Salt Lake Valley Transfer Station PT Deck-Pit Repair – Technical Specifications Summary

This document consists of technical specifications and procurement requirements for the Salt Lake County Facilities Management Division's Post-Tension (PT) Deck and Pit Repair project at the Salt Lake Valley Transfer Station located at 502 West 3300 South, Salt Lake City, Utah 84115. The Work encompasses all divisions (01 through 33) of the project specifications and includes repair of the post-tension concrete deck surface and replacement and repair of the pit surround with metal treatment. The Architect is HHY Associates (2180 South 1300 East, Suite 210, Salt Lake City, Utah 84106). The project is scheduled under a single prime contract with Notice to Proceed expected in fall 2026 (October 2026), identified as the optimal timeframe for the Transfer Station facility to accommodate construction operations. The Contract Documents include detailed provisions for substitution requests (both during and after the bidding phase), contract modification procedures, payment applications, project management and coordination, construction progress documentation, submittal procedures, quality requirements, and closeout procedures.

The specifications establish comprehensive administrative and procedural requirements for the Contractor, including mandatory submission of a schedule of values, detailed Contractor's construction schedule using Critical Path Method (CPM) with no individual activity exceeding 20 days, and Cost-loaded schedules coordinated with payment applications. Progress payments are due by the 25th of each month for work completed through the end of the previous month, with applications requiring three signed and notarized original copies submitted to the Architect. The Contractor must comply with strict work restrictions including a non-smoking facility policy (no smoking within 25 feet of building entrances), controlled substance prohibitions, employee identification requirements, and drug and background screening compliance. The specifications require submission of multiple schedules and reports including a startup construction schedule within 14 days of Notice to Proceed, submittal schedules coordinated with the construction schedule, weekly material location reports, and daily construction reports documenting weather, personnel, deliveries, and unusual events. All submittals must be prepared as PDF packages and transmitted via email, with 15 days allowed for initial review and 21 days for sequential review involving consultants or Owner approval.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Specifications

For

SALT LAKE VALLEY

TRANSFER STATION

PT DECK/PIT REPAIR

Project Address:

502 West 3300 South, Salt Lake City, Utah 84115

May 11, 2026

Solicitation #

Owner:

Salt Lake County

Facilities Management Division 2001 South State Street, S3-120 Salt Lake City, UT 84114-3300

Telephone: 385 468 0361

Architect:

2180 South 1300 East

Suite 210

Salt Lake City, Utah 84106

Telephone: 801 466 3996

Fax: 801 466 6022 mail@hhyassoc.com

SLCo. SALT LAKE VALLEY TRANSFER STATION PT DECK/PIT REPAIR HHY ASSOCIATES

TABLE OF CONTENTS 01 0001 - 1

TABLE OF CONTENTS

00 0001 TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

PER OWNER

DIVISION 01 – GENERAL REQUIREMENTS

01 1000 SUMMARY

01 2500 SUBSTITUTION REQUEST

CSI Form 1.5C - Substitution Request During the Bidding Stage CSI Form 13.1A – Substitution request After the Bidding Stage

01 2600 CONTRACT MODIFICATION PROCEDURES

01 2900 PAYMENT PROCEDURES

01 3100 PROJECT MANAGEMENT AND COORDINATION

01 3200 CONSTRUCTION PROGRESS DOCUMENTATION

01 3233 PHOTOGRAPHIC DOCUMENTATION

01 3300 SUBMITTAL PROCEDURES

01 4000 QUALITY REQUIREMENTS

01 4200 REFERENCES

01 5000 TEMPORARY FACILITIES AND CONTROLS

01 6000 PRODUCT REQUIREMENTS

01 7300 EXECUTION

01 7329 CUTTING AND PATCHING

01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 7700 CLOSEOUT PROCEDURES

01 7839 PROJECT RECORD DOCUMENTS

DIVISION 02 – EXISTING CONDITIONS

02 4119 SELECTIVE DEMOLITION

DIVISION 03 – CONCRETE

03 0130 MAINTENANCE OF CAST-IN-PLACE CONCRETE

DIVISION 05 – METALS

05 5000 METAL FABRICATIONS

05 7610 WIRE MESH PANELS

END OF TABLE OF CONTENTS

DIVISION 01 – GENERAL REQUIREMENTS

DIVISION 01 – GENERAL REQUIREMENTS

01 1000 SUMMARY

01 2500 SUBSTITUTION REQUEST

CSI Form 1.5C - Substitution Request During the Bidding Stage CSI Form 13.1A – Substitution request After the Bidding Stage

01 2600 CONTRACT MODIFICATION PROCEDURES

01 2900 PAYMENT PROCEDURES

01 3100 PROJECT MANAGEMENT AND COORDINATION

01 3200 CONSTRUCTION PROGRESS DOCUMENTATION

01 3233 PHOTOGRAPHIC DOCUMENTATION

01 3300 SUBMITTAL PROCEDURES

01 4000 QUALITY REQUIREMENTS

01 4200 REFERENCES

01 5000 TEMPORARY FACILITIES AND CONTROLS

01 6000 PRODUCT REQUIREMENTS

01 7300 EXECUTION

01 7329 CUTTING AND PATCHING

01 7419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 7700 CLOSEOUT PROCEDURES

01 7839 PROJECT RECORD DOCUMENTS

SUMMARY 01 1100 - 1

SECTION 01 1100 – SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes:

1. Project information.

2. Work covered by Contract Documents.

3. Phased construction.

4. Work under separate contracts.

5. Notice to Proceed.

6. Access to site.

7. Work restrictions.

8. Coordination with occupants.

9. Specification and drawing conventions.

B. Related Section:

1. Division 1 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 PROJECT INFORMATION

A. Project Identification: Salt Lake County - Salt Lake Valley Transfer Station PT Deck/Pit Repair.

Location: 502 West 3300 South, Salt Lake City, Utah 84115.

B. Architect: HHY Associates, 2180 South 1300 East, Suite 210, Salt Lake City, Utah 84106, 801.466.3996.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of the following:

1. The Work includes all of the work of Divisions 01 thru 33 for the Salt Lake County – Salt Lake Valley Transfer Station PT Deck/Pit Repair.

B. Type of Contract.

1. Project will be constructed under a single prime contract.

1.4 WORK UNDER SEPARATE CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts.

Coordinate the Work of this Contract with work performed under separate contracts.

SUMMARY 01 1100 - 2

B. Preceding Work: Owner may award separate contract(s) for construction operations at Project site. Those operations are scheduled to be completed before work under this Contract begins.

C. Concurrent Work: Owner may award separate contract(s) for concurrent construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

D. Subsequent Work: Owner may award separate contract(s) for subsequent additional work to be performed at site following 100% Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.

1.5 NOTICE TO PROCEED

A. Notice to Proceed for the project will be issued in the fall (October 2026), being the best time for the Transfer Station facility to accommodate the construction.

1.6 ACCESS TO SITE

A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

B. Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Limit site disturbance, including earthwork and clearing of vegetation, to site areas indicated on the drawings.

2. Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.

1.7 WORK RESTRICTIONS

A. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.

B. Controlled Substances: Use of tobacco products and other controlled substances on the Project site is not permitted.

C. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Architect and Owner not less than two days in advance of proposed disruptive operations.

SUMMARY 01 1100 - 3

2. Obtain Architect's and Owner's written permission before proceeding with disruptive operations.

D. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.

E. Employee Screening: Comply with Owner's requirements for drug and background screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Owner's representative.

1.8 COORDINATION WITH OCCUPANTS

A. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to 100% Completion of the Work, provided such occupancy does not interfere with completion of the Work.

Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1. Architect will prepare a Certificate of Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.

2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy.

3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.

4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.9 INTERPRETATION OR CORRECTION OF BIDDING DOCUMENTS

A. The Drawings and the Specifications shall be interpreted as equals. If conflicts arise between the Drawings and the Specifications, and are not clarified in the addenda, then the Bidder is to bid the more expensive interpretation, and complete the work within the original contract time.

1.10 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 1 General Requirements: Requirements of Sections in Division 1 apply to the Work of all Sections in the Specifications.

SUMMARY 01 1100 - 4

C. Drawing Coordination: Requirements for materials and products identified on the Drawings are described in detail in the Specifications. One or more of the following are used on the Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 1100

SUBSTITUTION PROCEDURES 01 2500 - 1

SECTION 01 2500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

B. Related Requirements:

1. Section 01 6000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.

1.3 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed

Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner.

1.4 ACTION SUBMITTALS

A. Substitution Requests: Submit documentation identifying product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use form provided in Project Manual.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.

b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section.

Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

f. Certificates and qualification data, where applicable or requested.

SUBSTITUTION PROCEDURES 01 2500 - 2

g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.

h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for Project, from

ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.

Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's

Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.5 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.6 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

1.7 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

SUBSTITUTION PROCEDURES 01 2500 - 3

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 2500

SUBSTITUTION

REQUEST

(During the Bidding Phase)

Project:

To:

Re:

Substitution Request Number: ____________________________

From:

Date:

A/E Project Number:

Contract For:

Specification Title: Description:

Section: Page: Article/Paragraph:

Proposed Substitution:

Manufacturer: Address: Phone:

Trade Name: Model No.:

Attached data includes product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.

Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its proper installation.

The Undersigned certifies:

x Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

x Same warranty will be furnished for proposed substitution as for specified product.

x Same maintenance service and source of replacement parts, as applicable, is available.

x Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

x Proposed substitution does not affect dimensions and functional clearances.

x Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.

Submitted by:

Signed by:

Firm:

Address:

Telephone:

A/E’s REVIEW AND ACTION

Substitution approved - Make submittals in accordance with Specification Section 01330.

Substitution approved as noted - Make submittals in accordance with Specification Section 01330.

Substitution rejected - Use specified materials.

Substitution Request received too late - Use specified materials.

Signed by: Date:

Supporting Data Attached: Drawings X Product Data Samples Tests Reports

© Copyright 1996, Construction Specifications Institute, 99 Canal Center Plaza, Suite 300 Alexandria, VA 22314

Page of September 1996 CSI Form 1.5C

SUBSTITUTION

REQUEST

(After the Bidding Phase) Project:

To:

Re:

Substitution Request Number:

From:

Date:

A/E Project Number:

Contract For:

Specification Title: Description:

Section: Page: Article/Paragraph:

Proposed Substitution:

Manufacturer Address: Phone:

Trade Name: Model No.:

Installer: Address: Phone

History: New product 2-5 years old X 5-10 years old More than 10 years old

Differences between proposed substitution and specified product:

X Point-by-point comparative data attached

Reason for not providing specified item:

Similar Installation:

Project: Architect:

Address: Owner:

Date Installed:

Proposed substitution affects other parts of Work: X No Yes; explain

Savings to Owner for accepting substitution: ($ ).

Proposed substitution changes Contract Time: No Yes [Add] [Deduct] days.

Supporting Data Attached: Drawings Product Data Samples Tests Reports

© Copyright 1996, Construction Specification Institute, 99 Canal Center Plaza, Suite 300 Alexandria, VA 22314

Page of September 1996 CSI Form 13.1A

CONTRACT MODIFICATION PROCEDURES 01 2600 - 1

SECTION 01 2600 - CONTRACT MODIFICATION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

B. Related Requirements:

1. Section 01 2500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.

2. Section 01 3100 "Project Management and Coordination" for requirements for forms for contract modifications provided as part of web-based Project management software.

1.3 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within 7 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use forms acceptable to Architect.

CONTRACT MODIFICATION PROCEDURES 01 2600 - 2

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Proposal Request Form: Use form acceptable to Architect.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor.

1.6 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 2600

PAYMENT PROCEDURES 01 2900 - 1

SECTION 01 2900 - PAYMENT PROCEDURES

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.2 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of

Contractor's construction schedule.

1. Correlate line items in the schedule of values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with continuation sheets.

b. Submittal schedule.

c. Items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Architect at earliest possible date but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

3. Subschedules for Phased Work: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.

B. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Name of Architect.

c. Architect's project number.

d. Contractor's name and address.

e. Date of submittal.

2. Arrange schedule of values consistent with format of Owner’s Application and

Certificate for Payment with Continuation Sheets on forms standard with Salt Lake County.

3. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of Contract Sum.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

PAYMENT PROCEDURES 01 2900 - 2

5. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

6. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

7. Each item in the schedule of values and Applications for Payment shall be complete.

Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.

8. Schedule Updating: Update and resubmit the schedule of values before the next

Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Payment Application Times: Progress payments shall be submitted to Architect by the 25th day of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.

D. Application for Payment Forms: Use Owner’s Application and Certificate for Payment with

Continuation Sheets on forms standard with Salt Lake County.

E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

PAYMENT PROCEDURES 01 2900 - 3

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to

Owner.

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Schedule of unit prices.

5. Submittal schedule (preliminary if not final).

6. List of Contractor's staff assignments.

7. List of Contractor's principal consultants.

8. Copies of building permits.

9. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

10. Initial progress report.

11. Report of preconstruction conference.

12. Certificates of insurance and insurance policies.

I. Application for Payment at Final Acceptance: After issuing the Certificate of 100% Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Completion issued previously for Owner occupancy of designated portions of the Work.

J. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706-1994, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A-1994, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707-1994, "Consent of Surety to Final Payment."

7. Evidence that claims have been settled.

8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Final Acceptance or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

PAYMENT PROCEDURES 01 2900 - 4

9. Final liquidated damages settlement statement.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 01 2900

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 1

SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project, including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Digital project management procedures.

5. Web-based Project management software package.

6. Project meetings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

C. Related Requirements:

1. Section 01 3200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.

2. Section 01 7300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 7700 "Closeout Procedures" for coordinating closeout of the Contract.

1.3 DEFINITIONS

A. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.4 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

B. Key Personnel Names: Within 5 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 2

site. Identify individuals and their duties and responsibilities; list addresses, cellular telephone numbers, and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1. Post copies of list in Project meeting room, in temporary field office, in web-based Project software directory, and in prominent location inbuilt facility. Keep list current at all times.

1.5 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

1.6 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 3

a. Use applicable Drawings as a basis for preparation of coordination drawings.

Prepare sections, elevations, and details as needed to describe relationship of various systems and components.

b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.

c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

d. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

e. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

f. Indicate required installation sequences.

g. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.

Provide alternative sketches to Architect indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

1.7 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Owner name.

3. Owner's Project number.

4. Name of Architect.

5. Architect's Project number.

6. Date.

7. Name of Contractor.

8. RFI number, numbered sequentially.

9. RFI subject.

10. Specification Section number and title and related paragraphs, as appropriate.

11. Drawing number and detail references, as appropriate.

12. Field dimensions and conditions, as appropriate.

13. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

14. Contractor's signature.

15. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 4

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Architect.

1. Attachments shall be electronic files in PDF format.

D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt by Architect of additional information.

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 01 2600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 5 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number, including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect's response was received.

8. Identification of related Minor Change in the Work, Construction Change Directive, and

Proposal Request, as appropriate.

9. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1.8 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 5

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times a minimum of 10 working days prior to meeting.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Architect, within three days of the meeting.

B. Preconstruction Conference: a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement.

1. Attendees: Authorized representatives of Owner Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Responsibilities and personnel assignments.

b. Tentative construction schedule.

c. Phasing.

d. Critical work sequencing and long lead items.

e. Designation of key personnel and their duties.

f. Lines of communications.

g. Use of web-based Project software.

h. Procedures for processing field decisions and Change Orders.

i. Procedures for RFIs.

j. Procedures for testing and inspecting.

k. Procedures for processing Applications for Payment.

l. Distribution of the Contract Documents.

m. Submittal procedures.

n. Preparation of Record Documents.

o. Use of the premises.

p. Work restrictions.

q. Working hours.

r. Owner's occupancy requirements.

s. Responsibility for temporary facilities and controls.

t. Procedures for moisture and mold control.

u. Procedures for disruptions and shutdowns.

v. Construction waste management and recycling.

w. Parking availability.

x. Office, work, and storage areas.

y. Equipment deliveries and priorities.

z. First aid.

aa. Security.

bb. Progress cleaning.

3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity when required by other Sections and when required for coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 6

installations that have preceded or will follow, shall attend the meeting. Advise Architect of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner and Architect, but no later than 60 days prior to the scheduled date of 100% Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of Owner, Architect, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of Record Documents.

b. Procedures required prior to inspection for 100% Completion and for final inspection for acceptance.

c. Procedures for completing and archiving web-based Project software site data files.

PROJECT MANAGEMENT AND COORDINATION 01 3100 - 7

d. Submittal of written warranties.

e. Requirements for preparing operations and maintenance data.

f. Requirements for delivery of material samples, attic stock, and spare parts.

g. Requirements for demonstration and training.

h. Preparation of Contractor's punch list.

i. Procedures for processing Applications for Payment at 100% Completion and for final payment.

j. Submittal procedures.

k. Coordination of separate contracts.

l. Owner's partial occupancy requirements.

m. Installation of Owner's furniture, fixtures, and equipment.

n. Responsibility for removing temporary facilities and controls.

4. Minutes: Entity conducting meeting will record and distribute meeting minutes.

E. Progress Meetings: Conduct progress meetings at bi-weekly intervals as needed. Meeting format shall be Owner’s format or template.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so.

Discuss whether schedule revisions are required to…