To be eligible for consideration and award, contractors must meet two key requirements: 1) Have no more than three serious violations, or one repeat violation, or one willful OSHA/EPA violation in the past 3 years, and 2) Maintain an EMR of 1.0 or less. Contractors must provide a self-certification on company letterhead regarding their safety/environmental record and submit their current EMR information on their insurance carrier's letterhead. If a contractor's EMR exceeds 1.0, they must provide a written explanation from their insurance carrier describing the reasons and anticipated date for reduction below 1.0.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PER VHA DIRECTIVE 7715 (06 April 2017) - SAFETY &

ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION

RATE (EMR):

Contractor Certification Regarding Project:

To be eligible for consideration and award, the contractor shall have no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years and have an EMR of equal to or less than 1.0.

All Offerors shall submit the following information pertaining to their past Safety & Environmental Record and EMR with their offer.

1. SAFETY & ENVIRONMENTAL RECORD: A self-certification on company letterhead that the contractor has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years.

2. EMR: All Offerors shall submit information regarding their current EMR. This information shall be obtained from the Offerors’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an Offeror’s EMR is above 1.0, Offeror shall submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.

2022 2023 2024 2025 Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations. (Four serious, one repeat, or one willful disqualifies the contractor.)

Number of violations from EPA within the last 3 years. Please attach explanation for any violations.

Company’s Current Insurance Experience Modification Rate (EMR) =

(Note: Contractor must support the EMR with a signed letter from Insurance Carrier on their letterhead.)

Signature: