Santa Teresa Solicitation 47PH0825R0004.pdf
PDF 2 MB Posted
- Solicitation number
- 47PH0825R0004
About this file
This is a solicitation document for a design-build contract to improve and construct border roadways at the Santa Teresa Land Port of Entry (LPOE) in New Mexico. The solicitation (47PH0825R0004) is set aside for small businesses under NAICS code 237310 with a size standard of $45 million.
The project involves repairing approximately 190,000 square feet of concrete pavement using Low Embodied Carbon (LEC) materials including asphalt, concrete, and steel. The work includes complete reconstruction, surface reconstruction, shoulder hardening, joint sealing, and patching of 8-13 inch thick reinforced concrete across eleven areas within the LPOE. The estimated price range is $5-10 million with a 300-day performance period. Proposals are due March 4, 2025 at 12:00 PM local time, with award anticipated in April/May 2025. A virtual pre-proposal conference will be held January 22, 2025, followed by a site visit on January 23, 2025. The project will be awarded using a "Best Value" methodology with four evaluation factors: Past Performance/Experience of Key Personnel (40%), Past Experience of Company (25%), Technical/Management Approach (20%), and Sustainability-LEC Materials (15%). The project is partially funded through the Inflation Reduction Act and requires specific environmental product declarations for construction materials.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
47PH0825R0004
Acquisition Management Division Program Support Branch 819 Taylor St. STE: 11A09 Fort Worth, TX 76102 USA
Santa Teresa Land Port of Entry (LPOE) Border Roadway Improvement and Construction (BRIC) Project, Santa Teresa, NM Solicitation # 47PH0825R0004
Via email: jeffrey.kang@gsa.gov and Jason.gerloff@gsa.gov
7PQA
Jeffrey Kang 682-210-1163
01/14/2025
3/4/2025
12:00 PM
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
GSA/PBS Acquisition Management Division (7PQA) 819 Taylor Street: STE 11A09 Fort Worth, TX 76102
GSA/PBS Acquisition Management Division (7PQA) 819 Taylor Street: STE 11A09 Fort Worth, TX 76102
DESCRIPTION TOTAL
CLIN 0001 - IRA BASE SCOPE (Design) -$
CLIN 0002 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0003 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0004 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0005 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0006 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0007 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0008 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0009 - IRA LEC MATERIALS
LEC Concrete -$
Pharr LPOE Price Proposal
Construction
Option 2 - COMMSRD1
Option 8 - POVSRD1 and POVSRD2
Low Embodied Carbon Materials
Base Scope
Santa Teresa LPOE Cost Summary
GSA SOL Number - 47PH0825R0004
Option 7 - POVPRD1 and POVPRD2
Option 1 - COMMPRD2 and COMMPRD3
Option 3 - CIDOCKRD1A
Option 4 - CIDOCKRD1B
Option 5 - CIDOCKRD1C
Option 6 - CIDOCKPK1 and DOCK DRAIN RECONSTRUCTION
LEC Asphalt -$
LEC Steel -$
CLIN 0010 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0011 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0012 - IRA LEC MATERIALS
LEC Concrete -$
LEC Asphalt -$
LEC Steel -$
CLIN 0013 - DIVISION 1 -$
CLIN 0014 - DIVISION 31 -$
CLIN 0015 - DIVISION 32 -$
OVERHEAD % -$
PROFIT % -$
Subtotal - Overhead, Profit
INSURANCE % -$
BOND % -$
Subtotal - Bond, Insuranc
TOTAL EVALUATED PRICE -$
Type or Print Name
Title
Signature
Firm Name
Date
Option 9 - COMMRD1, COMMRD2 and COMMRD3
Option 10 - SIDEWALKS / SHOULDER HARDENING
Option 11 - GANTRYRD1
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Clin 0003AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - COMMSRD1
Clin 0003AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - COMMSRD1
CLIN 0008 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction) COST / TOTAL
Clin 0007AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - CIDOCKPK1 and DOCK DRAIN
RECONSTRUCTION
Clin 0005AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - CIDOCKRD1B
Clin 0002AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES -COMMPRD2 and COMMPRD3
Clin 0002AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - COMMPRD2 and COMMPRD3
Clin 0002AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - COMMPRD2 and COMMPRD3
CLIN 0006 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction) COST / TOTAL
CLIN 0005 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction)
CLIN 0003 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL
CLIN 0004 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL
Clin 0004AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - CIDOCKRD1A
Clin 0004AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - CIDOCKRD1A
Clin 0006AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - CIDOCKRD1C
Clin 0006AB - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - CIDOCKRD1C
Clin 0003AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - COMMSRD1
IRA LEC OPTIONS (CONSTRUCTION) IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS
CLIN 0001 - DESIGN AND ASSOCIATED EXPENSES
CLIN 0002 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL
CLIN 0007 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction) COST / TOTAL
Clin 0004AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - CIDOCKRD1A
Low Embodied Carbon Materials
Santa Teresa LPOE Paving
GSA SOL Number - 47PH0825R0004
Description
BASE SCOPE CLIN 0001 - (Design) IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS COST / TOTAL
COST / TOTAL
Clin 0006AC - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - CIDOCKRD1C
Clin 0005AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - CIDOCKRD1B
Clin 0005AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - CIDOCKRD1B
Clin 0007AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - CIDOCKPK1 and DOCK DRAIN
RECONSTRUCTION
Clin 0007AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - CIDOCKPK1 and DOCK DRAIN
RECONSTRUCTION
Clin 0008AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - POVPRD1 and POVPRD2
Clin 0008AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - POVPRD1 and POVPRD2
Clin 0008AC - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - POVPRD1 and POVPRD2
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Quantity Unit
C.Y
C.Y
Tons
Type or Print Name
Title
Signature
Firm Name
Date
CLIN 0011 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction)
CLIN 0012 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction)
COST / TOTAL
COST / TOTAL
Clin 0011AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - SIDEWALKS / SHOULDER HARDENING
Clin 0011AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - SIDEWALKS / SHOULDER HARDENING
Clin 0010AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - COMMRD1, COMMRD2 and COMMRD3
CLIN 0010 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction) COST / TOTAL
CLIN 0009 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction)
Subtotal - Bond, Insurance
CLIN 0013 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction)
COST / TOTAL
COST / TOTAL
Total Evaluated Price -$
Bond 0.00% -$
Clin 009AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - POVSRD1 and POVSRD2
Clin 009AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - POVSRD1 and POVSRD2
Profit 0.00%
0.00%
-$ Clin 0014 - Div. 31 Earthwork
Overhead 0.00% -$
Subtotal - Overhead, Profit
Insurance
CLIN 0014 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction)
Clin 009AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - POVSRD1 and POVSRD2
Clin 0012AA - LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - GANTRYRD1
Clin 0012AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - GANTRYRD1
Clin 0012AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - GANTRYRD1
Clin 0013 - Division 1
COST / TOTAL
CLIN 0015 - IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS (Construction) COST / TOTAL
Clin 0015 - Div. 32 Exterior Improvements
Clin 0010AB - LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES - COMMRD1, COMMRD2 and COMMRD3
Clin 0010AC - LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES - COMMRD1, COMMRD2 and COMMRD3
Clin 0011AA- LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES - SIDEWALKS / SHOULDER HARDENING
Design Build Contract for: Santa Teresa Land Port of Entry Border Roadway
Improvement and Construction (BRIC), Santa Teresa, NM
The Solicitation 47PH0825R0004
January 14, 2025
GSA Solicitation No. 47PH0825R0004
Document: DB201A-SB/2 April 2024 (The Solicitation)
CUI
Table of Contents
I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference
E. Estimated Price Range F. FAR 52.228-1 Bid Guarantee G. FAR 52.236-27 Site Visit – Construction
H. Receipt of Offers
II. Proposals A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal
E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors
III. General Provisions
A. Availability of Funds B. Requests for Clarification or Interpretation
C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Affirmative Procurement Program F. Notice Concerning Preparation of Proposals G. Bond Requirements H. Contractor Performance Information
I. Safeguarding and Dissemination of Controlled Unclassified Information (CUI)
Building Information
IV. FAR/GSAR Solicitation Provisions
A. FAR 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR 101-29
B. FAR 52.216-1 Type Of Contract
C. FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of Work D. FAR 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal
Employment Opportunity for Construction E. Buy American Requirements F. Buy American Exceptions G. FAR 52.233-2 Service of Protest
H. FAR 52.252-1 Solicitation Provisions Incorporated by Reference I. GSAR 552.102 Incorporating Provisions and Clauses by Reference J. Additional Provisions
(i) GSAR 552.236-74, Evaluation of Options (Mar 2019)
(ii) GSAR Clause 552.236-77, Government’s Right to Exercise Options (Mar 2019)
(The Solicitation)
V. Instructions to Offerors and Clauses
A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition
VI. Method Of Award
A. Evaluation of Offers B. Determination of Responsibility C. Price Reasonableness/Price Realism D. Unbalanced Price E. Total Evaluated Price
F. Non Price Factors G. Evaluation of Joint Ventures H. Basis of Award
VII. Attachments
1. GSA Affiliated Custom Accounts (GACA) for Google Drive
2. Past Experience/Past Performance Questionnaire (Factor 1)
3. Past Experience/Past Performance Questionnaire (Factor 2)
4. Factor 4 LEC Material IRA Sustainability Factor Table.
5. Wage Decisions (TX20240003 & TX20240255)
6. GSA 527-21 - Contractor’s Qualifications and Financial Information
7. Offeror Representations and Certifications Form December 2023
8. Award Allocation Form IRA
9. Sample IRA Project Submittal/ Reporting Form
10. Concrete – GSA IRA Low Embodied Carbon Requirements (Dec. 2023)
11. Steel – GSA IRA Low Embodied Carbon Requirements (Dec. 2023)
12. Asphalt – GSA IRA Low Embodied Carbon Requirements (Dec. 2023)
13. Final Concepts Report
14. Standard Form 24 Bid Bond
VII. VIII Reference Materials
1. GSA P. 100 Facilities Standards for the Public Buildings Services (PBS) Dated May 2024
(The Solicitation)
I. General Information
I.A. The Solicitation and Contract
(1) This Solicitation is set-aside for Small Business Concerns, in accordance with FAR 19. This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.
(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.
(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer.
No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.
(4) The Inflation Reduction Act of 2022 (IRA), Pub. L. No. 117-169, enacted in August 2022, provided GSA with significant funding for (a) measures necessary to convert facilities to high-performance green buildings, (b) acquisition and installation of construction materials and products with substantially lower levels of embodied greenhouse gas emissions, and (c) emerging and sustainable technologies. The Contract resulting from this Solicitation will be funded in part by IRA appropriations, and it contains numerous IRA-specific requirements. Requirements include, but are not limited to, requirements regarding pricing, invoicing, submittals, materials, and construction. In addition, please note that this Solicitation contains an evaluation factor favoring certain construction materials with the lowest possible levels of embodied carbon. Offerors shall carefully review this Solicitation, the Agreement, the Statement of Work, the Specifications, and the Drawings. In addition, please note that this Solicitation contains an evaluation factor favoring certain construction materials with the lowest possible levels of embodied carbon. Offerors are responsible for accurately pricing and, if successful, fully performing all Contract requirements.
I.B. List of Solicitation Documents
The Solicitation Documents are comprised of:
(1) The Solicitation
(2) Offeror Representations and Certifications Form
(3) Standard Form (SF) 1442 – Solicitation Offer and Award
(4) The Agreement and Attachments to the Agreement
(5) The Statement of Work
(6) Other Forms Required for Submission with Proposals
(The Solicitation)
CUI
GACA Account: Vendors are required to create or use an existing GSA Affiliated Custom Account (GACA) for access to documents greater than 25MB. GACA instructions are included as an attachment to this Solicitation. Once the account has been created, notify the GSA Contract Specialist Jeff Kang (jeffrey.kang@gsa.gov), to receive a link to the Google Drive folder containing any additional Solicitation documents (i.e. Attachments, Specifications and other Attachments to the SOW).
I.C. Authorized Representatives
The following individuals are designated as the authorized GSA representatives under this
Solicitation:
Authorized Representative Information:
Contracting Officer’s Information
Name: Jason Gerloff
Address: 819 Taylor Street: Floor 11, Fort Worth, TX 76102
Telephone: (817) 201-8269
Email: jason.gerloff@gsa.gov
Alternate POC Information
Name: Jeff Kang
Address: 819 Taylor Street: Floor 11, Fort Worth, TX 76102
Telephone: 682-210-1163
Email: jeffrey.kang@gsa.gov
I.D. Pre-Proposal Conference
Date: January 22, 2025
Time: 10:00 am Central
Pre-Proposal Meeting Location: Virtual
I.E. Estimated Price Range
The estimated price range for the Project is between $5,000,000 and $10,000,000.
mailto:(jeffrey.kang@gsa.gov), mailto:jason.gerloff@gsa.gov mailto:jeffrey.kang@gsa.gov
I.F. FAR 52.228-1 Bid Guarantee (SEP 96)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds
(including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)
(1) The clauses at FAR 52.236-2, Differing Site Conditions, and FAR 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, Offerors are urged and expected to inspect the site where the work will be performed.
(2) A site visit will be held at the following date and time:
Date: January 23, 2025
Time: 10:00 am Local Time
(3) All offerors who would like to attend the pre-proposal conference and site visit will need to email the individual names, Company names, email addresses and phone numbers to jeffrey.kang@gsa.gov of those planning on attending to receive a meeting invite to the meeting.
Those that are interested in attending the site-walk at the Santa Teresa LPOE, will have to also provide, Date of Birth, last four of your social security number, Driver’s License number and state issued, of the individuals that are attending the site-walk. The additional information provided will be submitted to Customs and Border Protection (CBP) to run a background check.
This is required as the meeting will be on an active Border Crossing. Once the clearance is approved and final, the individuals will receive an email with the additional information to attend the meeting. Please arrive early as you will have to go through a security checkpoint to be escorted to the meeting room. No walk-ins without an invitation will be permitted to attend the site visit. The maximum number of attendees for a company is three (3). Offerors must submit the request no later than Friday, January 17, 2025, at 12:00 p.m. CST. Failure to submit on time will exclude you from the meeting and if you are not cleared by CBP you will not be allowed on-
Document: DB201A-SB/2 April 2024 (The Solicitation)
CUI
https://www.acquisition.gov/far/part-52#FAR_52_236_2 https://www.acquisition.gov/far/part-52#FAR_52_236_3
(The Solicitation)
CUI
site for the walk through.
For further information about the site visit or access requirements, please contact:
Name: Jeff Kang
Telephone: 682-210-1163
Email: jeffrey.kang@gsa.gov
I.H. Receipt of Offers
(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 12:00 pm local time on the following date and at the following address.
Date: March 4, 2025
Address: jeffrey.kang@gsa.gov and jason.gerloff@gsa.gov
Electronic Submission of Proposals
Electronic Submission of Proposals: Offers must be received by the email address of the GSA Point of Contact (POC) listed herein on or before the date and time established for receipt of offers. The date and time of receipt will be established according to the Government computer system’s documentation showing the exact official time of receipt by the GSA POC listed herein and not by the time the electronic proposal was sent by the Offeror or received by the GSA server. It is the Offeror’s responsibility to ensure proposals are complete and submitted early enough to be received by the GSA POC before the deadline, and to confirm receipt before the deadline. Proposals or portions of proposals which are received by the GSA POC later than the time noted within will be rejected and will not be considered.
NOTE: The maximum file size is 25 MB. GSA has occasionally experienced delays in delivery of emails from the GSA server to an email account. Therefore contractors/offerors need to plan accordingly.
WARNING: Consistent with GAO case law on the issue of “late-is-late rule” related to electronically submitted proposals, GSA will strictly comply with and enforce FAR 52.215-1(c)(3)(ii)(A). Pursuant to GAO’s application of FAR 52.215-1(c)(3)(ii)(A), an electronically submitted proposal that is received late will not be considered unless (1) it is received before award is made, (2) the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition and (3) it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals. FAR 52.215-1 (c)(3)(ii)(A)(1).
II. Proposals
II.A. Proposal Contents
Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:
mailto:jeffrey.kang@gsa.gov
(The Solicitation)
1. Price Proposal
2. Technical Proposal
3. Representations and Certifications
4. Standard Form 24, Bid Bond
5. GSA Form 527 – Contractor’s Qualification and Financial Information
6. Other Documents as Required
II.B. Proposal Format
Firms shall submit one (1) electronic copy of the technical proposal, one (1) electronic copy of the price proposal and attachment 4 (LEC Spreadsheet in both PDF and Excel). The submission should be organized to correspond with the evaluation factors listed below.
Electronic copies must be submitted by email to Jeff Kang at Jeffrey.kang@gsa.gov and copied to Jason Gerloff at Jason.gerloff@gsa.gov. Electronic copies must be received by the date and time listed in this solicitation. The proposal is considered received upon the date and the time stamp showing receipt by the Contracting Officer’s Government email inbox and not when the contractor sent the email.
The total technical proposal submission should not exceed 40 pages one sided, 8 ½” x 11”, vertical (portrait) format pages, consisting only of the specified materials described in this solicitation. The reference questionnaires, and Environmental Product Declarations (EPD’s) required will not count toward the page number limit.
References: The questionnaire form or the FINAL evaluation from the Contractor Performance Assessment Reporting System (CPARS) shall be submitted for each project presented in the RFP. Offeror will submit the questionnaire or Final CPARS with their technical proposal set forth in the RFP. The Government may consider all past performance information that it becomes aware of during the evaluation process.
The proposal should include a cover page with the firm’s point of contact, phone number and email. Also included is the company's DUNs number, UEI number, and TIN number and name, phone number, email of the person who is authorized to negotiate on behalf of the offeror.
The price proposal section portion of the proposal does not count towards the 40-page limit.
This solicitation does not commit the Government to pay any costs incurred in the submission of any proposals. Nor does it commit the Government to procure or contract for said services. The Contracting Officer is the only individual who can commit the Government to the expenditure of public funds in connection with this proposed procurement.
II.C. Price Proposal
(1) Contents
The Price Proposal shall consist of:
a. Standard Form (SF) 1442 blocks 14, 15, 16, 17, 19, & 20a, b, c signed and dated by an authorized individual. Please include the offeror UEI and EIN number in Block 14 of the SF1442 (note: Block 14 “code” and “facility code” can be left blank). Indicate the
(The Solicitation)
Base Contract Price plus options in Block 17 of the SF 1442, which must be fully executed by the Offeror.
b. Pricing Sheet (excel and signed PDF), with prices and/or rates indicated for each price element shown on the pricing sheet with a signature by an authorized individual on the pricing sheet. Pricing Sheet total shall match what is listed on the 1442.
c. The Bid Bond in accordance with FAR 52.228-1 Bid Guarantee
d. Acknowledgement of all amendments in Block 19 of the SF1442.
(2) Qualifications, Exclusions and Conditions
If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.
(3) GSA is required to track spending for each of the three appropriations it received under the Inflation Reduction Act of 2022 (IRA) -- for low-embodied carbon (LEC) materials, emerging and sustainable technologies, and high-performance green building measures -- and has established “budget activities” for each of these appropriations. A contract line-item number (CLIN) for each of these budget activities has been included in the Agreement as necessary. In addition, sub-CLINs will be used to track spending on each of the LEC materials designated for IRA funding -- asphalt, concrete, glass, and steel. Offerors must include separate prices for IRA work under the corresponding IRA CLINs and sub-CLINs.
Amounts for each IRA CLIN should reflect all expenses necessary to accomplish acquisition and installation of IRA work elements. A list of possible expenses follows below; this list is not exhaustive.
● Expenses of acquiring and transporting products and materials required for IRA funded work to the construction site;
● Labor, general and administrative expenses, and overhead and profit reasonably attributable to installation of IRA-funded work;
● Expenses for materials, tools, riggings and equipment (including safety equipment) required to install IRA-funded work;
● Design, submittal and documentation expenses reasonably attributable to IRA funded work;
● Demolition and disposal expenses reasonably necessary for and attributable to
IRA-funded work;
● Expenses necessary to return space to its condition preceding IRA-funded work;
● Environmental remediation expenses required in execution of IRA-funded work;
and
● Phasing and commissioning expenses reasonably attributable to IRA-funded work.
(The Solicitation)
II.D. Technical Proposal
The Technical Proposal shall include the information requested below for the non-price factors described in Section VI. Non-Price Factors, when combined, are significantly more important than Total Evaluated Price.
The term "similar projects" shall be defined for evaluation purposes projects that meet all three elements of size, complexity, and type as further defined herein. The project requires the phased working of various aspects of the project as day-to-day functions of the Land Port of Entry are accommodated for the full duration of construction with minimal impact on operations.
Each project need not contain every element, but the combination of projects should demonstrate the ability to perform these services in a satisfactory manner.
Similar in size projects are:
● Exceed $5,000,000 in total construction costs, two (2) projects completed in the last eight (8) years from the date of the Solicitation. One (1) of the two (2) project submissions can be incomplete, however it must be 75% complete from the date of the proposal submission.
Similar in complexity projects are:
● Design and construction of roadway repair and replacement of 300,000 SF of concrete pavement 8” or more in depth
● Phasing and planning of work to include road/lane closures
● Project is occupied during normal business hours to allow traffic flow to continue during construction
Similar in type projects are:
● A project consisting of major modernization or renovation for road repair of a Land Port of Entry (LPOE), complex, military base, commercial docks, or facility area, University Campuses, and highway road construction repair projects.
Additional examples include, but are not limited to, highways, airport runways, tarmacs, commercial dock areas, bridges, and distribution center projects.
● Projects involving POV and commercial primary inspection lanes with booths, secondary POV inspection area with inspection canopies, and road and paving site work that meet the minimum depth (8 inches thick) of concrete.
Projects NOT considered similar:
● Stand-alone parking lots, sidewalks, and driveways
GSA’s asphalt, concrete (and cement), glass and steel requirements establish numeric global warming potential (GWP) limits for each of the EPA-approved construction materials: concrete
(and cement), asphalt, steel, and glass (IRA-Eligible Materials). For each IRA-Eligible Material, GWP limits have been established for the best performing 20% of materials in terms of embodied carbon, as reported in terms global warming potential (Top 20% Limits), the best performing 40% of materials in terms of embodied carbon (Top 40% Limits) and better than industry average (Better Than Average Limit). In accordance with its proposal, Contractor shall provide all IRA-Eligible Materials required for performance of the Contract in compliance with the following IRA Limits.
https://www.gsa.gov/system/files/Asphalt%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Concrete%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Glass%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Steel%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf
(The Solicitation)
IRA-Eligible Material* IRA Limit (e.g., Top 20% Limit, Top 40%, Better than Average)
GWP Value for IRA Limit
(The Solicitation)
Concrete Specified concrete strength class
(compressive strength [f'c] in pounds per square inch [PSI])
≤ 4000 PSI
[CO to specify each limit as applicable - limits for the Top 20%, Top 40% and Better than Average prepopulated below]
284 326 352 kgCO2e/m3
5000 PSI
305 357 382 kgCO2e/m3
6000 PSI
319 374 407 kgCO2e/m3
≥7200 PSI
321 362 402 kgCO2e/m3
Cement**
751 819 858 kgCO2e/metric ton
Concrete Masonry Units
217 256 290 kgCO2e/m3
Asphalt
55.4 64.8 72.6 kgCO2e/metric ton
Steel
Fabricated Rebar
728 794 850 kgCO2e/metric
Unfabricated Rebar
611 716 760 kgCO2e/metric
Hollow Structural Sections (fabricated)
1,778 1,854 1,898
Hollow Structural Sections from Electric Arc Furnaces (unfabricated)
1,580 1,620 1,652
Hot-Rolled Sections (fabricated)
1,022 1,128 1,163
Hot-Rolled Sections
686 713 869 kgCO2e/metric
(The Solicitation)
Cold-Formed and Galvanized (stud, track, framing, etc.)
2,228 2,324 2,408
Structural Steel Plate from Electric Arc Furnaces
987 1,152 1,190
Flat Glass
1,331 1,370 1,401
* Required construction product assemblies (such as window assemblies) are included in IRA-Eligible Material categories and are bound by IRA Limits. At least 80% of the assembly’s total cost or total weight must be composed of compliant IRA-Eligible
Materials.
** Where provision of concrete that qualifies under these GSA IRA Limits is impractical, GSA’s IRA Limits for cement may be applied to the cement being used in the concrete mix.
Contractor compliance with IRA Limits will be verified by reference to provided materials’ environmental product declarations (EPDs). EPDs must meet the standards reflected in
GSA’s asphalt, concrete (and cement), glass and steel requirements (see Compliance
Documentation criteria listed for each IRA-Eligible Material - Attachments 10., 11. & 12.).
1. Factors and Weights
Factor Evaluation Criteria Elements Weight
1 Past Performance, Experience and Qualifications of Key Personnel (Design/Build Project Team)
40%
2 Past Experience and Performance of the Company 25%
3 Technical and Management Approach 20%
4 Sustainability - LEC Construction Materials 15%
Total 100%
2. Scoring of Technical Factors
Each technical factor will be given a score of 0-10 based on how they relate to the standard
(see Evaluation Criteria Scoring table below). After each technical factor has been evaluated, the overall technical score will be established by calculating the sum of all factors. Each factor https://www.gsa.gov/system/files/Concrete%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Asphalt%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Concrete%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Glass%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Steel%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf
(The Solicitation) is weighted accordance with weights shown in the table below. The highest overall technical score possible is 10, and the lowest overall technical score possible is 0. SCORE shall be carried to the tenth place.
EVALUATION CRITERIA SCORING
UNSATISFACTORY MARGINAL SATISFACTORY VERY
GOOD
EXCEPTIONAL
0 - 1 2 - 3 4 - 5 6 - 7 8 - 10
Does not meet the
Meets some
Meets, but does
Meets the
Significantly minimum of the not exceed the minimum exceeds the requirements. Major minimum minimum requirements standard.
revisions are requirements, requirements. and exceeds Innovative, required to make the but lacks in Weaknesses are in some comprehensive proposal acceptable. some areas. deemed areas. No proposal which is
Major deficiencies Lacks correctable. No deficiencies complete in all and/or weaknesses essential deficiencies or details. No are not readily information. weaknesses deficiencies or correctable. Significant weaknesses deficiencies and/or weaknesses.
1. FACTOR 1 – Past Performance, Experience and Qualifications of Key Personnel
Weight: 40%
a. FACTOR DESCRIPTION
Factor 1 considers the qualifications, past performance, and experience of key personnel on the Offeror’s team. The Offeror shall submit the information requested in the Solicitation and resumes for the Design Build contractor’s key personnel noted below: The Offeror shall also include any relevant credentials or specialized training for each individual.
• Design Firm Project Manager
• General Contractor’s Project Manager (Construction)
• Project Superintendent
• Quality Control Manager
b. MINIMUM STANDARDS
(The Solicitation)
The minimum standard is met for each resume when:
● The key individuals identified have the appropriate qualifications and document experience required for the position to be assigned for this project.
● Each individual has a minimum of 7 years experience in their respective role and completed at least two similar projects within the past 8 years..
● One similar project for each individual must have the construction successfully completed or has reached substantial completion within the past eight (8) years.
Some examples of when the standard is exceeded include:
● Key personnel successfully completed more than 2 similar projects within the past eight (8) years.
● Key personnel have worked together and successfully completed similar projects in the past.
c. SUBMITTAL REQUIREMENTS:
Offerors shall submit resumes, with a narrative description for each individual, along with a list of relevant projects. The resume shall include education, general job experience, and any trade or professional credentials or accreditations.
The offeror shall submit a total of four (4) corresponding questionnaires (one for each
Key Personnel) (Attachment 3 of the Solicitation). Questionnaires shall be from the end-user representing who was involved during the construction of the referenced projects. Offeror will submit the questionnaire with their technical proposal by the due date and time set forth in the RFP. The reference must be available to be contacted by the Government.
For key personnel, the Offeror shall provide information on two or more recent projects not to exceed four that each individual has worked on with at least one similar project that reached substantial completion within the past eight (8) years. For each project listed, there should be a statement of what percentage of the individual’s time was dedicated to that project.
For projects not included in the Firm’s Past Performance projects, identify the project description, project name and location, contact name and information, total construction cost, actual construction start and completion date, and a brief statement indicating the similarities of the reference project to this project.
Note that a single project could count for multiple team members if they worked together on it. Team members having successfully worked together on similar projects is desirable, but not essential, and could result in additional favorable consideration during the evaluation.
Offeror’s Team is encouraged to provide information on problems encountered on the identified contracts and the project team’s corrective actions.
(The Solicitation)
2. FACTOR 2 – Past Experience and Performance of the Company
Weight: 25%
a. FACTOR DESCRIPTION
Factor 2 considers the Offeror’s past experience and performance demonstrating excellence as it relates to quality of work, timeliness of performance, business relations, sustainability experience, and overall customer satisfaction.
b. MINIMUM STANDARDS
The minimum standard is met when the Offeror demonstrates past experience indicating the following:
• Two (2) similar projects that have been completed within the last eight (8) years (from the date of this Solicitation) with a satisfactory/good rating or better, as evidenced by a minimum of one reference per project who indicates he/she would contract with the firm again for the same services. Offeror must explain how the characteristics of the project relate to the characteristics of this project.
• The firm must have completed at least one (1) project and the other being at least 75% completed, on-time (no liquidated damages assessed), within budget and in accordance with contract requirements.
• Experience in managing concrete placement, and removal of construction and demolition waste.
• Experience of Design and Construction of major modernization or renovation of a Land Port of Entry (LPOE), University campuses, military base, commercial docks, facility area, and highway road construction repair projects. Additional examples include, but are not limited to, highways, airport runways, tarmacs, commercial dock areas, bridges, and distribution center projects.
• Experience with project sites that are open and require phasing of lane closures and coordination with end users.
• Experience with each project need not contain every element, but the combination of projects should demonstrate the ability to perform these services in a satisfactory manner.
Some examples of when the standard is exceeded include:
• The prime contractor has successfully completed two or more similar projects and received a
Very Good or greater rating from two or more references.
• One or more of the projects was successfully executed by multiple members of the proposed Team working together. Experience reflected in written recommendations from references / customers that indicated exceptional customer service.
• Experience with modernization or renovation work on occupied southern border LPOEs, including but not limited to POV and commercial primary inspection lanes with booths, (The Solicitation) secondary POV inspection area with inspection canopies, and road and paving site work that meet the minimum depth (8 inches thick) of concrete.
The Offeror shall submit a minimum of two (2) projects that demonstrate the history of successful team project delivery, based upon the standards listed above, for similar projects completed within the last eight (8) years. If one (1) of the projects is not complete, it must be 75% complete from the date of the proposal submission.
The offeror shall submit two (2) corresponding questionnaires (Attachment 2 of the Solicitation) or the FINAL evaluation from the Contractor Performance Assessment Reporting System (CPARS). Questionnaires shall be from the end-user representing who was involved during the design and construction of the referenced projects. Offeror will submit the questionnaire or Final CPARs with their technical proposal by the due date and time set forth in the Solicitation. The reference must be available to be contacted by the Government.
The Government also reserves the right to use other government data available in its assessment of the offeror. The quality of the reference information supplied will be considered.
In accordance with FAR 15.306, If award will be made without conducting discussions, offerors may be given the opportunity to clarify certain aspects of proposals (e.g., the relevance of an offeror’s past performance information and adverse past performance information to which the offeror has not previously had an opportunity to respond) or to resolve minor or clerical.
Project references are not included in the proposal page count limit.
Offeror is encouraged to provide information on problems encountered on the identified projects/contracts and the Offeror’s Team corrective actions.
For each project presented, the Offeror shall submit the following data/information:
1. Project Title.
2. Owner and/or Occupants/Tenants
3. Location
4. Project team including the subcontractors that performed major divisions of work
5. Description including square footage of work area
6. Any special considerations or plans associated with working in occupied space
7. Contract Award Date
8. Contract Type and Contractor’s Responsibilities
9. Date of Substantial Completion
10. Date of Final Completion
11. Contract Award Amount
12. Contract Award Amount at Completion
13. Original Scheduled Completion Time at Contract Award (Calendar Days).
14. Actual Completion Time (Calendar Days)
15. Number of Change Orders
16. Reasons for Change Orders
17. Describe the similarities to this project
(The Solicitation)
3. FACTOR 3 – Management Plan
Weight: 20%
a. FACTOR DESCRIPTION:
Factor 3 considers the Offeror’s understanding of the technical project goals, requirements, and risks associated with planning, managing, and controlling the work to achieve timely completion within scope and budget.
The Management Plan shall be tailored to this project and shall describe the Offeror’s technical approach on how the work will be accomplished on time and within budget. This factor considers proposed design-build experience in concrete placement, managing, sorting, and removal of concrete and demolition waste. In addition, the plan shall include the following:
Management Plan shall include an organizational chart indicating offeror’s organizational structure and key personnel listed by name and title and who will be full-time, part-time, and on or off site.
Management plan shall include a narrative explaining quality assurance/quality control plan.
Management plan shall include a schedule that is well planned and include phasing to provide the best possible outcome for design and construction activities while avoiding excessive shut down time.
b. MINIMUM STANDARDS
The minimum standard is met when the Offeror’s proposed management plan demonstrates the following:
● Includes all submittal requirements as listed in the next section.
● The Plan is tailored specifically for this project and includes detailed phasing arrangements.
● The Offeror has a comprehensive and logical plan for executing the design build project, performing quality control, managing resources, coordinating various trades,and coordinating with the government.
● The proposal has a logical schedule with major milestones identified and activities laid out in a critical path method (CPM) schedule.
● The plan reasonably identifies the main risk drivers for this project with an acceptable mitigation strategy.
Some examples of when the standard is exceeded include:
● The Offeror’s plan includes innovative ideas to minimize tenant impact.
● The Offeror has demonstrated experience with solving problems and tracking and controlling the schedule, resulting in time and cost savings.
● The firm’s management approach for coordinating the work of various trades with the GSA and the tenant agencies has been successfully implemented on more than two past projects, as evidenced by a brief description/narrative.
● The Risk Mitigation plan successfully addresses likely issues without impacts to performance or the Government.
(The Solicitation)
● The Offeror identifies experience indicating superior understanding of the effort and resources required for coordinating and sequencing the work on similar construction projects, and that experience supports the Offeror’s ability to complete the requirements.
The Offeror shall submit a management plan addressing the following critical components:
1. A narrative discussion of the management philosophy and plan for executing the project; discuss an effective system for controlling day to day project issues and potential changes.
2. An organizational chart delineating relationships and lines of authority for Key Personnel proposed for this project. The chart will identify who is on site full time, off site full time, and who is a combination of both.
3. Identification of risk articulating the unique risks for this project that are relevant and realistic. The plan must identify the risk event, probability of occurrence, the impact of the event if it occurs and a description of the mitigation strategy used to manage the risk. Consider impacts on labor, materials, and equipment as a result of Pharr area market cost inflation.
4. Identify cost control methods and demonstrate how the Offeror intends to control costs during construction to ensure the project is completed within budget.
5. Preliminary project schedule that addresses all submittal requirements and provides sufficient detail to track and control construction of the project. The project schedule must be a CPM schedule that shows the sequencing of tasks (predecessors and successor relationships) and the critical path for a schedule that runs from the contract award date through the required date for contract completion. Include scheduling milestones on a bar chart or Gantt chart showing major actions necessary to successfully deliver the project. This schedule is not included in the factor or proposal page count limit.
6. Offerors shall provide a Design and…