This notice describes a solicitation for irrigation and road renovation projects at Biloxi National Cemetery. The scope of work involves replacing irrigation components including mainlines, control valves, wiring, lateral lines, and sprinkler heads. It also includes reconstructing roads and installing curbs in various areas of the cemetery. There are four contract line items, with the first two being base requirements and the second two additive options. Line item one is for replacing the irrigation system, and line item two is for road renovations in specified areas. The solicitation will be issued on or around July 9, 2020 as an invitation for bid utilizing electronic bid submission and telephonic bid opening. The estimated value is between $2-5 million. This procurement is set aside solely for verified service-disabled veteran-owned small businesses. Firms must be registered in the System for Award Management and Vendor Information Pages databases. The point of contact is provided for any questions.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work (SOW)
Irrigation and Road Renovations
Project Number 832CM3032
Biloxi National Cemetery, 400 Veterans Avenue Bldg. 1001, Biloxi, MS 39531-2410
CLIN 0001, GENERAL CONSTRUCTION: Replace Irrigation Components
Installation of all work shown on the Volume I plans and described in the Volume I specifications including but not limited to all work necessary to remove and replace irrigation components downstream of the existing well and pump including mainline, remote control valves and wiring, lateral lines, and sprinkler heads. The only exceptions are the irrigated turf areas within sections AB, N, M, 58 and 59 which are currently undergoing renovations to develop pre-placed lawn crypts and in-ground cremains burial sites. These areas include new remote-control zone valves, laterals, and heads. The intent is to integrate these new lateral zones into the new system by tying the valves into the new main line and 2-wire control system. Work includes the installation of a new variable frequency device for more efficient operation of the irrigation pump. The overall performance period for this project is 360 calendar days from issuance of the notice-to proceed (NTP).
CLIN 0002, GENERAL CONSTRUCTION: Road Renovations
All work shown on the Volume II, Reconstruct Roads and Install Curbs, for Base Bid Areas 2,3,5,7 & the Maintenance Yard, as shown on the plans and described in the specifications shall be performed.