This addendum pertains to a construction project for the Department of Veterans Affairs to upgrade the emergency department and GI lab air handling unit at the Comley-O'Neil VA Medical Center in Topeka, Kansas. The addendum provides clarification and changes to the drawings and specifications for the project, which is part of Phase 2 of the emergency department upgrades. Specifically, it requires contractors to incorporate work indicated on mechanical sheets MC800 and MC801 dated May 7, 2021 related to test and balancing and commissioning of the existing air handling units. The contractor must include this addendum in their proposal, and it forms part of the contract documents, taking precedence over original drawings and specifications where conflicts occur.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No.1
142 N. Mosley Street | Wichita, Kansas 67202
P 316.262.2500 | F 316.264.2300
Page | 1 Issued BY: Duane Hickerson
Project No: #589A5-115B Date of Issuance: 07/07/2021
Project: Upgrade Emergency Department
AHU Commissioning part of Phase 2 Addendum:No.001
Address: Comley-O Neil VA Medical Center Topeka, KS
To: Gislaine Dorvil Contracting Officer
Description:
Provide all labor and materials as required to incorporate work as indicated by the information and instructions as described below on the attached sheets. The sheet will be part of the Phase 2
Emergency Department Upgrades to include Part of GI Lab AHU Test and Balancing and
Commissioning of existing AHU units.
Mechanical: Sheets MC800 and MC801dated 5/07/2021
The contractor shall include this addendum as a part of his proposal. This addendum forms a part of the contract documents. The following items are to change and or clarify the drawings and specifications for construction of the referenced building and shall take precedence over the original drawings and specifications where a conflict occurs.