About this file
This is a Performance Bond document template applicable to the City of Meriden, Connecticut's RFP026-46 for gymnasium floor replacement services at Casimir Pulaski Elementary School. The bond serves as a financial guarantee that the selected contractor will faithfully perform all work in accordance with the contract terms and conditions. The performance bond is required in an amount equal to 100 percent of the bid amount and must be executed by the contractor as principal, a surety company, and the City of Meriden as obligee. The pre-bid meeting is scheduled for March 24, 2026, at 10:00 a.m. at the school site, with questions due by March 31, 2026, at 4:00 p.m. Electronic proposals are due April 7, 2026, at 11:00 a.m. via the City eProcurement Portal. The project must commence on or after June 29, 2026, following the conclusion of the school year, and be substantially completed by August 7, 2026.
Under the bond terms, the surety is liable for the full contract price and assumes responsibility for ensuring project completion if the contractor defaults. The surety waives notice of any alterations, defaults, or time extensions made by the owner and may elect to either complete the contract directly or obtain bids for completion from responsible third parties. The owner may recover from the surety all costs associated with remedying the default, including completion costs and damages, up to the bond amount. Any legal action against the bond must be instituted within two years from the date final payment is due. The bond runs concurrently with the contract term and protects only the City of Meriden as the named obligee, with no third-party beneficiary rights. Liquidated damages are assessed at $2,200 per calendar day for project delays beyond the August 7, 2026, completion deadline.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS, that (here insert full name and address or legal title of Contractor) as Principal herinafter called contractor and (here insert full name and address or legal title of Surety
As Surety, hereinafter called Surety, are held and firmly bound unto (here insert full name and address or legal title of Owner)
As Obligee, hereinafter called Owner, in the amount of
Dollars $___________________________ for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS,
Contractor has by written agreement dated 20 , entered into a contract with Owner for (here insert full name, address and description of project)
In accordance with Drawings and Specifications prepared by (here insert full name and address or legal title of Engineer/Architect)
Which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
PERFORMANCE BOND
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor, shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
The Surety hereby waives, notice of any alteration or defaults, under the contract or contracts of completion extension of time made by the Owner. arranged under this paragraph sufficient funds to pay the cost of completion less the balance of the contract price;
Whenever Contractor shall be, and declared by Owner but not exceeding, including other costs and damages to be in default under the Contract, the Owner having for which the Surety may be liable hereunder, the amount performed Owner’s obligations thereunder, the surety set forth in the first paragraph hereof. The term “balance may promptly remedy the default, or shall promptly of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor
1) Complete the Contract in accordance with its terms under the Contract and any amendments thereto, less and conditions, or the amount properly paid by Owner to Contractor.
2) Obtain a bid or bids for completing the Contract in Any suit under this bond must be instituted before accordance with its terms and conditions, and upon de- the expiration of two (2) years from the date on which termination by Surety of the lowest responsible bidder, final payment under the Contract falls due.
or, if the Owner elects, upon determination by the Owner and the Surety jointly of the lowest responsible No right of action shall accrue on this bond to or for bidder, arrange for a contract between such bidder and the use of any person or corporation other than the Owner, and make available as Work progresses (even Owner named herein or the heirs, executors, adminis-though there should be a default of a succession of trators or successors of the Owner.
Signed and sealed this day of 20