This is a Base Offer Cost Breakdown template for a construction project to upgrade the steam distribution system at VA Central Western Massachusetts Healthcare System Edward P Boland Campus (Solicitation Number: 36C24126Q0173). The template requires offerors to provide project identification information, including the VA-assigned project number and title, offeror details (name, street address, city, state, zip), and project location. Costs must be broken down by construction divisions following the MasterFormat standard, spanning Division 1 (General Requirements) through Division 34 (Transportation), with separate columns for labor costs, material costs, and total costs per division.
The template includes structured sections for detailed labor calculations (listing labor categories, hourly rates, hours worked, and totals) and materials and equipment details (itemizing materials with unit rates, quantities, and totals). Offerors must calculate division subtotals, then apply overhead, profit, and bond percentages sequentially to arrive at the total base offer cost. The document provides sample examples for labor detail (plumber and laborer rates) and materials and equipment details (pipe, couplings, and pump rental) to guide proper cost entry. All fields are currently populated with zero placeholders, requiring complete cost data entry from responding contractors.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer
Base Offer Cost Breakdown
Project Number:
Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
| Edward L Roy: VA assigned Project Title | Project Location | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | - 0 | - 0 | - 0 |
| Division 3 | Concrete | - 0 | - 0 | - 0 |
| Division 4 | Masonry | - 0 | - 0 | - 0 |
| Division 5 | Metals | - 0 | - 0 | - 0 |
| Division 6 | Wood and Plastic | - 0 | - 0 | - 0 |
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | - 0 |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0
Labor Detail
| Sample Example | ||||
| Division | Labor Category | Labor Rate | Hours | Total |
| 1 | Plumber | $35.00 | 123 | $4,305.00 |
| 1 | Laborer | 14.75 | 70 | $1,032.50 |
| $5,337.50 |
Materials and Equipment Details
| Sample Example | ||||
| Division | Item | Rate | Units | Total |
| 1 | Pipe - 150' | $1.50 | 150 | $225.00 |
| 1 | 90 Degree Coupling | $1.10 | 5 | $5.50 |
| 1 | Pump Rental - Hour | $200.00 | 6 | $1,200.00 |
| $1,430.50 |