STAR Center AHU Replacement Project - Construction Documents Summary
These are 100% Construction Documents for the Young-Rainey STAR Center Air Handling Unit (AHU) 104, 161, and 162 Replacement project in Pinellas County, Florida (Project PID# 4566A), prepared by Brady & Anglin dated December 19, 2025. The project involves the full replacement of three chilled water air handling units: one outdoor unit (AHU-104) located on the roof and two indoor units (AHU-161 and AHU-162) located on a hanging structural platform that will be consolidated into one new unit. All new units will be equipped with new Direct Digital Controls (DDC) utilizing Niagara4 supervisory software and BACnet communication protocols. The scope includes complete mechanical systems with associated ductwork, piping, controls, insulation, and electrical infrastructure. Key specifications include new outdoor air/return air dampers, electric heating for AHU-104, vibration isolation, testing and balancing, and comprehensive Building Automation System (BAS) integration with existing fiber optic network infrastructure. The project requires strict coordination with Raytheon Company occupancy requirements, including security clearance and badging procedures for all contractor personnel, with weekend scheduling mandated for crane operations and equipment installation to minimize tenant disruption.
The project specifications emphasize a phased construction approach accommodating owner occupancy during construction, with all mechanical systems requiring compliance with the 2023 Florida Building Code (Mechanical and Energy Conservation editions). Contractor qualifications for the BAS work require factory authorization, minimum five years' experience with Niagara4 systems, three factory-trained technicians, and proof of local service capability. The specifications mandate pre-construction coordination with the Star Center facility engineer, submittal of Microsoft Project schedules, and detailed shop drawings forty-five days from contract award. Submittals must include equipment warranties, parts lists, balance and test readings, and operating instructions in electronic PDF format. The project includes three sets of filters per unit, factory start-up services, demonstration and operator training two weeks prior to substantial completion, and closeout documentation including as-built drawings in AutoCAD format, operation and maintenance manuals, and system commissioning records. No pricing, contract term, or award date information is contained in these construction documents.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
YOUNG-RAINEY STAR CENTER
AHU 104, 161, 162 REPLACEMENT
Pinellas County Project PID# 4566A
Brady & Anglin Project #25017
100% CONSTRUCTION DOCUMENTS
December 19, 2025
YOUNG-RAINEY STAR CENTER - AHU 104, 161, 162 REPLACEMENT 12/19/2025
TABLE OF CONTENTS
BRADY & ANGLIN
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01100 ........... SUMMARY OF WORK
01200 ........... PROJECT COORDINATION
01300 ........... SUBMITTALS
01400 ........... STARTING OF SYSTEMS
01500 ........... CLOSEOUT PROCEDURES
DIVISION 15 – MECHANICAL SYSTEMS
15010 ........... BASIC MECHANICAL REQUIREMENTS
15140 ........... SUPPORTS AND ANCHORS
15190 ........... MECHANICAL IDENTIFICATION
15242 ........... VIBRATION ISOLATION
15260 ........... PIPING INSULATION
15280 ........... EQUIPMENT INSULATION
15290 ........... DUCTWORK INSULATION
15400 ........... TESTING OF PIPING SYSTEMS
15510 ........... HYDRONIC PIPING
15515 ........... HYDRONIC SPECIALTIES
15790 ........... ELECTRIC DUCT HEATERS
15855 ........... AIR HANDLING UNITS WITH COILS
15890 ........... DUCTWORK
15910 ........... DUCTWORK ACCESSORIES
15975 ........... BAS INSTRUMENTATION AND CONTROL
TABLE OF CONTENTS
BRADY & ANGLIN
15990 ........... TESTING, ADJUSTING, AND BALANCING
DIVISION 16 – ELECTRICAL SYSTEMS
16010 ........... BASIC ELECTRICAL REQUIREMENTS
16060 ........... ELECTRICAL DEMOLITION FOR REMODELING
16111 ........... CONDUIT
16120 ........... BUILDING WIRE AND CABLE
16130 ........... BOXES
16190 ........... SUPPORTING DEVICES
16195 ........... ELECTRICAL IDENTIFICATION
16440 ........... DISCONNECT SWITCHES
CONSTRUCTION DOCUMENTS 01100-1
BRADY & ANGLIN
SECTION 01100 - SUMMARY OF WORK
PART 1 – GENERAL
1.1 SECTION INCLUDES
A. Contract Description: See contract documents for Scope of Work.
B. Contractor use of site and premises.
C. Work Sequence.
D. Owner occupancy.
1.2 WORK BY CONTRACTOR
A. The scope of work listed on drawings and in the project specifications.
1.3 CONTRACTOR USE OF SITE AND PREMISES
A. General: The Contractor shall have limited use of the premises for construction operations throughout the course of the work until Substantial Completion. The Contractor's use of the premises is limited by the Owner's and Tenant’s right to continue operations. Confine operations to areas within construction area. Portions of the site beyond the construction area are not to be disturbed.
B. The Contractor shall submit to and comply with all access and security requirements of the Star Center and Raytheon Company. Contractors and sub-contractors who are to work inside the Raytheon areas must be a U.S citizen. All will need to submit a driver’s license and an original certified birth certificate or a passport (current or expired) shortly after the notice to proceed has been issued. Persons who fail to gain escort clearance will not be allowed inside the building and it is the contractor’s responsibility to ensure they have personnel who are escort clearance capable to be allowed into the building BEFORE the project commencement. All personnel applying for a non-escort badge or visitor’s badge shall provide their full legal names to the STAR Center project manager for submission prior to the start of the project. There are no exceptions.
C. A maximum of (3) three non-escort badges shall be allowed for the Prime
Contractor. Each Subcontractor shall be allowed a maximum of (2) two non-escort badges. All other technicians shall apply for daily visitor’s badges when entering Raytheon.
D. The Contractor shall maintain full care and control of the portion of the site where construction operations are occurring. However, the building
YOUNG-RAINEY STAR CENTER - AHU 104, 161, 162 REPLACEMENT 12/05/2025
CONSTRUCTION DOCUMENTS 01100-2
will remain occupied and normal operations will continue therein.
E. All areas disturbed by construction operations shall be returned to their original condition prior to Substantial Completion.
F. Any work that will cause interruptions to STAR Center tenants, whether the work is inside the tenant space or outside of the tenant space, especially welding, must be completed after hours or on weekends and coordinated with the STAR Center and the tenants.
G. Emergency Building Exits During Construction: Shall be accessible at all times.
H. Construction Operations: Scheduled by Contractor and approved by STAR center project manager.
I. Time Restrictions for Performing Interior and Exterior Work: Scheduled by Owner.
1.4 WORK SEQUENCE
A. The contractor shall obtain all necessary permits, authorizations, code inspections and site inspections required by local and/or regional authorities on a timely basis so as not to delay the project.
B. Construct Work in phases to accommodate Owner's occupancy during the construction period, coordinate construction schedule and operations with Owner.
1.5 OWNER OCCUPANCY
A. The Owner intends to occupy portions of the premises during construction. Schedule work with Owner.
B. Cooperate with Owner to minimize conflict, and to facilitate Owner's operations.
C. Schedule the Work to accommodate this requirement.
PART 2 - PRODUCTS
A. Not Used
PART 3 - EXECUTION
SECTION END
CONSTRUCTION DOCUMENTS 01200-1
BRADY & ANGLIN
SECTION 01200 - PROJECT COORDINATION PART
1 - GENERAL
A. Project coordination by the County Project Manager.
B. Construction mobilization.
C. Schedules.
D. Submittals.
E. Coordination drawings.
F. Closeout procedures.
1.2 RELATED SECTIONS
A. Section Contract Closeout: Contract Closeout Procedures.
1.3 PROJECT COORDINATOR
A. Project Coordinator: Brad Grabo, PE, Facility Engineer.
1.4 CONSTRUCTION MOBILIZATION
A. Cooperate with the Project Coordinator in allocation of mobilization areas of site; for field offices and sheds, for access, traffic, and parking facilities.
B. During construction, coordinate use of site and facilities through the
Project Coordinator.
C. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.
D. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities.
E. Coordinate field engineering and layout work under instructions of the Project Coordinator.
CONSTRUCTION DOCUMENTS 01200-2
1.5 SCHEDULES
A. The Contractor shall prepare and submit a Microsoft project management schedule file. Approval of the schedule by the Engineer and Owner shall not relieve the Prime Contractor of responsibility for scheduling the work and maintaining progress as specified in the Contract Documents.
1. Schedule shall show critical submittal dates related to each activity or prepare separate coordinated listing of critical submittal dates. Show phases of work within each activity for major elements which involve purchase lead-time, fabrication, or other coordination issues, as well as installation. In addition to a critical path for each of the work segments, an overall critical path relating these segments to the overall project completion time shall be indicated.
1.6 PERSONNEL
A. Prior to Notice to Proceed, Contractor shall submit a list of staff assignments, including the Superintendent and Project Manager. List business contact telephone numbers. Identify the Contractor's point of contact for all communication regarding the project.
B. Comply with the Star Center and Raytheon Company requirements for security and access into the building and onto the roof prior to the start of the project.
1.7 LIST OF SUBCONTRACTORS
A. At the pre-construction meeting the Contractor shall submit to the Owner a list of all subcontractors for the project.
B. Note: When any work is being completed on the project by sub-contractors the Prime Contractor shall have the project leader or one of the other technicians with a non-escort badge be onsite during completion of the work.
1.8 SUBMITTALS
A. Submit preliminary shop drawings, product data and samples in accordance with Section Submittals for review and compliance with Contract Documents, for field dimensions and clearances, for relation to available space, and for relation to work of separate contracts. Revise and resubmit as required.
B. Submit applications for payment on forms requested by Owner for review, and for transmittal to Owner.
CONSTRUCTION DOCUMENTS 01200-3
BRADY & ANGLIN
C. Submit requests for interpretation of Contract Documents, and obtain instructions through the Design Professional and Owner.
D. Process requests for substitutions, and change orders, through the
Design Professional and Owner.
E. Deliver closeout submittals for review and preliminary inspection reports, for transmittal to Design Professional and Owner.
1.9 COORDINATION DRAWINGS
A. Provide information required by Design Professional for preparation of coordination drawings.
B. Review drawings prior to submission to Owner.
1.10 CLOSEOUT PROCEDURES
A. Notify Design Professional when Work is considered ready for Substantial Completion. Accompany Project Coordinator on preliminary inspection to determine items to be listed for completion or correction in Contractor's Notice of Substantial Completion.
B. Comply with Project Coordinator's instructions to correct items of work listed in executed Certificates of Substantial Completion and for access to Owner occupied areas.
C. Notify Project Coordinator when Work is considered finally complete.
Accompany Project Coordinator on preliminary final inspection.
D. Comply with Project Coordinator's instructions for completion of items of Work determined by Owner's final inspection.
CONSTRUCTION DOCUMENTS 01300-1
SECTION 01300- SUBMITTALS
PART 1 - GENERAL
A. Submittal procedures.
B. Construction progress schedules.
C. Proposed Products list.
D. Shop Drawings.
E. Product Data.
F. Samples.
G. Manufacturer's instructions.
H. Manufacturers' certificates.
I. Construction photographs.
A. Section Contract Closeout: Contract warranty and manufacturers' certificates closeout submittals.
1.3 SUBMITTAL PROCEDURES
A. All submittals shall be submitted at the same time as one package with the exception of long lead items such as AHUs, curb adapters, etc.
B. Transmit each submittal with Design Professional’s submittal form.
C. Sequentially number the transmittal form. Resubmittals to have original number with an alphabetic suffix.
D. Each submittal shall include specification section number and name in the electronic file for tracking. If this is not done, the submittal shall be rejected for correction.
E. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.
F. Apply Contractor's stamp, signed or initialed certifying that review, CONSTRUCTION DOCUMENTS 01300-2
BRADY & ANGLIN
verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.
G. Schedule submittals to expedite the Project, and deliver to Owner at business address. Coordinate submission of related items.
H. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.
I. Provide space for Contractor and Design Professional Approval stamps.
J. Revise and resubmit submittals as required, identify all changes made since previous submission.
K. Distribute copies of reviewed submittals to concerned parties. Instruct parties to promptly report any inability to comply with provisions.
1.4 PRODUCT DATA
A. Submit electronic PDF files to the project manager, which will forward to the engineer.
B. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information unique to this Project.
C. After reviewed and approved provide approved electronic file for
Closeout Record Documents described in Section Contract Closeout.
1.5 MANUFACTURER INSTALLATION INSTRUCTIONS
A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, in quantities specified for Product Data.
B. Identify conflicts between manufacturers' instructions and Contract
Documents.
C. Shall be in accordance with FBC Mechanical 304.1.
1.6 MANUFACTURER CERTIFICATES
A. When specified in individual specification sections, submit manufacturer's certificate to Owner, for review, in quantities specified for Product Data.
CONSTRUCTION DOCUMENTS 01300-3
BRADY & ANGLIN
B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Owner.
1.7 WELDING CERTIFICATES
A. Provide certificates (current) for welder(s) that have passed AWS Qualification Tests per AWS D1.1 Structural Welding Code - Steel.
PART 2- PRODUCTS
PART 3- EXECUTION
CONSTRUCTION DOCUMENTS 01400-1
BRADY & ANGLIN
SECTION 01400- STARTING OF SYSTEMS
PART 1 – GENERAL
A. Starting systems.
B. Demonstration and instructions.
C. Testing, adjusting, and balancing.
A. Section Contract Closeout: System operation and maintenance data and extra materials.
1.3 STARTING SYSTEMS
A. Refer to Manufacturer’s installation and startup requirements for the air handling units. All AHUs will be installed over a weekend and a basic start-up shall be performed to provide cooling by 7 AM Monday morning.
B. Notify Owner seven days prior to start-up of each item. Factory start-up shall be provided after installation is complete and performed so as to minimize interruption to the STAR center and its tenants.
C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or for other conditions which may cause damage.
D. Verify that tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of responsible manufacturer's representative in accordance with manufacturers' instructions.
G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
H. Submit a written report in accordance that equipment or system has been properly installed and is functioning correctly.
CONSTRUCTION DOCUMENTS 01400-2
1.4 DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of Products to Owner's personnel two weeks prior to date of Substantial Completion.
B. Demonstrate Project equipment by a qualified manufacturers' representative who is knowledgeable about the Project.
C. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.
D. Utilize operation and maintenance manuals as basis for instruction.
Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.
E. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, and designated location.
F. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
1.5 TESTING, ADJUSTING, AND BALANCING
A. Refer to Section 15990 for additional information.
CONSTRUCTION DOCUMENTS 01500-1
SECTION 01500 – CLOSEOUT PROCEDURES
1.1 SUMMARY
A. General: This section includes general requirements near end of Contract Time, in preparation for substantial completion, final acceptance, final payment, normal termination of contract, occupancy and similar actions evidencing completion of the work.
Specific requirements for individual units of work are specified in other specification sections.
Time of closeout is directly related to "Substantial Completion", and therefore may be either a single time period for entire work or a series of time periods for individual parts of the work which have been noted as substantially complete at different dates.
1.2 PREREQUISITES TO SUBSTANTIAL COMPLETION
A. General: Prior to requesting inspection for certification of substantial completion
(for either entire work or portions thereof):
1. Provide final record documents including air handling unit factory start-up documents for the entire project of portion thereof.
2. Provide operating and maintenance manuals.
3. Provide training/instructions to Owner maintenance personnel.
4. Start-up testing of all systems.
5. Testing, balancing, adjusting and commissioning of all systems.
6. Discontinue (or change over) and remove from project site temporary facilities and services, along with construction tools and facilities, and similar elements.
7. In progress payment request, coincident with or first following date claimed, show either 95% completion for portion of work claimed as "substantially complete", or list incomplete items, value of work not completed, and reasons for being incomplete. Include supporting documentation for completion as indicated in these contract documents.
B. Inspection Procedures: Upon receipt of Contractor's request, the
Design Professional will either proceed with inspection or advise Contractor of prerequisites not fulfilled. Following initial inspection, the Design Professional will
CONSTRUCTION DOCUMENTS 01500-2
BRADY & ANGLIN
note substantial completion, or advise Contractor of work which must be performed and repeat inspection when requested and assured that work has been substantially completed. Results of completed inspection will form initial "punch-list" for final acceptance.
1.3 PREREQUISITES TO FINAL ACCEPTANCE
A. General: Prior to requesting final inspection for certification of final acceptance and final payment, as required by General Provisions and Conditions, complete the following and list known exceptions (if any) in request:
1. At the finish of substantial completion, the 95% completion payment pay app can be submitted. Once all of the punch list items are completed and verified, the final pay app for retainage can be submitted.
2. Submit copy of final punch-list of itemized work to be completed or corrected, stating that each item has been completed or otherwise resolved for acceptance.
3. Complete final cleaning up requirements, including touch-up painting of marred surfaces.
4. Touch-up and otherwise repair and restore marred exposed finishes.
B. Reinspection Procedure: Upon receipt of Contractor's notice that the work has been completed, including punch-list items resulting from earlier inspections, and excepting incomplete items delayed because of acceptable circumstances, the Design Professional will reinspect the work. Upon completion of reinspection, the Design Professional will either prepare certificate of final acceptance or advise Contractor of work not completed or obligations not fulfilled as required for final acceptance. If necessary, procedure will be repeated.
C. Record Sample Submittal: Immediately prior to date(s) of substantial completion, the Design Professional and the Owner will meet with Contractor at site, and will determine which (if any) of submitted samples maintained by Contractor during progress of the work are to be retained by the Owner. Comply with the Design Professional instructions for packaging, identification marking, and delivery.
2.1 INSTRUCTIONS TO MAINTENANCE PERSONNEL
A. Where instructions to maintenance personnel are specified in other sections furnish, without additional expense to the Owner, the services of competent instructors, who will give full instruction in the care, adjustment, and operation of the systems and equipment to designated maintenance personnel.
B. Each instructor shall be familiar with all parts of the system on which he is to give instruction and shall be trained in operating theory as well as in practical
CONSTRUCTION DOCUMENTS 01500-3
BRADY & ANGLIN
operation and maintenance work. Employ factory trained instructors wherever practical and available.
C. Unless otherwise required or approved, give instruction during the regular work week prior to the equipment being accepted and turned over to the Owner for regular operation. Where significant changes or modifications in equipment are made under the terms of the guarantee, provide additional instruction as may be necessary to acquaint the operating personnel of the changes or modifications.
When more than four man-days (32 hours) of instruction are specified, approximately half of the time shall be classroom instruction and the other half with the equipment or system.
D. Utilize the maintenance manual for the system or equipment as a text for instruction. Instruction shall include a review of the maintenance manual.
E. Upon completion, obtain written acknowledgment from the Owner that the required instruction was completed.
2.2 POSTED OPERATING INSTRUCTIONS
A. Post operating instructions approved by the Design Professional for each system and each principal piece of equipment for the use of operation and maintenance personnel.
Include wiring and control diagrams showing the complete layout of the entire system including equipment, piping, and valves, and control sequence, framed under glass or approved laminated plastic and posted where directed by the Design Professional.
Printed or engraved operating instructions for each principal piece of equipment including start-up, proper adjustment, operating, lubrication, shut-down, safety precautions, procedure in the event of equipment failure, and any other necessary items of instruction as recommended by the manufacturer of the unit shall be attached to or posted adjacent to the piece of equipment.
Operating instructions exposed to the weather shall be made of weather-resisting materials or shall be suitably enclosed to be weather protected.
Operating instructions shall not fade when exposed to sunlight and shall be secured to prevent easy removal or peeling.
BASIC MECHANICAL REQUIREMENTS 15010-1
BRADY & ANGLIN
SECTION 15010 - BASIC MECHANICAL REQUIREMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Basic mechanical requirements specifically applicable to Division 15 Sections, in addition to Division 1—General Requirements, General Conditions and Supplementary General Conditions.
B. This Division of the specifications includes mechanical;
1. Heating, Ventilating, Air Conditioning (HVAC)
1.02 GENERAL NOTES
A. All work shall be performed in strict accordance with the construction documents.
B. All work shall be performed at a minimum in strict accordance with the requirements of the 2023 Florida Building Code (7th Edition) and the 2023 Florida Fire Protection Code.
C. The contractor shall coordinate the sequencing and execution of all trades in strict conformance with the requirements of all construction drawings and contract documents.
D. The contractor shall maintain and protect from damage all Portions of the existing facility scheduled to remain or not indicated for demolition. All damaged areas and elements shall be replaced to match existing adjacent construction in all respects.
E. Prior to any demolition, the contractor and owner shall walk through the project and establish a Punch List of existing conditions. Items not identified and later damaged due to construction shall be the contractor’s responsibility.
F. Field verify all dimensions prior to demolition work. Coordinate as required for new work.
G. The contractor shall provide for the cutting, patching, and painting of all exterior and interior finished surfaces to match existing as required to facilitate scope of work.
H. The contractor shall protect the tenants from construction activities and provide for a secure construction site.
I. The contractor shall coordinate all work with Owner’s policies and procedures prior to commencement of construction.
BASIC MECHANICAL REQUIREMENTS 15010-2
BRADY & ANGLIN
J. The contractor shall construct temporary dust and noise control barrier ass required for the safety and protection of the occupants during work in progress and throughout the phases of the work. Coordinate such barriers with the Owner and occupants as required.
K. Any work that will cause interruptions to Star Center tenants, whether the work is inside the tenant space or outside of the tenant space, especially welding, must be completed after hours or on weekends and coordinated with the Star Center and the tenants.
1.03 SPECIAL GENERAL NOTES
Special security clearance requirements below roof work locations: all contractors must apply for access into Raytheon spaces and must be U.S. citizens. Each person must provide proof of citizenship (Driver License AND passport (current or expired). There are no exceptions.
A. Areas Below roof work are occupied by a government contractor (Raytheon) and requires a security background check for all contractor personnel working inside Raytheon areas. All contractor employees required to work within the Raytheon tenant areas for this project shall be required to register with, and be authorized by Raytheon security to work in their spaces. All visitors and crew personnel shall coordinate arrival and departure times with facility engineer. A maximum of three non-escort badges will be awarded to the prime contractor. Each subcontractor will be allowed a maximum of two non-escort badges. All other technicians shall apply for daily visitor badges when entering Raytheon. Security clearance of employees required to work within the Raytheon tenant spaces shall be obtained prior to the start of work in these areas. Contact the Star Center facility engineer for more information.
B. Existing roof surface protection and approved contractor note: at all times, areas on the roof used for staging work / used as access to the project areas, shall be covered with plywood sheathing to protect the existing roof surface from damage or punctures, no exceptions. The prime contractor is responsible for repairing and its cost for any damage to the roof caused by the prime contractor or any of the subcontractors. A Star Center approved roofing contractor shall be used for all roofing work on this project, no exceptions. Any new roofing work within the scope of the project, or repair to the damages to the existing roof caused by the contractor during the project shall be done by the contractor using a Star Center approved roofing contractor. (PCG SBR registered roofing contractors – Precision Roofing Services PRS or Allied Roofing).
C. The contractor shall provide a proposed work schedule to the Star Center (SC) project manager (PM) at the time of the pre-construction meeting. Refer to project specifications and drawings. The work schedule for all trades shall be coordinated with the Star Center PM Any work affecting tenant operations shall be scheduled at night or on the weekend as approved by the Star Center manager and tenant(s).
BASIC MECHANICAL REQUIREMENTS 15010-3
BRADY & ANGLIN
D. The space below AHU-104 is occupied by a tenant that requires escorting by the tenant at all times. This work shall be scheduled and coordinated well in advance with the SC PM and the tenant representative. Any work in Raytheon spaces shall follow the Raytheon badging requirements and contractor safety requirements listed in item 1, and elsewhere in the project specifications and drawings.
E. The removal and installation of AHU-104 utilizing a crane shall be completed over scheduled weekend. Crane lifting activities shall start at approximately 5PM on a Friday and unit installation shall be completed by Monday morning at 7AM.
F. The removal of AHU 161 & 162 shall be completed over scheduled weekends. Starting at approximately 5PM on Friday and unit installation completed by 7AM on Monday.
G. There is structural welding required in the project. Submit certifications for welder(s) on the project. Their certification shall be in accordance with AWS D1.1 Structural Welding Code – Steel. Provide certifications during submittal process.
1.04 INTENT
A. It is the intention of these specifications and drawings to call for finished work, tested, and ready for operation. Wherever the word "provide" is used, it shall mean "furnish and install complete and ready for use."
B. Minor details not usually shown or specified, but necessary for the proper installation and operation, shall be included in the work, the same as if herein specified or shown.
C. The term “Basis of Design” used throughout this document shall be understood to mean a particular manufacturer’s equipment (as scheduled specifically on the drawings or specifications) has been used as the basis by the Design Engineer to establish physical dimensions, quality, and performance required, in addition to providing a basis for interaction with other ancillary components and/or other trades. Therefore, it shall be understood that use of a piece of equipment other than that identified as the Basis of Design may impact performance of an overall engineered system or may require revisions to ancillary interfacing equipment, and thus any manufacturer’s equipment other than that listed as Basis of Design shall require written approval via Addendum prior to bid except where the manufacturer’s name is specifically listed in these specifications as a pre-approved substitute or an accepted manufacturer. All substitutes, pre-approved substitutes, accepted manufacturers, and/or Basis of Design are subject to all requirements of quality, physical characteristics (i.e., dimension, sound, etc), and performance, etc., as set forth in these specifications and contract documents.
BASIC MECHANICAL REQUIREMENTS 15010-4
BRADY & ANGLIN
1.05 SURVEYS AND MEASUREMENTS
A. Base all measurements, both horizontal and vertical from established bench marks. All work shall agree with these established lines and levels. Verify all measurements at site and check the correctness of same as related to the work. All material take-offs for the site shall be field measured prior to bids.
1.06 DRAWINGS
A. Drawings are diagrammatic and indicate the general arrangement of systems and work included in the contract. Drawings are not to be scaled.
The architectural drawings and details shall be examined for exact location of fixtures and equipment. Where they are not definitely located, this information shall be obtained from the Architect.
B. If directed by the Engineer, the Contractor shall, without extra charge, make reasonable modifications in the layout as needed to prevent conflict with work of other trades or for proper execution of the work.
C. At the time of each shop drawing submission, the Contractor shall call the Engineer's attention (in writing) to, and plainly mark on shop drawings, any deviations from the Contract Documents. (See Paragraph 1.06, B.)
D. Samples, drawings, specifications, and catalogs submitted for approval shall be properly labeled indicating specific service for which material or equipment is to be used, location, section and article number of specifications governing, Contractor's name, and name of job. All equipment shall be labeled to match labeling on contract documents.
E. Control Systems: Submit description of operation and schematic drawings of the entire control system. Include bulletins describing each item of control equipment or component.
F. Catalogs, pamphlets, or other documents submitted to describe items on which approval is being requested, shall be specific and identification in catalog, pamphlet, etc. of item submitted shall be clearly made in ink. Data of a general nature will not be accepted.
G. Approval rendered on shop drawings shall not be considered as a guarantee of measurements or building conditions. Where drawings are approved, said approval does not mean that drawings have been checked in detail; said approval does not in any way relieve the Contractor from his responsibility or necessity of furnishing material or performing work as required by the contract drawings and specifications.
H. All shop drawings shall be submitted to the Engineer by Contractor no later than 30 days from the day of contract award.
BASIC MECHANICAL REQUIREMENTS 15010-5
BRADY & ANGLIN
I. Failure of the Contractor to submit shop drawings in ample time for checking shall not entitle him to an extension of contract time, and no claim for extension by reason of such default will be allowed.
J. Submit all Division 15 submittals at one time in one integral group. Piece-by-piece submission of individual items will not be acceptable. Engineer may check contents of each submittal set upon initial delivery; if not complete as set forth herein, submittal sets may be returned to Contractor without review and approval and will not be accepted until made complete.
K. Routing and methods of support of piping shall be shown on shop drawings and shall have the review of the Engineer prior to fabrication and installation.
Spacing of supports shall be as specified in Section 15140, or if not specified, shall not exceed the suggested maximum spacing recommended in ANSI B31.1 for each type of line. Supports shall be fabricated as detailed on reviewed shop drawings. Provide supports so located that temporary supports are not required during removal of valves or equipment. Insofar as possible, support lines directly from Building structure.
L. At the close of the job, prior to final review, electronic PDF files on thumb drive or CD ROM shall be submitted by transmittal letter to the Engineer for review and acceptance:
1. Equipment warranties;
2. Contractor's warranty;
3. Parts list and manuals for all equipment;
4. Balance and test readings;
5. Operating instructions (in writing);
6. Written instructions on maintenance and care of the system.
1.07 SUBMITTALS
A. Submit Manufacturer's published technical data, catalog cuts, wiring diagrams, shop drawings, samples and testing and balancing logs for all elements of the HVAC work. Submit under provisions of General Conditions and Supplementary General Conditions.
B. No equipment, piping, ductwork or components shall be fabricated, delivered, erected, or connected other than from shop drawings reviewed and approved by the Engineer.
C. It shall be understood that review of shop drawings by the Engineer does not supersede the requirement to provide a complete and functioning system in compliance with the Contract Documents.
D. Equipment Supports: Submit detailed shop drawings indicating equipment weight and dimensions, support material, connections, anchoring, and vibration isolation.
BASIC MECHANICAL REQUIREMENTS 15010-6
BRADY & ANGLIN
E. Submittals shall include, but not be limited to the following:
1. Submit long lead items first (AHU’s, VFD’s, etc.), then remaining items in one package.
2. All equipment; cooling, heating, plumbing, electrical motors, starters, controls, etc.
3. Voltage, phase, and amps of each electrical item, such as motors, etc.
4. All auxiliary equipment.
5. Pipe, ductwork, valves, insulation, etc.
1.08 SUBSTITUTIONS
A. Materials and equipment are specified herein by a single or by multiple Manufacturers to indicate quality and performance required. The drawings are based upon equipment scheduled on drawings and specified. If another Manufacturer is considered for substitution during the bidding process, the Mechanical Contractor shall be responsible for coordinating all electrical, mechanical or structural changes, and any costs associated with said changes. Comparable equipment Manufacturers which are listed below equipment indicated as “Basis of Design” shall be considered as substitutes.
Manufacturers other than the Basis of Design shall submit catalog information and 1/4" scale plan and section drawings showing proper fit and all clearances for maintenance items.
B. The only Substitutions shall be considered approved so named in the specifications as a pre-approved substitute. The approval of any substitutions shall not be construed as a shop drawing approval. The substitute or equal must be submitted as described in the specifications and meet all the requirements of the specifications and drawings.
C. Where the Contractor proposes to use an item of equipment other than that specified or detailed on the drawing, which requires any redesign of the structure, partitions, foundations, piping, wiring, or any other part of the mechanical or electrical, all such redesign, and all new drawings and detailing required therefore, shall be prepared by the Subcontractor at his own expense and submitted to the Architect/Engineer for approval.
D. Where such approved deviation requires quantity and arrangement of ductwork, piping, wiring, conduit, and equipment from that specified or indicated on the drawings, the Contractor shall furnish and install any such ductwork, piping, structural supports, insulation, controllers, motors, starters, electrical wiring and conduit, and any other additional equipment required by the system, at no additional cost to the Owner.
BASIC MECHANICAL REQUIREMENTS 15010-7
BRADY & ANGLIN
1.09 COOPERATION WITH OTHER TRADES
A. Give full cooperation to other trades and furnish in writing to the General Contractor, with copies to the Architect, any information necessary to permit the work of all trades to be installed satisfactorily and with the least possible interference or delay.
B. When work installed under this Division will be in close proximity to, or will interfere with work of other trades, assist in working out space conditions to make a satisfactory adjustment. If so directed by the Engineer/Architect, prepare composite working drawings and sections at a suitable scale not less than 1/4" = 1'0", clearly showing how work is to be installed in relation to the work of other trades. If the work is installed before coordinating with other trades, or so as to cause any interference with work of other trades, make all the necessary changes in work to correct the condition without extra charge.
C. Furnish to other trades, as required, all necessary templates, patterns, setting plans, and shop details for the proper installation of work and for the purpose of coordinating adjacent work.
1.10 PROTECTION
A. Protect all work and material provided under this Division from damage. All damaged equipment work or material provided under this Division shall be replaced with new. Re-builts are not acceptable.
B. Protect all work and equipment until inspected, tested, and accepted.
Protect work against theft, injury, or damage; and carefully store material and equipment received on site which are not immediately installed. Close open ends of work with temporary covers or plugs during storage and construction to prevent entry of obstructing material.
1.11 SCAFFOLDING, RIGGING, AND HOISTING
A. Provide all scaffolding, rigging, hoisting, and services necessary for erection and delivery into the premises of any equipment and apparatus furnished.
Remove same from premises when no longer required.
1.12 REMOVAL OF RUBBISH
A. This Contractor shall at all times keep premises free from accumulations of waste materials or rubbish caused by his employees or work. Clean every day at completion of work he shall remove all his tools, scaffolding, materials, and rubbish from the building and site. He shall leave the premises and his work in a clean, orderly, and acceptable condition every day.
B. All plaster, concrete, cement, etc. shall be removed from all pipe, hangers, and equipment prior to painting and/or concealment.
BASIC MECHANICAL REQUIREMENTS 15010-8
BRADY & ANGLIN
1.13 SAFETY
A. This Contractor shall comply with Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C.333), Title 29—Labor, Chapter XIII, Bureau of Standards, Department of Labor, Part 1518—Safety and Health Regulations for Construction; and that his housekeeping and equipment be maintained in such a manner that they comply with the Florida Industrial Commission Safety Code and Regulations of the Federal Williams—Steiger Occupational Safety and Health Act of 1970 (OSHA), wherein it states that the Contractor shall not require any laborer or mechanic employed in the performance of the contract to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to his health and safety.
1.14 SUPERVISION
A. This Contractor shall provide a competent, experienced, full time superintendent who is acceptable to the Engineer and Owner, and who is authorized to make decisions on behalf of the Contractor.
1.15 LUBRICATION
A. Where necessary, provide means for lubricating all bearings and other machine parts. If a part requiring lubrication is concealed or inaccessible, extend a lubrication tube with suitable fitting to an accessible location and suitably identify it.
B. After installation, properly lubricate all parts requiring lubrication and keep them adequately lubricated until final acceptance by the Owner.
1.16 VALVE CHARTS, TAGS, AND NAMEPLATES
A. Provide at a location designated by the Engineer and the Owner, a valve chart enclosed in an aluminum frame with clear plastic shield. Chart shall show the designated number of each valve, its location and service. Valve numbers shall be same as those shown on the "As-Built" drawings.
B. Each valve shown on the chart shall have a 1-1/2" diameter, 18 gauge brass tag with clearly visible stamped numbers, securely fastened to the valve stem or handle with a heavy brass hook or chain.
C. Each panel mounted switch, thermometer, gauge, or controller for fans, pumps, or other electrically operated equipment shall be clearly designated by a black plastic nameplate of size approved by the Engineer securely fastened with metal pins or screws to the panel directly under the item designated.
D. Refer to Section 15190 for additional information.
BASIC MECHANICAL REQUIREMENTS 15010-9
BRADY & ANGLIN
1.17 WIRING DIAGRAMS
A. Furnish for use under Division 16 all wiring diagrams as may be required for the installation of the wiring to insure proper operation and control of the equipment provided under this Division. Provide the diagrams in time to avoid delays.
1.18 MATERIAL AND WORKMANSHIP
A. All materials and apparatus required for the work, except as specifically specified otherwise, shall be new, of first-class quality, and shall be furnished, delivered, erected, connected and finished in every detail, and shall be so selected and arranged as to fit properly into the building spaces.
Where no specific kind or quality of material is given, a first-class standard article as approved by the Engineer shall be furnished. Refer to substitutions in this Section.
B. Unless otherwise specifically indicated on the plans or specifications, all equipment and materials shall be installed with the approval of the Engineer in accordance with the recommendations of the Manufacturer. This includes the performance of such tests as the Manufacturer recommends.
1.19 QUIET OPERATION AND VIBRATION
A. All work shall operate under all conditions of load without any sound or vibration which is objectionable in the opinion of the Engineer and the Owner. In case of moving machinery, sound, or vibration noticeable outside of room in which it is installed, or annoyingly noticeable inside its own room, will be considered objectionable. Sound or vibration conditions considered objectionable by the Engineer and the Owner shall be corrected in an approved manner at no additional expense to the Owner. Vibration control shall be by means of approved vibration eliminators in a manner as specified in Section 15242.
1.20 ACCESSIBILITY
A. This Contractor shall be responsible for the sufficiency of the size of shafts and chases, the adequate clearance in double partitions and hung ceilings for the proper installation of his work. He shall cooperate with all other Contractors whose work is in the same space, and shall advise them of his requirements. Such spaces and clearances shall, however, be kept to the minimum size required.
B. This Contractor shall locate all equipment which must be serviced, operated, or maintained in fully accessible positions. Equipment shall include but not be limited to, valves, traps, clean-outs, motors, controllers, switchgear, and drain points. If required for better accessibility, furnish access doors for this purpose. Minor deviations from drawings may be made to allow for better accessibility.
BASIC MECHANICAL REQUIREMENTS 15010-10
BRADY & ANGLIN
C. This Contractor shall provide the access panels for concealed mechanical equipment, valves, controls, dampers, or other device requiring service.
(Refer to Paragraph 1.20 of this section.)
1.21 FOUNDATIONS, SUPPORTS, PIERS, AND ATTACHMENTS
A. Construction of foundations, supports, pads, bases, and piers where mounted on the floor, shall be the same materials and same quality of finish as the adjacent and surrounding flooring material.
B. This Contractor shall furnish and install all necessary foundations, supports, pads, bases and piers required for all air conditioning equipment, piping, pumps, tanks, compressors, and for all other equipment furnished under this Division, and shall submit drawings to the Architect and Engineer for approval before purchase, fabrication or construction of same.
C. For rotating machinery, and for all equipment where foundations are indicated, provide concrete pads as shown. All pads shall be extended six inches (6") beyond machine base in all directions with top edge chamfered.
Inset six inch (6") steel dowel rods into floors to anchor pads. All pads shall have a minimum of 6 x 6 W2.9/W2.9 WWF unless otherwise noted. Shop drawings of all foundations and pads shall be submitted to the Engineer for approval before same are constructed.
D. All equipment, unless shown otherwise, shall be securely attached to the building structure in an approved manner. Attachments shall be of a strong and durable nature and any attachments that are, in the opinion of the Architect and the Engineer, not strong enough shall be replaced as directed.
1.22 WELDING
A. All structural welding shall be done per the structural drawings. The Contractor shall furnish proof of the competency of each welding operator for both field and shop welds and during the submittal process. Certification meeting – AWS-D1.1. Refer to section 01300 – Submittals for additional information.
B. Welded pipe joints shall be made by electric process in accordance with the Code of Pressure Piping ASA B31.1.
C. Welding shall be done with good quality modern welding equipment, by competent operators, and in thorough, first class manner, conforming to AWS Standards.
D. Filler-metal for the welding process shall conform to ASTM A233 "Specification for Mild Steel Arc-Welding Electrodes". Classification of electrodes shall be one of the following: E6010, E6015, E7016, E7018.
E. When welding is to be performed, precautionary measures must be taken to prevent fire. Remove flammable materials and debris from the area.
BASIC MECHANICAL REQUIREMENTS 15010-11
BRADY & ANGLIN
Provide an appropriate extinguisher nearby and a fire-watch at all times.
Refer to Item O. for hot work permit.
F. Pipes shall be cut short and cold sprung into place before welding or fabricating to compensate for expansion of lines when hot.
G. Welds shall be of the single vee butt type. Pipe end shall be shop beveled to 45 degrees to within 1/16 inch of the inside wall surface.
H. The abutting ends of the joints shall be separated before welding to permit complete fusion, tacked in two or more points to maintain alignment, and welded. Welding shall be continuous around the pipe.
I. Welds shall be of sound weld metal, thoroughly fused into the ends of the pipe and to the bottom of the vee, and shall be built up in excess of the pipe wall to give a reinforcement of one-quarter (1/4) the pipe wall thickness and in such a manner that one weld metal will present a gradual increase in thickness from the surface of the pipe to the center of the weld. The minimum width of the weld shall be 2-1/2 times the pipe wall thickness.
J. The fillet welds from the flanges of fittings shall be fused into the pipe and plate for minimum distance of 1-1/2 times the pipe wall thickness and shall be built up to present a minimum throat thickness of depth of weld of 1-1/4 times the pipe wall thickness.
K. Branch connections shall be fabricated by welding. Openings cut into pipe for welded connections shall be accurately made to give carefully matched intersections and welding fittings shall be carefully welded into the pipe system.
L. Welding ells shall be used at all turns in welded pipe lines; no mitered ells will be approved.
M. Where branch piping is three times smaller than the main, branch connections shall be made up with the appropriate manufactured weld-on fitting. Welded tees shall be used for all other branch connections, unless otherwise approved by the Architect/Engineer for a specific case.
1. Approved Manufacturers
a. Allied Piping Products.
b. Bonney Forge.
c. Branch Connections.
d. Branchlets.
e. Tube Turn.
f. Thread-O-Lets.
N. Welds in piping shall be annealed after welding to remove the welding strains. The temperature need not exceed that causing a dull red, and shall
BASIC MECHANICAL REQUIREMENTS 15010-12
BRADY & ANGLIN
be uniform around the pipe. Welds made in place shall be annealed, but the pipe shall be free to expand and shall be properly supported so as to avoid stresses. Annealing shall always be followed by slow cooling.
O. Prior to any welding on roof or in the building, a hot work permit must be obtained from Star Center Operations.
1.23 REGULATORY REQUIREMENTS
A. Conform to applicable Codes and Standards as follows:
1. Standard
a. Certain standard materials and installation requirements are described by reference to standard specifications. These standards are as follows:
ASA ............. American Standards Association.
ASTM .......... American Society for Testing Materials.
ASME ..........
This is the start of the file's text. The full file is on GovTribe.