This document package includes construction plans for a burial expansion project at Dallas Fort-Worth National Cemetery. The plans show existing site conditions, proposed site layout and grading, roadway profiles, utility details, signage, landscaping, and irrigation. The project involves expanding burial areas and constructing related site improvements across approximately 28 acres. Relevant details include specifications for new crypts, roads, stormwater features, and landscaping/amenities. The solicitation number is 36C78620B0019 and seeks bids for the burial expansion project through the VA's eCMS portal only. Evaluation and award will be based on competitive fixed-price bids. The project is being undertaken by the Department of Veterans Affairs National Cemetery Administration.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF
VETERANS AFFAIRS
DALLAS COUNTY
DALLAS, TEXAS
BURIAL EXPANSION
PROJECT NUMBER: 916CM3017
BID DOCUMENTS
PROJECT
LOCATION
LOCATION MAP
N.T.S.
VICINITY MAP
N.T.S.
GI001
COVER SHEET
SITE/CIVIL
1. GI001 COVER SHEET
2. GI002 GENERAL NOTES, SYMBOLS AND ABBREVIATIONS
3. VL100 OVERALL EXISTING CONDITIONS PLAN
4. BI100 BORING LOCATION PLAN
5. GC100 CONSTRUCTION ACCESS PLAN
6. CS100 OVERALL SITE PLAN AND KEY MAP
7. GC101 EROSION AND SEDIMENT CONTROL PLAN - NORTHWESTERN AREA
8. GC102 EROSION AND SEDIMENT CONTROL PLAN
9. GC501 EROSION AND SEDIMENT CONTROL DETAILS
10. CS101 SITE LAYOUT PLAN
11. CS102 SITE LAYOUT PLAN
12. CS103 SITE LAYOUT PLAN
13. CS110 BURIAL SECTION LAYOUT PLAN SECTIONS 40 & 42
14. CS111 BURIAL SECTION LAYOUT PLAN SECTION 44
15. CS112 BURIAL SECTION LAYOUT PLAN SECTION 41
16. CS113 BURIAL SECTION LAYOUT PLAN SECTION 43
17. CS114 BURIAL SECTION LAYOUT PLAN SECTION 45
18. CS115 BURIAL SECTION LAYOUT PLAN SECTIONS 51 & 53
19. CS116 BURIAL SECTION LAYOUT PLAN SECTION 49
20. CS117 BURIAL SECTION LAYOUT PLAN SECTION 47
21. CS118 BURIAL SECTION LAYOUT PLAN SECTION 52
22. CS119 BURIAL SECTION LAYOUT PLAN SECTION 50
23. CS120 BURIAL SECTION LAYOUT PLAN SECTION 48
24. CS121 BURIAL SECTION LAYOUT PLAN SECTION 46
25. CG101 GRADING AND DRAINAGE PLAN
26. CG102 GRADING AND DRAINAGE PLAN
27. CG103 GRADING AND DRAINAGE PLAN
28. CG110 BURIAL SECTION GRADING ENLARGEMENT SECTION 40
29. CG111 BURIAL SECTION GRADING ENLARGEMENT SECTION 42
30. CG112 BURIAL SECTION GRADING ENLARGEMENT SECTION 44
31. CG113 BURIAL SECTION GRADING ENLARGEMENT SECTION 41
32. CG114 BURIAL SECTION GRADING ENLARGEMENT SECTION 43
33. CG115 BURIAL SECTION GRADING ENLARGEMENT SECTION 45
34. CG116 BURIAL SECTION GRADING ENLARGEMENT SECTIONS 51 & 53
35. CG117 BURIAL SECTION GRADING ENLARGEMENT SECTION 49
36. CG118 BURIAL SECTION GRADING ENLARGEMENT SECTION 47
37. CG119 BURIAL SECTION GRADING ENLARGEMENT SECTION 52
38. CG120 BURIAL SECTION GRADING ENLARGEMENT SECTION 50
39. CG121 BURIAL SECTION GRADING ENLARGEMENT SECTION 48
40. CG122 BURIAL SECTION GRADING ENLARGEMENT SECTION 46
41. CT201 ROADWAY CENTERLINE PROFILE
42. CT202 ROADWAY CENTERLINE PROFILE
43. CT203 ROADWAY CENTERLINE PROFILE
44. CU260 STORM SEWER PROFILES
45. CU261 STORM SEWER PROFILES
46. CU262 STORM SEWER PROFILES
47. CU263 SWM CROSS SECTIONS
48. CU264 STORM SEWER COMPUTATIONS
49. DT501 CRYPT AND BURIAL SECTION DETAILS
50. DT502 CRYPT AND BURIAL SECTION DETAILS
51. DT503 ROADWAY DETAILS
52. DT504 STORM DRAINAGE DETAILS
53. DT505 STORM DRAINAGE DETAILS
54. DT506 STORM DRAINAGE DETAILS
55. CJ100 DRAINAGE AREA MAP
56. CI100 SITE SIGNAGE PLAN
57. CI501 SITE SIGNAGE DETAILS
58. CI502 SITE SIGNAGE DETAILS
LANDSCAPE
59. L-101 LANDSCAPE PLAN
60. L-102 LANDSCAPE PLAN
61. L-103 LANDSCAPE PLAN
62. L-501 PLANTING DETAILS
63. L-502 SITE AMENITY DETAILS
IRRIGATION
64. LI100 IRRIGATION NOTES AND LEGEND
65. LI101 IRRIGATION PLAN
66. LI102 IRRIGATION PLAN
67. LI103 IRRIGATION PLAN
68. LI500 IRRIGATION DETAILS
69. LI501 IRRIGATION DETAILS
70. LI502 IRRIGATION DETAILS
ELECTRICAL
71. EP101 ELECTRICAL SITE PLAN
72. EP501 ELECTRICAL DETAILS
DRAWING INDEX
NO. DRAWING DRAWING TITLE
Know what's below.
before you dig.Call
R
DALLAS-FORT WORTH NATIONAL CEMETERY
OKLAHOMA
LOUISIANA
GULF OF
MEXICO
MEXICO
NEW MEXICO
GRAVESITE YIELD SUMMARY
COLUMBARIUM
NICHES
TOTAL NUMBER
OF GRAVESITES
IN-GROUND
CREMAIN SITES
(4'x4')
6,000
CREMAIN PLOTS
MEMORIAL
MARKERS
MEMORIAL SITES
PRE-PLACED
DOUBLE-DEPTH
CRYPTS (3'x8')
CASKET PLOTS
PRE-PLACED
OVERSIZED
CRYPTS (4'x10')
TRADITIONAL
FULL CASKET
PRIVATE VAULT
GRAVESITES
(4'x10')
NO. DRAWING DRAWING TITLE
Project Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
916CM3017
MAY 26, 2020 RPP MAC Dwg. of 72
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Revisions: Date:
Drawing Title
Approved:
Phase
Project Director
Building Number
BID DOCUMENTS
VA FORM 08 - 6231
321 4 5 6 7 8 9 10
DALLAS-FORT WORTH NATIONAL
CEMETERY BURIAL EXPANSION
DALLAS COUNTY, TEXAS
Fil e P ath : G
:\P
RO
JE
CT
\S
BU
\E
NG
IN
\33
\02
\P
LA
NS
\B
ID
D
OC
UM
EN
TS
\G
I-0
.D W
G
Gordon
148 S. Queen Street, Suite 201
Martinsburg, WV 25401
Phone: 304-725-8456 www.gordon.us.com
PROGRAMMING AND PLANNING
CIVIL ENGINEERING
LANDSCAPE ARCHITECTURE
SURVEY AND MAPPING
SECURITY CONSULTING
Aqua Engineering
(970) 372-6104 rvi
(512) 480-0032
AES Group
(303) 841-3922
8,000 14,000
ARKANSAS
PROJECT
LOCATION
Gordon
148 S. Queen Street, Suite 201
Martinsburg, WV 25401
Phone: 304-725-8456 www.gordon.us.com
PROGRAMMING AND PLANNING
CIVIL ENGINEERING
LANDSCAPE ARCHITECTURE
SURVEY AND MAPPING
SECURITY CONSULTING
ACREAGE
24.85 AC.
DEVELOPED AREA
planning + landscape architecture
712 Congress Avenue, Suite 300
Austin, Texas 78701
(512) 480-0032
Group, Inc.
11031 SOUTH PIKES PEAK DRIVE #202
PARKER, COLORADO 80138
PH: 303.841.3922
WWW.AES-GRP.COM
ROBERT W. BECCARD
84064
P
R
O
F
E
S
S
I
O
N A L
E
N
G
I
N
E
E
R
S
T
A
T
E
O F
T
E
X
A
S
L
I
C
E
N S
E
D
GI002
GENERAL NOTES, SYMBOLS AND
ABBREVIATIONS
EXISTING PROPOSED
BOUNDARY/RIGHT-OF-WAY LINE
LIMITS OF GRADING
LIMITS OF WORK
CONSTRUCTION NOTES:
1. THE CONTRACTOR IS RESPONSIBLE FOR REVIEWING THE CONSTRUCTION DOCUMENTS PRIOR TO CONSTRUCTION AND NOTIFYING THE U.S. DEPARTMENT OF
VETERANS AFFAIRS OF ANY CIRCUMSTANCES FOUND WITHIN THESE PLANS IN NEED OF VERIFICATION SO THAT APPROPRIATE REVISIONS CAN BE MADE, IF
WARRANTED.
2. CONTRACTOR SHALL CONTACT TEXAS ONE CALL SYSTEM, INC. AT 1-800-344-8377 OR 811 A MINIMUM OF SEVENTY-TWO (72) HOURS PRIOR TO ANY EXCAVATION, DEMOLITION OR OTHER EARTH DISTURBING ACTIVITIES WITHIN AREAS SERVED BY UNDERGROUND UTILITIES. THE CONTRACTOR IS RESPONSIBLE FOR FIELD
VERIFYING THE PRESENCE OF ANY UNDERGROUND UTILITIES PRIOR TO CONSTRUCTION.
3. EROSION AND SEDIMENT CONTROL DEVICES ARE TO BE IN PLACE PRIOR TO ANY LAND DISTURBING ACTIVITIES. REFER TO EROSION AND SEDIMENT CONTROL PLAN
FOR PHASING AND DETAILS.
4. ALL LAND ON OR OFF-SITE WHICH IS DISTURBED BY CONSTRUCTION AND WHICH IS NOT BUILT UPON OR SURFACED SHALL BE ADEQUATELY STABILIZED TO CONTROL
EROSION AND SEDIMENTATION
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFYING THE CONTRACTING OFFICER OF ANY CHANGES OR CONDITIONS ATTACHED TO PERMITS REQUIRED FOR
CONSTRUCTION.
6. THE CONTRACTOR SHALL PROVIDE ADEQUATE MEANS OF CLEANING TRUCKS AND/OR EQUIPMENT OF MUD AND DEBRIS, PRIOR TO ENTERING PAVED AREAS. IT IS THE CONTRACTOR'S RESPONSIBILITY TO CLEAN STREETS OF MUD AND/OR LAYING DUST AND TO TAKE ALL APPROPRIATE MEASURES NECESSARY TO ENSURE THAT
STREETS ARE KEPT IN A CLEAN AND DUST FREE CONDITION AT ALL TIMES.
7. THE CONTRACTOR SHALL VISIT THE SITE AND SHALL VERIFY EXISTING CONDITIONS PRIOR TO STARTING CONSTRUCTION ACTIVITIES.
8. GORDON DOES NOT CERTIFY TO THE SUB-SURFACE CONDITIONS OF THE SITE, THE LOCATION OF UNDERLYING ROCK, OR THE LOCATION OF POTENTIAL SINKHOLES.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DIGGING OF TEST HOLES TO VERIFY SUB-SURFACE CONDITIONS PRIOR TO BEGINNING ANY CONSTRUCTION. IF SINKHOLES ARE FOUND IN THE FIELD, REMEDIATION WILL BE REQUIRED AS SPECIFIED BY A QUALIFIED GEOTECHNICAL ENGINEERING FIRM.
9. ALL PROPOSED GRADES AS SHOWN HEREIN ARE FINISHED GRADE UNLESS OTHERWISE NOTED ON THE PLAN.
10. THE CONTRACTOR SHALL BE RESPONSIBLE FOR NOTIFYING THE CONTRACTING OFFICER OF ANY CONDITIONS FOUND IN THE FIELD PRIOR TO STAKEOUT THAT VARY FROM THE APPROVED PLANS OR THAT MAKE CONSTRUCTIBILITY IMPOSSIBLE. ANY OBSERVATIONS REGARDING APPARENT INCONSISTENCIES IN THE PLANS SHALL BE BROUGHT TO THE CONTRACTING OFFICER ATTENTION FOR VERIFICATION PRIOR TO STAKEOUT.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR INITIATING, MAINTAINING AND SUPERVISING ALL SAFETY PRECAUTIONS AND PROGRAMS IN CONNECTION WITH THE PERFORMANCE OF ITS WORK AND THE WORK OF ITS SUBCONTRACTORS. THE VA SHALL NOT HAVE CONTROL OVER, CHARGE OF, OR RESPONSIBILITY FOR THE CONSTRUCTION MEANS, METHODS, TECHNIQUES, SEQUENCES OR PROCEDURES OR FOR SAFETY PRECAUTIONS AND PROGRAMS IN CONNECTION WITH THE WORK.
12. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING A SAFE WORK AREA AT ALL TIMES. TEMPORARY BARRICADES, ROAD CLOSURE SIGNAGE, FENCES AND OTHER WARNING DEVICES SHALL BE USED TO PREVENT PUBLIC ACCESS TO CONSTRUCTION WORK AREAS. VA MAINTENANCE OPERATIONS SHALL NOT BE UNDULY
IMPEDED BY THE CONTRACTOR'S OPERATIONS.
13. THE CONTRACTOR SHALL NOTIFY THE CEMETERY DIRECTOR AND THE CONTRACTING OFFICER TWO DAYS BEFORE ANY DEMOLITION WORK BEGINS. ANY PLANNED INTERRUPTIONS IN SERVICES SHALL BE COORDINATED WITH THE CONTRACTING OFFICER AT LEAST TWO DAYS IN ADVANCE.
14. THE CONTRACTOR SHALL CONFINE HIS EQUIPMENT AND OPERATIONS TO THE LIMITS OF CONSTRUCTION SHOWN. THE CONTRACTOR ASSUMES FULL RESPONSIBILITY FOR THE SAFETY AND SECURITY OF ALL MATERIALS AND EQUIPMENT ON SITE.
15. THE CONTRACTOR SHALL USE ONLY APPROVED ROADWAYS FOR CONSTRUCTION AND DELIVERY ACCESS. DAMAGE TO THE EXISTING ROADS SHALL BE REPAIRED AT
NO COST TO THE OWNER.
16. CONTRACTOR IS RESPONSIBLE FOR REPAIR OF EXISTING CEMETERY GROUNDS DUE TO CONSTRUCTION ACTIVITY.
17. CONTRACTOR SHALL COMPLETE INSTALLATION OF THE TEMPORARY GRAVEL CONSTRUCTION ACCESS ROAD BEFORE ANY OTHER PROJECT WORK IS STARTED. VA TO ACCEPT WORK ON THE ROAD ONCE INSTALLATION IS COMPLETE FOR SHARED USE BY A SEPARATE CONTRACT.
18. NOTE PLAN LOCATIONS WHERE CONSTRUCTION LIMITS CROSS THE EXISTING GAS MAIN. TEST PIT TO CONFIRM HORIZONTAL AND VERTICAL LOCATION OF EXISTING GAS LINE WITHIN LIMITS OF WORK. EXPECTED COVER IS +/- 6'. IF HORIZONTAL LOCATION OR DEPTH OF COVER VARIES FROM PLAN LOCATION, NOTIFY RE/COR & A/E.
GAS LINE UTILITY TOLERANCES REQUIRE NEGLIGIBLE REDUCTION IN COVER OVER EXISTING LINE AND LESS THAN 6" INCREASE IN COVER. GRADING ADJUSTMENT
MAY BE NECESSARY AS A RESULT OF VARIATION.
HEADSTONE FACE DIRECTION
BURIAL CRYPT PLOTS
WETLANDS
GRAVESITE GRID MONUMENT
CONCRETE SECTION MARKER
CIVIL LEGENDGENERAL NOTES:
1. THE TOPOGRAPHIC CONTOUR INTERVAL IS ONE (1) FOOT. TOPOGRAPHIC INFORMATION WAS COMPILED FROM AN AERIAL TOPOGRAPHIC SURVEY PREPARED BY
TUCK MAPPING SOLUTIONS, INC. WITH A FLIGHT DATE OF MARCH 28, 2018. HORIZONTAL DATUM IS REFERENCED TO THE TEXAS STATE PLANE, NORTH CENTRAL
ZONE (NAD 83) COORDINATE SYSTEM. VERTICAL DATUM IS REFERENCED TO (NAVD 88).
2. UNDERGROUND UTILITIES SHOWN HAVE BEEN LOCATED FROM VISIBLE EVIDENCE AND RECORD DRAWINGS FROM PHASE 1 AND PHASE 2. THE UTILITIES SHOWN MAY OR MAY NOT REFLECT ALL UNDERGROUND UTILITIES IN SERVICE OR ABANDONED. UTILITIES SHOULD BE VERIFIED BY APPROPRIATE UTILITY COMPANIES PRIOR TO ANY CONSTRUCTION. GORDON DOES NOT CERTIFY TO THE LOCATION OR THE EXISTENCE OF EXISTING UNDERGROUND UTILITIES. THE CONTRACTOR IS RESPONSIBLE FOR THE DIGGING OF TEST HOLES PRIOR TO BEGINNING CONSTRUCTION. IF CONDITIONS ARE FOUND IN THE FIELD WHICH ARE MATERIALLY
DIFFERENT FROM THE PLANS, THE CONTRACTOR SHALL NOTIFY THE CONTRACTING OFFICER.
3. THE SUBJECT PROPERTY IS LOCATED ON F.E.M.A. MAP 48113C0455M DATED MARCH 21, 2019. NO PORTION OF THIS PROPERTY IS LOCATED WITHIN THE 100-YEAR
FLOODPLAIN AREA (ZONE A). THE PROPERTY IS IN ZONE D.
4. BURIAL CEREMONIES WILL BE SCHEDULED THROUGHOUT THE COURSE OF THIS PROJECT. DURING ALL CEREMONIES LIGHT WORK ACTIVITY MAY CONTINUE IF IT DOES NOT CREATE NOISE OR DISTRACTIONS TO THE CEREMONY. COORDINATE DAILY ACTIVITIES WITH THE CEMETERY DIRECTOR OR HIS APPROVED
REPRESENTATIVE TO ACCOMMODATE SCHEDULED BURIALS.
5. DUE TO THE SENSITIVE NATURE OF THE CEMETERY SITE, CONTRACTOR SHALL MAINTAIN EACH WORK AREA IN A CLEAN AND ORDERLY APPEARANCE. TRASH AND WASTE MATERIALS SHALL BE STORED IN APPROVED CONTAINERS AND ROUTINELY DISPOSED OF OFF-SITE. CLEANUP SHALL BE REQUIRED AT THE END OF EACH
DAY AND/OR MORE FREQUENTLY AS REQUIRED.
6. AFFECT OF WORK ON PUBLIC ACCESS SHALL BE MINIMAL AND SHALL BE COORDINATED WITH THE CEMETERY DIRECTOR. ANY ALTERED PUBLIC TRAFFIC ROUTES SHALL BE WELL DEFINED WITH PROFESSIONALLY MADE SIGNAGE AND/OR OTHER APPROVED CONVENTIONAL METHODS.
7. THERE SHALL BE AT ALL TIMES WHEN WORK IS BEING DONE, A COMPETENT PERSON WHO IS APPRISED OF THE CONDITION AND PROGRESS OF ALL AREAS OF WORK ON SITE. THIS PERSON SHALL BE ABLE TO SPEAK FOR AND ACT IN THE BEHALF OF THE CONTRACTOR. THEY SHALL BE AWARE AND KNOWLEDGEABLE OF ALL THE SAFETY CONCERNS ON THE JOB SITE. THEY SHALL BE EMPOWERED TO IMMEDIATELY AND EFFECTIVELY MITIGATE THE ACTIONS OF ANY WORKMAN ON SITE.
RETAINING WALL
DRAINAGE FLOW ARROW
xx
XXXX
DETAIL #
SHEET REFERENCE
DETAIL LABEL
INTERIOR CRYPT
(TYP.)
PERIMETER
CRYPT (TYP.)
KEYNOTE REFERENCE LABEL
Project Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
916CM3017
MAY 26, 2020 RPP MAC Dwg. of 72
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Revisions: Date:
Drawing Title
Approved:
Phase
Project Director
Building Number
BID DOCUMENTS
VA FORM 08 - 6231
321 4 5 6 7 8 9 10
DALLAS-FORT WORTH NATIONAL
CEMETERY BURIAL EXPANSION
DALLAS COUNTY, TEXAS
Fil e P ath : G
:\P
RO
JE
CT
\S
BU
\E
NG
IN
\33
\02
\P
LA
NS
\B
ID
D
OC
UM
EN
TS
\G
I-0
.D W
G
Gordon
148 S. Queen Street, Suite 201
Martinsburg, WV 25401
Phone: 304-725-8456 www.gordon.us.com
PROGRAMMING AND PLANNING
CIVIL ENGINEERING
LANDSCAPE ARCHITECTURE
SURVEY AND MAPPING
SECURITY CONSULTING
Aqua Engineering
(970) 372-6104 rvi
(512) 480-0032
AES Group
(303) 841-3922
XX
GRANITE SECTION MARKER
EASEMENT LINE
ROAD CENTERLINE
HEADER CURB
CURB & GUTTER
EDGE OF PAVEMENT
CHAIN LINK FENCE
OVERHEAD UTILITY LINE
UNDERGROUND UTILITY LINE
WATER MAIN
BUILDINGS
SIDEWALK
SANITARY SEWER MAIN
STORM SEWER LINE
TREES/SHRUBS
INDEX CONTOUR LINE
INTERMEDIATE CONTOUR LINE
SPOT ELEVATIONS
MISCELLANEOUS SIGNS
SITE LIGHT WITH POLE
DRIP LINE OF TREES
REVERSE CURB
543.6
TO BE
REMOVED
TO
REMAIN
BOARD FENCE
8" W/M8" W/M
8" PVC SAN. SEW.
15" HDPE
TRANS.CURB
WIRE FENCE
EDGE OF GRAVEL
GUARDRAIL
EDGE OF CONCRETE
LP
SANITARY SEWER CLEAN-OUT
SANITARY SEWER MANHOLE
STORM SEWER MANHOLE
STORM SEWER DROP INLET
STORM SEWER CURB INLET
STORM SEWER RIP-RAP
STORM SEWER END SECTION
FIRE HYDRANT
WATER VALVE
WATER METER
MAIL BOX
UTILITY POLE
FEATURE WALL
OVERHEAD COMMUNICATIONS LINE
UNDERGROUND COMMUNICATIONS LINE
BUILDING MOUNTED LIGHT
UTILITY POLE GUY WIRE
SANITARY SEWER FORCE MAIN
8" PVC SAN. SEW.
15" HDPE
UNDERGROUND GAS LINE
C3
CO
45 0
GS 45 0
TC 45 0
INV
EX.
EX.
X
CO
MB
33 33
STORM SEWER HEADWALL
STORM SEWER CLEANOUT
STORM SEWER YARD INLET
EUTILITY BOX
ELECTRICAL TRANSFORMER
E
GROUND LIGHT
TRTR
STORM SEWER UNDERDRAIN
CO
IN-GROUND CREMAIN SITES
ABBREVIATIONS:
A AREA OR ARC
AC ACRE
ADA AMERICANS WITH DISABILITIES ACT
ADMIN AMDINISTRATION
AGE ABOVE GROUND ELECTRIC
AGEC ABOVE GROUND ELECTRIC CONDUIT
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
APPROX APPROXIMATE
ARCH ARCHITECTURAL
ASPH ASPHALT
AST ABOVE-GROUND STORAGE TANK
ATS ACTIVE TREATMENT SYSTEM
AVE AVENUE
AWWA AMERICAN WATER WORKS ASSOCIATION
A/C AIR CONDITIONING
BC BOTTOM OF CURB
BF BASEMENT FLOOR
BFP BACKFLOW PREVENTER
BFV BUTTERFLY VALVE
BITUM BITUMINOUS
BL BASE LINE
BLDG BUILDING
BLVD BOULEVARD
BM BENCHMARK, BASELINE MARKER
BMP BEST MANAGEMENT PRACTICES
BOE BOTTOM OF EXCAVATION
BOV BLOW OFF VALVE
BRG BEARING
BRL BUILDING RESTRICTION LINE
BV BALL VALVE
BW BOTTOM OF WALL
C COEFFICIENT OF RUNOFF
CALC CALCULATE
CB CATCH BASIN OR CHORD BEARING
CC CENTER TO CENTER
CCTV CLOSED CIRCUIT TELEVISION
CD CONSTRUCTION DOCUMENTS, CONTRACT DOCUMENTS OR CHECK DAM
CDW CHILLED DRINKING WATER
CDWR CHILLED DRINKING WATER RETURN
CDWS CHILLED DRINKING WATER SUPPLY
CE CONSTRUCTION ENTRANCE
CEM CEMENT OR CEMETERY
CF CONTRACTOR FURNISHED
CFS CUBIC FEET PER SECOND OR COMPOST FILTER SOCK
CG CURB AND GUTTER
CHD CHORD
CIP CAST IRON PIPE OR CULVERT INLET PROTECTION
CJ CONTRACTION JOINT
CL CENTERLINE, CLASS
CMP CORRUGATED METAL PIPE
CMU CONCRETE MASONRY UNIT
CN CURVE NUMBER
CND CONDUIT
CNR CORNER
CO CLEANOUT
COL COLUMN
COMM COMMUNICATIONS
CONC CONCRETE
COND CONDITION OR CONDENSER
CONF CONFERENCE
CONN CONNECTION
CON CONTAMINATED
CONSTR CONSTRUCTION
CONT CONTINUATION
CONTR CONTRACT OR CONTRACTOR
COR CONTRACTING OFFICER'S REPRESENTATIVE
COTG CLEANOUT TO GRADE
COV COVER OF CUT OFF VALVE
CPv CHANNEL PROTECTION VOLUME
CPPE CONSERVATION PRACTICE PHYSICAL EFFECTS
CPP CORRUGATED PLASTIC PIPE
CRN CROWN
CSB CONCRETE SPLASH BLOCK
CSI CONSTRUCTION SPECIFICATIONS INSTITUTE
CSS COMMITTAL SERVICE SHELTER
CSP CONCRETE SEWER PIPE
CT COURT
CTR CENTER OR CONTOUR
CTRL CONTROL
CTS COOLING TOWER SUPPLY
CTV CABLE TELEVISION
CV CONTROL VALVE
CW CLOCKWISE OR CONCRETE WASHOUT
CWP COLD WATER PIPING
D DEPTH
DAT DATUM
DB DEED BOOK; DESIGN-BUILD; DRAIN BASIN
DBL DOUBLE
DD DIVERSION DIKE
DEG DEGREE
DEMO DEMOLITION
DEPT DEPARTMENT
DESC DESCRIPTION
DET DETAIL
DI DROP INLET
DIA DIAMETER
DIFF DIFFERENCE
DIP DUCTILE IRON PIPE
DIST DISTANCE
DM DROP MANHOLE
DOC DOCUMENT
DOM DOMESTIC
DR DRIVE
DRE DECOMPOSED ROCK ELEVATION
DS DOWNSPOUT
DWG DRAWING
D/W DRIVEWAY
D DELTA
EA EACH
EBL EAST BOUND LANE
EC EDGE OF CONCRETE
ECL EROSION CONTROL LOG
EG EDGE OF GUTTER
EJ EXPANSION JOINT
ELEV ELEVATION
ELEC ELECTRICAL
ENTR ENTRANCE
EOI END OF INFORMATION
EP EDGE OF PAVEMENT
EPA ENVIRONMENTAL PROTECTION AGENCY
E&S EROSION & SEDIMENT
ES END SECTION
ESMT EASEMENT
ETO EARLY TURNOVER
EPT EXTERNAL PIPE THREAD
EQ EQUAL
EW END WALL
EXP EXPANSION
EX EXISTING
EXT EXTERIOR
FAR FLOOR AREA RATIO
FC FACE OF CURB
FD FOUNTAIN DRAIN
FF FIRST FLOOR OR FINISHED FLOOR
FG FINISHED GRADE
FH FIRE HYDRANT
FIN FINISHED
FLR FLOOR
FN FENCE
FP FLOOD PLAIN
FOC FACE OF CURB
FOTG FIELD OFFICE TECHNICAL GUIDE
FOY FOYER
FP FLAG POLE OR FIRE PROTECTION
FPS FEET PER SECOND
FR FROM
FS FILTER SOCK
FT FEET
FWS FLOWER WATERING STATION
G GAS
GAL GALLON
GDR GUARD RAIL
GEN GENERATOR
GFA GROSS FLOOR AREA
GIP GALVANIZED IRON PIPE
GL GROUND LEVEL
GOVT GOVERNMENT
GR GRADE
GR GUARD RAIL
GS GROUND SHOT
H HORIZONTAL
HC HANDICAP
HCP HANDICAPPED
HDPE HIGH DENSITY POLYETHYLENE
HDR HEADER
HDWL HEADWALL
HGL HYDRAULIC GRADE LINE
HH HAND HOLE
HLBC HOT LAID BITUMINOUS CONCRETE
HMA MOT-MIX ASPHALT
HP HIGH POINT OR HIGH PRESSURE
HR HAND RAIL
HT HEIGHT
HW HOT WATER
HWSR HOT WATER SUPPLY & RETURN
HWY HIGHWAY
HYD HYDRANT
HYDR HYDRAULIC
I RAINFALL INTENSITY
ID INSIDE DIAMETER
IGC IN-GROUND CRYPT
IN INCH
INV INVERT
IP IRON PIPE OR INLET PROTECTION
IPF IRON PIPE FOUND
IPS IRON PIPE SET
IRR IRRIGATION
IW IRRIGATION WATER
JB JUNCTION BOX
K ONE THOUSAND (KILO)
KWY KEYWAY
L LENGTH
LAT LATERAL
LF LINEAR FEET
LOC LOCATION
LONG LONGITUDE
LOS LINE OF SIGHT
LP LOW POINT OR LOW PRESSURE
LT LIGHT OR LEFT
LL LOWER LEVEL
M MARKER
MAINT MAINTENANCE
MAT MATERIAL
MAX MAXIMUM
MB MAIL BOX
MECH MECHANICAL
MED MEDIUM
MEMO MEMORANDUM
MEP MECHANICAL, ELECTRICAL, PLUMBING
MFG MANUFACTURING
MGT MANAGEMENT
MH MANHOLE
MI MILE
MIN MINIMUM
MISC MISCELLANEOUS
ML MATERIALS LIST
MN MAGNETIC NORTH
MOD MODEL OR MODIFY
MON MONUMENT
MS MEDIAN STRIP
MSL MEAN SEA LEVEL
MTG MEETING
MTL MATERIAL
MULT MULTIPLE
MUNIC MUNICIPAL
N NORTH
N/F NOW OR FORMERLY
NA MOT APPLICABLE
NAT MATURAL
NATL NATIONAL
NBC NATIONAL BUILDING CODE
NBL NORTH BOUND LANE
NCA NATIONAL CEMETERY ADMINISTRATION
NCPS NATIONAL CONSERVATION PRACTICE STANDARDS
NCTCOG NORTH CENTRAL TEXAS COUNCIL OF GOVERNMENTS
NE NOT EXCEEDING
NFA NET FLOOR AREA
NHCP NATIONAL HANDBOOK OF CONSERVATION PRACTICES
NIC NOT IN CONTRACT
NO NUMBER
NOI NOTICE OF INTENT
NOM NOMINAL
NPDES NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM
NRCP NON-REINFORCED CONCRETE PIPE
NRCS NATURAL RESOURCES CONSERVATION SERVICE
NTP NOT TO PROCEED
NTS NOT TO SCALE
OC ON CENTER
OCEW ON CENTER EACH WAY
OD OUTSIDE DIAMETER
OFB ORGANIC FILTER BERM
OFD OVERFLOW DRAIN
OFT ORGANIC FILTER TUBE
OH OVERHANG
OHC OVERHEAD COMMUNICATIONS
OHE OVERHEAD ELECTRIC
OP OUTLET PROTECTION
OS OVER-SIZED
OZ OUNCE
P PERIMETER, RAINFALL DEPTH
PAR PARALLEL
PAT PATTERN
PB PULL BOX
PC POINT OF CURVATURE
PCA PORTLAND CEMENT ASSOCIATION
PCC POINT OF COMPOUND CURVE
PCEP POINT OF CURVE, EDGE OF PAVEMENT
PCT PERCENT
PCTC POINT OF CURVE, TOP OF CURB
PERF PERFORATED
PED PEDESTAL
PG PAGE
PGL POINT OF GRADE LINE
PH PROFILE HOLE
PI POINT OF INTERSECTION
PIC PUBLIC INFORMATION CENTER
PIV POST INDICATOR VALVE
PL PROPERTY LINE
POTW POTABLE WATER
PP POLYPROPYLENE (PLASTIC)
PPC PRE-PLACED CRYPT
PRC POINT OF REVERSE CURVE
PRELIM PRELIMINARY
POTW PUBLICLY-OWNED TREATMENT WORKS
PROP PROPOSED
PSI POUNDS PER SQUARE INCH
PSL PIPE SLEEVE
PT POINT OF TANGENCY
PTS PASSIVE TREATMENT SYSTEM
PV PRIVATE VAULT
PVC POLY VINYL CHLORIDE (PLASTIC PIPE)
PVI POINT OF VERTICAL INTERSECTION
PVMT PAVEMENT
PVT POINT OF VERTICAL TANGENCY
P&P PLAN AND PROFILE
Q FLOW, AMOUNT OF RUNOFF
Qf EXTREME FLOOD VOLUME Qp OVERBANK FLOOD PROTECTION VOLUME
QTR QUARTER
QTY QUANTITY
QUAD QUADRANT
QUAL QUALITY
R RISER, RADIUS
RAD RADIANS
RCN RUNOFF CURVE NUMBER
RCP REINFORCED CONCRETE PIPE, REFLECTED CEILING PLAN
RD ROAD, ROOF DRAIN
RDC REDUCER
RE RESIDENT ENGINEER
REP REPAIR
REQ REQUIRED
REV REVISION
REv RECHARGE VOLUME
RGP ROUGH GRADING PLAN
RPA RESOURCE PROTECTION AREA
RR RAILROAD
RTE ROUTE
RT RIGHT
RV RELIEF VALVE
RW RETAINING WALL
R/W RIGHT-OF-WAY
SAN SANITARY
SB SPLASH BLOCK OR SEDIMENT BASIN
SBL SOUTH BOUND LANE
SCF SEDIMENT CONTROL FENCE
SCHED SCHEDULE
SD STORM DRAIN
SDMH STORM DRAIN MANHOLE
SEC SECTION
SEG SEGMENT
SEL SELECT
SEW SEWER
SF SQUARE FEET OR SILT FENCE
SSF SUPER SILT FENCE
SJ SCORED JOINT
SLV SLEEVE
SM SECTION MARKER
SMH STEAM MANHOLE
SOV SHUT OFF VALVE
SP SITE PLAN
SPEC SPECIFICATION
SPKLR SPRINKLER
SQ SQUARE
SS SANITARY SEWER, STORM SEWER OR STEAM SUPPLY
ST STREET OR SEDIMENT TRAP
STA STATION
STD STANDARD
STE STEAM
STK STACK
STM STORM
SUPT SUPPORT
SURV SURVEY
SVC SERVICE
SWM STORMWATER MANAGEMENT
S/W SIDEWALK
SWPPP STORM WATER POLLUTION PREVENTION PLAN (SWP3)
SWG SEWAGE
Sx CROSS SLOPE
SYM SYMBOL
T TANGENT
T&M TIME AND MATERIALS
TB TEST BORE
TC TOP OF CURB
Tc TIME OF CONCENTRATION
TCEQ TEXAS COMMISSION ON ENVIRONMENTAL QUALITY
TCP TERRA COTTA PIPE, TRAFFIC CONTROL PLAN
TELE TELEPHONE
TH TEST HOLE
TNL TUNNEL
TOB TOP OF BANK
TOC TOP OF CURB
TOP TOP OF PAVEMENT
TOPO TOPOGRAPHY
TP TEST PIT, TELEPHONE POLE, OR TREE PROTECTION
TPDES TEXAS POLLUTANT DISCHARGE ELIMINATION SYSTEM
TW TOP OF WALL
TXDOT TEXAS DEPARTMENT OF TRANSPORTATION
TYP TYPICAL
UD UNDERDRAIN
U/G UNDERGROUND
UGC UNDERGROUND COMMUNICATIONS
UGE UNDERGROUND ELECTRIC
UFC UNIFORM FIRE CODE
UL UPPER LEVEL
UON UNLESS OTHERWISE NOTED
UP UTILITY POLE
USACE U.S. ARMY CORPS OF ENGINEERS
USDA U.S. DEPARTMENT OF AGRICULTURE
UTIL UTILITY
V VERTICAL
VA VETERANS ADMINISTRATION, VIRGINIA
VAR VARIES
VC VERTICAL CURVE
VEL VELOCITY
VERT VERTICAL
VF VERTICAL FOOT
VIC VICINITY
VID VIDEO
VIF VERIFY IN FIELD
VOL VOLUME
W WATER, WEST OR WIDE
W/ WITH
W/O WITHOUT
WBL WEST BOUND LANE
WI WROUGHT IRON
WL WATER LINE
WM WATER MAIN OR WATER METER
WO WORK ORDER
WQv WATER QUALITY VOLUME
WSE WATER SURFACE ELEVATION
WT WATER TIGHT
WW WASTE WATER
X-ING CROSSING
YI YARD INLET
YR YEAR
Z SIDE SLOPES
490 485
485480
535540
EX. LIGHT
POLE (TYP.)
BURIAL
SECTION 76
BURIAL
SECTION 77
S
E
R
V
I
C
E
E
N
T
R
Y
O
A
D
S
E
R
V
I
C
E
E
N
T
A
D
P A
T R
I O
T
A V
E N
U E
L
O
N
S
T
A
C
I
R
C
L
E
LONE STAR CIRCLE
L
O
R
C
L
E
L
O
R
C
L
E
L
O
R
C
L
E
T
R
I N
I
W
Y
T R
I N
I T
Y
W
A Y
T
R
I
N
I
Y
T
R
I N
I
Y
T
E
J
A
S
B
O
U
L
E
V
A
R
D
TEJAS BOULEVARD
T E
J A
S B
O U
L E
V A
R D
T
E
J
A
S
B
O
U
L
E
V
A
R
D
TEJAS BOULEVARD
TEJAS BOULEVARD
P
A
T
R
I
O
T
A
V
E
N
U
E
RIO GRANDE DRIVE
MOUNTAIN CREEK PARKWAY
MOUNTAIN CREEK PARKWAY
MOUNTAIN CREEK PARKWAY
M
O
U
N
T
A
E
K
P
R
K
W
A
Y
M
O
U
N
T
A
E
K
R
K
W
A
Y
A D
M
IN
/M A
IN
T
.R O
A D
S
P
U
A
T
R
I
R
K
W
A
Y
S
P
A
T
R
I
R
K
W
A
Y
S
P
A
T
R
I
R
K
W
A
Y
BURIAL
SECTION 27
BURIAL
SECTION 26
BURIAL
SECTION 25
BURIAL
SECTION 24
BURIAL
SECTION 23
BURIAL
SECTION 22
BURIAL
SECTION 86
BURIAL
SECTION 88
BURIAL
SECTION 87
BURIAL
SECTION 89
BURIAL
SECTION 91
BURIAL
SECTION 90
BURIAL
SECTION 92
BURIAL
SECTION 93
BURIAL
SECTION 95
BURIAL
SECTION 97
BURIAL
SECTION 98
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION 106
BURIAL
SECTION 107
BURIAL
SECTION 105
BURIAL
SECTION 5
BURIAL
SECTION 6
BURIAL
SECTION 7
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION
BURIAL
SECTION 14A
BURIAL
SECTION 14B
BURIAL
SECTION 14C
BURIAL
SECTION 14D
BURIAL
SECTION 14F
BURIAL
SECTION 14E
BURIAL
SECTION 15B
BURIAL
SECTION 15A
BURIAL
SECTION
16A
BURIAL
SECTION
16B
BURIAL
SECTION
17A
BURIAL
SECTION
17B
BURIAL
SECTION
18A
BURIAL
SECTION 21
BURIAL
SECTION
18B
BURIAL
SECTION
19B
BURIAL
SECTION
19A
BURIAL
SECTION 94
BURIAL
SECTION 96
BURIAL
SECTION 27A
COLUMBARIUM E
COLUMBARIUM C
& MEMORIAL
WALL 1
COLUMBARIUM A
COLUMBARIUM B
COLUMBARIUM D
BURIAL
SECTION 28
BURIAL
SECTION 29
BURIAL
SECTION 30
BURIAL
SECTION 31
BURIAL
SECTION 32 BURIAL
SECTION 33
BURIAL
SECTION 84
BURIAL
SECTION 85
SPUR 303 (W KIEST BOULEVARD)
S P
U R
(W
K
IE
S T
B O
U L E
V A
R D
BURIAL
SECTION 15C
COMMITTAL
SHELTER A
COMMITTAL
SHELTER B
PUBLIC
INFORMATION &
RESTROOMS
ASSEMBLY
AREA
ADMINISTRATION
BUILDING
ADMINISTRATION/
MAINTENANCE
COMPLEX
VETERANS
LAKE
COMMITTAL
SHELTER C
EX. CARILLON
W
S 88°49'11" W
915.43'
W
'5
E
N
W
N 88°59'57" W
185.00'
W
N 89°48'46" E
2105.60'
N 88°58'56" E
1527.48'
N 88°58'56" E
348.46' (R&M)
M
S
E
S
W
S 89°28'13" W
551.81'
N 89°27'56" E
505.30'
D
R
L
C
B
L
R
M
D
R
L
C
B
L
R
M
D =07°02'49"
R =666.30'
L=81.95'
C B
=N 86°39'49" W
C L=81.90'
D
R
L
C
B
S
L
R
M
D
R
L
C
B
L
M
D
R
L
C
B
L
R
M
D
R
L
C
B
L
M
D =8°29'10"
R =1969.86'
L=291.76'
C B
=N
86°28'22" W
C L=291.49'
(R
M
D=11°06'33"
R=2939.79'
L=570.00'
CB=S 83°15'55" W
CL=569.11' (R
&M)
EX. UNITED GAS PIPELINE
COMPANY (TRACT 1)
30' EASEMENT
VOLUME 74139, PAGE 2931
D.R.D.C.T.
UNITED GAS PIPELINE COMPANY
30' EASEMENT
VOLUME 71134, PAGE 1276
D.R.D.C.T.
EX. CITY OF DALLAS
15' SANITARY SEWER EASEMENT
VOLUME 78196, PAGE 1433
D.R.D.C.T.
EX. UNDERGROUND COMMUNICATION
LINES-TELEPHONE CABLE & FIBER OPTIC
CABLE IN 4"Ø PVC CONDUIT W/ 4"Ø PVC
SPARE CONDUIT (LOCATION
APPROXIMATE)
EX. 30"Ø HIGH PRESSURE GAS
TRANSMISSION
MAIN (LOCATION APPROXIMATE)
EX. UTILITY EASEMENT
VOLUME 98193, PAGE 2128
(O.P.R.D.C.T.)
O'GUINN
CREEK
MEMORIAL
WALKWAY
EX. UNITED GAS PIPELINE
COMPANY (TRACT 1)
30' EASEMENT
VOLUME 74139, PAGE 2931
D.R.D.C.T.
13.2 KV ELECTRIC
UNDERGROUND
DISTRIBUTION
LINE IN 50' EASEMENT.
LOCATION APPROXIMATE.
N.F.V.
ELECTRIC TRANSMISSION
TOWER IN 100' EASEMENT
138 KV ELECTRIC
TOWER TRANSMISSION
LINES IN 100' EASEMENT.
LOCATION APPROXIMATE.
N.F.V.
ELECTRIC TRANSMISSION
TOWER IN 100' EASEMENT
ELECTRIC TRANSMISSION
TOWER IN 100' EASEMENT
UNDERGROUND PRIMARY ELECTRIC SERVICE
(2) 4" CONCRETE ENCASED PVC CONDUITS
(1 ACTIVE, 1 SPARE). (LOCATION APPROXIMATE)
EX. WROUGHT IRON
FENCE (TYP.)
APPROXIMATE
LOCATION OF
100-YEAR FLOOD
PLAIN
APPROXIMATE
LOCATION OF
100-YEAR FLOOD
PLAIN
PROJECT AREA
LIMITS (TYP.)
PROJECT AREA
LIMITS (TYP.)
PERENNIAL
TRIBUTARY
STREAM
28.35 ACRES (GRAVEL DRIVE INCLUDED)
1. TOPOGRAPHIC INFORMATION WAS COMPILED FROM AN AERIAL TOPOGRAPHIC
SURVEY PREPARED BY TUCK MAPPING SOLUTIONS, INC. DATED MARCH 28, 2018.
HORIZONTAL DATUM IS REFERENCED TO TEXAS NORTH CENTRAL ZONE NAD 83
(2011). VERTICAL DATUM IS REFERENCED TO NAVD 88
2. UNDERGROUND UTILITIES SHOWN HAVE BEEN LOCATED FROM VISIBLE EVIDENCE.
THE UTILITIES SHOWN MAY OR MAY NOT REFLECT ALL UNDERGROUND UTILITIES IN
THE AREA EITHER IN SERVICE OR ABANDONED. UTILITIES SHOULD BE VERIFIED
PRIOR TO ANY CONSTRUCTION.
3. UTILITIES SHOWN ON THESE DRAWINGS ARE BASED ON INFORMATION AND
REFERENCE DRAWINGS FURNISHED BY DALLAS-FORT WORTH NATIONAL
CEMETERY AND APPLICABLE UTILITY COMPANIES. IT SHALL BE THE CONTRACTOR'S
RESPONSIBILITY TO CONTACT DALLAS-FORT WORTH NATIONAL CEMETERY AND
APPLICABLE UTILITY COMPANIES AND FOR THE EXACT LOCATION OF
UNDERGROUND UTILITIES, INCLUDING UTILITIES NOT SHOWN ON THE PLANS.
NOTES:
28.35 ACRES (GRAVEL DRIVE INCLUDED)
LEGEND:
PROJECT AREA LIMITS
Project Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
A
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
916CM3017
MAY 26, 2020 RPP MAC Dwg. of 72
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
Revisions: Date:
Drawing Title
Approved:
Phase
Project Director
Building Number
BID DOCUMENTS
VA FORM 08 - 6231
321 4 5 6 7 8 9 10
DALLAS-FORT WORTH NATIONAL
CEMETERY BURIAL EXPANSION
DALLAS COUNTY, TEXAS
Fil e P ath : G
:\P
RO
JE
CT
\S
BU
\E
NG
IN
\33
\02
\P
LA
NS
\B
ID
D
OC
UM
EN
TS
\V
L-
0.D W
G
Gordon
148 S. Queen Street, Suite 201
Martinsburg, WV 25401
Phone: 304-725-8456 www.gordon.us.com
PROGRAMMING AND PLANNING
CIVIL ENGINEERING
LANDSCAPE ARCHITECTURE
SURVEY AND MAPPING
SECURITY CONSULTING
Aqua Engineering
(970) 372-6104 rvi
(512) 480-0032
AES Group
(303) 841-3922
GRAPHICAL SCALE: 1" = 250'
250 125 0 250 500 750
VL100
OVERALL EXISTING CONDITIONS
PLAN
| Sheets and Views |
| 01 COVER SHEET |
| 02 GENERAL NOTES, SYMBOLS AND ABBREVIATIONS |
| 03 OVERALL EXISTING CONDITIONS PLAN |
| 04 BORING LOCATION PLAN |
| P-dfw-minor-LI100 |
| Sheets and Views |
| LI100 |
| P-dfw-minor-LI101 |
| Sheets and Views |
| LI101 |
| P-dfw-minor-LI102 |
| Sheets and Views |
| LI102 |
| P-dfw-minor-LI103 |
| Sheets and Views |
| LI103 |
| P-dfw-minor-LI500 |
| Sheets and Views |
| LI500 |
| P-dfw-minor-LI501 |
| Sheets and Views |
| LI501 |
| P-dfw-minor-LI502 |
| Sheets and Views |
| LI502 |
File details come from the government source that posted it. Updated .