are of acceptable quality and standards.
The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be re-quired by the Contracting Officer as a result of such inspection.
1.7 DEFINITIONS
a. Final completion and acceptance - the stage in the progress of the work, as determined by the Con-tracting Officer and confirmed in writing to the Contractor, at which all work required under the contract has been completed in a satisfactory manner in accordance with contract requirements, subject to the discovery of defects after final completion and except for items specifically excluded in the notice of final acceptance.
b. Date of final completion and acceptance - the date determined by the Contracting Officer on which final completion of the work occurs, as…