S02 - Spec - Preparation - Rehab and Built-Up.pdf
PDF 228 KB Posted
- Attached to
- Z1DA--528A8-20-801 ROOF REPLACEMENT-RESTORATION
- Solicitation number
- 36C24220B0048
About this file
This solicitation is for roof replacement and restoration services at the VA Western New York Healthcare System in Albany, New York. The contractor shall provide all labor, equipment, materials and supervision to replace and restore the roof in accordance with drawings, specifications and scope of work defined in the solicitation. The project magnitude is between $250,000 and $500,000. The solicitation is a 100% set aside for service-disabled veteran owned small businesses and bidders must be verified and visible in VetBiz. The NAICS code is 238160 with a small business size standard of $16.5M. Bidders must register in SAM and a teleconference will be held for the bid opening to comply with social distancing requirements. The Department of Veterans Affairs Veterans Health Administration VISN 2 is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01 RA 40 Ambulatory Surgery (OR).jpg | JPG image | |
| 02 RA 49 Over Dentistry (at Areaway 14).jpg | JPG image | |
| 03 RA 51 Kitchen Area.jpg | JPG image | |
| 36C24220B0048 0001.docx | DOCX document | |
| 04 RA 69 Respiratory Therapy (Bldg 26).jpg | JPG image | |
| RA 69 Roof Layouts-VA.pdf | ||
| S02 - Davis-Bacon Act WD NY20200002.pdf | ||
| S02 - 36C24220B0048_Solicitation.pdf | ||
| S02 - Roof Layout Drawings and Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 07 01 50
PREPARATION FOR RE-ROOFING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Roof tear-off.
2. Removal of base flashings.
3. Roof replacement preparation.
B. Related Requirements:
1.2 DESCRIPTION OF WORK
A. Re-roofing preparation Work consists of the following:
1. Preparation for Roof Area RA#1: Roof 51-Kitchen:
a. Preparation for: Roof replacement.
b. Existing Roof Type: Ballasted BUR.
c. Existing Deck Type: Concrete deck.
d. Roof tear-off.
e. Removal and reinstallation of indicated components, accessories, and equipment.
f. Removal of base flashings.
g. Removal of vegetation with growing media
2. Preparation for Roof Area RA#2: Roof 69- Building 26:
a. Preparation for: Roof replacement.
b. Existing Roof Type: Ballasted BUR.
c. Existing Deck Type: Metal deck.
d. Roof tear-off.
e. Removal of base flashings.
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, reinstalled, or otherwise indicated to remain
Owner's property, demolished materials shall become Contractor's property and shall be removed from Project site.
1.4 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 and glossary in NRCA's "The NRCA Roofing and
Waterproofing Manual" for definition of terms related to roofing work in this Section.
B. Existing Membrane Roofing System: Roofing system identified above, including roofing membrane, roof insulation, surfacing, and components and accessories between deck and roofing membrane.
C. Roof Re-Cover Preparation: Existing roofing membrane that is to remain and be prepared for reuse or rehabilitation.
D. Roof Tear-Off: Removal of existing membrane roofing system from deck.
E. Partial Roof Tear-Off: Removal of a portion of existing membrane roofing system from deck or removal of selected components and accessories from existing membrane roofing system.
F. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and reinstalled.
G. Existing to Remain: Existing items of construction that are not indicated to be removed.
H. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
I. Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
J. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
K. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
L. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
M. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Temporary Roofing: Include Product Data and description of temporary roofing system. If temporary roof will remain in place, submit surface preparation requirements needed to receive permanent roof, and submit a letter from roofing membrane manufacturer stating acceptance of the temporary membrane and that its inclusion will not adversely affect the roofing system's resistance to fire and wind.
1.6 INFORMATIONAL SUBMITTALS
A. Digital Images or Videos: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, which might be misconstrued as having been damaged by reroofing operations. Submit before Work begins.
B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property for environmental protection. Indicate proposed locations and construction of barriers.
C. Schedule of Re-Roofing Preparation Activities: Indicate the following:
1. Detailed sequence of re-roofing preparation work, with starting and ending dates for each activity. Ensure occupants' on-site operations are uninterrupted.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services.
4. Use of elevator and stairs.
5. Coordination of Owner's continuing occupancy of portions of existing building.
D. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant was recovered.
E. Landfill Records: Indicate receipt and acceptance of hazardous wastes, such as asbestos-containing material, by a landfill facility licensed to accept hazardous wastes.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: Installer of new membrane roofing system.
B. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.
C. Regulatory Requirements: Comply with governing EPA notification regulations before beginning membrane roofing removal. Comply with hauling and disposal regulations of authorities having jurisdiction.
D. Reroofing Conference: Conduct conference at Project site.
1. Meet with Owner; Owner's insurer if applicable; testing and inspecting agency representative; roofing system manufacturer's representative; deck Installer; roofing Installer including project manager, superintendent, and foreman; and installers whose work interfaces with or affects reroofing including installers of roof accessories and roof-mounted equipment.
2. Review methods and procedures related to roofing system tear-off and replacement including, but not limited to, the following:
a. Reroofing preparation, including membrane roofing system manufacturer's written instructions.
b. Procedures for salvaging and recycling of demolition and construction waste
c. Temporary protection requirements for existing roofing system that is to remain during and after installation.
d. Existing roof drains and roof drainage during each stage of reroofing, and roof drain plugging and plug removal requirements.
e. Construction schedule and availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.
f. Existing deck removal procedures and Owner notifications.
g. Condition and acceptance of existing roof deck and base flashing substrate for reuse.
h. Structural loading limitations of deck during reroofing.
i. Base flashings, special roofing details, drainage, penetrations, equipment curbs, and condition of other construction that will affect reroofing.
j. HVAC shutdown and sealing of air intakes.
k. Shutdown of fire-suppression, -protection, and -alarm and -detection systems.
l. Asbestos removal and discovery of asbestos-containing materials.
m. Governing regulations and requirements for insurance and certificates if applicable.
n. Existing conditions that may require notification of Architect before proceeding.
1.8 PROJECT CONDITIONS
A. Owner will occupy portions of building immediately below reroofing area. Conduct reroofing so
Owner's operations will not be disrupted. Provide Owner with not less than 48 hours' notice of activities that may affect Owner's operations.
1. Coordinate work activities daily with Owner so Owner can place protective dust or water leakage covers over sensitive equipment or furnishings, shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below the work area.
2. Before working over structurally impaired areas of deck, notify Owner to evacuate occupants from below the affected area. Verify that occupants below the work area have been evacuated before proceeding with work over the impaired deck area.
B. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.
C. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
D. Limit construction loads on roof to rooftop equipment wheel loads and uniformly distributed loads not exceeding recommendations of Contractor's professional engineer based upon site inspection and analysis.
E. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.
F. Daily Protection: Coordinate installation of roofing so insulation and other components of roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.
G. Hazardous Materials: It is not expected that hazardous materials such as asbestos-containing materials will be encountered in the Work.
1. Hazardous materials will be removed by Owner before start of the Work. Existing roof will be left no less watertight than before removal.
If materials suspected of containing hazardous materials are encountered, do not disturb;
immediately notify Owner. Hazardous materials will be removed by Owner under a separate contract.
PART 2 - PRODUCTS
2.1 INFILL MATERIALS
A. Use infill materials matching existing membrane roofing system materials unless otherwise indicated.
2.2 TEMPORARY ROOFING MATERIALS
A. Design and selection of materials for temporary roofing are responsibilities of Contractor.
2.3 TEMPORARY ROOF DRAINAGE
A. Design and selection of materials for temporary roof drainage are responsibilities of the
Contractor.
PART 3 - EXECUTION
3.1 PREPARATION, GENERAL
A. Pollution Control: Comply with environmental regulations of authorities having jurisdiction.
Limit spread of dust and debris.
1. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
2. Remove debris from building roof by chute, hoist, or other device that will convey debris to grade level.
B. Air Intake Shutdown: Coordinate with Owner to shut down air-intake equipment in the vicinity of the Work. Cover air-intake louvers before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork.
C. Temporary Weather Protection: During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain.
D. Roof Drain Protection: Maintain roof drains in functioning condition to ensure roof drainage at end of each workday. Prevent debris from entering or blocking roof drains and conductors. Use roof-drain plugs specifically designed for this purpose. Remove roof-drain plugs at end of each workday, when no work is taking place, or when rain is forecast.
1. If roof drains are temporarily blocked or unserviceable due to roofing system removal or partial installation of new membrane roofing system, provide alternative drainage method to remove water and eliminate ponding. Do not permit water to enter into or under existing membrane roofing system components that are to remain.
E. Verify that rooftop utilities and service piping have been shut off before beginning the Work.
3.2 ROOF TEAR-OFF
A. General: Notify Owner each day of extent of roof tear-off proposed for that day.
B. Remove aggregate ballast from roofing membrane.
C. Remove loose aggregate from aggregate-surfaced built-up bituminous roofing using a power broom.
D. Roof Drainage: Remove roof drainage items indicated for removal.
E. Roof Tear-Off: Remove existing roofing membrane and other membrane roofing system components down to the deck.
1. Bitumen and felts that are firmly bonded to concrete decks are permitted to remain if felts are dry. Remove unadhered bitumen and felts and wet felts.
2. Remove excess asphalt from steel deck. A maximum of 15 lb/100 sq. ft. (0.72 kg/sq. m) of asphalt is permitted to remain on steel decks.
3. Remove fasteners from deck or cut fasteners off slightly above deck surface.
3.3 DECK PREPARATION
A. Inspect deck after tear-off of membrane roofing system.
B. Concrete Roof Deck: Verify that concrete substrate is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method according to ASTM D 4263 or by pouring 1 pint (0.5 L) of hot roofing asphalt on deck at start of each day's work and at start of each roof area or plane.
Do not proceed with roofing work if moisture condenses under the plastic sheet or if asphalt test sample foams or can be easily and cleanly stripped after cooling.
C. Roof Deck: If broken or loose fasteners that secure deck panels to one another or to structure are observed or if deck appears or feels inadequately attached, immediately notify Architect. Do not proceed with installation until directed by Architect.
1. Unsuitable Deck: If deck surface is not suitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify Architect. Do not proceed with installation until directed by the Owner.
3.4 TEMPORARY ROOFING MEMBRANE
A. Install approved temporary roofing membrane over area to be reroofed.
B. Remove temporary roofing membrane before installing new roofing membrane.
3.5 EXISTING BASE FLASHINGS
A. Remove existing base flashings around parapets, curbs, walls, and penetrations.
B. Do not damage metal counter flashings that are to remain. Replace metal counter flashings damaged during removal with counter flashings of same metal, weight or thickness, and finish.
3.6 DISPOSAL
A. Collect demolished materials and place in containers. Promptly dispose of demolished materials.
Do not allow demolished materials to accumulate on-site.
1. Storage or sale of demolished items or materials on-site is not permitted.
B. Transport and legally dispose of demolished materials off Owner's property.
3.7 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by preparation for re-roofing operations. Return adjacent areas to condition existing before operations began.
END OF SECTION 07 01 50
070150.72 - REHABILITATION OF BUILT-UP ROOFING
SECTION 070150.72 - REHABILITATION OF BUILT-UP ROOFING
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Roof re-coating preparation.
2. Application of reinforced fluid-applied roof membrane and flashings over existing built-up asphalt roofing.
B. Related Requirements:
1. Division 00 Document "Available Information," including the following pre-construction test report attachments.
a. Roof moisture survey report.
2. Division 07 Section "Preparation for Re-Roofing" for existing roofing tearoff, patching, and substrate preparation for rehabilitation of roofing membrane.
1.2 MATERIALS OWNERSHIP
A. Demolished materials shall become Contractor's property and shall be removed from Project site.
1.3 DEFINITIONS
A. Roofing Terminology: Refer to ASTM D 1079 and glossary in NRCA's "The NRCA Roofing
Manual" for definition of terms related to roofing work in this Section.
B. Roofing Re-Coating Preparation: Existing roofing that is to remain and be prepared to accept restorative coating application.
C. Patching: Removal of a portion of existing membrane roofing system from deck or removal of selected components and accessories from existing membrane roofing system and replacement with similar materials.
D. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and reinstalled.
E. Existing to Remain: Existing items of construction that are not indicated to be removed.
F. Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
G. Demolition Waste: Building and site improvement materials resulting from re-roofing preparation, demolition or selective demolition operations.
H. Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
I. Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
J. Salvage: Recovery of demolition or construction waste and subsequent sale or reuse in another facility.
K. Salvage and Reuse: Recovery of demolition or construction waste and subsequent incorporation into the Work.
1.4 ROOFING CONFERENCES
A. Roofing Rehabilitation Preinstallation Conference: Conduct conference at Project site. Review methods and procedures related to roofing system.
1. Meet with Owner, Architect, roofing re-coating materials manufacturer's representative;
roofing re-coating Installer including project manager and foreman; and installers whose work interfaces with or affects re-coating including installers of roof accessories and roof-mounted equipment requiring removal and replacement as part of the Work.
2. Review methods and procedures related to re-coating preparation, including rehabilitation roofing system manufacturer's written instructions.
3. Review drawings and specifications.
4. Procedures for salvaging and recycling of demolition and construction waste.
5. Review temporary protection requirements for existing roofing system that is to remain, during and after installation.
6. Review roof drainage during each stage of re-coating and review roof drain plugging and plug removal procedures.
7. Review and finalize construction schedule, and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.
8. Review base flashings, special roofing details, drainage, penetrations, equipment curbs, and condition of other construction that will affect re-coating.
9. Review HVAC shutdown and sealing of air intakes.
10. Review shutdown of fire-suppression, -protection, and -alarm and -detection systems.
11. Review governing regulations and requirements for insurance and certificates if applicable.
12. Review procedures for asbestos removal or unexpected discovery of asbestos-containing materials.
13. Review existing conditions that may require notification of Owner before proceeding.
1.5 ACTION SUBMITTALS
A. Product Data: For each type of product specified.
B. Sustainable Design Submittals:
1. Product Test Reports: For roof coating, indicating that coated roof will comply with solar reflectance index requirement.
2. Indicate Food, Conservation, and Energy Act of 2008 Bio-based material requirement compliance.
a. Indicate type of bio-based material in product.
b. Indicate the percentage of bio-based content per unit of product.
c. Indicate relative dollar value of bio-based content product to total dollar value of product included in project.
1.6 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer, Manufacturer, and Roofing Inspector.
1. Letter written for this Project indicating manufacturer approval of Installer to apply specified products and provide specified warranty.
B. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, and for dust control. Indicate proposed locations and construction of barriers.
C. Product Test Reports: Upon request, submit reports based on evaluation of comprehensive tests performed by manufacturer and witnessed by a qualified testing agency, for components of roofing rehabilitation system.
D. Contractor's Product Certificate: Submit notarized certificate, indicating products intended for Work of this Section, including product names and numbers and manufacturers' names, with statement indicating that products to be provided meet the requirements of the Contract Documents.
1. Provide manufacturer's UL listing certificate for roofing system.
E. Warranties: Unexecuted sample copies of special warranties.
F. Existing Conditions Photographs: Show existing conditions of adjoining construction and site improvements, including exterior finish surfaces adjacent to the Work, which might be misconstrued as having been damaged by re-coating operations. Submit before Work begins.
G. Inspection Reports: Daily reports of Roofing Inspector. Include weather conditions, description of work performed, tests performed, defective work observed, and corrective actions required and carried out.
1.7 CLOSEOUT SUBMITTALS
A. Maintenance Data: To include in maintenance manuals.
B. Warranties: Executed copies of approved warranty forms.
1.8 QUALITY ASSURANCE
A. Installer Qualifications: An employer of workers trained by manufacturer, including a full-time on-site supervisor with a minimum of three years' experience installing products comparable to those specified, able to communicate verbally with Contractor, Architect, and employees, and the following:
1. Installer qualified by the manufacturer to install manufacturer's products and furnish warranty of type specified.
B. Manufacturer Qualifications: Primary product manufacturer that is UL listed for roofing system identical to that used for this Project, with minimum five years' experience in manufacture of comparable products in successful use in similar applications, and able to furnish warranty with provisions matching specified requirements.
1. Approval of Other Manufacturers and Comparable Products: Submit the following in accordance with project substitution requirements, within time allowed for substitution review:
a. Product data, including certified independent test data indicating compliance with requirements.
b. Samples of each component.
c. Sample submittal from similar project.
d. Project references: Minimum of five installations of specified products with Owner and Architect contact information.
e. Sample warranty.
C. If Contractor chooses to bid a substitute system, Contractor must bid specified system and submit separate bid for the substitute system. Substitute system must be identified publicly during the pre-bid conference to give all bidders equal opportunity. Bidding contractors proposing substitutes shall submit the following to Architect a minimum of 10 (ten) business days prior to bid date:
1. Written explanation of why the substitute system should be considered.
2. Accredited third-party testing certifications showing that the physical and performance characteristics of the substitute system’s products will meet or exceed those of the specified materials.
3. Printout of current UL assembly approval, meeting or exceeding specified wind uplift and fire rating requirements, showing exact proposed substitute materials.
4. A written summary sheet showing a comparison of physical properties all of the specified products against the proposed substitute products; including printed versions of all manufacturers’ current product data sheets for all products being proposed or compared in the required summary.
5. List minimum five (5) roofing projects, installed within 50 miles of Albany NY project site, using the exact combination of proposed substitute materials. Include all project contact information including project size, names, addresses and contact phone numbers of Owners and Architects involved. Include copies of current warranties for verification.
6. Smallest standard package of, and product data sheets for, all proposed substitute adhesives, mastics, sealants, ply sheets and flashings.
7. Any proposed substitute system that the Architect deems as qualified to compete for the project will be acknowledged by written addendum before the bid date.
8. Voluntary alternate roofing systems submitted by the low bid Contractor, without pre-approval acknowledged by the Architect through the published addendum process, may be rejected without cause by the Owner's Representative.
D. Roofing Inspector Qualifications: A technical representative of manufacturer not engaged in the sale of products and experienced in the installation and maintenance of the specified roofing system, qualified to perform roofing observation and inspection specified in Field Quality Control Article, to determine Installer's compliance with the requirements of this Project, and approved by the manufacturer to issue warranty certification. The Roofing Inspector shall be one of the following:
1. An authorized full-time technical employee of the manufacturer.
2. An independent party certified as a Registered Roof Observer by the Roof Consultants
Institute, retained by the Contractor or the Manufacturer and approved by the Manufacturer.
E. Manufacturer's Installation Instructions: Obtain and maintain on-site access to manufacturer's written recommendations and instructions for installation of products.
1.9 PROJECT CONDITIONS
A. Weather Limitations: Proceed with rehabilitation work only when existing and forecasted weather conditions permit Work to proceed without water entering into existing roofing system or building.
1. Store all materials prior to application at temperatures recommended by manufacturer.
2. Apply coatings within range of ambient and substrate temperatures recommended by manufacturer.
3. Do not apply roofing in snow, rain, fog, or mist.
B. Protect building to be rehabilitated, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from rehabilitation operations.
C. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
D. Daily Protection: Coordinate installation of roofing so insulation and other components of roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.
E. Owner will occupy portions of building immediately below re-coating area. Conduct re-coating so Owner's operations will not be disrupted. Provide Owner with not less than 72 hours' notice of activities that may affect Owner's operations.
1.10 WARRANTY
A. Manufacturer: Manufacturer's standard warranty form, covering work of this Section, in which manufacturer agrees to repair or replace components of roofing system that fail in materials or workmanship within warranty period.
1. Warranty Period: 20 years from date of completion.
B. Installer Warranty: Installer's warranty signed by Installer, covering the Work of this Section, on form acceptable to Roofing Manufacturer and Owner.
1. Warranty Period: 2 years from date of completion.
C. Manufacturer Inspection Services: By manufacturer's technical representative, to report maintenance responsibilities to Owner necessary for preservation of Owner's warranty rights. The cost of manufacturer's inspections is included in the Contract Sum.
1. Inspections to occur in following years: 2, 5, 10, 15 following completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Manufacturer/Product: The roof system specified in this Section is based upon products of Tremco, Inc., Beachwood, OH, (800) 562-2728, www.tremcoroofing.com that are named in other Part 2 articles. Provide specified products.
1. Subject to compliance with requirements, approved alternate manufacturers are:
a. Kemper
b. Sika
B. Source Materials: Obtain roofing materials from single source from single manufacturer.
2.2 PERFORMANCE REQUIREMENTS
A. General Performance: Rehabilitated roofing shall withstand exposure to weather without failure or leaks due to defective manufacture or installation.
1. Accelerated Weathering: Roofing system shall withstand 2000 hours of exposure when tested according to ASTM G 152, ASTM G 154, or ASTM G 155.
B. Material Compatibility: Provide roofing materials that are compatible with one another under conditions of service and application required, as demonstrated by roofing manufacturer based on testing and field experience.
C. Exterior Fire-Test Exposure: Roofing system exterior fire-test exposure performance following application of rehabilitation coating shall be not be less than that of the prerehabilitated roof performance when tested in accordance with ASTM E 108, based upon manufacturer's tests of identical applications.
D. Bio-Based Content: Provide roofing rehabilitation coating materials meeting requirements of USDA Bio-based Affirmative Procurement Program, with not less than 20 percent bio-based content.
2.3 MATERIALS
A. General: Rehabilitative re-coating materials recommended by roofing system coating manufacturer for intended use and compatible with components of existing membrane roofing system.
B. Infill Materials: Where required to replace test cores and to patch existing roofing, use infill materials matching existing membrane roofing system materials, unless otherwise indicated.
C. Temporary Roof Drainage: Design and selection of materials for temporary roof drainage are responsibilities of the Contractor.
2.4 FLUID-APPLIED ROOFING MEMBRANE
A. Polyurethane Elastomeric Fluid-Applied System: Two-coat fluid-applied roofing membrane formulated for application over prepared existing roofing substrate.
1. Polyurethane roof coating system base coat, bio-based, low-odor low-VOC two-part, for use with a compatible top coat.
a. Basis of design product: Tremco, AlphaGuard BIO Base Coat.
b. Combustion Characteristics, UL 790: Class A, for two-coat system.
c. Volatile Organic Compounds (VOC), maximum, ASTM D3960: 1 g/L.
d. Accelerated Weathering, 5000 hours, ASTM G154: Pass.
e. Hardness, Shore A, minimum, ASTM D2240: 88.
f. Solids, by volume, ASTM D2697: 100 percent.
g. Bio-Based Content, Minimum: 70 percent.
h. Minimum Thickness, Base Coat reinforced over Smooth BUR, MB, Concrete, Single-Ply: 48 mils (1.22 mm) wet.
2. Polyurethane roof coating system top coat, bio-based low-odor low-VOC two-part, for application over compatible base coat.
a. Basis of design product: Tremco, AlphaGuard BIO Top Coat.
b. Combustion Characteristics, UL790: Class A, for two-coat system.
c. Volatile Organic Compounds (VOC), maximum, ASTM D3960: <6 g/L.
d. Solar Reflectance Index (SRI), ASTM E1980: For white, not less than 103.
e. Accelerated Weathering, 5000 hours, ASTM G 154: Pass.
f. Hardness, Shore A, minimum, ASTM D2240: 81.
g. Solids, by volume, ASTM D2697: 100 percent.
h. Bio-Based Content, Minimum: 60 percent.
i. Minimum Thickness, reinforced system: 32 mils (0.81 mm) wet.
j. Minimum Thickness, Slip-Resistant Coat: 24 mils (0.60 mm) wet.
k. Color: White.
3. Primer for Asphaltic and Single-Ply Membranes: Water-based, polymer-modifed quick-dry low odor primer.
a. Basis of design product: Tremco, AlphaGuard WB Primer.
b. Volatile Organic Compounds (VOC), maximum, ASTM D3960: <1 g/L.
c. Solids, by weight: 70 percent.
4. Primer for Masonry Surfaces: Two-part high-solids epoxy-penetrating low-odor primer for masonry and concrete surfaces.
a. Basis of design product: Tremco, AlphaGuard C-Prime.
b. Volatile Organic Compounds (VOC), maximum, ASTM D3960: 0 g/L.
c. Solids, by weight: 100 percent.
5. Primer for Non-Porous Surfaces: Single-part, water based primer to promote adhesion of urethanes to metals, PVC and other non-porous surfaces.
a. Basis of design product: Tremco, AlphaGuard M-Prime.
b. Volatile Organic Compounds (VOC), maximum, ASTM D3960: 22 g/L.
c. Nonvolatile Content, minimum, ASTM D2369: 5 percent.
d. Density at 77 deg F (25 deg C): 8.3 lb/gal (1kg/L).
6. Primer for Intercoat and Substrate Adhesion: Single-part, quick-drying primer to promote adhesion of urethane products to previous urethane coats and to other approved surfaces.
a. Basis of design product: Tremco, Geogard Primer.
b. Volatile Organic Compounds (VOC), maximum, ASTM D3960: 5 g/L.
c. Coverage Rate, 400 sq. ft/ gal.: 4 mils (0.10 mm) wet.
2.5 AUXILIARY MATERIALS
A. General: Auxiliary materials recommended by roofing system manufacturer for intended use and compatible with existing roofing system and fluid-applied roofing system.
B. Reinforcing Fabric:
1. Polyester Reinforcing and Protection Fabric: 100 percent stitch-bonded mildew-resistant polyester fabric intended for reinforcement of compatible fluid-applied membranes and flashings and as a protection layer under pavers or stone aggregates.
a. Basis of design product: Tremco, Permafab.
b. Tensile Strength, Minimum, ASTM D1682: 50 lbf (23 kg) avg..
c. Elongation, Minimum, ASTM D1682: 60 percent.
d. Tear Strength, Minimum, ASTM D1117: 16 lbf (7.3 kg) avg..
e. Weight: 3 oz./sq. yd (102 g/sq. m).
C. Miscellaneous Accessories: Provide miscellaneous accessories recommended by roofing system manufacturer.
2.6 WALKWAYS
A. Walkway Product: Compatible slip-resistant fluid-applied walkway product.
1. Polyurethane Bio-Based Top Coat, Slip-Resistant: Second top coat with broadcast slip-resistant aggregate.
a. Basis of design product: Tremco, AlphaGuard BIO Top Coat Slip Resistant.
b. Minimum Thickness, Non-Skid Coat: 1.5 gals/SQ (24 wet mils); (0.60 mm) wet.
c. Silica Sand Aggregate: 20 to 30 lb/100 sq. ft..
d. Color: White.
e. Volatile Organic Content (VOC) ASTM D3960: <6 g/l .
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine existing roofing substrates, with Installer present, for compliance with requirements and for other conditions affecting application and performance of roof coatings.
1. For the record, prepare written report, endorsed by Installer, listing conditions detrimental to performance.
2. Verify compatibility of approved re-coating system with and suitability of substrates.
3. Verify that substrates are visibly dry and free of moisture.
4. Verify that roofing membrane surfaces have adequately aged to enable proper bond with re-coating system base coat.
5. Verify that existing roofing membrane is free of blisters, splits, open laps, indications of shrinkage, and puncture damage or other indications of impending roof system failure.
6. Commencing application of fluid-applied re-coating membrane indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Protect existing roofing system that is indicated not to be rehabilitated, and adjacent portions of building and building equipment.
1. Mask surfaces to be protected. Seal joints subject to infiltration by coating materials.
2. Limit traffic and material storage to areas of existing roofing membrane that have been protected.
3. Maintain temporary protection and leave in place until replacement roofing has been completed.
B. Pollution Control: Comply with environmental regulations of authorities having jurisdiction.
Limit spread of dust and debris.
1. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
2. Remove debris from building roof by chute, hoist, or other device that will convey debris to grade.
C. Shut down air intake equipment in the vicinity of the Work in coordination with the Owner. Cover air intake louvers before proceeding with re-coating work that could affect indoor air quality or activate smoke detectors in the ductwork.
1. Verify that rooftop utilities and service piping affected by the Work have been shut off before commencing Work.
D. Maintain roof drains in functioning condition to ensure roof drainage at end of each workday.
Prevent debris from entering or blocking roof drains and conductors. Use roof-drain plugs specifically designed for this purpose. Remove roof-drain plugs at end of each workday, when no work is taking place, or when rain is forecast.
1. Do not permit water to enter into or under existing membrane roofing system components that are to remain.
3.3 ROOFING COATING PREPARATION
A. Roofing Partial Tear-off and Patching: Refer to requirements of Section 070150 "Preparation for Re-roofing."
B. Removal of Wet Insulation: Remove portions of roofing membrane with underlying wet insulation. Remove wet insulation, fill in tear-off areas to match existing insulation and membrane, and prepare patched membrane for application of roof coating specified below.
C. Repair of Ponding Areas: Repair areas indicated as ponding areas or areas of inadequate drainage by removing roof membrane, adding additional insulation as required to provide minimum slopes to drain required by roofing rehabilitation coating manufacturer, and replace membrane with material matching existing. Submit photographic report indicating compliance.
D. Membrane Surface Preparation:
1. Remove walkway pads, pavers and accessories from roofing membrane. Discard damaged pavers. Recycle pavers.
2. Remove blisters, ridges, buckles, roofing membrane fastener buttons projecting above the membrane, and other substrate irregularities from existing roofing membrane that would inhibit application of uniform, waterproof coating.
3. Broom clean existing substrate.
4. Substrate Cleaning: Clean substrate in accordance with requirements of Section 070150.16 "Maintenance Cleaning of Membrane Roofing."
5. Verify that existing substrate is dry before proceeding with application of coating. Spot check substrates with an electrical capacitance moisture-detection meter.
6. Verify adhesion of new products.
E. Existing Flashing and Detail Preparation: Repair flashings, gravel stops, copings, and other roof-related sheet metal and trim elements. Reseal joints, replace loose or missing fasteners, and replace components where required to leave in a watertight condition.
1. Do not damage metal counterflashings that are to remain. Replace metal counterflashings damaged during removal with counterflashings of same metal, weight or thickness, and finish.
2. Roof Drains: Remove drain strainer and clamping ring. Grind metal surfaces down to clean, bare, metal.
F. Surface Priming: Prime surfaces to receive fluid-applied coating using coating manufacturer's recommended product for substrate material. Apply at application rate recommended by manufacturer.
1. Ensure primer does not puddle and substrate has complete coverage.
2. Allow to cure completely prior to application of coating.
3.4 FLUID-APPLIED FLASHING APPLICATION
A. Fluid-Applied Flashing and Detail Base Coat Application: Complete base coat and fabric reinforcement at parapets, curbs, penetrations, and drains prior to application of field of fluid-applied membrane. Apply base coat in accordance with manufacturer's written instructions.
1. Apply base coat on prepared and primed surfaces and spread coating evenly. Extend coating minimum of 8 inches up vertical surfaces and 4 inches onto horizontal surfaces.
2. Back roll to achieve minimum coating thickness as follows, unless additional thickness is recommended by manufacturer; verify thickness of base coat as work progresses.
3. Fabric Reinforcement: Embed fabric reinforcement into wet base coat. Lap adjacent flashing pieces of fabric minimum 3 inches along edges and 6 inches at end laps.
a. Roll surface of fabric reinforcing to completely embed and saturate fabric. Leave finished base coat with fabric free of pin holes, voids, or openings.
4. Roof Drains: Install base coat onto surrounding membrane surface and metal drain bowl flange. Install target piece of fabric reinforcement immediately into wet base coat and roll to fully embed and saturate fabric. Reinstall clamping ring and strainer following application of top coat. Replace broken drain ring clamping bolts.
3.5 FLUID-APPLIED MEMBRANE APPLICATION
A. Fluid-Applied Membrane Base Coat Application: Apply base coat to field of membrane in accordance with manufacturer's written instructions.
1. Apply base coat on prepared and primed surfaces and spread coating evenly.
2. Back roll to achieve minimum coating thickness as follows, unless greater thickness is recommended by manufacturer; verify thickness of base coat as work progresses.
3. Fabric Reinforcement: Embed fabric reinforcement into wet base coat. Lap adjacent flashing pieces of fabric minimum 3 inches along edges and 6 inches at end laps.
a. Roll surface of fabric reinforcing to completely embed and saturate fabric. Leave finished base coat with fabric free of pin holes, voids, or openings.
B. Top Coat Application: Apply top coat to field of membrane and flashings uniformly in a complete, continuous installation.
1. Following curing of base coat and prior to application of top coat, sand raised or exposed edges of fabric reinforcement.
2. Allow base coat to cure prior to application of top coat.
3. Prime base coat prior to application of top coat if top coat is not applied within 72 hours of the base coat application, using manufacturer's recommended primer.
4. Apply top coat extending coating up vertical surfaces and out onto horizontal surfaces.
Install top coat over field base coat and spread coating evenly.
5. Apply top coat and back roll to achieve not less than minimum coating thickness indicated in Part 2 product listing, unless greater thickness is recommended by manufacturer. Verify application thickness as work progresses.
6. Avoid foot traffic on new fluid-applied membrane for a minimum of 24 hours.
C. Joint Sealant: Apply joint sealant at terminations of coating application and in locations required for complete weathertight application.
D. Slip-Resistant Walkway Top Coat: Apply walkway second top coat following application and curing of top coat. Locate walkways as indicated on Drawings.
1. Mask walkway location with tape.
2. Prime first top coat prior to application of walkway top coat if walkway top coat is not applied within 72 hours of the first top coat application, using manufacturer's recommended primer.
3. Apply walkway top coat and back roll to achieve not less than minimum coating thickness indicated in Part 2 product listing, unless greater thickness is recommended by manufacturer. Verify application thickness as work progresses.
4. Broadcast Slip-Resistant Top Coat Aggregate in wet top coat at rate indicated in Part 2 product listing or as otherwise recommended by coating manufacturer.
a. Back roll sand and top coat creating even dispersal of sand. Remove masking immediately.
3.6 FIELD QUALITY CONTROL
A. Roofing Inspector: Owner will engage a qualified roofing inspector to perform roof tests and inspections and to prepare test reports.
B. Roof Inspection: Engage roofing system manufacturer's technical personnel to inspect roofing installation, and submit report to the Architect. Notify Architect and Owner 48 hours in advance of dates and times of inspections. Inspect work as follows:
1. Upon completion of preparation of roof coating substrate, prior to application of coating materials.
2. Following application of coating to flashings and application of base coat to field of roof.
3. Upon completion of coating but prior to re-installation of other roofing components.
C. Repair fluid-applied membrane where inspections indicate that they do not comply with specified requirements.
D. Arrange for additional inspections, at Contractor's expense, to verify compliance of replaced or additional work with specified requirements.
3.7 DISPOSAL
A. Collect demolished materials and place in containers. Promptly dispose of demolished materials.
Do not allow demolished materials to accumulate on-site.
1. Storage or sale of demolished items or materials on-site is not permitted.
B. Transport and legally dispose of demolished materials off Owner's property.
3.8 PROTECTING AND CLEANING
A. Protect roofing system from damage and wear during remainder of construction period.
B. Correct deficiencies in or remove coating that does not comply with requirements, repair substrates, and reapply coating.
C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.
END OF SECTION 070150.72
075113.13 - Page 1 of 11
BUILT-UP ASPHALT ROOFING, COLD-APPLIED
SECTION 075113.13 - BUILT-UP ASPHALT ROOFING, COLD-APPLIED
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Cold-applied built-up asphalt roofing system on concrete deck and metal deck, including but not limited to:
a. Roof insulation.
b. Roof insulation cover board.
c. Roofing membrane ply sheets.
d. Base flashings.
e. Roof surfacing consisting of aggregate surfacing.
f. Walkway material.
B. Related Sections:
1. Division 07 Section "Preparation for Re-Roofing" for existing roofing tear off, patching, and substrate preparation for reroofing.
1.2 DEFINITIONS
A. Roofing Terminology: See ASTM D 1079 and glossary of NRCA's "The NRCA Roofing and Waterproofing Manual" for definition of terms related to built-up roofing.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Roofing Conference: Conduct conference at Project site.
1. Meet with Owner, Owner's insurer if applicable, testing and inspecting agency representative, roofing Installer, roofing manufacturer's representative, and installers whose work interfaces with or affects roofing, including installers of roof accessories and roof-mounted equipment.
2. Review drawings and specifications.
3. Review methods and procedures related to roofing installation, including manufacturer's written instructions.
4. Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.
5. Examine substrate conditions and finishes for compliance with requirements, including flatness and fastening.
6. Review structural loading limitations of roof deck during and after roofing.
7. Review base flashings, special roofing details, roof drainage, roof penetrations, equipment curbs, and condition of other construction that will affect roofing.
8. Review governing regulations and requirements for insurance and certificates if applicable.
9. Review temporary protection requirements for roofing during and after installation.
10. Review roof observation and repair procedures after roofing installation.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: For roofing system, include plans, elevations, sections, details, and attachments to other work. Provide roof plan showing orientation and types of roof deck, orientation of membrane roofing, and fastening spacings and patterns for mechanically fastened components.
1. Base flashings and built-up terminations.
a. Indicate that details meet requirements of this Section.
2. Tapered insulation, including slopes.
3. Crickets, saddles, and tapered edge strips, including slopes.
4. Insulation fastening patterns for corner, perimeter, and field-of-roof locations.
5. Membrane fastening or adhesion requirements.
075113.13 - Page 2 of 11
C. Wind Uplift Resistance Submittal: For roofing system, indicating compliance with wind uplift performance requirements.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer, Manufacturer, and Roofing Inspector.
1. Include letter from Manufacturer written for this Project indicating approval of Installer.
B. Contractor's Product Certificate: Submit notarized certificate, indicating products intended for
Work of this Section, including product names and numbers and manufacturers' names, with statement indicating that products to be provided meet the requirements of the Contract Documents.
C. Manufacturer Certificates: Signed by roofing manufacturer certifying that built-up roofing complies with requirements specified in "Performance Requirements" Article.
1. Submit evidence of compliance of proposed roofing system with performance requirements, including UL listing certificate.
2. Product Compatibility: Indicate manufacturer has verified compatibility of roofing system components, including but not limited to: Roofing membrane, flashing sheets, adhesives, and sealants.
D. Product Test Reports: Based on evaluation of comprehensive tests performed by manufacturer and witnessed by a qualified testing agency, for components of built-up roofing.
E. Warranties: Unexecuted sample copies of special warranties.
F. Field Quality Control Reports: Daily reports of Roofing Inspector. Include weather conditions, description of work performed, tests performed, defective work observed, and Contractor's corrective actions taken to correct defective work.
1.6 CLOSEOUT SUBMITTALS
A. Maintenance Data: To include in maintenance manuals.
B. Warranties: Executed copies of warranties.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: An employer of workers trained and certified by manufacturer, including a full-time on-site supervisor with a minimum of five years' experience installing similar work, able to communicate verbally with Contractor, Architect, and employees, and qualified by the manufacturer to furnish warranty of type specified.
B. Manufacturer Qualifications: Approved manufacturer with UL listed roofing systems comparable to those specified for this Project, with minimum five years' experience in manufacture of comparable products in successful use in similar applications, and able to furnish warranty with provisions matching specified requirements.
C. If Contractor chooses to bid a substitute system, Contractor must bid specified system and submit separate bid for the substitute system. Substitute system must be identified publicly during the pre-bid conference to give all bidders equal opportunity. Bidding contractors proposing substitutes shall submit the following to Architect a minimum of 10 (ten) business days prior to bid date:
1. Written explanation of why the substitute system should be considered.
2. Accredited third-party testing certifications showing that the physical and performance characteristics of the substitute system’s products will meet or exceed those of the specified materials.
3. Printout of current UL assembly approval, meeting or exceeding specified wind uplift and fire rating requirements, showing exact proposed substitute materials.
4. A written summary sheet showing a comparison of physical properties all of the specified products against the proposed substitute products; including printed versions of all manufacturers’ current product data sheets for all products being proposed or compared in the required summary.
075113.13 - Page 3 of 11
5. List minimum five (5) roofing projects, installed within 50 miles of Albany NY project site, using the exact combination of proposed substitute materials. Include all project contact information including project size, names, addresses and contact phone numbers of Owners and Architects involved. Include copies of current warranties for verification.
6. Smallest standard package of, and product data sheets for, all proposed…