S02 ICRA Radiology HVAC .pdf
PDF 581 KB Posted
- Attached to
- Z1DA--Correct Radiology HVAC
- Solicitation number
- 36C24524B0017
About this file
This document is an Infection Control Risk Assessment (ICRA) and Construction Hazard Recognition and Control Program for a construction project at a Department of Veterans Affairs (VA) medical facility.
The ICRA classifies the construction activities into three risk levels based on the potential for generating dust and disrupting patient care areas. It outlines the specific infection control precautions required for each risk level, such as erecting barriers, controlling airflow, and cleaning procedures. The document also details the Interim Life Safety Measures (ILSM) that must be implemented based on the impact to the facility's fire detection, alarm, and suppression systems. The ICRA and ILSM must be reviewed and approved by the project coordinator, facilities management, safety, and infection control prior to the start of construction. The related federal contract opportunity is Solicitation Number 36C24524B0017 for the "Correct Radiology HVAC" project at the VA medical facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24524B0017 0006.docx | DOCX document | |
| S07 Bid Abstract 7-16-24 Correct Radiology HVAC.pdf | ||
| S07 attendance bid opening 7-16-24.pdf | ||
| S06 Answers to RFI Follow Up Correct Radiology HVAC.pdf | ||
| 36C24524B0017 0005.docx | DOCX document | |
| S06 Roof Picture RFI.pdf | ||
| 36C24524B0017 0004.docx | DOCX document | |
| 36C24524B0017 0003.docx | DOCX document | |
| S05 pre-bid RFI Correct Radiology HVAC combine.pdf | ||
| S04 pre bid attendance 6-21-24.pdf | ||
| 36C24524B0017 0002.docx | DOCX document | |
| S04 Pre Bid Agenda Correct Radiology HVAC.pdf | ||
| 36C24524B0017 0001.docx | DOCX document | |
| S02 Specifications.pdf | ||
| S02 Combined Drawing Set.pdf | ||
| S02 Wage Determination 5-3-2024 .pdf | ||
| 36C24524B0017.docx | DOCX document | |
| S02 SOW Correct Radiology HVAC - Construction-FINAL rev2 - Copy.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT A
VAMC MEMORANDUM 517-2018-138-23, Construction Hazard Recognition Control Program
RISK ASSESSMENT MATRIX: IC GUIDELINES FOR CONSTRUCTION
CLASS CONSTRUCTION ACTIVITY RISK PRECAUTIONS REQUIRED
CLASS
I
Type A: Inspection and Non-Invasive Activities.
Includes, but not limited to:
1. Small scale removal of ceiling tiles for visual inspection or minor installation.
2. Painting (but not sanding).
3. Wallcovering, electrical trim work, minor plumbing, and activities that do not generate dust or require cutting of walls.
Low or Moderate
Risk Patients
Only High Risk Requires Class II
Precautions
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace a ceiling tile displaced for visual inspection.
CLASS
II
Type B: Small scale, short duration activities that create minimal dust.
Includes, but not limited to:
1. Access to chase spaces.
2. Cutting of walls or ceiling where dust migration can be controlled.
Low or Moderate
Risk Patients
Only High Risk Requires Class III
Precautions
1. Notify staff in the immediate area.
2. Provide active means to prevent airborne dust from dispersing into air.
3. Water mist work surfaces while cutting.
4. Seal unused doors with duct tape.
5. Block off and seal air vents.
6. Place dust mat at entrance/exit of area.
7. Contain construction waste before transport in tightly covered containers.
8. Upon completion, wipe work surfaces with disinfectant, wet mop and/or vacuum and remove isolation of the Heating, Ventilation and Air Conditioning (HVAC) system.
CLASS
III
Type C: Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components and assemblies or new construction.
Includes, but not limited to:
1. Sanding of walls for painting or wall covering.
2. Removal of floor coverings, ceiling tiles, and casework.
3. New wall construction.
4. Uncontained duct, HVAC or electrical work above ceiling.
5. Major cabling activities.
6. Any other project where high levels of dust are generated.
Moderate or High Risk Patients only Low Risk Requires Class II
Precautions
In addition to Class II Precautions above,
1. Obtain IC concurrence before construction begins.
2. Complete all critical barriers, i.e., sheetrock, plywood, plastic, to seal from non-work area or implement control cube method (cart with plastic covering/sealed connection to work site with vacuuming prior to exit) before construction begins.
3. Isolate HVAC system in area and maintain negative air pressure within work site.
4. Cover transport receptacles or carts.
5. Seal holes, pipes, conduits, and punctures.
6. Personnel are required to ensure shoes are not tracking when leaving the work site.
7. Upon completion, do not remove barriers until inspected by Safety and IC and thoroughly cleaned by FMS. Remove barrier materials carefully to minimize spreading of dirt and debris.
Attachment A, VAMC MEMORANDUM 517-2018-138-23, Construction Hazard Recognition Control Program
PATIENT RISK GROUP
Low Risk Group Medium Risk Group High Risk Group
Administrative Offices Lobbies Public Corridors Elevators Day Rooms Canteen Retail Store
Outpatient, Urgent Care and Primary Care Clinics Laboratory, Radiology and Nuclear Medicine Physical Therapy Respiratory Therapy Pharmacy Food Services Interim Care and Medical Units
SPD Storage/Sterilization Intensive Care Units TB Negative Pressure isolation rooms Operating Room
ATTACHMENT A1
ICRA Project Determination: _____________________________________________
CONSTRUCTION RISK REDUCTION PLAN
Location of Construction: Project Start Date:
Contractor Performing Work: Estimated Duration:
√ CONSTRUCTION ACTIVITY √ IC RISK GROUP
Type A: Inspection, non-invasive, minor Low Risk
Type B: Small scale, short duration, moderate levels. Medium Risk
Type C: Major activity generates moderate to high levels of dust. High Risk
INFECTION CONTROL PRECAUTIONS
CLASS
I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
CLASS
II
1. Provides active means to prevent air-borne dust from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tape.
4. Block off and seal air vents.
5. Place dust mat at entrance and exit of work area.
6. Contain construction waste before transport in tightly covered containers.
7. Upon completion, wipe work surfaces with disinfectant, wet mop and/or vacuum and remove isolation of HVAC system.
CLASS
III
In addition to Class II Precautions above,
1. Obtain IC concurrence before construction begins.
2. Complete all critical barriers or implement control cube method before construction begins.
3. Control airflow: Isolate HVAC system in areas where work is being performed and maintain negative air pressure within work site.
4. Cover transport receptacles or carts.
5. Seal holes, pipes, conduits, and punctures appropriately
6. Personnel are required to ensure shoes are not tracking dust and soil when leaving the work site.
7. Upon completion, do not remove barriers until inspected by Safety and Infection Control and thoroughly cleaned by FMS. Remove barrier materials carefully to minimize spreading of dirt and debris.
Signatures:
Project Coordinator____________________________________ Date___________
FMSL Chief___________________________________________ Date___________
Signatures:
Safety Manager___________________________________ Date___________
Infection Control_________________________________ Date___________
Select Number
ATTACHMENT A2
INTERIM LIFE SAFETY MEASURES (ILSM)
√ CLASS ACTIVITY ILSM PRECAUTIONS
CLASS
I
Minor: No breech of fire detection, alarm or fighting systems. No egress or access blockage.
None required beyond routine general safety precautions.
Ensure egress. Ensure access for Emergency forces.
Ensure operational Life Safety Systems.
Prohibit smoking.
CLASS
II
Moderate: Short-term breech of fire detection, alarm or fighting systems < a single work shift. Blockage of egress or access but second means available.
In addition to Class I ILSMs, apply at-the-site measures.
Notify staff in the immediate area.
Control combustible loads.
Repair/construction staff immediately available at the site.
Compensate for compartmentalization deficiencies.
Each single breech of fire barrier immediately replaced.
CLASS
III
Major: Multiple or continuous breech of fire detection, alarm or fighting systems. Blockage of egress or access. Work > a single shift.
In addition to Class I and II ILSMs, obtain Safety Manager concurrence before construction begins.
Construct temporary smoke tight barriers of non-combustible materials.
Provide additional fire fighting equipment.
Designate alternative exit/access routes.
Increase Hazard Surveillance.
Provide additional education to applicable Medical Center Staff/Incident Response Team Conduct 2 fire drills per shift in local areas vs. all areas.
Notify Emergency Forces.
Utility failure issues:
Emergency procedures:
Additional Requirements (yes/no/NA,comments):
Air quality:
Noise:
Vibration:
Other issues not addressed above:
______________________________________________________________________________________________________ Signatures:
Project Coordinator________________________________ Date___________
FMSL Chief_______________________________________ Date___________
Signatures:
Safety Manager___________________________________ Date___________
Infection Control_________________________________ Date___________
| CONSTRUCTION HAZARD RECOGNITION AND CONTROL PROGRAM |
| CONSTRUCTION HAZARD RECOGNITION AND CONTROL PROGRAM |
| CLASS |
| I |
| CLASS |
| II |
| CLASS |
| III |
| PATIENT RISK GROUP |
| High Risk Group |
| Medium Risk Group |
| Low Risk Group |
| Outpatient, Urgent Care and Primary Care |
| Administrative Offices |
| Clinics |
| CLASS |
| I |
| CLASS |
| II |
| CLASS |
| III |
| Infection Control & Safety Orientation for Construction Service Workers |
| Infection Control & Safety Orientation for Construction Service Workers |
| Environmental Control |
| Environmental Control |
| Environmental Control |
| General |
| General |
| Safe Work Practices |
| Safe Work Practices |
| Hot Work Permitting and Operations |
| Hot Work Permitting and Operations |
| Confined Spaces |
| Confined Spaces |
| Excavations and Trenches |
| Excavations and Trenches |
| Construction/Renovation Project Surveillance Report |
| Construction/Renovation Project Surveillance Report |
| N/A |
| FAIL |
| PASS |
| Issue |
| Completion Phase |
| Completion Phase |
| VABHS Environmental Compliance Assessment Form |
| VABHS Environmental Compliance Assessment Form |
| Compliance Checklist |
| Compliance Checklist |
| VABHS Environmental Compliance Assessment Form |
| VABHS Environmental Compliance Assessment Form |
| ICRA Project Determination: 517-21-002 Correct Radiology HVAC | |
| Location of Construction: Building 1, 2nd Floor, A side | |
| Project Start Date: TBD | |
| Contractor Performing Work: TBD | |
| Estimated Duration: TBD | |
| fill_10: | |
| fill_11: | |
| Low Risk: | |
| fill_12: | |
| Medium Risk: | |
| fill_14: | |
| fill_15: | |
| High Risk: | |
| Project Coordinator: | |
| Date: | |
| Safety Manager: | |
| Date_2: | |
| FMSL Chief: | |
| Date_3: | |
| Infection Control: | |
| Date_4: | |
| fill_15_2: | |
| fill_16_2: | |
| fill_17_2: | |
| Major Multiple or continuous breech of fire detection alarm or fighting systems Blockage of egress or access Work a single shift: | |
| Other issues not addressed above: | |
| Project Coordinator_2: | |
| Date_5: | |
| Safety Manager_2: | |
| Date_6: | |
| FMSL Chief_2: | |
| Date_7: | |
| Infection Control_2: | |
| Date_8: | |
| 2024-03-28T15:57:42-0400 | |
| JUSTIN GREENE |
| 2024-03-28T16:18:52-0400 | |
| MEREDITH WHITTAKER |
| 2024-03-29T10:36:47-0400 | |
| BERLIN BEAVER |
| 2024-03-29T08:43:54-0400 | |
| JOHN MONTGOMERY |
| 2024-03-29T10:37:12-0400 | |
| BERLIN BEAVER |
| 2024-03-29T08:44:25-0400 | |
| JOHN MONTGOMERY |
| 2024-03-28T15:58:08-0400 | |
| JUSTIN GREENE |
| 2024-03-28T16:18:01-0400 | |
| MEREDITH WHITTAKER |
| Check Box12: Off |
| Check Box13: Yes |
| Check Box14: Off |
| Check Box19: Off |
| Check Box20: Yes |
| Check Box24: Off |
| Check Box25: Yes |
| Check Box26: Off |
| Dropdown31: [Yes] |
| Dropdown32: [Yes] |
| Dropdown33: [No] |
| Check Box41: Off |
| Check Box42: Off |
| Check Box43: Yes |
| Dropdown44: [Yes] |
| Text45: Filter on intakes as needed. |
| Dropdown46: [Yes] |
| Text48: Notification to the adjacent areas. |
| Text49: Notification to the adjacent area. |
| Text50: Utility outages are planned. |
| Text51: None anticipated. |
| Check Box52: Off |
File details come from the government source that posted it. Updated .