This is a Scope of Work Statement for federal contract 538-18-101 concerning domestic water system improvements at a federal facility. The project aims to reduce the risk of Legionella contamination and associated patient injury through comprehensive water system upgrades.

The scope encompasses demolition and construction activities including: removal of dead-legs and unused fixtures; installation of thermostatic mixing valves at point-of-use locations for scald protection; re-balancing of existing hot water recirculation loops and addition of new recirculation loops; installation of ultraviolet treatment equipment; installation of water monitoring equipment; integration of water monitoring and water quality instrumentation with the Building Automation System (BAS); installation of a fiber optic backbone for the BAS; demolition of abandoned equipment in Building 256; relocation and upgrade of the site domestic water storage tank valving and instrumentation; and installation of new site water delivery equipment extending from the municipality water meter through the Building 256 pump room. All work must be performed in accordance with project design documents.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

538-18-101 IMPROVE WATER SYSTEM TO REDUCE RISK OF LEGIONELLA CONTAMINATION AND PATIENT

INJURY

Scope of Work Statement

Perform all demolition and construction to provide domestic water system improvements, in accordance with project design documents. The improvements include dead-leg and unused fixture removal; installation of thermostatic mixing valves at point-of-use for scald protection; re-balancing of existing hot water recirculation loops and addition of new recirculation loops; installation of ultraviolet treatment equipment; installation of water monitoring equipment; connection and integration of water monitoring equipment and other water quality related instrumentation to the BAS; installation of a fiber optic backbone for the Building Automation System (BAS); demolition of abandoned equipment in

Building 256; relocation of the site domestic water storage tank valving and upgrade to tank instrumentation; and installation of new site water delivery equipment between municipality water meter through Building 256 pump room.