This document contains a contractor price estimate worksheet and information on a related federal contract opportunity for expansion of the Sarasota National Cemetery. The price estimate worksheet is a template for contractors to provide unit pricing for various construction-related line items involved in a renovation project. It includes line items for demolition, concrete, masonry, metals, woods, thermal and moisture protection, finishes, specialties, fire suppression, plumbing, HVAC, electrical, communications, security, and other construction-related work. The related federal contract opportunity is a solicitation from the Department of Veterans Affairs National Cemetery Administration for the gravesite expansion project at the Sarasota National Cemetery. The solicitation number is 36C78622B0025 and involves construction work to increase capacity at the cemetery. Pricing is to be submitted using the contractor price estimate worksheet template provided.

View the file

Other files

File Type Posted
36C78622B0025 0003.docx DOCX document
AMMEND 9-1-22 Design Sh 133-140 Sarasota Expansion.pdf PDF
AMMEND 9-1-22 Design Spec Appen A Sarasota Expansion.pdf PDF
AMMEND 9-1-22 Design Specifications Sarasota Expansion.pdf PDF
C03 Sarasota Ammended 36C78622B0025 0002.pdf PDF
AMMEND 9-1-22 Design Sh 141-144 Sarasota Expansion.pdf PDF
AMMEND 9-1-22 Design Spec Appen B Sarasota Expansion.pdf PDF
AMMEND 9-1-22 Design Sh 119-132 Sarasota Expansion.pdf PDF
AMMEND 9-1-22 Design Sh 113-117 Sarasota Expansion.pdf PDF
AMMEND 9-1-22 Design Sh 118 Sarasota Expansion.pdf PDF
36C78622B0025 0001.docx DOCX document
Sarasota Expansion Design Sh 012-019b.pdf PDF
Sarasota Expansion Design Sh 095-112.pdf PDF
Sarasota 931004_Specifications.pdf PDF
Sarasota Expansion Design Sh 054-069.pdf PDF
Sarasota Expansion Design Sh 070-094.pdf PDF
Sarasota Expansion Design Sh_020-034.pdf PDF
Sarasota Expansion Design Sh 035-053.pdf PDF
Sarasota Expansion Design Sh 001-011.pdf PDF
Sarasota Expansion Design Sh 113-147.pdf PDF
P07 Sarasota Wage Determination Building.txt TXT text file
P07 Sarasota Wage Determination Heavy.txt TXT text file
S02_Attachment-_852.219-77_Limitations on Subcontracting-Contractor Certification.pdf PDF
P09 - SSP Sarasota Ph 2 Expansion Project 19 Apr 22.docx DOCX document
P07 Sarasota Wage Determination Highway.txt TXT text file
36C78622B0025.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

DescriptionUnitCost/Unit# UnitsTotal CostRemarks
Offeror shall use and edit to fit Task Order Project
Division 01 - General Requirements
Project set-upL.S.$0.000$0.00
CoordinationL.S.$0.000$0.00
General DemolitionL.S.$0.000$0.00
Selective demo. GWB / Act ceilingSF$0.000$0.00
Selective demo. of floor fin and floor prep.SF$0.000$0.00
Selective demo. WallsEach$0.000$0.00
Selective demolition & salvageEach$0.000$0.00
Job supervision and misc. laborWeek$0.000$0.00
Mobilization / DemobilizationJob$0.000$0.00
Division 02 - Existing Conditions
$0.000$0.00
Division 03 - Concrete
Concrete floor trenching and infillL.S.$0.000$0.00
Concrete floor prep., flash patchL.S.$0.000$0.00
Division 04 - Masonry
$0.000$0.00
Division 05 - Metals
Misc. equipment supportsL.S.$0.000$0.00
Modification to Metal Window frameEach$0.000$0.00
Division 06 - Wood, Plastics, and Composites
Misc. blocking, framingL.S.$0.000$0.00
Chair RailLF$0.000$0.00
Blocking for CaseworkL.S.$0.000$0.00
Wood Trim (At Tech Station)LF$0.000$0.00
Plywood and wood trim (at Lockers)LF$0.000$0.00
Coat RodEach$0.000$0.00
Division 07 -Thermal & Moisture Protection
FirestoppingLF$0.000$0.00
Joint sealantsLF$0.000$0.00
Division 08 - Openings
New Door and Mtl. FrameEach$0.000$0.00
New Lead-lined door and frame assemblyEach$0.000$0.00
Modifications to existing lead windowsEach$0.000$0.00
Division 09 - Finishes
Acoustical ceiling tileSF$0.000$0.00
Existing Wall PatchingSF$0.000$0.00
Metal stud, gyp.board assembliesLF$0.000$0.00
GWB over exist framingLF$0.000$0.00
PaintSF$0.000$0.00
Vinyl BoarderLF$0.000$0.00
Resilient baseLF$0.000$0.00
Sheet Vinyl flooring and accessoriesSF$0.000$0.00
CarpetYr$0.000$0.00
Division 10 - Specialties
Hospital Curtain and TrackLF$0.000$0.00
Toilet and Bath AccessoriesEach$0.000$0.00
Casework Base and WallLF$0.000$0.00
CountertopsLF$0.000$0.00
Countertops with supportsLF$0.000$0.00
P. Lam ShelvingLF$0.000$0.00
Med. CabinetEach$0.000$0.00
LockersEach$0.000$0.00
Wall HooksL.S.$0.000$0.00
White BoardEach$0.000$0.00
Division 11 - Equipment
$0.000$0.00
Division 12 - Furnishings
-$0.000$0.00

Division 13 - Special Construction

Division 14 - Conveying Equipment

Division 21 - Fire Suppression
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 22 - Plumbing
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 23 - HVAC
RemovalsLS$0.000$0.00
Computer Room A/C % HumidifierEach$0.000$0.00
Electric Reheat CoilsEach$0.000$0.00
Fan Coil UnitEach$0.000$0.00
DuctworkLS$0.000$0.00
RGD'sEach$0.000$0.00
HVAC InsulationLS$0.000$0.00
Temperature ControlsLS$0.000$0.00
Test and BalanaceLS$0.000$0.00
Division 25 - Intergrated Automation
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 26 - Electrical
General Conditions and Administration-$0.000$0.00
Allowance-$0.000$0.00
Wiring DevicesEach$0.000$0.00
Wiring Device CircuitingEach$0.000$0.00
Light Fixtures & CircuitingEach$0.000$0.00
Specialty Light Fixtures & CircuitingEach$0.000$0.00
Relocate Panel board & circuitsEach$0.000$0.00
Relocate Nurse CallLS$0.000$0.00
Telephone / DataEach$0.000$0.00
Cath Equipment Connections & FeederLS$0.000$0.00
HVAC Equipment ConnectionsLS$0.000$0.00
DemolitionLS$0.000$0.00
Division 27 - Communications
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 28 - Electronic Safety and Security
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 31 - Earthwork
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 32 - Exterior Improvements
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 33 - Utilities
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 34 - Transportation
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 35 - Waterway and Marine Construction
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 40 - Process Interconnections
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 41 - Material Processing and Handling
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 42 - Process Heating, Cooling, and Drying
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 43 - Process Gas and Liquid Handling
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 44 - Pollution and Waste Control
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 45 - Industry-Specific Manufacturing
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 46 - Water and Wastewater Equipment
TBDLS$0.000$0.00
TBD-$0.000$0.00
Division 48 - Electrical Power Generation
TBDLS$0.000$0.00
TBD-$0.000$0.00
General Construction Subtotal$0.00
Mechanical, Electrical, Plumbing Subtotal$0.00

Total Base Construction Cost $0.00

Overhead0%$0.00
Profit0%$0.00
Bonding (If applicable)0%$0.00

Total Estimated Construction Cost $0.00

&8B & J Multi Services

Relace Water Main&"Arial,Bold"Estimated Construction
Cost Worksheet&8VA-528-07-RP-0135

Project # 528A8-04-808