This document is a pre-solicitation notice for an invitation for bid to renovate the irrigation system and roads at Biloxi National Cemetery. The Department of Veterans Affairs intends to issue the solicitation on or about July 9, 2020 seeking bids for four contract line items. CLIN 0001 is for replacing irrigation components including mainlines, control valves, lateral lines, and sprinklers, excluding certain areas undergoing development. CLIN 0002 is for roads renovations covering base bid areas 2, 3, 5, and 7 and the maintenance yard. CLIN 0003 and 0004 are additive options to also renovate additional roads areas. The NAICS code is 237990 and business size standard is $36.5 million. The acquisition is a 100% set-aside for verified Service-Disabled Veteran Owned Small Businesses. The performance period for CLIN 0001 is 360 calendar days. Interested parties must register at beta.sam.gov and vetbiz.gov and acknowledge any amendments posted to beta.sam.gov by the response due date. The point of contact is provided for any questions.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF VETERANS AFFAIRS
NATIONAL CEMETERY ADMINISTRATION OFFICE
OF DESIGN AND CONSTRUCTION
WASHINGTON, D.C.
BID DOCUMENTS
VOLUME II
RECONSTRUCT ROADS AND INSTALL CURBS
BILOXI NATIONAL CEMETERY
BILOXI, MS
IFB NUMBER VA-XXXXXXXX
PROJECT NO. 832IC3033
19 MAY 2020
Volume II - Reconstruct Roads and Install Curbs Project No. 832IC3033
Biloxi National Cemetery, Biloxi, MS 19 May 2020
THIS SHEET INTENTIONALLY LEFT BLANK
SIGNATURE PAGE
Architect-Engineer:
VALI COOPER INTERNATIONAL
Sections covered by this seal include:
Divisions: All Divisions
TABLE OF CONTENTS
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
NCA MASTER SPECIFICATIONS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 02 General Requirements (Minor NCA Projects)
01 32 17 Network Analysis Schedules (Microsoft Project Gantt Chart)
01 33 23 Shop Drawings, Product Data, and Samples
01 42 19 Reference Standards
01 45 29 Testing Laboratory Services
01 57 19 Temporary Environmental Controls
01 74 19 Construction Waste Management
DIVISION 02 – EXISTING CONDITIONS
02 41 10 Demolition and Site Clearing
DIVISION 31 – EARTHWORK
31 20 00 Earth Moving
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement & Concrete for Exterior Improvements
32 12 16 Asphalt Paving
00 01 10-2
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
G-001 COVER SHEET
V-107 V-108 V-109 V-110 V-111 V-112 V-113 V-114 V-115 V-116 V-117 V-118 V-119 V-120 V-121 V-122 V-123 V-124 V-125 V-127 V-128
OVERALL SITE PLAN (SURVEY)
PLAN & PROFILE (BASELINE A) STATION 10+00 TO STATION 16+50
PLAN & PROFILE (BASELINE A) STATION 17+00 TO STATION 23+50
PLAN & PROFILE (BASELINE A) STATION 24+00 TO STATION 27+00
PLAN & PROFILE (BASELINE B) STATION 40+00 TO STATION 47+00
PLAN & PROFILE (BASELINE B) STATION 47+50 TO STATION 55+50
PLAN & PROFILE (BASELINE C) STATION 60+00 TO STATION 64+09.49
PLAN & PROFILE (BASELINE D) STATION 80+00 TO STATION 84+50
PLAN & PROFILE (BASELINE D) STATION 85+00 TO STATION 89+00
PLAN & PROFILE BASELINE E & BASELINE F
PLAN & PROFILE (BASELINE G) STATION 140+00 TO STATION 145+87.5
PLAN & PROFILE (BASELINE H) STATION 160+00 TO STATION 165+050
MAINTENANCE BUILDING AREA CROSS SECTIONS
ROAD CROSS SECTIONS (BASELINE A)
ROAD CROSS SECTIONS (BASELINE A)
ROAD CROSS SECTIONS (BASELINE B)
ROAD CROSS SECTIONS (BASELINE C)
ROAD CROSS SECTIONS (BASELINE D)
ROAD CROSS SECTIONS (BASELINES E & F)
ROAD CROSS SECTIONS (BASELINE G)
ROAD CROSS SECTIONS (BASELINE H)
D-101 DEMOLITION PLAN
D-102 DEMOLITION PLAN (BASELINE A) STATION 10+00 TO STATION 16+50
D-103 DEMOLITION PLAN (BASELINE A) STATION 17+00 TO STATION 23+50
D-104 DEMOLITION PLAN (BASELINE A) STATION 24+00 TO STATION 27+00
D-105 DEMOLITION PLAN (BASELINE B) STATION 40+00 TO STATION 47+00
D-106 DEMOLITION PLAN (BASELINE B) STATION 47+50 TO STATION 55+50
D-107 DEMOLITION PLAN (BASELINE C) STATION 60+00 TO STATION 64+09.49
D-108 DEMOLITION PLAN (BASELINE D) STATION 80+00 TO STATION 84+50
D-109 DEMOLITION PLAN (BASELINE D) STATION 85+00 TO STATION 89+00
D-110 DEMOLITION PLAN (BASELINE G) STATION 140+00 TO STATION 145+87.5
D-111 DEMOLITION PLAN (BASELINE G) STATION 160+00 TO STATION 165+00
C-101 ROAD RENOVATION OVERALL SITE PLAN
C-102 PLAN & SECTION (BASELINE A) STATION 10+00 TO STATION 16+50
C-103 PLAN & SECTION (BASELINE A) STATION 17+00 TO STATION 23+50
C-104 PLAN & SECTION (BASELINE A) STATION 24+00 TO STATION 27+00
C-105 PLAN & SECTION (BASELINE B) STATION 40+00 TO STATION 47+00
C-106 PLAN & SECTION (BASELINE B) STATION 47+50 TO STATION 55+50
C-107 PLAN & SECTION (BASELINE C) STATION 60+00 TO STATION 64+09.49
LIST OF DRAWING SHEETS
00 01 15 - 2
C-108 PLAN & SECTION (BASELINE D) STATION 80+00 TO STATION 84+50
C-109 PLAN & SECTION (BASELINE D) STATION 85+00 TO STATION 89+00
C-110 PLAN & SECTION (BASELINE G) STATION 140+00 TO STATION 145+87.5
C-111 PLAN & SECTION (BASELINE G) STATION 160+00 TO STATION 165+00
C-112 EROSION AND SEDIMENT CONTROL PLAN
C-401 GRADING AND DRAINAGE PLAN
C-402 GRADING AND DRAINAGE PLAN
C-501 ROAD RENOVATION SECTIONS AND DETAILS
C-502 EROSION AND SEDIMENT CONTROL DETAILS
- - - END - - -
i
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
1.2 STATEMENT OF BID ITEM(S)
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.4 construction security requirements
1.5 FIRE SAFETY
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS (NOT USED)
1.8 ENVIRONMENTAL CONTROLS
1.9 DISPOSAL AND RETENTION
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS
1.11 RESTORATION
1.12 PHYSICAL DATA
1.13 PROFESSIONAL SURVEYING SERVICES
1.14 LAYOUT OF WORK
1.15 As-Built Drawings
1.16 USE OF ROADWAYS
1.17 COR'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT (NOT USED)
1.19 TEMPORARY TOILETS
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
1.21 NEW TELEPHONE EQUIPMENT (NOT USED)
1.22 TESTS (NOT USED)
1.23 INSTRUCTIONS (NOT USED)
1.24 GOVERNMENT-FURNISHED PROPERTY (NOT USED)
1.25 RELOCATED ITEMS (NOT USED)
1.26 CONSTRUCTION SIGN
1.27 SAFETY SIGN
1.28 CONSTRUCTION DIGITAL IMAGES
1.29 FINAL ELEVATION PHOTOGRAPHS (NOT USED)
1.30 HISTORIC PRESERVATION
1.31 PROJECT HEALTH AND SAFETY PLAN
ii
This page intentionally blank
GENERAL REQUIREMENTS
01 00 02 - 1
SECTION 01 00 02
GENERAL REQUIREMENTS (MINOR NCA PROJECTS)
1.1 GENERAL INTENTION
A. Contractor shall completely prepare site for the reconstruction of
Cemetery roads and minor drainage work, including the milling and removal of existing roadway surfacing, and stripping and preparation for earthwork to correct drainage issues with existing drain inlets, and furnish labor, materials, equipment and services and perform and complete all work for VA NCA Biloxi National Cemetery Roadway Design project as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Cemetery Director.
C. Offices of Vali Cooper International, LLC, as Architect-Engineers
(A/E), may render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the
Government without affirmations by the VA Contracting Officer or duly authorized representative.
D. All Testing Laboratory services will be retained and paid for by the
Contractor (see Spec Section 01 45 29, Testing Laboratory Services).
However, the Department of Veterans Affairs may elect to retain its own
Testing Laboratory for any purpose. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with security requirements as established by the COR. They shall be restricted from unauthorized access.
F. Prior to commencing work, general contractor shall provide proof that an OSHA certified “competent person” (CP) 29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
G. Training:
1. All employees of the general contractor or his subcontractors shall, at the minimum, have successfully completed the 10-hour OSHA
GENERAL REQUIREMENTS
01 00 02 - 2 certified Construction Safety course and/or other relevant competency training, as determined by VA CP.
2. Submit OSHA training records of all employees for approval before the start of work.
1.2 STATEMENT OF BID ITEM(S)
A. CLIN 0002, GENERAL CONSTRUCTION: All work shown on the Volume II, Reconstruct Roads and Install Curbs, for Base Bid Areas 2,3,5,7 & the
Maintenance Yard, as shown on the plans and described in the specifications shall be performed.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. AFTER AWARD OF CONTRACT, one electronic set of specifications and drawings will be furnished to the contractor.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the site without following the procedures approved by the COR. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. For working outside the “regular hours” as defined in the contract, The General Contractor shall give 3 days’ notice to the COR so that appropriate arrangements can be provided for the Cemetery employees.
This notice is separate from any notices required for utility shutdown described later in this section.
01 00 02 - 3
3. No photography of VA premises is allowed without written permission of the COR.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the COR.
C. Guards:
1. No guards required onsite unless requested by the COR.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including toolboxes and parked machines, and to take any necessary emergency action.
E. Document Control:
1. The General Contractor is responsible for safekeeping of all drawings, project manuals, and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. All electronic information shall be stored in a specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
F. Motor Vehicle Restrictions
1. The number and location of contractor employee vehicles will be determined by the Cemetery Director and the COR.
1.5 FIRE SAFETY
A. Applicable Publications: Publications listed below form part of this
Article to the extent referenced. Publications are referenced in text by basic designations only.
1. American Society for Testing and Materials (ASTM):
E84-2009a Surface Burning Characteristics of Building
Materials
2. National Fire Protection Association (NFPA):
10-2010 Standard for Portable Fire Extinguishers
30-2008 Flammable and Combustible Liquids Code
01 00 02 - 4
51B-2009 Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2008 National Electrical Code
241-2009 Standard for Safeguarding Construction, Alteration, and Demolition Operations
3. Occupational Safety and Health Administration (OSHA):
29 CFR 1926 Safety and Health Regulations for Construction
B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to start of work, prepare a plan detailing project-specific fire safety measures, including periodic status reports, and submit to COR/Cemetery Director for review for compliance with contract requirements in accordance with Section 01 33
23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Prior to any worker for the contractor or subcontractor’s beginning work, they shall undergo a safety briefing provided by the General Contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of NCA equipment, etc.
Documentation shall be provided to the COR that individuals have undergone the Contractor’s safety briefing.
C. Site and Building Access: Maintain free and unobstructed access to emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.
D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet).
E. Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
F. Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30.
G. Hot Work: Perform and safeguard hot work operations in accordance with
NFPA 241 and NFPA 51B. Coordinate with COR.
H. Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas weekly. Coordinate with, and report findings and corrective actions weekly to COR.
I. Smoking: Smoking is prohibited except in designated smoking rest areas.
01 00 02 - 5
J. Dispose of waste and debris in accordance with NFPA 241. Remove from site weekly.
K. Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage trailers, office trailers) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the
Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roads constructed by the
Contractor when and as authorized by the COR. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the
Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as shown on the drawings. Contractor parking will be only in areas and on roadways designated and agreed to by the RE/COR in agreement of the
Cemetery.
E. Workmen are subject to rules of the Cemetery applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Cemetery as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
01 00 02 - 6
G. Phasing: To ensure such executions, the Contractor shall furnish the
COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site. The contractor shall plan and manage his work to provide continuous vehicular access to all portions of the cemetery within a reasonable delay (10 minutes maximum) to visitors to the cemetery. In addition, the Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of the site.
H. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article 1.16, USE OF ROADWAYS.
1.7 ALTERATIONS (NOT USED)
1.8 ENVIRONMENTAL CONTROLS
A. In general, following preventive measures shall be adopted during construction to keep down dust.
1. Dampen debris to keep down dust
B. Final Cleanup:
1. Upon completion of the project, or as work progresses, remove all construction debris.
1.9 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of the site, or parts thereof, shall be disposed of as follows:
1. Reserved items: There are no reserved items for the Government.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Cemetery.
1.10 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.
01 00 02 - 7
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the
Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge
Elimination System (NPDES) permit is required for this project. The
Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate NCA
Central/Cemetery) office. The contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:
1. Designating areas for equipment maintenance and repair.
2. Providing waste receptacles at convenient locations and provide regular collection of wastes.
3. Locating equipment wash down areas on site and provide appropriate control of wash-waters.
4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials.
5. Providing adequately maintained sanitary facilities.
01 00 02 - 8
1.11 RESTORATION
A. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
C. At the Contractor's own expense, the Contractor shall immediately restore to service and repair any damage caused by the Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services which are indicated on drawings and which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Vali Cooper
International, LLC, and their surveyor, Brown & Root.
B. Subsurface conditions have been developed by core borings. Logs of subsurface exploration conducted by Fugro USA Land, Inc. are in the geotechnical portion of the Roadway Assessment report.
C. A copy of the geotechnical report is an Appendix to these specifications section 31 20 00 and shall be considered part of the contract documents.
D. The Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine the site of work and logs of borings and, after investigation, decide for themselves the character of materials and make their bids accordingly. Upon proper application to the Department
01 00 02 - 9 of Veterans Affairs, including approved scheduling, bidders will be permitted to make subsurface explorations of their own at site.
1.13 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.14 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks indicated on the drawings and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at the Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the COR. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the COR until authorized to remove them. If such marks are destroyed by the
Contractor or through Contractor's negligence before their removal is authorized, the COR may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark, such lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each roads and parking area are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to
01 00 02 - 10 the COR before any work and other major controlling features is placed.
D. During progress of work, the Contractor shall have lines, grades, locations and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the
COR before any major items of concrete work are placed. In addition, furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of elevations of all swales.
2. Lines and elevations of roads, streets and curb and gutter.
E. Upon completion of the work, the Contractor shall furnish the COR with reproducible drawings, in AutoCAD form, at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.15 AS-BUILT DRAWINGS
A. The Contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, which will include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR's review, as often as requested.
C. At substantial completion, the Contractor shall secure the services of a professional land surveyor, as defined in Section 1.13, to perform a site survey within the project limits in accordance with the NCA Site, Topographic, Utility, Landscape & Soil Survey scope of services, as listed in the appendix of this specification. Elements to be surveyed include, but are not limited to:
1. Location, alignment, and dimension of roads, curbs, walks, parking, and paved areas. Indicate road centerlines with true bearings and lengths by 15 m (50') stationing. Describe curves by designating the points of curvature and tangency by station. Include all curve data as well as location of radius and vertex points. Designate
01 00 02 - 11 roads with curbs by double lines. Show equalities for intersecting roads by station.
2. Crown, grade, and climb of curb at road crossings contours.
3. Elevations on 50' centers on centerline of roads, edges of roads, and top and bottom of curbs.
4. Type of pavement of roads.
5. Surface elevations on a 50' grid pattern, except where terrain features require greater detail. At abrupt changes in grade, show elevations at the tops and bottoms of slopes to the nearest 0.1'.
D. The Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after acceptance of the project by the COR.
D. Paragraphs A, B, C & D shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and designated permanent roads on Cemetery property when indicated or authorized by the COR.
Temporary roads shall be constructed or modified by the Contractor at the Contractor's expense following approved plans that include:
construction, operation, maintenance, and restoration. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
B. New permanent roads are a part of this contract, the Contractor may construct them to facilitate other construction operations. These completed roads may be used by all who have business at the cemetery.
1.17 COR'S FIELD OFFICE (NOT USED)
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT (NOT USED)
1.19 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections, or when approved by COR provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.20 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to
01 00 02 - 12 the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the COR, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the
Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
C. The Contractor shall install meters at the Contractor's expense and furnish the Cemetery a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR's discretion) of use of water from the Cemetery's system.
01 00 02 - 13
3. Where not available or not convenient to connect to the Cemetery distribution system, the Contractor shall supply water via portable/temporary means at his own expense.
1.21 NEW TELEPHONE EQUIPMENT (NOT USED)
1.22 TESTS (NOT USED)
1.23 INSTRUCTIONS (NOT USED)
1.24 GOVERNMENT-FURNISHED PROPERTY (NOT USED)
1.25 RELOCATED ITEMS (NOT USED)
1.26 CONSTRUCTION SIGN
A. Provide a Construction Sign where directed by the COR. All wood members shall be of framing lumber. Cover sign frame with 0.7 mm (24 gage) galvanized sheet steel nailed securely around edges and on all bearings. Sign face shall be 4 feet x 5 feet and 6 inches. Provide two 100 by 100 mm (4 inch by 4 inch) posts (or equivalent round posts) set 900 mm (three feet) into ground. Set bottom of sign level at 900 mm (three feet) above ground and secure to posts with through bolts.
Make posts full height of sign. Brace posts with 50mm x 100 mm (two by four inch) material as directed.
B. Paint all surfaces of sign and posts two coats of white semi-gloss paint. Border and letters shall be of black gloss paint, except project title which shall be blue gloss paint.
C. Maintain sign and remove it when directed by the COR.
D. Detail Drawing of construction sign showing required legend and other characteristics of sign is a part of the drawings and specifications.
1.27 SAFETY SIGN
A. Provide a Safety Sign where directed by COR. Signboard shall be three feet x four feet, 19 mm (3/4-inch) thick exterior grade plywood.
Provide two 100 mm by 100 mm (four by four inch) posts extending full height of sign and 900 mm (three feet) into ground. Set bottom of sign level at 1200 mm (four feet) above ground.
B. Paint all surfaces of Safety Sign and posts with one prime coat and two coats of white gloss paint. Letters and design shall be painted with gloss paint of colors noted.
C. Maintain sign and remove it when directed by COR.
D. Detail Drawing of safety sign showing required legend and other characteristics of sign is included in the drawings and specifications.
E. Post the number of accident free days on a daily basis.
01 00 02 - 14
1.28 CONSTRUCTION DIGITAL IMAGES
A. During construction period through completion, furnish Department of
Veterans Affairs weekly color digital photographs of construction progress (8 to 10 images per week.) Photographs of the reinforcing steel shall be taken after all reinforcing steel, sleeves, inserts, etc. are in place. Photographs must show distinctly, at as large a scale as possible, all parts of work embraced in picture.
B. Photographs are to be taken with a high-resolution digital camera, minimum 6 megapixels, with good wide-angle capability. The images shall be recorded in JPEG format with a minimum of 24-bit color and no reduction in actual picture size.
1. Compressed size of the file shall be no less than 80% or the original with no loss of information.
2. File names shall contain the Project number, the date the image was taken, and a unique sequential identifier, for example:
101CM3202_10-01-2013_0001. Use underscore, not spaces in digital file names.
C. The digital photo files shall become property of Government and will be both e-mailed and submitted on CD-ROM.
1. The images shall be forwarded electronically to the COR via email to
NAME@va.gov within 2 days of when the photo was taken. Identify the content of each picture by a caption incorporated in the photo.
2. The digital photo files shall also be submitted on CD-ROM to the COR at the conclusion of the project. The CD-ROM shall also contain an index of all the images contained therein in either a TXT or
Microsoft Word format.
1.29 FINAL ELEVATION PHOTOGRAPHS (NOT USED)
1.30 HISTORIC PRESERVATION
A. Where the Contractor or any of the Contractor's employees, prior to, or during the construction work, are advised of or discover any possible archeological, historical and/or cultural resources, the Contractor shall stop work in that area and immediately notify the COR verbally, and then with a written follow up.
1.31 PROJECT HEALTH AND SAFETY PLAN
A. Prior to commencing any construction, the Contractor shall submit a site specific Project Health and Safety Plan (PHSP). At a minimum, the
PHSP shall cover the following topics:
1. Organizational structure (including Responsible Persons)
01 00 02 - 15
2. Site Characterization and Job Hazard Identification
3. Site Control and Security
4. Training - List of Certified Employees trained in CPR
5. PPE
6. Heat Stress
7. Spill Containment
8. Decontamination
9. Emergency Response
10. Trench Safety
- - - E N D - - -
01 00 02 - 16
NETWORK ANALYSIS SCHEDULE
01 32 17-1
SECTION 01 32 17
NETWORK ANALYSIS SCHEDULES
(MICROSOFT PROJECT GANTT CHART)
PART 1 - GENERAL
1.1 DESCRIPTION
A. The Contractor shall develop a Microsoft Project 2003 (or later) Gantt
Chart (bar chart) schedule demonstrating fulfillment of the contract requirements. The Contractor shall keep the network up-to-date in accordance with the requirements of this section. The Contractor shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). The Gantt Chart will be used to satisfy time applications.
1.2 CONTRACTOR’S REPRESENTATIVE
A. The Contractor shall designate an in-house representative who will be responsible to prepare the schedule, review the schedule and report progress of the project to the Contracting Officer's Representative.
B. The Contractor's in-house representative shall be given authority to act on behalf of the Contractor in fulfilling the requirements of this specification section. Such authority shall not be interrupted throughout the duration of the project.
1.3 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide to VA monthly computer processing of all computer produced schedules generated from monthly project updates. The
Contractor shall provide to VA two (2) copies of the updated Microsoft
Project Gantt Chart and an electronic copy of this data. This must be submitted with and substantively support the contractor’s monthly payment request.
B. The Contractor is responsible for the correctness and timeliness of the computer-produced reports. The Contractor is also responsible for the accurate and timely submittal of the updated project schedule.
C. VA shall report errors in computer-produced reports to the Contractor’s representative within ten (10) calendar days from receipt of reports. The
Contractor shall reprocess the Gantt Chart and associated CDs, when requested by the Contracting Officers Representative, to correct errors that affect the schedule for the project.
01 32 17-2
1.4 THE COMPLETE PROJECT GANTT CHART SUBMITTAL
A. The Complete Project Microsoft Project Gantt Chart will contain work activities/events as necessary to fully detail the project schedule.
B. Within ten (10) calendar days after receipt of the Notice to Proceed, the
Contractor shall submit for the Contracting Officer's review, a Microsoft
Project Gantt Chart and a CD. Each activity/event on the Gantt Chart schedule shall contain as a minimum, but not limited to, activity/event description, duration, start dates and finish dates. Activity constraints, not required by the contract, will not be accepted. Logic events (non-work) will be permitted where necessary to reflect proper sequence among work events, but must have zero duration.
C. The complete working Gantt Chart shall reflect the Contractor's approach to scheduling the complete project. The final Gantt Chart in its original form shall contain no contract changes or delays that may have been incurred during the final Gantt Chart development period. It shall reflect the Contractors “AS BID” or “DAY 1” schedule. Changes and /or delays shall be entered at the first monthly update after the final Gantt
Chart has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with
Article, ADJUSTMENT OF CONTRACT COMPLETION.
D. Within ten (10) calendar days after receipt of the complete project Gantt
Chart, the Contracting Officer or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. Schedule a meeting with the Contractor at, or near the job site, for joint review, correction or adjustment of the proposed plan. Within ten (10) calendar days after the joint review, the Contractor shall revise and shall submit two (2) copies of the revised Gantt Chart and a revised CD as specified to the Contracting Officer. The revised submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved.
1.5 WORK ACTIVITY/EVENT AND COST DATA INFORMATION
A. The Contractor shall not be required to “cost load” the computerized
Microsoft Project Gantt Chart. As part of this submission, the Contractor shall provide a separate Schedule of Costs on AIA document G703. This
Schedule of Costs shall reflect and contain all the same activities/events identified on the Gantt Chart.
01 32 17-3
B. The Contractor and the Contracting Officer shall use this Schedule of
Costs for monthly payment purposes as referenced in the General
Requirements of this agreement.
C. The Contractor and Contracting Officer shall agree on percentages for monthly work accomplished. The cumulative total amount of all cost loaded activities/events (including alternates) shall equal the total contract price.
D. Prorate overhead, profit and general conditions on all work activities/events for the entire project. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
1.6 GANTT CHART REQUIREMENTS
A. Show on the Gantt Chart the sequence and interdependence of work activities/events required for complete performance of all items of work.
In preparing the Gantt Chart, the Contractor shall:
1. Show the following on each work activity/event:
a. Concise description of the work represented by the activity/event.
b. Duration (in work days.)
2. Show activities/events as:
a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.
b. Contracting Officer Representative's and Architect-Engineer's review and approval of shop drawings, equipment schedules, samples, template, or similar items.
c. Interruption of VA Cemetery utilities, delivery of Government furnished equipment, project phasing and any other specification requirements.
3. Break up the work into activities/events of durations no longer than thirty (30) work days each, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the Contracting Officer may approve the showing of a longer duration. [The duration for VA approval of any required submittal, shop drawing, or other submittals shall not be less than ten (10) workdays.] The construction time as determined by the Gantt Chart schedule from start to finish for any sub-phase, phase or the entire project shall not exceed the total contract duration. Describe work activities/events clearly, so the work is readily identifiable for assessment of completion. Activities/events labeled "start,"
01 32 17-4
"continue," or "completion," are not specific and will not be allowed.
Lead and lag time activities will not be acceptable.
1.7 PAYMENT TO THE CONTRACTOR
A. Monthly, the contractor shall submit the Gantt Chart updated for remaining activity durations and a Schedule of Costs updated for costs. AIA application and certification for payment documents G702 and G703 will be used. The payment request should reflect and be in accordance with the provisions of the following Article, PAYMENT AND PROGRESS REPORTING. The
Contractor is entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated Schedule of
Costs unless, in special situations, the Contracting Officer permits an exception to this requirement. Monthly payment requests shall include:
two (2) copies of the updated Microsoft Project Gantt Chart, a listing of all project schedule changes, and associated data, made at the update.
These must be submitted with and substantively support the contractor’s monthly application and certificate for payment request documents.
B. When the Contractor fails or refuses to furnish to the Contracting Officer the information and the associated updated Gantt Chart data, which, in the sole judgment of the Contracting Officer, are necessary for validating the monthly progress payment, the Contractor shall not be deemed to have provided supporting schedule data upon which progress payment may be reasonably determined.
1.8 PAYMENT AND PROGRESS REPORTING
A. Monthly job site progress meetings shall be held on dates mutually agreed to by the Contracting Officer (or Contracting Officer's Representative) and the Contractor. Presence of subcontractors during the progress meeting is optional unless required by the Contracting Officer (or
Contracting Officer's Representative). Job progress will be reviewed to verify:
1. Actual start and/or finish dates for updated/completed activities/events.
2. Remaining duration, required to complete each activity/event started, or scheduled to start, but not completed.
3. Time and cost data for change orders, and supplemental agreements that are to be incorporated into the Gantt Chart.
4. Percentage for completed and partially completed activities/events.
01 32 17-5
5. Logic and duration revisions required by this section of the specifications.
6. Activity/event duration and percent complete shall be updated independently.
B. The Contractor shall submit a narrative report as a part of his monthly review and update, in a form agreed upon by the Contracting Officer. The narrative report shall include a description of problem areas; current and anticipated delaying factors and their estimated impact on performance of other activities/events and completion dates; and an explanation of corrective action taken or proposed.
C. As part of the monthly jobsite progress meeting, the General Contractor, specifically requested subcontractors and the Contracting Officers
Representative shall meet to discuss the monthly updated schedule. The main emphasis shall be to address work activities to avoid slippage of project schedule and to identify any necessary actions required to maintain project schedule during the reporting period.
1.9 RESPONSIBILITY FOR COMPLETION
A. Whenever it becomes apparent from the monthly progress review meeting or the monthly computer-produced Gantt Chart schedule that phasing or contract completion dates will not be met, the Contractor shall execute some or all of the following remedial actions:
1. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of work.
2. Increase the number of working hours per shift, shifts per working day, working days per week, the amount of construction equipment, or any combination of the foregoing to eliminate the backlog of work.
3. Reschedule the work in conformance with the specification requirements.
B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the Contracting Officer for the proposed schedule changes. If such actions are approved, the revisions shall be incorporated by the Contractor into the Gantt Chart before the next update, at no additional cost to the Government.
1.10 CHANGES TO GANTT CHART SCHEDULE
A. Within ten (10) calendar days after VA acceptance and approval of any updated computer-produced schedule, the Contractor shall submit a revised
Gantt Chart, the associated CDs, and a list of any activity/event changes including predecessors and successors for any of the following reasons:
01 32 17-6
1. Delay in completion of any activity/event or group of activities/events, which indicate an extension of the project completion by twenty (20) working days or 10 percent of the remaining project duration, whichever is less. Such delays which may be involved with contract changes, strikes, unusual weather, and other delays will not relieve the Contractor from the requirements specified unless the conditions are shown on the Gantt Chart as the direct cause for delaying the project beyond the acceptable limits.
2. Delays in submittals, or deliveries, or work stoppage are encountered which make rescheduling of the work necessary.
3. The schedule does not represent the actual prosecution and progress of the project.
4. When there is, or has been, a substantial revision to the activity/event costs of the network diagram regardless of the cause for these revisions.
B. Revisions made under this paragraph, which affect the previously approved computer-produced schedules for Government furnished equipment, contract phase(s) and sub phase(s), utilities furnished by the Government to the
Contractor, or any other previously contracted item, must be furnished in writing to the Contracting Officer for approval.
C. Contracting Officer's approval for the revised Gantt Chart and all relevant data is contingent upon compliance with all other paragraphs of this section and any other previous agreements by the Contracting Officer or the Contracting Officer’s Representative.
D. The cost of revisions to the Gantt Chart resulting from contract changes will be included in the cost of the change.
E. The cost of revisions to the Gantt Chart not resulting from contract changes is the responsibility of the Contractor.
1.11 ADJUSTMENT OF CONTRACT COMPLETION
A. The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the contract completion date by the Contractor shall be supported with a justification, Gantt Chart data and supporting evidence as the Contracting Officer may deem necessary for determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract. Submission of proof based on revised activity/event logic, durations (in work days) and costs is obligatory to any approvals.
01 32 17-7
B. The Contracting Officer's determination as to the total number of days of contract extension will be based upon the current computer-produced Gantt
Chart schedule for the time period when the change took place and all other relevant information. The Contracting Officer will, within thirty
(30) calendar days after receipt of such justification and supporting evidence, advise the Contractor in writing of his decision on the matter.
C. The Contractor shall submit each request for a change in the contract completion date to the Contracting Officer in writing. The Contractor shall include, as a part of each change order proposal, a sketch showing all revisions, duration (in workdays) changes, and cost changes, for work in question and…