This document is a comprehensive set of architectural and engineering design drawings for a Building 1 Entrance Enclosure project at the Lebanon VA Medical Center in Pennsylvania. The project involves modifying the existing Stair 2 exit passageway to provide direct exterior discharge, with key modifications including creating a new exit route through a staff room and mechanical courtyard, installing a security grille, and constructing a new sidewalk to the public way.
The project involves multiple disciplinary drawings including architectural, structural, mechanical, electrical, fire protection, and fire alarm plans. Specific scope includes removing existing windows and walls, installing a new 48-inch door, relocating mechanical equipment, adding a radiant ceiling panel in the corridor, modifying sprinkler and fire alarm systems, and ensuring all work complies with VA fire protection design manual and current building codes. The work is designed to improve emergency egress while maintaining the facility's operational integrity and existing system configurations.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEBANON VAMC
BUILDING 1 ENTRANCE ENCLOSURE
LEBANON, PENNSYLVANIA
DESIGN NARRATIVE
Bid Document SUBMISSION
January 24, 2023
VA Project 595-20-401
AEW #VLEB-009
Prepared by
VA # 595-20-401
AEW | VLEB-009
AE Works Ltd.
Jan. 24, 2023
Lebanon VAMC Building 1 Entrance Enclosure | Narrative
Bid Document
TABLE OF CONTENTS
EXECUTIVE SUMMARY
VA DESIGN GUIDELINES
PHYSICAL SECURITY DESIGN REQUIREMENTS
CONCEPT DEVELOPMENT
DESIGN OPTIONS
ARCHITECTURAL BASIS OF DESIGN
SI T E DE VE LO PM EN T BA SI S O F DESI G N
STRUCTURAL BASIS OF DESIGN
MECHANICAL BASIS OF DESIGN
ELECTRICAL BASIS OF DESIGN
PLUM BI NG BA SI S O F DESI G N
FI RE SU PP RE SSI O N BA SI S O F DESI G N
FI RE ALA RM BA SI S O F DE SI G N
APPENDICES
AE Works Ltd.
EXECUTIVE SUMMARY
The scope of this project has been updated to only account for egress out of Stair 2 (North stair tower) in Building 1. The Stair 2 discharge can be extended with an exit passageway through an existing Staff Room and exterior mechanical courtyard. The design team has detailed the pathway for the new exit in a concept drawing that includes new sidewalks leading to a public way.
An initial building walk-through with the VA was done to observe and discuss existing egress issues and possible solutions. The VA directive on site was to provide options to extend exit passageways for all stairways to an exterior public way. This would provide maximum flexibility for the facility during any future renovation project where an egress pathway may be temporarily unavailable. Since this initial walk thru, it has been determined that only the Stair 2 egress will be resolved.
AE Works Ltd.
VA DESIGN GUIDELINES
MANUALS
The reference manuals and guidelines listed below shall be considered minimum requirements. Nothing shall prevent the architect and engineer from exceeding the applicable requirements. In all cases the most recent editions of referenced standards and guidelines shall apply.
▪ VA Site Development Design Manual
▪ VA Architectural Design Manual
▪ Physical Security Design Manual
▪ PG-18-1 Master Construction Specifications
▪ PG-18-3 Design and Construction Procedures
▪ PG-18-4 Standard Details and CAD Standards
▪ PG-18-5 Equipment Guide List
▪ PG-18-9 Space Planning Criteria and VA-Space & Equipment Planning System
(VA-SEPS)
▪ PG-18-10 Design Manuals
▪ PG-18-12 Design Guides
▪ PG-18-13 Barrier Free Design Guide
▪ PG-18-14 Room Finishes, Door & Hardware Schedule
▪ PG-18-15 Minimum Requirements for A/E Submissions
PHYSICAL SECURITY DESIGN REQUIREMENTS
PHYSICAL SECURITY
All new building elements and passageway additions are proposed within the building footprint and the interior courtyard. No blast-resistance design will be included.
All new exterior doors added to the building will always have free exit access. Controlled access can be provided from the exterior side of the new South Entryway door. Door operations and hardware will be developed in future submissions.
AE Works Ltd.
CONCEPT DEVELOPMENT
SCOPE OF WORK DESIGN GOALS
The main design goals for the project include the following:
▪ Provide an egress pathway improvement from Building 1, Stair Tower 2.
EXISTING FACILITY ASSESSMENT
BUILDING 1
▪ Stair 2 has 2 exits, South Corridor G027 and the radiology corridorat Staff Room
6A. There is an option to extend an exit passageway to an exterior discharge through the Staff Room and mechanical courtyard.
o It is impractical to construct a fire-rated passageway in Corridor G027 as this is a patient circulation pathway to Building 17 and is the main entrance to the Radiology suite.
o Code compliance upgrades will focus on a new exit passageway through the Staff Room and mechanical courtyard.
AE Works Ltd.
DESIGN OPTIONS
STAIR 2
Stair 2 will require construction of a new exit passageway to an exterior exit discharge.
The most practical option would involve a new pathway through the Staff Room and the mechanical courtyard.
The existing electrical closets may not be enclosed by the new passageway. Therefore, the pathway may not extend to the left of the stair door and must cross the existing corridor in a straight line.
The passageway must allow access from both sides to maintain egress from the
Radiology department. The doors are located within recesses to prevent the door swing from obstructing the egress pathway from the stairs. This configuration also has the smallest impact to the sitting area to the right of the stairs.
AE Works Ltd.
STAIR 2 EXIT PASSAGEWAY PLAN
A new exterior door would be installed at an existing window opening. The window opening must be enlarged to match the door size of Stair 2.
The remaining portion of the staff break room will remain a break room with an access door located outside the exit passageway.
The exterior portion of the passageway will require a security grille defining the egress pathway and separating the mechanical equipment from occupants. An opening is being provided in the existing CMU enclosure and a connecting sidewalk installed to complete the pathway.
AE Works Ltd.
STAIR 2 EXTERIOR EXIT PASSAGEWAY PLAN
The location of the new exterior door will avoid existing downspouts along the exterior wall.
The exterior pathway beyond the mechanical enclosure will require modified grading and new site lighting. A portion of the existing retaining wall and stairs will be removed.
The existing courtyard gate and the passageway between the enclosure and Building 1 is too narrow to meet egress requirements and is not considered to be used as part of the egress.
Any new mechanical equipment installed in the courtyard must be positioned to maintain the proposed egress pathway.
AE Works Ltd.
MECHANICAL COURTYARD – EXTERIOR WALL
MECHANICAL COURTYARD – ENCLOSURE
AE Works Ltd.
MECHANICAL COURTYARD – EXTERIOR WALL
MECHANICAL COURTYARD – SIDEWALK
AE Works Ltd.
ARCHITECTURAL BASIS OF DESIGN
APPLICABLE CODES, GUIDELINES & STANDARDS
In performing the technical analysis required in the analysis of the building exit requirements, the following documents, standards, regulations, codes, and design criteria were incorporated:
▪ VA Architectural Design Manual
▪ VA Physical Security Design Manual for Mission Critical Facilities
▪ VA Guidelines, as noted on page 4.
▪ VA Specifications
▪ NFPA 101, Life Safety Code (LSC) – 2021 Edition
▪ International Building Code, 2021 Edition
▪ NFPA 220 – Standard on Types of Building Construction, 2021 Edition
▪ ABAAS – Architectural Barriers Act Accessibility Standards
EXISTING CONDITIONS
The design team performed multiple site walk-throughs with Mark Sternagle throughout September and October to investigate existing conditions around Building
1, Stair 2.
DEMOLITION
STAIR 2
Construction of a new exit passageway will require demolition of portions of the existing
Staff Room 6A. This includes removal of a portion of the corridor wall and room entrance.
A new exterior exit will require removal of an existing window and portion of the exterior wall. Thr exterior opening will have to be increased to match the size of the existing Stair 2 door.
The Stair 2 door will have to be removed and replaced so that it will swing in the direction of travel.
Exterior demolition work will include a new opening in the existing CMU mechanical enclosure and removal and / or repairs to the existing exterior retaining wall and stairs.
AE Works Ltd.
DESIGN
STAIR 2
The new interior exit passageway walls are required to be fire barriers. They will be constructed out of 6” CMU. A horizontal fire-rated barrier will be built between the existing ceiling plane and the passageway and will have a finished gypsum board surface. All rated assemblies must be tested in accordance with ANSI/UL 263 or
ASTM E119 as noted is specifications.
All new interior doors and frames will be hollow metal and are required to have a 90-minute fire resistance rating if located in new rated passageway. Vision panels are permitted in 90-minute doors at the maximum size tested. All doors will have panic hardware in the direction of egress travel.
The new exterior door will have panic hardware in the direction of egress travel.
A new security grille barrier to define the egress pathway is required within the mechanical courtyard.
FINISH MATERIALS
Interior finish materials will be selected as a basis of design to complement the existing medical center for cohesive design aesthetics and standard material maintenance by staff.
Where possible, finishes will match adjacent spaces that have been newly renovated to keep a consistent aesthetic to blend existing with new. Where necessary, some flooring materials will be suggested to be completely new in corridors where older VCT flooring cannot be matched. Materials selected are intended to be durable, sustainable and follow existing maintenance protocols.
Colors and patterns will be presented as part of the complete interior aesthetic package in follow up submissions. This palette of materials will be selected to promote a healing interior environment. Material selections will follow the requirements listed in the VA
Program Guide PG-18-14, Room Finishes, Door, and Hardware Schedule.
AE Works Ltd.
SITE DEVELOPMENT BASIS OF DESIGN
The site development shall comply with the latest local, national, international codes and standards:
▪ PG-18-1 through PG-18-17 VA Guidelines and Specifications
▪ International Existing Building Code (IBC) – 2021 Edition
SCOPE OF WORK
STAIR 2:
Stair 2 is located along the north wall at the west end of Building 1. A new exit path to the south of Building 1 at the mechanical equipment enclosure is to be designed. Site drawings are to be prepared of the existing grading and utilities at the existing mechanical pad and southward to the existing sidewalk and steps. The free-standing masonry wall enclosure and the existing mechanical equipment will be located on the plans.
DEMOLITION
STAIR 2:
A portion of existing masonry wall enclosure at the mechanical pad will be removed.
Existing foundation for light pole may be reused if possible, near existing sidewalk and steps.
EXISTING CONDITIONS
SURVEY
The existing utilities need to be determined for the proposed work at Stair 2.
DESIGN
The main site goals for the project are to:
▪ Provide positive drainage away from buildings and improvements.
▪ Provide tree protection if applicable.
▪ Identify erosion and sediment measures to prevent siltation ofexisting stormwater facilities and tracking of soil onto parking areas and roadways.
▪ Provide route to exit from Stair 2 of Building 1 to outside and through wall enclosure at the mechanical pad.
AE Works Ltd.
▪ Provide construction fencing locations to protect pedestrians during construction.
SITE GRADING
The site development shall consist of determining the location of all underground utilities in the existing courtyard and mechanical enclosure at Stair 2.
UTILITIES
SANITARY SEWER
The existing sanitary sewer should not interfere with the proposed construction. The location of all sanitary sewer components requires verification.
STORM SEWER
The existing storm sewer should not interfere with the proposed construction. The location of all storm sewer components requires verification.
AE Works Ltd.
STRUCTURAL BASIS OF DESIGN
The design of the structural system shall comply with the latest local, national, and international codes and standards.
▪ International Existing Building Code (IBC) - 2021 Edition
▪ VA Physical Security Design Manual for Mission Critical Facilities
▪ VA Structural Design Manual for Hospital Project – February 2014
▪ PG-18-1 thru PG-18-17 VA Guidelines and Specifications
▪ American Concrete Institute (ACI) 318: Building Code Requirements for Structural
Concrete
▪ American Institute of Steel Construction (AISC): Specification for Structural Steel
Building
▪ American Society of Civil Engineers (ASCE): Minimum Design Loads and
Associated criteria for Buildings and Other Structures
▪ American Iron and steel Institute (AISI): North American Specifications for the
Design of Cold-formed Steel Structural Members
EXISTING CONDITIONS
STAIR 2:
Stair 2 is located along the north wall at the west end of Building 1. The existing structure is comprised of concrete floor beams and slab and brick walls. A new exit door is will be located at the first floor. An existing window opening in the south wall will be replaced with the new exit door. Mechanical equipment is located at grade in an area south of the exterior building wall. A free-standing masonry wall encloses the existing mechanical equipment space.
DESIGN CRITERIA
SYSTEM DESCRIPTION
SUPERSTRUCTURE
STAIR 2:
The existing structure at stair 2 is to remain and modifications are not anticipated. New partition walls will consist of 6” CMu. The existing window and brick below the window
AE Works Ltd.
will be removed as required to install the new door. A new lintel above the door opening will be required.
The existing masonry wall enclosure will be analyzed for the new opening. New sidewalk will be comprised of concrete slab-on-grade over a compacted aggregate stone.
AE Works Ltd.
MECHANICAL BASIS OF DESIGN
In performing the analysis of existing mechanical system elements, the following documents, standards, regulations, codes, and design criteria will be incorporated:
▪ VA HVAC Design Manual – March 2022
▪ International Mechanical Code (IMC) - 2021
▪ International Energy Conservation Code (IECC) - 2021
▪ International Existing Building Code (IEBC) – 2021
▪ NFPA 90A – Standard for Installation of Air-Conditioning and Ventilating Systems -
▪ Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA) -
▪ American Society of Heating, Refrigeration, and Air-Conditioning Engineers
(ASHRAE) Standard 62 and 90.1 – 2019
▪ PG-18-1 through PG-18-17 VA Guidelines and Specifications
SYSTEM DESCRIPTION | EXISTING CONDITIONS
EXISTING DRAWINGS
Existing record drawings have been provided for the South Entryway project. The design team requested additional documentation for the area of work at Stair 2, the Staff Room, and the mechanical courtyard. As built mechanical and plumbing drawings were submitted to AE Works prior to this submission.
SURVEY
A site survey was conducted following receipt of existing drawings and selection of a concept that verified the condition of the existing HVAC system(s) in the scope of work areas. There are three existing hot water heaters and one 2-pipe fan coil unit serving the staff room area where the new exit pathway is being proposed. An additional survey was conducted to confirm the as built documentation provided by the VA. Drawings and specifications have been altered since 65% submission.
SYSTEM DESCRIPTION | PROPOSED CONDITIONS
The existing HVAC system(s) will be modified as required to support the new architectural layouts in the scope of work areas. The (3) existing 2-pipe fan coil units are being removed and two out of the three 2-pipe fan coil units will be relocated and installed to serve the cooling load. The heating load can be served by the existing ceiling mounted unit heater in the existing staff room space. This existing unit heater will need to be
AE Works Ltd.
Bid Document relocated along with new piping, however the existing valve assembly may remain. A new set of valves can be implemented if the VA desires. Existing thermostats will be utilized to locally control the fan coil units and unit heater.
A new electric fired radiant ceiling panel will be installed in the corridor area. This radiant panel is required to serve the demand during the heating season. The corridor is an extension of the exit stairway, so according to NFPA 101 forced ventilation air is not acceptable or required. Heating however for that area is required.
CALCULATION METHODOLOGY
The outdoor design conditions (for cooling/heating load calculations) will be based on the closest weather station in the Carrier Hourly Analysis Program (HAP) to the VA’s HVAC
Design Manual conditions for Lebanon, PA which are as follows:
VA Weather Station Data (Harrisburg, PA)
Summer (0.4% db/wb): 92.5/73.8 °F
Winter (99.6% db): 10.7 °F
HAP Weather Station Data (Harrisburg, PA)
Summer (db/wb): 92/74 °F
Winter (db): 9°F
The indoor design conditions are as follows:
Corridors
Winter: 70°F DB
Summer: 75 °F DB
Lounge
Winter: 70°F DB
Summer: 75 °F DB
AE Works Ltd.
ELECTRICAL BASIS OF DESIGN
The electrical engineering design will comply with the latest local, national, and international codes and standards. The following list contains the most relevant and applicable codes and standards to be employed:
▪ VA Electrical Design Manual – December 2019
▪ VA Lighting Design Manual – December 2022
▪ PG-18-1 through PG-18-17 VA Guidelines and Specifications
▪ NFPA 70 – National Electrical Code 2023
▪ NFPA 99-Healthcare Facilities Code 2021
▪ NFPA 101 – Life Safety Code – 2021
▪ IEBC – International Existing Building Code - 2021
▪ IECC – International Energy Conservation Code - 2021
▪ IES Handbook – Illuminating Engineering Society Handbook - 10th Edition
SCOPE OF WORK
The new construction will be connected to existing power distribution in the building. No new panelboards or lighting control panels are planned.
EXISTING DRAWINGS
Existing record drawings have been provided for the South Entryway project. The design team requests additional documentation for the area of work at Stair 2, the Staff Room, and the mechanical courtyard.
LIGHTING AND LIGHTING CONTROLS
The new corridors will be designed with recessed LED light fixtures. An alternating pattern of normal only power and life safety power will feed the new light fixtures. New EXIT signs will be designed along the corridor. Additional exterior lighting and EXIT signs will be added along the exterior pathways. These lights will be connected to the life safety power.
Lighting controls will be connected to existing lighting control panels in the building.
AE Works Ltd.
Nov 11, 2022
POWER DISTRIBUTION
New receptacles will be added per the current VA Guidelines. Power connections will be shown for relocated mechanical equipment.
ENERGY BUDGET AND CONNECTED LOAD REQUIREMENTS
The addition will slightly increase the power consumption in the building. No new panelboards are planned.
AE Works Ltd.
PLUMBING BASIS OF DESIGN
In performing the analysis of existing plumbing system elements, the following documents, standards, regulations, codes, and design criteria will be incorporated:
▪ International Plumbing Code (IPC) - 2021
▪ International Existing Building Code (IEBC) – 2021
▪ ASHRAE 90.1-202 Energy Standards for Buildings Except Low-rise Residential
Buildings - 2022
▪ VA Plumbing Design Manual – May 2021
▪ PG-18-1 through PG-18-17 VA Guidelines and Specifications
SYSTEM DESCRIPTION | EXISTING CONDITIONS
EXISTING DRAWINGS
Existing record drawings have been provided for the South Entryway project. The design team requests additional documentation for the area of work at Stair 2, the Staff Room, and the mechanical courtyard.
SURVEY
A site survey was conducted following receipt of existing drawings and selection of a concept to verify and evaluate the condition of the existing plumbing systems in the scope of work areas.
SYSTEM DESCRIPTION | PROPOSED CONDITIONS
The existing plumbing systems are modified as required to support the new architectural layouts in the scope of work areas. No interior plumbing work needs to occur for construction. Storm water management was coordinated with architecture for exterior drainage in the courtyard.
AE Works Ltd.
FIRE SUPPRESSION BASIS OF DESIGN
In general, the Department of Veterans Affairs (VA) relies on NFPA codes and standards for fire suppression requirements. The following codes and standards are applicable to this project:
▪ VA Fire Protection Design Manual (VAFPDM) – 2021 Edition
▪ NFPA 101, Life Safety Code (LSC) – 2021 Edition
▪ NFPA 13, Standard for the Installation of Sprinkler Systems – 2022 Edition
▪ International Building Code (IBC) - 2021 Edition
▪ NFPA 70, National Electrical Code – 2020 Edition
▪ NFPA 72, National Fire Alarm and Signaling Code - 2022 Edition
▪ Other relevant NFPA documents and manufacturer requirements, as applicable.
FIRE SUPPRESSION SCOPE OF WORK
This project will modify the existing sprinkler systems in the impacted building to accommodate the planned renovation. Sprinkler protection will be provided throughout the renovated areas. The sprinkler modifications included in the project area will be designed per the 2022 edition of NFPA 13 and the 2021 edition of the VAFPDM.
SYSTEM DESCRIPTION | EXISTING CONDITIONS
The areas of work are currently supplied by wet pipe sprinkler systems. The sprinkler systems are served by a fire pump located in the basement of Building 1. Portions of the sprinkler system in the area of work are supplied using plastic sprinkler piping. All plastic sprinkler piping in the area of work will be replaced with metal piping conforming to VAFPDM specifications.
DEMOLITION
Sprinklers and piping in the areas of work will be added and/or relocated as necessary to accommodate the planned renovations. Portions of the existing sprinkler systems within the areas of work will be demolished, as necessary. In accordance with NFPA 13 requirements, removed sprinklers shall not be reused.
The existing zone control assemblies and main piping in the areas of work are existing to remain and will be reused to the extent possible.
Sprinkler protection shall remain in service in all areas outside of the area of work for the duration of construction.
AE Works Ltd.
Bid Document
SYSTEM DESCRIPTION | PROPOSED CONDITIONS
The areas of work are primarily Light Hazard occupancies. The new sprinkler system modifications will be supplied from existing zone control assemblies. New sprinkler piping will be concealed in all areas with finished ceilings and exposed in areas without finished ceilings.
New sprinkler piping shall be metal and shall be sized based on the existing pipe schedule.
Sprinkler types will be as follows, and will match existing to the extent possible:
▪ Recessed, white, ordinary temperature, quick response, pendent-type sprinklers in the areas of work with finished ceilings.
▪ Brass ordinary temperature, quick response, upright or pendant-type sprinklers in the areas of work without finished ceilings.
Schedule 40 pipe shall be used for pipe sizes 2-inches and smaller and a minimum of
Schedule 10 pipe shall be used for pipe 2.5-inches in diameter and greater. These requirements are addressed in the project drawings and specifications.
Sprinkler system components that do not directly serve the new exit passageway will not be permitted inside the 2-hour fire-resistance-rated exit passageway enclosure.
AE Works Ltd.
FIRE ALARM BASIS OF DESIGN
In general, the Department of Veterans Affairs (VA) relies on NFPA codes and standards for fire suppression requirements. The following codes and standards are applicable to this project:
▪ VA Fire Protection Design Manual (VAFPDM) – 2021 Edition
▪ NFPA 101, Life Safety Code (LSC) – 2021 Edition
▪ NFPA 13, Standard for the Installation of Sprinkler Systems – 2022 Edition
▪ International Existing Building Code (IBC) - 2021 Edition
▪ NFPA 70, National Electrical Code – 2023 Edition
▪ NFPA 72, National Fire Alarm and Signaling Code - 2022 Edition
▪ Other relevant NFPA documents and manufacturer requirements, as applicable.
FIRE ALARM SCOPE OF WORK
This project will modify the existing fire alarm and mass notification systems in the areas of work to accommodate the planned renovations. The fire alarm system modifications included in the areas of work will be designed per the 2022 edition of NFPA 72 and the 2021 edition of the VAFPDM.
SYSTEM DESCRIPTION | PROPOSED CONDITIONS
The areas of work are currently served by the existing Building 1 fire alarm system. Minimal impact to the fire alarm system is anticipated. The existing controls matrix will be reused.
DEMOLITION
Fire alarm and mass notification devices will be added and/or relocated to accommodate the planned renovations. The existing fire alarm system components outside of the area of work are existing to remain and will be re-used to the extent possible. The fire alarm system shall remain in service in all areas outside of the area of work for the duration of construction.
SYSTEM DESCRIPTION | PROPOSED CONDITIONS
Fire alarm and mass notification system components in work will be added or relocated as necessary to accommodate the planned renovations. All new fire alarm devices shall match existing equipment installed in the building. It is anticipated that existing circuits will be reused and that an additional NAC panel will not be needed to support this project.
Fire alarm system components that do not directly serve the new exit passageway will not be permitted inside the 2-hour fire-resistance-rated exit passageway enclosure.
AE Works Ltd.
APPENDICES
Appendix A 95% Cost Estimate
Appendix B Bldg. Inspection
Appendix A
Cost Estimate
PROJECT SUMMARY
Project Information
Client Lebanon VA Health System
Project Vleb-009 Temporary Entrance
Location 123 Main Street
Lebanon PA
Architect AE Works
Estimator RS
Estimate Id 100%
Project Duration
Date 1/11/2023
Building Type Hospital 680 SF
Project Costs Summary
PROJECTED CONSTRUCTION COSTS $1,281 /sf $870,931
All other exclusions and clarifications regarding the estimate can be found in the estimate detail on the following page. Items not specifically listed within the detail are not included. Allowances have been included specifically for items which ample detail is not yet available to price on a unit cost basis. HVAC and Electrical systems are priced based on modifications within the renovation space and do not inlcude upgrades to shared hospital systems.
The estimate specifically excludes: design fees, permitting fees, third party testing, commissioning, financing, furnishings, owner equipment other than those shown in the body of the estimate, owner's contingency, builder's risk insurance, harmful materials testing and abatement outside of allowance, and unforeseen conditions.
The estimate is predicated on the project being completed in a maximum of 1 phases during normal work hours. After a maximum of six months, the estimate should be updated to reflect current market conditions. The cost estimate should be updated as the design evolves and is completed. The cost estimate represents our opinion of probable construction cost for this project. We have exercised due professional diligence in the preparation of the estimate; and, since we do not have control over bidding strategies and market conditions, no guarantee is implied with the estimate.
Construction Area
Insert Project Image
Lebanon VA Health System Date: 1/11/2023
123 Main Street Construction SF: 500
Systems
Number Description Cost/SF Total
01 DEMOLITION $83.64 $56,878
02 SITEWORK $11.36 $7,725
03 CONCRETE $73.38 $49,897
04 MASONRY $40.38 $27,460
05 STRUCTURAL $25.99 $17,670
06 ROUGH CARPENTRY/CASEWORK $1.51 $1,025
07 BUILDING ENVELOPE $0.00 $0
08 DOORS/WINDOWS $29.42 $20,007
09 INTERIORS $33.78 $22,968
10 SPECIALTIES CONSTRUCTION $0.11 $75
11 PLUMBING/PROCESS PIPING $0.00 $0
12 FIRE PROTECTION $62.82 $42,720
13 MECHANICAL $25.60 $17,408
14 ELECTRICAL $42.71 $29,040
15 JOBSITE MANAGEMENT $264.71 $180,000
16 PROJECT REQUIREMENTS $116.34 $79,114
SUBTOTAL $811.75 $551,987
Design Contingency 2.00% $16.23 $11,040
Bidding Contingency 15.00% $124.20 $84,454
Permits & Fees 3.00% $24.35 $16,560
Escalation End 2024 8% per year 16.64% $135.07 $91,851
Contractor OH & P 8%/7% 15.56% $169.18 $115,040
PROJECTED CONSTRUCTION COSTS $1,280.78 $870,931
SYSTEMS SUMMARY
Estimate ID: 100%Vleb-009 Temporary Entrance
Vleb-009 Temporary Entrance $870,931.35 Estimate ID: 100%
Lebanon VA Health System $789,662.00
123 Main Street $81,269.35
Construction SF: 680
Group
Phase
Description Comments Quantity Unit Material Labor Total
02 00 00 Existing Conditions
02 41 00 Demolition
Demo Patio for door 361 sf $8.00 $18.00 $9,386 0% 0%
Demolish retaining Wall 25 lf $20.00 $25.00 $1,125 0% 0%
Selective Demolition - Masonry 32 sf $5.00 $20.00 $800 0% 0%
Selective Demolition - Salvage cast stone veneer 21 sf $5.00 $30.00 $735 0% 0%
Selective Demolition - VCT 493 sf $5.00 $8.00 $6,409 0% 0%
Selective Demolition - Doors w/ Ptns 3 ea $0.00 $30.00 $90 0% 0%
Selective Demolition - ACT Ceilings 493 sf $10.00 $12.00 $10,846 0% 0%
Selective Demolition - DW Ceilings 25 sf $16.00 $15.00 $775 0% 0%
Selective Demolition - DW Ptn 20 lf $16.00 $15.00 $620 0% 0%
Selective Demolition - Masoonry 64 sf $5.00 $18.00 $1,472 0% 0%
Selective Demolition - Ductwork 500 lbs $10.00 $5,000 0% 0%
Selective Demolition - Unit Heaters 2 ea $500.00 $1,000 0% 0%
Selective Demolition - Hydronic Piping 120 lf $1.00 $20.00 $2,520 0% 0%
Selective Demolition - Electrical Make Safe 1 ls $6,500.00 $6,500 0% 0%
Selective Demolition - Protection 1 ls $6,000.00 $6,000 0% 0%
Selective Demolition - Dumpster 4 ea $900.00 $3,600 0% 0%
Demolition Total $12,208.00 $44,670.00 $56,878
Earthwork
Regrade at Demolished Wall 32.50 cy $40.00 $50.00 $2,925 0% 0%
Landscaping 480 sf $2.00 $8.00 $4,800 0% 0%
Site Work Total $2,260.00 $5,465.00 $7,725
03 00 00 Concrete
03 01 00 Maintenance of Concrete
03 30 00 Cast In Place Concrete
Continuous Footer Assembly 3 cy $620.00 $480.00 $3,504 0% 0%
Sidewalk Assembly 700 sf $25.00 $30.00 $38,500 0% 0%
Hand Set Curb Assembly 42 lf $36.50 $80.00 $4,893 0% 0%
Concrete Stairs 25 sf $80.00 $40.00 $3,000 0% 0%
Concrete Total $23,008.00 $26,889.00 $49,897
04 00 00 Masonry
04 20 00 Unit Masonry
Concrete Masonry Unit 878 sf $12.00 $18.00 $26,340 0% 0%
Cast Stone Venner 20 sf $6.00 $50.00 $1,120 0% 0%
Masonry Total $10,656.00 $16,804.00 $27,460
05 00 00 Metals
05 12 00 Structural Steel Framing
Security Grille (fence) 210 sf $25.00 $20.00 $9,450 0% 0%
Misc. Metal 9 ea $350.00 $150.00 $4,500 0% 0%
Lintels 24 lf $75.00 $80.00 $3,720 0% 0%
Structural Total $10,200.00 $7,470.00 $17,670
06 00 00 Wood & Plastics
06 10 00 Rough Carpentry
Wood Blocking - Interior 250 lf $2.10 $2.00 $1,025 0% 0%
SYSTEM BACKUP
Matl Esc
Labor
Esc.
Unit Cost
Date: 1/11/2023
Group
Phase
Description Comments Quantity Unit Material Labor Total Matl Esc
Labor
Esc.
Unit Cost
06 02 00 Finish Carpentry
Carpentry Total $525.00 $500.00 $1,025
08 00 00 Openings
08 10 00 Doors
Hollow Metal Door 3'0" x 7'0" 2 ea $1,000.00 $600.00 $3,200 0% 0%
Hollow Metal Door 3'6" x 7'0" 1 ea $1,000.00 $600.00 $1,600 0% 0%
Hollow Metal Door 3'10" x 7'0" 2 ea $1,000.00 $600.00 $3,200 0% 0%
Hollow Metal Frame 5 ea $300.00 $100.00 $2,000 0% 0%
Fire Rated Doors (adder for ea FR door) 3 ea $200.00 $0.00 $600 0% 0%
Hardware 5 ea $1,500.00 $350.00 $9,250 0% 0%
08 80 00 Glazing
View Window Glazing 3.27 sf $30.00 $18.00 $157 0% 0%
Doors/Windows Total $11,699.00 $3,509.00 $20,007
09 00 00 Finishes
09 22 00 Interior Construction
Wall System (MS/Insulation/Bd 1 Side) 10' 35 lf $79.10 $77.00 $5,464 0% 0%
Drywall Ceiling 219 sf $6.25 $7.10 $2,924 0% 0%
2 hr Shaftwall system Ceiling 176 sf $10.93 $11.50 $3,948 0% 0%
Bulkhead 10 lf $35.50 $55.00 $905 0% 0%
09 50 00 Acoustical Ceiling
24" x 24" Ceiling System (Inserts/Grid/Ceiling) 180 sf $4.50 $8.00 $2,250 0% 0%
Wall Angle 45 lf $1.00 $2.50 $158 0% 0%
09 60 00 Flooring
Resilient Tile Floor 500 sf $8.00 $2.00 $5,000 0% 0%
Rubber Base 150 lf $2.10 $1.80 $585 0% 0%
09 70 00 Wall Finishes
InteriorPaint Walls (Prime/2 coats) 490 sf $0.95 $0.75 $833 0% 0%
InteriorPaint Ceiling (Prime/2 coats) 395 sf $0.95 $0.90 $731 0% 0%
Paint Door & Frame 2 ea $35.00 $50.00 $170 0% 0%
Interior Finishes Total $12,499.00 $10,471.00 $22,968
10 00 00 Specialties
10 14 00 Signage
Wall Mounted 1 ea $45.00 $30.00 $75 0% 0%
Specialties Total $45.00 $30.00 $75
21 00 00 FIRE Suppression
T.I Fire Sprinklers
Add New Head 4 ea $180.00 $450.00 $2,520 0% 0%
Relocate Sprinkler Pipe 100 lf $80.00 $110.00 $19,000 0% 0%
New Pipe 80 lf $80.00 $110.00 $15,200 0% 0%
Rework 1 LS $1,000.00 $5,000.00 $6,000 0% 0%
Subtotal: FIRE PROTECTION $16,120.00 $26,600.00 $42,720
23 00 00 MECHANICAL
HVAC Project Req.
Balance 24 hrs $125.00 $3,000 0% 0%
Sup/Ret/Gen. Exh. Duct 0% 0%
Galvanized Duct 250 lb. $10.85 $2,713 0% 0%
0% 0%
Air Distribution Devices 0% 0%
Supply Diffusers 1 ea. $90.00 $110.00 $200 0% 0%
Return Grilles 1 ea. $90.00 $110.00 $200 0% 0%
0% 0%
Description Comments Quantity Unit Material Labor Total Matl Esc
Labor
Esc.
Unit Cost
Terminal Zone Units 0% 0%
Fan Coil Unit 1 ea. $3,800.00 $2,400.00 $6,200 0% 0%
Relocate Unit Heater 200 1 ea. $250.00 $1,100.00 $1,350 0% 0%
Relocate FCU 300 1 ea. $200.00 $1,000.00 $1,200 0% 0%
0% 0%
Hydronic Piping 0% 0%
3/4" 60 lf $12.50 $14.10 $1,596 0% 0%
1/2" Condensate 20 lf $11.09 $7.85 $379 0% 0%
Int Wall Penetrations 6 ea $65.00 $30.00 $570 0% 0%
Subtotal: 13 MECHANICAL $5,792.00 $11,616.00 $17,408 0% 0%
0% 0%
23 00 00 ELECTRICAL 0% 0%
Site Lighting 0% 0%
LED Wall Pack 6 ea. $400.00 $500.00 $5,400 0% 0%
Branch Circuiting
120v Duplex Outlet (MC Cable) 2 ea $320.00 $180.00 $1,000 0% 0%
Relocate exterior conduit 30 lf $10.00 $35.00 $1,350 0% 0%
Light Fixtures
2x2 Fixture Surface Mount 3 ea $225.00 $230.00 $1,365 0% 0%
Exit Sign Fixture 4 ea $80.00 $150.00 $920 0% 0%
Modify Exit Sign 1 ea $35.00 $40.00 $75 0% 0%
Fire Alarm and Life Safety Systems
Tie In 1 ls $500.00 $2,000.00 $2,500 0% 0%
Relocate Conduit 1 ls $400.00 $1,500.00 $1,900 0% 0%
Pull Station 2 ea $300.00 $300.00 $1,200 0% 0%
Speaker Strobe 2 ea $450.00 $340.00 $1,580 0% 0%
Security Systems
Security Camera 1 ea $2,800.00 $1,000.00 $3,800 0% 0%
Card Reader 1 ea $950.00 $500.00 $1,450 0% 0%
Electric Strike Sensor 1 ea $500.00 $500.00 $1,000 0% 0%
Door Contact Sensor 1 ea $500.00 $500.00 $1,000 0% 0%
Tie In 1 ls $4,500.00 $4,500 0% 0%
Subtotal: ELECTRICAL $11,520.00 $17,520.00 $29,040 0% 0%
15 JOBSITE MANAGEMENT
Management
General Conditions 30 wk $6,000.00 $180,000 0% 0%
Subtotal: 15 JOBSITE MANAGEMENT $180,000 0% 0%
SYSTEMS SUBTOTAL $472,873 0% 0%
16 PROJECT REQUIREMENTS
Insurance
Genral Liability and Workers Comp
Insurance
1.10% 1 ls $4,731.68 $4,732 0% 0%
Bonding required 1.10% 1 ls $5,201.60 $5,202 0% 0%
State Sales Tax 6.00% 1 ls $6,991.92 $6,992 0% 0%
Site Conditions
Site Requirements 6.93 mo $6,500.00 $45,035 0% 0%
COVID-19 Premium 10% 1 ls $17,154.40 $17,154 0% 0%
Subtotal: 16 PROJECT REQUIREMENTS $79,114
SYSTEMS SUBTOTAL $551,987
Appendix B
Building
Inspection
BUILDING 1 ENTRANCE ENCLOSURE LIMITED ASBESTOS
BUILDING INSPECTION (TASK 595-20-401)
Lebanon VA Medical Center 1700 South Lincoln Avenue
Lebanon, Pennsylvania 17042
Submitted To:
AE Works Ms. Tracey Case-Dodds
418 Beaver Street
Sewickley, Pennsylvania 15143
Submitted By:
Pennoni Associates Inc.
4 Kacey Court
Mechanicsburg, Pennsylvania 17055
Michael Potts John-Thomas Graupensperger, PWS Associate Environmental Health & Safety Associate Vice President Professional
AEWLA20019 October 13, 2022
SECTION PAGE
EXECUTIVE SUMMARY
1. LIMITED ASBESTOS CONTAINING MATERIAL ASSESSMENT
2. CONCLUSIONS
3. RECOMMENDATIONS
4. CERTIFICATION
TABLES
TABLE 1 – Asbestos Bulk Sample Analysis Results
APPENDICES
APPENDIX A – Laboratory Analytical Results and Chain of Custody
APPENDIX B – Photographs
APPENDIX C – License
PENNONI
Consulting Engineers
Lebanon VA Medical Center
AEWLA20019
Limited Asbestos Building Inspection Lebanon, Pennsylvania
October 13, 2022
EXECUTIVE SUMMARY
On September 27, 2022, Pennoni was contracted by AE Works to perform a pre-renovation limited asbestos inspection at the facility located at 1700 South Lincoln Avenue, Lebanon, Pennsylvania 17042. This limited inspection was performed to identify Asbestos Containing Materials (ACM) present within the facility in areas identified to be impacted by renovations.
Suspect ACM Bulk samples (floor tile, wall systems, ceiling tile, and other building components) were collected and analyzed. The suspect materials sampled found to contain greater than one percent (>1%) asbestos were tan 9” x 9” floor tile, brown 9” x 9” floor tile, and dark brown 12” x 12” floor tile in the hallway outside Stairwell 2. Suspect material not sampled, but presumed to be ACM included the fire door entering into Room 6A. Recommendations are found at the conclusion of this report.
1. LIMITED ASBESTOS CONTAINING MATERIAL ASSESSMENT
On October 4, 2022, Pennoni personnel (Michael Potts [PA DOLI Certified Asbestos Inspector, Certification #061136]) performed a visual and tactile review of the suspected ACM within the facility in areas identified to be impacted by renovations and sampled said potentially impacted suspect ACM. The samples were submitted to EMLab P&K and analyzed using Polarized Light Microscopy (PLM). EMLab P&K is a National Voluntary Laboratory Accreditation Program (NVLAP Lab Code 200844-0) approved laboratory. Results are compared to the Occupational Safety and Health Administration (OSHA)/U.S. Environmental Protection Agency (U.S. EPA) definitions of asbestos (>1%).
Laboratory analytical results summarized in Table 1 below can be found in Appendix A.
Table 1
Asbestos Bulk Sample Analysis Results Building 1 Entrance Enclosure
1700 South Lincoln Avenue, Lebanon, Pennsylvania 17042 October 4, 2022
Sample ID
Homogeneous Material
Description
Location
Quantity
PLM Analytical Result
(% and Type)
Comments
LVA-10.4-01A Light Blue 12” x 12” Floor Tile
Room 6A 450 SF ND Asbestos not present in samples analyzed LVA-10.4-01B
LVA-10.4-02A Turquoise 12” x 12” Floor Tile
Room 6A 10 SF ND Asbestos not present in samples analyzed LVA-10.4-02B
LVA-10.4-03A Dark Blue 12” x 12” Floor Tile
Room 6A 450 SF ND Asbestos not present in samples analyzed LVA-10.4-03B
LVA-10.4-04A
Black 4” Cove Base Room 6A 200 LF ND
Asbestos not present in samples analyzed LVA-10.4-04B
LVA-10.4-05A Brown 4” Cove Base
Room 6A 10 LF ND Asbestos not present in samples analyzed LVA-10.4-05B
LVA-10.4-06A
Black 6” Cove Base Room 6A 20 LF ND
Asbestos not present in samples analyzed LVA-10.4-06B
Limited Asbestos Building Inspection
Table 1 Continued Asbestos Bulk Sample Analysis Results
Building 1 Entrance Enclosure 1700 South Lincoln Avenue, Lebanon, Pennsylvania 17042
October 4, 2022
Sample ID
Homogeneous Material
Location
PLM Analytical Result
(% and Type)
LVA-10.4-07A
White Ceiling Tile
Room 6A and Hallway
1,200 SF ND
Asbestos not present in samples analyzed LVA-10.4-07B
LVA-10.4-08A
Drywall
Room 6A and Hallway
2,000 SF ND
Asbestos not present in samples analyzed LVA-10.4-08B
LVA-10.4-09A
Joint Compound
Room 6A and Hallway
2,000 SF ND
Asbestos not present in samples analyzed LVA-10.4-09B
LVA-10.4-10A Gray Window Caulk
Hallway
Openings ND Asbestos not present in samples analyzed LVA-10.4-10B
LVA-10.4-11A
Gray 6” Cove Base Hallway 20 LF ND in samples analyzed LVA-10.4-11B
LVA-10.4-12A
Tan 9” x 9” Floor Tile
Hallway
75 SF
8% Chrysotile
Second sample not analyzed as first was positive for asbestos.
(Category I Non-friable, Miscellaneous)
LVA-10.4-12B
LVA-10.4-13A
Brown 9” x 9” Floor Tile
75 SF
analyzed as first was positive for asbestos.
(Category I Non-
LVA-10.4-13B
LVA-10.4-14A
Dark Brown 12” x 12” Floor Tile
50 SF
analyzed as first was positive for asbestos.
(Category I Non-
LVA-10.4-14B
LVA-10.4-15A Tan 18” x 18” Floor Tile
Hallway 30 SF ND Asbestos not present in samples analyzed LVA-10.4-15B
LVA-10.4-16A Light Gray Exterior Window Frame
Caulk
Exterior
Openings
ND
in samples analyzed LVA-10.4-16B
LVA-10.4-17A White Ground Caulk
Exterior 50 LF ND in samples analyzed LVA-10.4-17B
N/A
Fire Door
Entrance to 6A
1 Door
Presumed ACM
Asbestos presumed present. (RACM, Friable, Table Notes:
ND: Non-Detect for Asbestos SF: Square Feet CF: Cubic Feet LF: Linear Feet NA: Not Analyzed
Limited Asbestos Building Inspection
2. CONCLUSIONS
• The tan 9” x 9” floor tile, brown 9” x 9” floor tile, and dark brown 12” x 12” floor tile in the hallway outside Stairwell 2 were found to meet the EPA definition of asbestos containing material (greater than one percent [>1%] asbestos). The fire door entering into Room 6A was not sampled but presumed to contain asbestos. The flooring materials are Category I non-friable and can be disposed of as construction and demolition (C&D) waste. However, if material is rendered friable during abatement activities, it must be treated as Regulated Asbestos Containing Material (RACM) and abated in accordance with applicable federal (U.S. EPA, OSHA, Department of Transportation [DOT]), Pennsylvania (Pennsylvania Department of Environmental Protection [PA DEP]/Pennsylvania Department of Labor and Industry [DOLI]) and local regulations governing the removal, transport, and disposal of asbestos. The fire door is RACM and must be treated as outlined above.
• All other suspect ACM Bulk samples collected and analyzed were found to be non-detect for asbestos and therefore do not meet the EPA definition of asbestos containing material (greater than one percent [1%] asbestos).
3. RECOMMENDATIONS
• Asbestos abatement activities are recommended prior to any repair, renovation or demolition activities which would disturb the matrix of confirmed or Presumed Asbestos ContainingMaterials.
It is recommended that asbestos activity be performed in accordance with applicable U.S. EPA, U.S.
Department of Labor, OSHA, PA DEP, PA DOLI regulatory requirements. In order to comply with these requirements, the following is recommended:
1. Written notification to PA DEP and PA DOLI of demolition/renovation ten (10) working days prior to asbestos related activities, as required by the National Emission Standards for Hazardous Air Pollutants (NESHAPS) of the Clean Air Act, if material is or is expected to become friable.
2. Development of a written Asbestos Abatement Project Design Specification, dictating abatement work practices and control measures to reduce airborne fiber concentrations, waste disposal requirements and air sample collection and analysis requirements including the final clearance (re-occupancy) criteria.
3. Selection of a PA DOLI licensed Asbestos Contractor for the performance of asbestos response activities.
4. Air sample collection and analysis subsequent to asbestos abatement activities in compliance with project design requirements for the re-occupancy by non-protected individuals.
Occupant notifications concerning asbestos abatement are required ten (10) working days prior to their disturbance.
Limited Asbestos Building Inspection
• The site is required to maintain this report indefinitely in accordance with the OSHA Medical Recordkeeping Requirements identified in 29 CFR 1910.1020 and inform employees annually of their rights of access. If such a plan has been developed, an update based on the findings of this report to the site Operations, Maintenance and Repair Plan is recommended.
A copy of existing asbestos inspection reports must be provided to each contractor involved in the project.
4. CERTIFICATION
The information contained in this report is believed to be accurate and true to the best knowledge of the inspector(s). Findings and recommendations for this investigation are based on the observations of the conditions, as they existed at that time. The inspector(s) and Pennoni Associates, Inc. assumes no liability for financial or health consequences due to actions or lack of actions taken by the client as a result of this investigation.
Michael Potts John-Thomas Graupensperger, PWS Associate Environmental Health & Safety Associate Vice President Professional
MP/JG/ck
Attachments cc: File
APPENDIX A
Laboratory Analytical Results and Chain of Custody t!urofins k'PK Huilt f:rvironmerit Testing, .l.C EMLab ID: 3049114, Page 1 of 9 ÿ eurofins
Built Environment Testing
Report for:
Lynn Stutzman Pennoni Associates Inc - Mechanicsburg 4 Kacey CI Mechanicsburg, PA 17055
Eurofins EPK Built Environment Testing, LLC Regarding: Project: AEWLA20019; Building 1 Limited ACM Inspection
EML ID: 3049114
Approved by: Dates of Analysis.
Asbestos PLM: 10-10-2022
Approved Signatory Balu Krishnan
Service SOPs: Asbestos PLM (EPA 40CFR App E to Sub E of Part 763 & EPA METHOD 600/R-93-116, SOP EM-AS-5-1267) NVLAP Lab Code 200844-0
Euro fins EPK Built Environment Testing, LLC ("the Company"), a member of the Eurofine Built Environment Testing group of companies, shall have no liability to the client or the client's oJstomer with respect to decisions or recommendations made, actions taken or courses of condud implemented by eitherthe client orthe client's customer as a resuh ofor based uponthe Test Results. In no event shall the Company be liable to the client with respect to the Test Results except for the Company’s own willful misconduct or gross negligence nor shall the Company be liable for incidental or consequential damages or lost profits or revenues to the fullest extent such liability may be disclaimed by law, even if the Company has been advised of the possibility of such damages, lost profits or lost revenues. In no event shall the Company’s liability with respect to the Test Results exœed the amount paid to the Company by the client therefor.
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certificadon, approval, or endorsement by any agency of the federal government. The Company reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detecdon and reporting limit is less than 1% unless point coundng is performed. Floor die samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detecdon limit and to aid in asbestos idendficadon.
1 A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is reflected by the value of "x".
Eurofins EPK Built Environment Testing, LLC EMLab ID: 304911 4, Page 2 of 9
Client: Pennoni Associates Inc - Mechanicsburg CDO: Lynn Stutzman Re: AEWLA20019; Building 1 Limited ACM Inspection
Eurofms EPK Built Environment Testing, LLC 3000 Lincoln Drive East, Suite A, Marlton, NJ 08053
(866) 871-1984 www.eurofinsus.com*Built
Date of Sampling: 10-04-2022 Date of Receipt: 10-05-2022 Date of Report: 10-10-2022
ASBESTOS PLM REPORT
Total Samples Submitted: 34
Total Sam ples Analyzed: 31
Total Sam ples with Laver Asbestos Content > 1% 3
Location: LVA-10.4-01A, Light blue 12x12 tile Lab ID-Versions: 14701385-1
Sam pIe Layers Asbestos Content Blue Floor Tile
Black/Yellow Mastic
Sample Com posite Hornogeneitv: Good
Location: LVA-10.4-01B, Light blue 12x12 tile Lab ID-Versions: 14701386- 1
Blue Floor Tile
Black/Yellow Mastic
Location: LVA-10.4-02A, Turquoise 12x12 tile Lab ID-Versions: 14701387- 1
Blue Floor Tile
Sample Com posite Hornogeneitv: Good
Location: LVA-10.4-02B, Turquoise 12x12 tile Lab ID-Versions: 14701388- 1
Sam pIe Layers Asbestos Content
Blue Floor Tile
Black/Yellow Mastic http://www.eurofinsus.com/
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certificadon, approval, or endorsement by any agency of the federal government. The Company reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detecdon and reporting limit is less than 1% unless point coundng is performed. Floor die samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detecdon limit and to aid in asbestos idendficadon.
1 A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is
Eurofins EPK Built Environment Testing, LLC EMLab ID: 304911 4, Page 3 of 9
Re: AEWLA20019; Building 1 Limited ACM Inspection
ASBESTOS PLM REPORT
Eurofms EPK Built Environment Testing, LLC 3000 Lincoln Drive East, Suite A, Marlton, NJ 08053
(866) 871-1984 www.eurofinsus.com*Built
Date of Sampling: 10-04-2022 Date of Receipt: 10-05-2022 Date of Report: 10-10-2022
Location: LVA-10.4-03A, Dark bluel2xl2 tile Lab ID-Versions: 14701389- 1
Sam pIe Layers Asbestos Content
Blue Floor Tile
Black Mastic
Location: LVA-10.4-03B, Dark bluel2xl2 tile Lab ID-Versions: 14701390- 1
Blue Floor Tile
Black Mastic
Location: LVA-10.4-04A, Black 4 inch cove base Lab ID-Versions: 14701391-1
Black Baseboard
Beiee Mastic
Sample Com posite Hornogeneitv: Good
Location: LVA-10.4-04B, Black 4 inch cove base Lab ID-Versions: 14701392- 1
Sam pIe Layers Asbestos Content Black Baseboard
Beige Mastic
The test report shall not be reproduced except in full, without written approval of the laboratory. The report must not be used by the client to claim product certificadon, approval, or endorsement by any agency of the federal government. The Company reserves the right to dispose of all samples after a period of thirty (30) days, according to all state and federal guidelines, unless otherwise specified.
Inhomogeneous samples are separated into homogeneous subsamples and analyzed individually. ND means no fibers were detected. When detected, the minimum detecdon and reporting limit is less than 1% unless point coundng is performed. Floor die samples may contain large amounts of interference material and it is recommended that the sample be analyzed by gravimetric point count analysis to lower the detecdon limit and to aid in asbestos idendficadon.
1 A "Version" indicated by -"x" after the Lab ID# with a value greater than 1 indicates a sample with amended data. The revision number is
Eurofins EPK Built Environment Testing, LLC EMLab ID: 304911 4, Page 4 of 9
Re: AEWLA20019; Building 1 Limited ACM Inspection
ASBESTOS PLM REPORT
Eurofms EPK Built Environment Testing, LLC 3000 Lincoln Drive East, Suite A, Marlton, NJ 08053
(866) 871-1984 www.eurofinsus.com*Built
Date of Sampling: 10-04-2022 Date of Receipt: 10-05-2022 Date of Report: 10-10-2022
Location: LVA-10.4-05A, Brown 4 inch cove base Lab ID-Versions: 14701393-1
Sam pIe Layers Asbestos Content
Brown Baseboard
Tan Mastic
Location: LVA-10.4-05B, Brown 4 inch cove base Lab ID-Versions: 14701394- 1
Brown Baseboard
Tan Mastic
Location: LVA-10.4-06A, Black 6-inch cove base Lab ID-Versions: 14701395-1
Black Baseboard
Yellow Mastic
Sample Com posite Hornogeneitv: Good
Location: LVA-10.4-06B, Black 6-inch cove base Lab ID-Versions:…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .