This document provides guidance for calculating the percentage of self-performed work on Project 621-18-104 to Renovate B Ground for Acute Care. Offerors for general construction work (NAICS code 236220) must self-perform at least 15% of the total contract value in personnel costs. Specialty trades with NAICS codes starting with 237 or 238 must self-perform 25%. Offerors must provide a breakdown of personnel and material/equipment costs by specification division. Home office overhead, profit, and bond costs are calculated after subtotals. Self-performed personnel costs are calculated as the total personnel costs performed by the prime contractor and SDVOSB subcontractors, excluding non-SDVOSB subcontractor personnel costs.
The related federal contract opportunity is solicitation number 36c24920r0065 for Project 621-18-104 to Renovate B Ground for Acute Care from the Department of Veterans Affairs Veterans Health Administration VISN 9. The solicitation is for general construction services.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK Project 621-18-104, Renovate B Ground for Acute Care
Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for specialty trade NAICS codes with 237 and 238 prefix) of the cost of the contract performance incurred for personnel must be performed by the Service Disabled Veteran Owned Small Business (SDVOSB) awardee or those of a verified SDVOSB subcontractor. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
Specification Division SDVOB Vendor (Y or N) Personnel Cost Material/Equipment Costs
Division 01 $ $ Division 02 $ $ Division 03 $ $ (Add additional lines as necessary for each Division applicable to this project)
Sub Total (Personnel Costs, Material/Equipment Costs)
Profit $ Home Office Overhead $ Bond $ Grand Total $
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $
3. Remainder is ‘Total amount of work to be self-performed under the Contract’: $
4. Self-performed work = Line 3/Line 1 x 100 = %
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)