This document is a drawing for the electrical infrastructure upgrades to Building 33, which is part of a federal contract opportunity with Solicitation Number 36C25924Q0535.
The drawing shows the planned layout and installation of new electrical conduit, outlets, and breakers to support an IT data center upgrade for the Department of Veterans Affairs (VA) Veterans Integrated Service Network 19. The key details include: new 1-inch conduit runs (two black lines and two green lines) with associated outlets and wiring, demolition of an existing rack ladder, installation of four new 30A circuit breakers, and instructions for the VA to relocate stored items prior to the work commencing. The drawing specifies the expected installation approach, such as routing conduit along the ceiling to the breaker box where possible.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25924Q0535 0004.docx | DOCX document | |
| S02 - Building 33.pdf | ||
| S02 - JSA and FDS Zone Power Distribution 1 0 12-04-20.pdf | ||
| 36C25924Q0535 0003.docx | DOCX document | |
| S04 - Site Visit Meeting Doc.docx | DOCX document | |
| S04 - Site Visit Attendance - FE.docx | DOCX document | |
| S05 - RFI Questions - EHRM Data Center Upgrade for JSA and FDS - Electrical Conduit - FE.docx | DOCX document | |
| S02 - Amendment 1 - Page 1 Block 10.docx | DOCX document | |
| 36C25924Q0535 0001.docx | DOCX document | |
| S02 - Site Instructions.docx | DOCX document | |
| S22 - LOS - Attachment - 852.219-75 Blank.docx | DOCX document | |
| 36C25924Q0535_1.docx | DOCX document | |
| PPQ Blank.docx | DOCX document | |
| S02 - SPECS - JSA and FDS Zone Power Distribution.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ROOM
ROOM
ELECT
MECH
BUILDING 33
(IT)
VHAGRJGordoJ Rectangle
VHAGRJGordoJ Rectangle
VHAGRJGordoJ Rectangle
VHAGRJGordoJ Rectangle
VHAGRJGordoJ Text Box -Red boxes are projected new rack locations.
-Green box is existing and will stay.
-Black line will be new 1" conduit installed (x 2). Will include wiring and appropriate L21 outlets (x4) and will be able to accept upsized neutrals.
-Green line will be new 1" snubbed conduit, and appropriate L21 outlets (x2) and will be able to accept upsized neutrals. No wiring.
-Conduit should be run along the ceiling into the top of the breaker box as much as possible, but side installation with any associated equipment or boxes is acceptable, if required.
-Black X is the demo of the rack ladder. Cabling and whips will be unwound by the VA prior to work commencing. Ground to be relocated to existing rack. Existing cable and wire to be securely supported by from the ceiling in order to deconflict with new server connections.
-4 triple pole, single throw 30 A breakers installed.
-Blanks may be installed in remaining open spaces. All replaced circuit breakers are returned to the VA.
-VA to move all stored items prior to work commencing.
VHAGRJGordoJ Line
VHAGRJGordoJ Line
VHAGRJGordoJ Line
VHAGRJGordoJ Line
VHAGRJGordoJ Text Box X
VHAGRJGordoJ Line
VHAGRJGordoJ Line
VHAGRJGordoJ Line
VHAGRJGordoJ Line
| Sheets and Views |
| Building 33 Sep 17-Layout1 |
File details come from the government source that posted it. Updated .