Sample_Change_Order.pdf

PDF 73 KB Posted

Attached to
STAR Center AHU -104, -161, -162 Replacement
Solicitation number
26-0306-ITB-C
Issued by
Pinellas County, Clewiston City, Florida

About this file

This is a Sample Change Order form from the Pinellas County Purchasing Department in Clearwater, Florida, designed for use in construction and service contracts administered by the county. The form provides a standardized template for documenting modifications to existing agreements, including additions and deletions to project scope and corresponding adjustments to contract value. The document includes designated fields for fiscal numbers, change order numbers, account numbers, and original agreement amounts, with separate line items for additions and deletions to calculate the new total agreement value. The form requires execution by the contractor, acknowledgment by company representatives with authorized signatures, and approval by the County Attorney's Office and Board of County Commissioners, with specific signature blocks for the Director of Purchasing, County Attorney, Board Chairman, and Clerk.

The change order form explicitly stipulates that contractor execution constitutes a waiver of all claims or requests for additional time or compensation for activities prior to the change order's execution date related to included items, and that payment authorized by the change order represents full and complete compensation for all labor, materials, incidental expenses, overhead, profit, impact costs, and time associated with the work. The form directs parties to reference the contract documents for applicable claim procedures and establishes clear authorization requirements through witness signatures and dated acceptance, ensuring proper documentation and approval chain for any modifications to the underlying contract agreement.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX 2 – SAMPLE CHANGE ORDER

APPENDIX 2 – SAMPLE CHANGE ORDER

SAMPLE CHANGE ORDER

PINELLAS COUNTY PURCHASING DEPARTMENT

CLEARWATER, FLORIDA

FISCAL NO. CHANGE ORDER NO.

ACCOUNT NO.

TO Total Agreement $

FOR Addition $

IN CONNECTION WITH New Total $

Deletion $

New Total Agreement $

Execution by the contractor of this Change Order shall be considered a waiver of all claims or request for additional time or compensation for any activities prior to time of execution related to items included in the Change Order. The contractor also acknowledges that payment authorized by this Change Order represents full and complete compensation for labor, materials, incidental expenses, overhead profit, impact cost, and time associated with this Work. Claim procedures are outlined in the Contract documents.

Investigator

Director of Purchasing APPROVED AS TO FORM: Accepted this day of

OFFICE OF COUNTY ATTORNEY 20

By PINELLAS COUNTY Attorney BOARD OF COUNTY COMMISSIONERS

By Chairman

Attest: KEN BURKE, CLERK By

Deputy Clerk

Use Authorized Signatures Only Company

By Title

Witness